A22 - W912EK24B0014-SPEC_SOL-2024-03-26 .pdf

PDF 3 MB Posted

Attached to
Red Rock Lake Roads, Trails, and Infrastructure Repair
Solicitation number
W912EK24B0014
Issued by

About this file

This document is a solicitation for an Indefinite Delivery Indefinite Quantity (IDIQ) construction contract for road, trail, and infrastructure repairs at Lake Red Rock in Marion County, Iowa. The work includes removal of existing aggregate base, preparation of aggregate base, new compacted aggregate base, compacted Portland cement or fly ash modified base course, asphalt pavement patching, asphalt milling, asphalt and concrete crack/joint sealing, pavement and curb/gutter demolition and removal, new concrete pavements and slabs, guardrail installation, and related work. The contractor will be issued delivery orders for specific quantities of work within set dollar and performance time ranges. Payment will be made for actual quantities installed. The contract will be awarded competitively under full and open competition. Key details include a 3-ordering period contract term, a $1.5 million contract ceiling, and 45-225 calendar day performance periods based on delivery order value.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION NO.: W912EK24B0014

B5IDIQPM202303

US Army Corps of Engineers Rock Island District

DES MOINES RIVER BASIN

LAKE RED ROCK RESERVOIR

MARION COUNTY, IOWA

INDEFINITE DELIVERY INDEFINITE

QUANTITY (IDIQ)

Construction Solicitation and Specifications

MARCH 2024

Chief, Geotechnical Branch

Chief, Hydrology and Hydraulics Branch

Chief, Design Branch

Chief, Technical Services Branch

Chief, Engineering and Construction Division

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 10 SUBMITTALS FOR CONTRACT CLAUSES

00 73 05 SPECIAL CONTRACT REQUIREMENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 20 00 PRICE AND PAYMENT PROCEDURES

01 32 16 CONSTRUCTION PROGRESS SCHEDULES

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 45 00 RESIDENT MANAGEMENT SYSTEM (RMS)

01 45 04 CONTRACTOR QUALITY CONTROL

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 78 00 CLOSEOUT SUBMITTALS

DIVISION 10 - SPECIALTIES

10 14 01 DETECTABLE WARNING PANELS

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 05 22 GEOTEXTILE

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 00 00 PAVEMENT REMOVAL

32 01 13 BITUMINOUS FOG COATS

32 01 16 MILLING OF PAVEMENTS

32 01 17 SEALING OF CRACKS AND JOINTS IN ASPHALT SURFACES

32 01 18 CUTTING AND SEALING OF JOINTS IN ASPHALT SURFACES

32 01 19 SEALING OF CRACKS AND JOINTS IN EXISTING CONCRETE SURFACES

32 01 20 SEALING OF JOINTS BETWEEN ASPHALT PAVEMENT AND CONCRETE

CURB AND GUTTERS

32 01 21 CUTTING AND SEALING OF JOINTS IN NEW CONCRETE SURFACES

32 01 29 ASPHALT PAVEMENT PATCHING

32 11 16 EXISTING BITUMINOUS SURFACES AND AGGREGATE BASES

32 11 23 AGGREGATE COURSES

32 11 34 PORTLAND CEMENT, FLY ASH, OR LIME MODIFIED BASE COURSE

32 12 10 TACK COAT

32 12 16 HOT-MIX ASPHALT (HMA) PAVING

32 13 13 CONCRETE PAVEMENTS, SLABS, SIDEWALKS, AND CURB AND GUTTERS

32 15 00 AGGREGATE SHOULDERS

32 16 00 TOPSOIL

32 17 23 PAVEMENT MARKINGS

32 92 19 SEEDING

32 98 00 STEEL-BACKED TIMBER GUARDRAIL

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 01 10

SUBMITTALS FOR CONTRACT CLAUSES

PART 1 GENERAL

1.1 SUBMITTALS

1.2 PAYROLLS - LABOR (FAR 52.222-8)

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

DOCUMENT 00 01 10 Page 1

SECTION 00 01 10

SUBMITTALS FOR CONTRACT CLAUSES

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Payrolls - Labor (FAR 52.222-8)

1.2 PAYROLLS - LABOR (FAR 52.222-8)

Submit weekly.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

DOCUMENT 00 01 10 Page 2

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 73 05

SPECIAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 ADDITIONAL COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

1.4 UNANTICIPATED HAZARDOUS MATERIAL

1.5 COORDINATION WITH OTHERS

1.6 ANTITERRORISM (AT) AND OPERATIONS SECURITY (OPSEC)

1.6.1 General Security Requirements and Guidance

1.6.2 Access and General Protection Policy and Procedures

1.6.2.1 Contractors who do not require CAC, but require access to a

DoD facility or installation

1.6.3 Physical Security and Access Control Requirements

1.6.4 Suspicious Activity Reporting Training

1.6.5 E-Verify Program

1.7 ACTIVITY REGULATIONS FOR CONTRACTOR ACCESS AND USE OF PREMISES

1.8 SUSTAINABILITY

1.9 MINIMUM AMOUNT OF INSURANCE REQUIRED

1.10 EVALUATION OF SUBDIVIDED ITEMS

1.11 VARIATIONS IN ESTIMATED QUANTITIES OF SUBDIVIDED ITEMS

1.12 CONDITION OF EXISTING STRUCTURES, ROADWAYS, AND OTHER FACILITIES

1.13 U.S. ARMY CORPS OF ENGINEERS SAFETY AND HEALTH MANUAL (EM 385-1-1)

1.14 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE

1.15 PROGRESS MEETINGS

1.16 INSPECTION

1.17 DAMAGE TO WORK

1.18 SPECIAL SAFETY REQUIREMENTS

1.19 LOCATION OF PARKING, STAGING, AND STORAGE AREAS

1.20 ELECTRICAL POWER LINES

1.21 BARRICADES AND WARNING SIGNS

1.22 ONE CALL SYSTEM FOR EXCAVATORS

1.23 EXCLUSIONS OF PERIODS IN COMPUTING COMPLETION SCHEDULES

1.24 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

1.25 ADDITIONAL PHYSICAL DATA CLAUSE INFORMATION

1.26 DELAYS DUE TO HIGH WATER

1.27 HIGH WATER ACTION PLAN

1.28 IOWA SALES AND USE TAX EXEMPTION CERTIFICATE

1.29 PROCESSING DAVIS-BACON ACT CERTIFIED LABOR PAYROLLS

1.30 AVAILABILITY AND USE OF UTILITY SERVICES

1.31 ISSUING DELIVERY ORDERS

1.32 INDEFINITE QUANTITY

PART 2 PRODUCTS

PART 3 EXECUTION

ATTACHMENTS:

DOCUMENT 00 73 05 Page 1

ATTACHMENT A - Personnel Change Request Form

DOCUMENT 00 73 05 Page 2

SECTION 00 73 05

SPECIAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EP 1110-1-8 (2021) Engineering and Design -- Construction Equipment Ownership and Operating Expense Schedule

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1926.106 Working Over or Near Water

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Background Checks; G SL Suspicious Activity Reporting Training; G, SL Access Control List (ACL); G SL Company Enrollment in E-Verify; G SL Form I-9; G SL

**NOTE: To protect the privacy of the Contractor, all Contractor employees, and all subcontractor employee's security information, submit with a cover page stating the Contract Number (e.g., W912EK23DXXXX), Contract Title, and the Contractor's point of contact information in a sealed envelope/container and mail to:

Security and Law Enforcement Office U.S. Army Corps of Engineers Rock Island District 1500 Rock Island Drive Rock Island, Illinois 61201

Insurance; G CT Pre-Construction Condition Survey; G High Water Action Plan; G ECDM

SD-11 Closeout Submittals

DOCUMENT 00 73 05 Page 3

Post-Construction Condition Survey; G ECDM

1.3 ADDITIONAL COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

In addition to the requirements of FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK, comply with the following requirements:

a. Work schedule is 7:00am to 5:00pm Monday through Friday or as coordinated with and approved by the Contracting Officer, or as indicated. Federal holiday and weekend work is not to commence unless approved.

b. Secure and keep unauthorized persons out of all work sites with signing, fencing, or by other approved means.

c. The Reservoir will be occupied by the employees of Lake Red Rock.

Accessibility is required for customer vehicles and deliveries during the construction period.

d. Work Area Requirements

(1) Radios and similar devices that can be heard outside the Contractor's work area are prohibited within that area(s).

(2) Remove dust and debris from the work areas daily.

(3) Complete work that generates noise above the exposure limits, as specified in EM 385-1-1, outside the building or during non-business hours. Schedule this work with the Contracting Officer in advance.

e. Provide all necessary protection, appurtenant equipment and supplies, including, but not limited to, enclosures, heating, lighting, and sufficient labor to accomplish the work required during the aforementioned periods, taking into account high water, low and high temperatures, wind forces, ice, sleet, snow, wind chill, high humidity, and heat index factors that may be encountered at the site and working adjacent to water. This may require additional labor or shifts and special equipment or special equipment maintenance to compensate for lost productivity caused by low or high temperatures and other associated environmental factors.

1.4 UNANTICIPATED HAZARDOUS MATERIAL

If a hazardous material(s) is encountered where it was not indicated, cease work and immediately notify the Contracting Officer of the located potential hazardous material(s) found. Upon direction from the Contracting Officer, it may be required to conduct sampling and testing of these suspect material(s) in accordance with an Industrial Hygienist's recommended procedures and the Contract Specification Section(s) as applicable that will be provided to the Contractor as a Modification to the Contract, unless already provided. Payment for this additional work will be handled under FAR 52.243-4 CHANGES.

1.5 COORDINATION WITH OTHERS

Schedule and coordinate operations affecting other Contractors, Government Personnel, utilities, and/or property occurring within the work limits.

Accomplish with lead time sufficient for coordination of all involved

DOCUMENT 00 73 05 Page 4 parties as necessary for timely completion of each Contract feature. At a minimum, establish coordination with each of the following point(s) of contact, as required:

Resident Engineer Western Area Office U.S. Army Corps of Engineers 5301 NW 78th Avenue Johnston, IA 50131 Telephone No.: 515-276-4656, Ext. 6559 (Collect calls not accepted.)

1.6 ANTITERRORISM (AT) AND OPERATIONS SECURITY (OPSEC)

1.6.1 General Security Requirements and Guidance

Clause applies to the Contractor, Contractor's personnel, and subcontractors for complying with all security requirements. Address questions regarding security matters to the Contracting Officer.

Contractor, Contractor's personnel and subcontractors are critical to the overall security and safety of Government property, and security awareness training contributing to those efforts. The Department of Defense (DoD) and Army security training requirements as specified, if applicable, are performance requirements; all applicable Contractor's personnel and subcontractors will complete initial training within 30 days after receiving the Notice to Proceed. Within five business days from the completion of training, notify the Contracting Officer. Include documentation of the names of Contractor's personnel and subcontractors trained and which training has been completed; maintain training records as part of Contract files and be prepared to provide copies of training certificates to Contracting Officer. Contractor, Contractor's personnel, and subcontractors and vehicles are subject to search when entering federal installations. Additionally, all Contractor, Contractor's personnel, and subcontractors will comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (RAMs), and Health Protection Condition (HPCON) measures. Meet all performance requirements during elevated FPCON and/or HPCON levels in accordance with Government installation plans and procedures and includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes affecting Contractor, Contractor's personnel, and subcontractors. Ensure all Contractor's personnel and subcontractors are aware of the security responsibilities, including any site-specific requirements identified in local policies or procedures.

1.6.2 Access and General Protection Policy and Procedures

The Contractor, Contractor employees, and all sub-contractor employees will follow installation and facility access guidelines and rules as stated.

Contractor workforce will comply with all personal identity verification requirements as directed by Department of Defense (DoD), Department of the Army Headquarters, Rock Island District, and/or local policy. In addition to the changes otherwise authorized by the Contract Clause 52.243-4 CHANGES, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in Contractor security matters or processes.

DOCUMENT 00 73 05 Page 5

In support of Rock Island District evaluation of personnel authorized for access to federal facilities, pay all fees for and submit background checks for each person accessing site location, that has been conducted by a bonded third party within the last 6 months of the Notice to Proceed date and mail authorize reports to Rock Island District Security and Law Enforcement Office by the third party, see paragraph "SUBMITTALS" for address and other requirements. The background check will cover, at a minimum, the last ten years covering the states the employee had/has lived in, national crime records check which includes felony and misdemeanor offenses, Department of Motor Vehicles (DMV) records, and a national sex offender registry check, submitted 14 days prior to accessing the project site.

As employees are added or deleted from the submitted and approved Access Control List (ACL), this information will be reported immediately to the Contracting Officer. Added employees will not be permitted on-site until requirements of this paragraph are completed, submitted, and approved.

Disqualifying factors include, but are not limited to:

a. Criminal conduct, in particular, violent crime and sex offenders;

b. Habitual use of intoxicating beverages to excess as evidenced by Driving Under the Influence (DUI) or public intoxication records;

or

c. Any illegal activity or other disqualification which makes the individual unfit for service (e.g., drug trafficking or procurement fraud).

In addition to the submitted background checks, supplemental agency checks may be performed at the discretion of the Rock Island District security personnel. The Contractor agrees to cooperate and ensure that Contractor employees and all sub-contractor employees provide any documentation required to complete these checks. Any employee lacking proper identification credentials or deemed a security threat may be denied access to the project. Such action in no way relieves the Contractor from performance of the Contract. The Rock Island District retains the right to deny any Contractor and sub-contractor employee(s) from working on this Contract awarded by the Rock Island District based on final background investigation results. All information received as a result of a background check will be handled in accordance with the Privacy Act regulation.

In the event that an unexpected change in personnel is required, due to sudden absence of a critical path employee, immediately contact the Contracting Officer to coordinate obtaining written approval from the Security and Law Enforcement Office to allow new/additional personnel brought on-site prior to background check acceptance. Submit ATTACHMENT A - Personnel Change Request Form and the Contractor will receive a written authorization from the Security and Law Enforcement Office prior to bringing new/additional personnel on-site, and will ensure a background check is sent to the Rock Island District Security and Law Enforcement Office no later than 10 days from written notice of approval. The Rock Island District reserves the right to terminate access of the employee upon completion of the Government's review of the background check. The Contractor will be notified immediately of any such Government decision.

In the event of an unforeseen change in work site conditions, which may require a Contract Modification, and the Contractor has to immediately add

DOCUMENT 00 73 05 Page 6 employees, submit the ATTACHMENT A - Personnel Change Request Form and the Contractor will receive written approval from the Security and Law Enforcement Office prior to bringing new/additional personnel on-site, and ensure a background check is sent to the Rock Island District Security and Law Enforcement Office no later than 10 days from written notice of approval. The Rock Island District reserves the right to terminate access of the employee upon completion of the Government's review of the background check and the Contractor will be notified immediately of any such Government decision.

Contractor employees and all sub-contractor employees not expected to be on the worksite for more than 15 days, may be allowed on-site with the following conditions:

a. Employee(s) will be on site a total of 15 days or less, for the duration of the project.

b. Employee(s) is added to the ACL as a short term employee.

c. Employee(s) is escorted at all times while on-site. This is defined as being in the line of sight of an identified employee who has a background check on file with the Rock Island District (as noted on the ACL).

d. Each Contractor employee can sponsor only up to five short term employees at a time.

Foreign National Employees: Due to a difference in background check procedures for long term foreign national employees, all such employees will provide a photocopy of their passport to the Rock Island District Security and Law Enforcement Office no later than 30 days prior to arrival on-site. Short term foreign national employees (e.g. specialists with a two week period of performance) may work on site with the following conditions:

a. Foreign national employee will be on-site a total of 15 days or less, for the duration of the project.

b. Foreign national employee in accordance with E-Verify requirements (see paragraph "E-Verify Program").

c. Approved and identified Contractor employee will escort the foreign national employee AT ALL TIMES while on-site.

d. Each Contractor employee can sponsor only one short term foreign national at a time.

1.6.2.1 Contractors who do not require CAC, but require access to a DoD facility or installation

All Contractor, Contractor employees, and subcontractor employees must comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by Government, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

DOCUMENT 00 73 05 Page 7

1.6.3 Physical Security and Access Control Requirements

Contractor, Contractor's personnel, and subcontractors requiring physical access to a Government installation will comply with the access control procedures of that Government installation. Contractor, Contractor's personnel, and subcontractors requiring unescorted access to meet Contract performance requirements will be evaluated by Rock Island District Security and Law Enforcement Officer and using the National Crime Information Center-Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB). Contractor, Contractor's personnel, and subcontractors will comply with all personal identity verification requirements as specified or directed. Contractor, Contractor's personnel, and subcontractors who do not meet requirements for unescorted access to Government installations will coordinate escorted access with the Contracting Officer. Contractor, Contractor's personnel, and subcontractors who receive keys, access cards, or lock combinations allowing access to restricted areas will comply with key and lock control procedures of the Government installation.

1.6.4 Suspicious Activity Reporting Training

iWATCH, CorpsWatch, or See Something, Say Something are examples. All Contractor, Contractor employees, and subcontractor employees will receive a briefing provided by the Rock Island District Security and Law Enforcement Office on the local suspicious activity reporting program.

This locally developed training will be used to inform Contractor employees of the types of behavior to watch for and instruct them to report suspicious activity to the Contracting Officer, security representative, or local law enforcement entity. This training must be completed within 30 calendar days of Notice to Proceed and within 30 calendar days of new/additional employees commencing performance with the results reported to the Contracting Officer by the Security and Law Enforcement Office via Memorandum of Record for Suspicious Activity Reporting Training no later than 5 calendar days after the completion of the training. Develop an OPSEC Plan including a description of the Government's critical information, why requires protection, the location, who is responsible for the activity, how will be protected, etc. Appoint a Operations Security coordinator and provide employee information. Develop the plan within 90 calendar days after receiving the Notice to Proceed for review by the Rock Island District Security and Law Enforcement Officer. Upon approval, submit the final plan.

1.6.5 E-Verify Program

Contractor will comply with the requirements set forth in FAR 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 to meet the Contract employment eligibility requirements using the E-Verify Program at website (website subject to change):

https://www.e-verify.gov/

Contractor is encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR Clause 22.102-1(i). Submit an initial list of verified/eligible candidates no later than 3 business days after receiving the Notice to Proceed as evidence of the Company Enrollment in E-Verify. When Contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit to the Contracting

DOCUMENT 00 73 05 Page 8

Officer as part of the official Contract file.

1.7 ACTIVITY REGULATIONS FOR CONTRACTOR ACCESS AND USE OF PREMISES

Follow all current Army Security Regulations concerning strict visitor control and preservation of all Government assets. Immediately report all security concerns to the Contracting Officer.

Work may be affected by the following Force Protection Conditions levels:

FPCON NORMAL

When there is no discernible terrorist activity. Routine security posture.

FPCON ALPHA

When there is a general threat of possible threat activity against personnel and the installation, or both. There will be a limited impact on normal operations.

FPCON BRAVO

When there is an increased or more predictable threat. There will be an impact on normal operations but it will not cause undue hardship to personnel, substantially affect operational capabilities, or cause aggravated relations with local authorities and civilians.

FPCON CHARLIE

When an incident occurs or intelligence is received indicating imminent terrorist action. If this lasts for more than a short period it will probably create hardships for personnel and affect the peacetime activities of units and personnel.

FPCON DELTA

When a terrorist attack has occurred or intelligence indicates likely terrorist action against a specific location. This is normally declared as a localized warning and requires implementation of mandatory security measures. This cannot be sustained for an extended period without causing significant hardships for personnel and affecting the peacetime activities of units and personal.

FPCON NORMAL through FPCON BRAVO will not affect the work. FPCON CHARLIE and FPCON DELTA will affect work. FPCON CHARLIE will subject the Contractor to a higher degree of inspection and may not be able to work on-site for short periods of time as decreed by the District Security Officer. FPCON DELTA, as determined by the District Security Officer, will close the site down and the Contractor will not be able to work on the site.

1.8 SUSTAINABILITY

a. Meet USEPA recycled content requirements. Ensure all Contractor-furnished supplies contain recycled content (e.g., insulation, restroom dividers, roofing materials). The list of

DOCUMENT 00 73 05 Page 9

USEPA-Designated Recovered Material Products is available online at:

http://bit.ly/2ak11jp

b. Meet USDA BioPreferred Program requirements. Ensure all Contractor-furnished supplies contain biobased content (e.g., interior wall panels, plastic insulating foam, plastic lumber). The list of USDA-Designated BioPreferred Program Product Categories is available online at:

http://bit.ly/2ajZE3V

c. Use energy- and water-efficient building-related products and equipment as applicable. Ensure all Contractor-furnished equipment meets energy efficiency requirements (e.g., light fixtures, gas water heaters, central air conditioners, windows, doors), and water efficient requirements (e.g., faucets, showerheads, toilets) (when applicable to the work to be performed). The list of USDOE Product Categories Covered by Efficiency Programs is available online at:

http://bit.ly/2ajZJ7S

d. Print all deliverables double-sided on paper that contains post-consumer fiber.

1.9 MINIMUM AMOUNT OF INSURANCE REQUIRED

a. Provide in accordance with FAR 52.228-5 INSURANCE - WORK ON A GOVERNMENT INSTALLATION and procure not less than the following types of insurance in the amount specified:

Minimum Type Amount

Workman's Compensation Insurance As required by State Law Employer's Liability Insurance $100,000 Comprehensive General Liability Insurance $500,000 B.I.

Comprehensive Automobile Liability Insurance $200,000/$500,000 B.I.

$ 20,000 P.D.

b. Provide insurance certificate with the following endorsement:

Cancellation or any material change in the policies adversely affecting the interests of the Government in such insurance will not be effective for such period as may be prescribed by the laws of the state in which the Contract is performed and in no event less than 30 days after written notice to the Contracting Officer.

c. Annotate insurance certificates with the Contract number and name.

1.10 EVALUATION OF SUBDIVIDED ITEMS

Bid Item Nos. 0001, 0002, 0016, 0017, 0018, 0030, 0101, 0102, 0116, 0117, 0118, 0130, 0201, 0202, 0216, 0217, 0218, 0230 are subdivided into two or more estimated quantities and separately priced. The Government will evaluate each of these items on the basis of total price of the subitems.

DOCUMENT 00 73 05 Page 10

1.11 VARIATIONS IN ESTIMATED QUANTITIES OF SUBDIVIDED ITEMS

FAR 52.211-18 VARIATION IN ESTIMATED QUANTITY is applicable only to Bid Item Nos. 0001, 0002, 0016, 0017, 0018, 0030, 0101, 0102, 0116, 0117, 0118, 0130, 0201, 0202, 0216, 0217, 0218, 0230.

a. Variation from the estimated quantity in the actual work performed under any second or subsequent sub-item or elimination of all work under such a second or subsequent sub-item will not be the basis for an adjustment in Contract unit price.

b. Where the actual quantity of work performed for Bid Item Nos. 0001, 0002, 0016, 0017, 0018, 0030, 0101, 0102, 0116, 0117, 0118, 0130, 0201, 0202, 0216, 0217, 0218, 0230 are less than 85 percent of the quantity of the first sub-item listed under such item, it will be paid at the Contract unit price for that sub-item for the actual quantity of work performed and, in addition, an equitable adjustment will be made.

c. If the actual quantity of work performed under Bid Item Nos. 0001, 0002, 0016, 0017, 0018, 0030, 0101, 0102, 0116, 0117, 0118, 0130, 0201, 0202, 0216, 0217, 0218, 0230 exceeds 115 percent or is less than 85 percent of the total estimated quantity of the sub-item under that item and/or if the quantity of the work performed under the second sub-item or any subsequent sub-item under Bid Item Nos. 0001, 0002, 0016, 0017, 0018, 0030, 0101, 0102, 0116, 0117, 0118, 0130, 0201, 0202, 0216, 0217, 0218, 0230 exceeds 115 percent or is less than 85 percent of the estimated quantity of any such sub-item, and if such variation causes an increase or a decrease in the time required for performance of this Contract, the Contract completion time will be adjusted.

1.12 CONDITION OF EXISTING STRUCTURES, ROADWAYS, AND OTHER FACILITIES

a. Pre-Construction Condition Survey - Prior to commencement of operations by the Contractor, make a detailed survey of all existing structures, Contractor staging and parking areas, roadways, boat ramps and other facilities that may be affected by the Contractor's operations.

Conduct the survey with the Contractor and the Contracting Officer and obtain signatures from both parties. Survey sufficiently in scope to provide advance agreement among all concerned as to the condition of the existing structures, Contractor staging and parking areas, roadways, boat ramps and other facilities. Presume responsibility for full and active participation in such pre-construction condition survey of existing structures, Contractor staging and parking areas, roadways, boat ramps and other facilities as deemed necessary to permit determination and accurate assessment of any subsequent damage to existing structures, Contractor staging and parking areas, roadways, boat ramps and other facilities which may be incurred during the Contract.

b. Post-Construction Condition Survey - After completion of the work, and prior to final acceptance of the work, make a detailed post-construction condition survey of the same structures, Contractor staging and parking areas, roadways, boat ramps and other facilities previously surveyed with the Contractor and the Contracting Officer and obtain signatures from all parties. Survey sufficiently in scope to provide for agreement among all concerned as to the post-project condition of the existing structures, Contractor staging and parking areas, roadways, boat ramps and other facilities. Presume responsibility for full and active participation in such

DOCUMENT 00 73 05 Page 11 post-construction condition survey as deemed necessary to permit determination and accurate assessment of any damage to existing structures, Contractor staging and parking areas, roadways, boat ramps and other facilities which have been incurred during the Contract.

c. Include, but do not limit the surveys to, photographs, videos, sketches, and written descriptions. Submit all documentation to each party involved.

d. If it is determined by the post-construction condition survey that damage has occurred to structures, Contractor staging and parking areas, roadways, and other facilities, then repair such damage to a condition equal to the pre-Contract conditions, as approved by the Contracting Officer, at the Contractor's expense.

1.13 U.S. ARMY CORPS OF ENGINEERS SAFETY AND HEALTH MANUAL (EM 385-1-1)

The Government Safety Manual, EM 385-1-1 (including all interim changes) will be followed and in effect on the date of award for all construction aspects of the Contract. EM 385-1-1 is at the following website:

https://www.publications.usace.army.mil/USACE-Publications/Engineer-Manuals/

1.14 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE

a. This special Contract requirement does not apply to terminations. See EP 1110-1-8 and FAR Part 49 TERMINATION OF CONTRACTS.

b. The base allowable cost for construction and equipment in sound workable condition, furnished by a Contractor or subcontractor at any tier on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the Contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the Contractor's accounting records, base costs for that equipment upon the applicable provisions of EP 1110-1-8, Region V.

Consider working conditions as average for determining equipment rates using the schedule unless specified otherwise by the Contracting Officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations applies. For retroactive pricing, the schedule in effect at the time the work was performed applies.

c. Equipment rental costs are allowable, subject to the provisions of FAR

31.105 CONSTRUCTION AND ARCHITECT-ENGINEER CONTRACTS, paragraph (d)(ii) and FAR 31.205-36 RENTAL COSTS. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.

d. When actual equipment costs are proposed and the total amount of the pricing action exceeds the Simplified Acquisition Threshold (SAT), the Contracting Officer will request a submission of either certified cost or pricing data, or partial/limited data, as appropriate. Submit data

DOCUMENT 00 73 05 Page 12 on Standard Form 1411, Contract Pricing Proposal Cover Sheet.

1.15 PROGRESS MEETINGS

a. Attend progress meetings as scheduled by the Government with an agenda prepared by the Contractor. The list of attendees includes, but is not limited to, the Contractor's key site personnel, supervisor(s)/superintendent(s), safety person(s), quality control manager(s), and subcontractors' representative(s).

b. Address and discuss such items as progress of the work, potential factors for delays, proposed daily work schedule for the next period, deficiencies, utility service interruptions, protection of adjacent areas, coordination with other Contractors and Government hired labor, materials delivery schedules, submittals, quality control, and safety issues, and any other issues requiring addressing or discussions.

c. Prepare minutes of the progress meetings and obtain a list of invitees and attendees from all parties. Submit minutes to all parties involved.

1.16 INSPECTION

The presence of a Government inspector does not relieve the Contractor of the responsibility for the proper execution of the work in accordance with the Contract Specifications and Drawings.

1.17 DAMAGE TO WORK

The responsibility for damage to any part of the permanent work is specified in FAR 52.236-7 PERMITS AND RESPONSIBILITIES. However, if, in the judgment of the Contracting Officer, any part of the permanent work performed or completed by the Contractor is damaged by flood, earthquake, or another natural disaster in which damage is not due to the failure of the Contractor and will take reasonable precautions or exercise sound engineering and construction practices to make the repairs as directed by the Contracting Officer, and full compensation for such repairs will be made at the applicable Contract unit or job price as fixed and established in the Contract. Also, if any damage to the permanent work is caused by users of the recreational facilities, the provisions as specified for flood or earthquake will apply, providing the Contractor complies with required construction protection areas instructions as specified. If, in the opinion of the Contracting Officer, Contract unit or job prices are not applicable to any part of scheduled work, an equitable adjustment pursuant to FAR 52.243-4 CHANGES will be made as full compensation for the repairs of that part of the permanent work. Except as provided, repair damage to all work (including temporary construction), utilities, materials, equipment, and plant to the satisfaction of the Contracting Officer at no additional cost to the Government, regardless of the cause of such damage.

1.18 SPECIAL SAFETY REQUIREMENTS

Remove any employee of the Contractor's who disregards safety regulations or displays unsafe attitudes and actions from the job site, as directed by the Contracting Officer, and in accordance with EM 385-1-1.

When working over or near water, be in accordance with 29 CFR 1926.106, Section 19.A.07(i).

a. Provide employees working over or near water, where the danger of

DOCUMENT 00 73 05 Page 13 drowning exists, with U.S. Coast Guard approved life jackets or buoyant work vests.

b. Prior to and after each use, inspect buoyant work vests or life preservers for defects which would alter their strength or buoyancy.

Do not use defective units.

c. Furnish ring buoys in accordance with EM 385-1-1 and refer to Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS, paragraph "LIFESAVING AND

SAFETY SKIFFS."

d. Provide at least one lifesaving skiff immediately available at a location where employees are working over or near water. Refer to Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS, paragraph

"LIFESAVING AND SAFETY SKIFFS."

When operating mechanized equipment on a floating plant, provide positive and acceptable means of preventing this equipment from moving or falling into the water. The type of equipment addressed by this clause includes front end-loaders, bulldozers, trucks (both on- and off-road), backhoes, track hoes, and similar equipment. If the Contractor intends to use such equipment on floating plant, then develop an Activity Hazard Analysis (AHA) for this feature of work. Include a detailed explanation of the type or types of physical barriers, curbs, structures, facilities, to be incorporated to protect the operator and prevent the equipment from entering the water. Nonstructural warning devices may be considered for situations where the use of structural barriers are impracticable.

Thoroughly address the procedure and submit the AHA to the Government prior to commencing work.

1.19 LOCATION OF PARKING, STAGING, AND STORAGE AREAS

The Contractors's parking, staging, and storage areas are as indicated or as coordinated and approved by the Contracting Officer.

1.20 ELECTRICAL POWER LINES

Prior to mobilization, if adjacent to power lines, provide appropriate danger signs where any equipment scheduled for use is incapable of contacting such lines. To confirm the location of underground lines, coordinate with the Contracting Officer. Either have aerial power lines temporarily shut off and prevent the lines from being energized, or maintain clearances required by EM 385-1-1. Do not proceed working into dangerous areas without assigning additional employees to watch the movements of other personnel and equipment. Ensure that designated clearances are maintained.

1.21 BARRICADES AND WARNING SIGNS

Provide and maintain barricades, danger and warning signs, and, if applicable, suitable and efficient lighting at all points of rerouting and entry to the area(s) that will be closed to public travel or access during construction operations. Furnish flagmen and watchmen to warn and direct traffic or to prevent travel on any portion of paved areas during the periods in which operations are performed as may be required to ensure safety and prevent accidents. Furnish facilities as prescribed by local highway authorities and is subject for approval by the Contracting Officer.

Separate payment will not be made for any costs incurred for furnishing

DOCUMENT 00 73 05 Page 14 barricades, and danger and warning signs. Costs will be considered as a subsidiary obligation and included in the mobilization costs.

1.22 ONE CALL SYSTEM FOR EXCAVATORS

One call systems, established by law, are operated by owners of underground utilities for excavators. Upon notification by an excavator through a one call system, all participating operators of underground utilities in a covered area will identify and locate utilities. Use of a ground penetrating radar or services of a utility locating company is acceptable to the Government. Identify One Call system by contacting:

"Call Before You Dig" Telephone No.: 811 Internet: http://www.call811.com

Iowa One Call 320 LeClaire Street Davenport, Iowa 52801 Telephone No.: Toll Free: 800-292-8989

1.23 EXCLUSIONS OF PERIODS IN COMPUTING COMPLETION SCHEDULES

Physical work at the project site is prohibited during the period between 1 December and 1 April inclusive, and such period is excluded from the Contract duration. Perform work during all or any part of this period upon giving prior written notice to and receiving approval from the Contracting Officer. Furthermore, this time period will not be considered in computing time extensions to the Contract and no time extensions will be granted for adverse weather during this period.

1.24 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

a. Provision ER 415-1-15 specifies the procedure for determination of time extensions for unusually severe weather in accordance with FAR 52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION). In order for the Contracting Officer to award a time extension, the following must occur:

(1) The weather experienced at the project site during the Contract period was found unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay is beyond the control and without the fault or negligence of the Contractor.

b. The following schedule of monthly anticipated adverse weather delays is based on National Weather Service Climatological Data for the project location and constitutes the base line for monthly weather time evaluations. The Contractor's progress schedule must include reflecting these anticipated adverse weather delays in all weather dependent activities.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON (7) DAY WORK WEEK

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

(31) (28) (27) (14) (09) (08) (05) (06) (06) (06) (22) (29)

DOCUMENT 00 73 05 Page 15

c. Upon receiving the Notice to Proceed (NTP) and continuing throughout the Contract, record on the daily Contractor's quality control report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day. The number of actual adverse weather delay days are to include days impacted by actual adverse weather (even if adverse weather occurred in the previous month), be calculated chronologically from the first to the last day of each month, and recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in list item b., the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with FAR 52.249-10 DEFAULT (FIXED-PRICE

CONSTRUCTION).

1.25 ADDITIONAL PHYSICAL DATA CLAUSE INFORMATION

Additional Contractor information associated with FAR 52.236-4 PHYSICAL

DATA.

(b) Weather Conditions

National Weather Service climatological data consisting of precipitation and temperature records observed at Knoxville, Iowa, are shown in the table below. These data are based on monthly averages for the 10-year period 2013-2022, inclusive.

DOCUMENT 00 73 05 Page 16

PRECIPITATION TEMPERATURE (Degrees Fahrenheit)

Days Over Days Over Total Average Average Monthly Days Below Month 0.1" 0.5" For Month Maximum Minimum Average 32 Degrees

January 3 1 1.27 31 12 22 28 February 4 0 1.31 33 13 23 25 March 5 2 2.18 48 28 38 22 April 6 2 3.72 60 38 49 8 May 9 3 4.55 70 51 61 0 June 8 3 4.79 82 62 72 0 July 5 2 4.56 85 65 75 0 August 6 2 2.54 83 63 73 0 September 6 3 4.07 78 57 68 0 October 6 3 3.76 63 42 53 5 November 4 1 1.97 48 29 39 18 December 3 1 1.53 37 20 29 26

(c) Hydraulic Data

Daily and historic river gage readings from the Lake Red Rock Reservoir Gage can be obtained from the U.S. Army Corps of Engineers web site as follows:

1. Go to http://www.rivergages.com

2. In Block "Choose an Option" Select Rock Island District or click on the Rock Island icon on the Map

3. In Block "Choose a Basin" Select Rock Island District Reservoirs

4. Scroll to locate Lake Red Rock Reservoir

5. Review date range, stage or elevation, and choose output format (plot, tabulate, tabulate yearly)

Historic reservoir stage duration curves may be constructed using the data provided in the output. Additional information and support is available upon request. Reservoir Gage datum is NGVD29. Project horizontal datum is NAD 83, Iowa South and project vertical datum is

NAVD88.

1.26 DELAYS DUE TO HIGH WATER

Upon mobilization and continuing throughout the Contract, record on the daily CQC report, the high water level elevation at the site and any resultant impact to normally scheduled Contract work or specify specifics.

The Contract period will be extended by the number of calendar days that water levels prevent such work. The Government will not reimburse the Contractor for standby costs associated with delays caused by high water levels. Delays caused by high water levels will not be the basis for an adjustment in Contract price. Refer to paragraph ADDITIONAL PHYSICAL DATA CLAUSE INFORMATION, Historic River Level Data for the Duration Curves.

Accurately interpret gages and duration curves. In the event of high water, the Contractor is responsible for removal of their equipment, tools, and construction materials.

DOCUMENT 00 73 05 Page 17

1.27 HIGH WATER ACTION PLAN

Provide a plan detailing the activities to minimize the adverse effects of high water. Include protection of accomplished work and Contractor's equipment and personnel. Include emergency measures to restore any damaged sections of the project. Emergency measures to provide sound engineering methods that provides protection at or greater than the height of the existing feature, should high water occur.

1.28 IOWA SALES AND USE TAX EXEMPTION CERTIFICATE

Materials physically incorporated into real estate projects property are exempt from Iowa Sales and Use Taxes. However, sales of tools, fuel, lumber for forms and other end use or consumption items which are not physically incorporated into real estate are taxable sales. After receiving the Notice to Proceed, the Contractor may request the Government Sales Tax Exemption Number.

1.29 PROCESSING DAVIS-BACON ACT CERTIFIED LABOR PAYROLLS

This is an option, to the Contractor, to use a commercially available electronic system to process and submit certified payrolls electronically to the Government. The requirements for preparing, processing, and providing certified labor payrolls are established by the Davis-Bacon Act as stated in FAR 52.222-8 PAYROLLS AND BASIC RECORDS and FAR 52.222-13

COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS AND RELATED REGULATIONS.

If the Contractor elects to use an electronic Davis-Bacon payroll processing system, the Contractor will be responsible for obtaining and providing for all access, licenses, and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the Contractor to comply with Davis-Bacon and related Act regulations. When the Contractor uses an electronic Davis-Bacon payroll system, ensure that the electronic payroll service prepares, processes, and maintains the relevant payrolls and basic records during all work and is capable of preserving these payrolls and related basic records for the required 3 years after Contract completion. If the Contractor chooses to use an electronic Davis-Bacon payroll system, then obtain and provide electronic system access to the Government, as required in accordance with the Davis-Bacon and related Act regulations over the Contract duration.

Include electronic review access by the Government Contract administration office to the electronic payroll processing system used by the Contractor.

Ensure that the Contractor's provision and use of an electronic payroll processing system meets the following basic functional criteria:

commercially available; compliant with appropriate Davis-Bacon Act payroll provisions in the FAR; able to accommodate the required numbers of employees and subcontractors planned to be employed; capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records (format at http://rmssupport.helpserve.com/) for export in an Excel spreadsheet to be imported into RESIDENT MANAGEMENT SYSTEM (RMS-CM), that in turn exports payroll data to the RESIDENT MANAGEMENT SYSTEM (RMS-GM);

demonstrated security of data and data entry rights; ability to produce Contractor-certified electronic versions of weekly payroll data; ability to identify erroneous entries and track the data/time of all versions of the certified Davis-Bacon payrolls submitted to the Government over the life of the Contract; placed on a CD or DVD and provide a PDF file record of data from the system database at end of the Contract closeout. Submit data from

DOCUMENT 00 73 05 Page 18 the electronic Davis-Bacon payroll processing system as a Closeout Submittal.

Include all Contractor-incurred costs related to the Contractor's provision and use of an electronic payroll processing service in the Contractor's price for the overall work under this Contract. The costs for Davis-Bacon Act compliance using electronic payroll processing services are not a separately bid, proposed, or reimbursed item under this Contract.

1.30 AVAILABILITY AND USE OF UTILITY SERVICES

The Government will not make any utility or facility services available to the Contractor. Provide utility services and maintain within the construction area a minimum field-type sanitary facility as approved.

1.31 ISSUING DELIVERY ORDERS

a. Each delivery order to have specific quantities with maximum allowable time frame. Although specific quantities will be specified in each delivery order, some variation in quantities will occur and payment will be made for the actual quantities installed in the work (Contract Clause VARIATIONS IN ESTIMATED QUANTITIES will apply to each individual delivery order only). No individual delivery order will be issued for less than the specified delivery order minimum nor more than the specified delivery order maximum.