B01 - BID SUMMARY SHEET - signed.pdf

PDF 153 KB Posted

Attached to
Red Rock Shoreline Erosion (Whitebreast-T'lam Cemetery)
Solicitation number
W912EK22B0009
Issued by

About this file

This bid summary sheet documents the bids received in response to Solicitation Number W912EK22B0009 from the Department of the Army Corps of Engineers Engineering District Rock Island. Five contractors submitted bids for the project to protect the shoreline from erosion at Whitebreast and T'lam Cemetery along the Des Moines River Basin in Red Rock Reservoir, Marion County, Iowa. The bids ranged from $1,901,555 from RK Excavation, LLC to $2,944,190 from Better By Design LLC, with the government estimate being $2,065,311.58. Gale Construction Company provided the lowest bid at $1,987,320.51. The solicitation included drawings and specifications outlining the erosion protection requirements along the shoreline.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID SUMMARY SHEET

W912EK22B0009

Red Rock Shoreline Erosion (Whitebreast - T’lam Cemetery)

ONE AMENDMENT ISSUED

IFB NO: W912EK22B009

DATE: August 15, 2022

TIME: 2:00 PM CT

PLACE: Webex

NO: BIDDER & ADDRESS AMOUNT

1.Better By Design LLC – Brookfield, MO $2,944,190.00

2. Gale Construction Company – Joliet, IL $1,987,320.51

3. Kovilic Construction Company, Inc. – Franklin Park, IL $2,595,400.00

4. Legacy Corporation – East Moline, IL $2,148,288.00

5. RK Excavation, LLC – Bloomsdale, MO $1,901,555.00

GOVERNMENT ESTIMATE: $2,065,311.58

Bid Opening Officer:

___________________________________ 15 August 2022 Nicholas M. Moore Date Contracting Officer

2022-08-15T14:56:27-0500
MOORE.NICHOLAS.M.1025006433