About this file

This document outlines a federal contract solicitation for flood risk management projects along the Cedar River in Cedar Rapids, Iowa. The solicitation includes a base bid for construction work at the 12th Avenue road closure, including demolition, traffic control, installation of sheet piles and other flood protection structures, road and utility reconstruction, and site restoration. An optional bid is also specified for a similar closure project at the Crandic Railroad. Bids for the work are due by May 4, 2022. The awarding agency is identified as the Department of the Army Corps of Engineers, Rock Island District. The document provides relevant details on the scope of both the base bid and optional projects in clear, direct language suitable for business.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

22B0001

AMEND 0002

The following modifications are made to the PROJECT TITLE PAGE, SCHEDULE OF PRICES, PROJECT TABLE OF CONTENTS, Section 00 73 05, Section 01 11 00, Section 01 22 00, SUBMITTAL REGISTER, Section 01 50 02, Section 01 53 01, Section 01 57 19, Section 02 21 00, Section 02 41 00, Section 03 11 14, Section 03 31 00, Section 03 41 00, Section 03 41 20, Section 07 42 13, Section 09 97 02, Section 31 00 00, Section 31 41 16, Section 31 62 16, Section 32 11 23, Section 32 13 13, Section 32 31 13, Section 32 92 19, Section 33 40 00, Section 33 71 02, Section 35 20 16, and Section 35 31 19.

PROJECT TITLE PAGE

a. ALL PAGES. Delete the Project Title Page in its entirety, and substitute therefor revised Project Title Page, Amendment 0002, April 8, 2022.

SCHEDULE OF PRICES

b. ALL PAGES. Delete the Schedule of Prices in its entirety, and substitute therefor revised Schedule of Prices, Amendment 0002, April 8, 2022.

PROJECT TABLE OF CONTENTS

c. ALL PAGES. Delete the Project Table of Contents in its entirety, and substitute therefor revised Project Table of Contents, Amendment 0002, April 8, 2022.

SECTION 00 73 05

d. ALL PAGES. Delete Section 00 73 05 in its entirety, and substitute therefor revised Section 00 73 05, Amendment 0002, April 8, 2022.

e. ATTACHMENT C. Delete Section 00 73 05 ATTACHMENT C in its entirety.

f. ATTACHMENT D. Delete Section 00 73 05 ATTACHMENT D in its entirety, and substitute revised Section 00 73 05 ATTACHMENT D, Amendment 0002, dated April 8, 2022.

g. ATTACHMENT E. Delete Section 00 73 05 ATTACHMENT E in its entirety.

SECTION 01 11 00

h. ALL PAGES. Delete Section 01 11 00 in its entirety, and substitute therefor revised Section 01 11 00, Amendment 0002, April 8, 2022.

SECTION 01 22 00

i. ALL PAGES. Delete Section 01 22 00 in its entirety, and substitute therefor revised Section 01 22 00, Amendment 0002, April 8, 2022.

SUBMITTAL REGISTER

j. ALL PAGES. Delete the Submittal Register in its entirety, and substitute therefor revised Submittal Register, Amendment 0002, April 8, 2022.

SECTION 01 50 02

k. PAGES 1 AND 6. Delete Section 01 50 02 Pages 1 and 6 in their entirety, and substitute therefor revised Section 01 50 02 Pages 1 and 6, Amendment 0002, April 8, 2022.

SECTION 01 53 01

l. ALL PAGES. Delete Section 01 53 01 in its entirety.

SECTION 01 57 19

m. ALL PAGES. Delete Section 01 57 19 in its entirety, and substitute therefor revised Section 01 57 19, Amendment 0002, April 8, 2022.

SECTION 02 21 00

n. PAGES 1, 2, 4, AND 5. Delete Section 02 21 00 Pages 1, 2, 4, and 5 in their entirety, and substitute therefor revised Section 02 21 00 Pages 1, 2, 4, and 5, Amendment 0002, April 8, 2022.

SECTION 02 41 00

o. PAGES 1, 4, 5, AND 6. Delete Section 02 41 00 Pages 1, 4, 5, and 6 in their entirety, and substitute therefor revised Section 02 41 00 Pages 1, 4, 5, and 6, Amendment 0002, April 8, 2022.

SECTION 03 11 14

p. PAGES 1 AND 6. Delete Section 03 11 14 Pages 1 and 6 in their entirety, and substitute therefor revised Section 03 11 14 Pages 1 and 6, SECTION 03 31 00

q. ALL PAGES. Delete Section 03 31 00 in its entirety, and substitute therefor revised Section 03 31 00, Amendment 0002, April 8, 2022.

SECTION 03 41 00

r. PAGES 1 AND 9. Delete Section 03 41 00 Pages 1 and 9 in their entirety, and substitute therefor revised Section 03 41 00 Pages 1 and 9, SECTION 03 41 20

s. ALL PAGES. Delete Section 03 41 20 in its entirety.

SECTION 07 42 13

t. ALL PAGES. Delete Section 07 42 13 in its entirety, and substitute therefor revised Section 07 42 13, Amendment 0002, April 8, 2022.

SECTION 09 97 02

u. ALL PAGES. Delete Section 09 97 02 in its entirety, and substitute therefor revised Section 09 97 02, Amendment 0002, April 8, 2022.

SECTION 31 00 00

v. ALL PAGES. Delete Section 31 00 00 in its entirety, and substitute therefor revised Section 31 00 00, Amendment 0002, April 8, 2022.

SECTION 31 41 16

w. ALL PAGES. Delete Section 31 41 16 in its entirety, and substitute therefor revised Section 31 41 16, Amendment 0002, April 8, 2022.

SECTION 31 62 16

x. ALL PAGES. Delete Section 31 62 16 in its entirety, and substitute therefor revised Section 31 62 16, Amendment 0002, April 8, 2022.

SECTION 32 11 23

y. ALL PAGES. Delete Section 32 11 23 in its entirety, and substitute therefor revised Section 32 11 23, Amendment 0002, April 8, 2022.

SECTION 32 13 13

z. ALL PAGES. Delete Section 32 13 13 in its entirety, and substitute therefor revised Section 32 13 13, Amendment 0002, April 8, 2022.

SECTION 32 31 13

aa. ALL PAGES. Delete Section 32 31 13 in its entirety.

SECTION 32 92 19

ab. ALL PAGES. Delete Section 32 92 19 in its entirety, and substitute therefor revised Section 32 92 19, Amendment 0002, April 8, 2022.

SECTION 33 40 00

ac. ALL PAGES. Delete Section 33 40 00 in its entirety, and substitute therefor revised Section 33 40 00, Amendment 0002, April 8, 2022.

SECTION 33 71 02

ad. ALL PAGES. Delete Section 33 71 02 in its entirety, and substitute therefor revised Section 33 71 02, Amendment 0002, April 8, 2022.

SECTION 35 20 16

ae. ALL PAGES. Delete Section 35 20 16 in its entirety, and substitute therefor revised Section 35 20 16, Amendment 0002, April 8, 2022.

SECTION 35 31 19

af. PAGES 1 and 5. Delete Section 35 31 19 Pages 1 and 5 in their entirety, and substitute therefor revised Section 35 31 19 Pages 1 and 5, ATTACHMENTS: Project Title Page; Schedule of Prices;

Project Table of Contents; Section 00 73 05;

Section 00 73 05 ATTACHMENT D; Section 01 11 00;

Section 01 22 00; Submittal Register;

Section 01 50 02 Pages 1 and 6; Section 01 57 19;

Section 02 21 00 Pages 1, 2, 4, and 5;

Section 02 41 00 Pages 1, 4, 5, and 6;

Section 03 11 14 Pages 1 and 6; Section 03 31 00;

Section 03 41 00 Pages 1 and 9; Section 07 42 13;

Section 09 97 02; Section 31 00 00; Section 31 41 16;

Section 31 62 16; Section 32 11 23; Section 32 13 13;

Section 32 92 19; Section 33 40 00; Section 33 71 02;

Section 35 20 16; and Section 35 31 19 Pages 1 and 5

AMEND. 0002

08 APR 2022

Solicitation No. W912EK22B0001

IOWA RIVER BASIN

CEDAR RIVER

CEDAR RAPIDS, IA

CEDAR RAPIDS FLOOD RISK

MANAGEMENT PROJECT

12TH AVENUE SE ROLLER GATE

CLOSURE STRUCTURE

Construction Solicitation and Specifications

FEBRUARY 2022

US Army Corps of Engineers Rock Island District

96514720193260

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The reason for this amendment is to extend the bid opening date to 04 May 2022 and remove Option A CRANDIC RR Roller Gate Closure Structure from the solictiation and resultant contract. Additional sections and clauses w ere revised or deleted as necessary. Plan Set VOL 302 is no longer applicable.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 13

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 20-Apr-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EK22B0001

X 9B. DATED (SEE ITEM 11)

22-Feb-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

20-Apr-2022

CODE

CONTRACTING DIVISION

US ARMY CORPS OF ENGINEERS 1500 ROCK ISLAND D

ROCK ISLAND IL 61201

W912EK 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912EK22B0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 08-Apr-2022 02:00 PM to 04-May-2022 02:00 PM.

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

The following have been added by full text:

MVR.13 INSTRUCTIONS TO BIDDERS

The Rock Island District has implemented the below procedures for all current bid openings.

Electronic Submission of Bids:

For this IFB Solicitation, the Rock Island District is requiring all electronic bids be submitted via email to the Contracting Officer and Contract Specialist.

Contracting Officer – Elizabeth A. Dennison, email at elizabeth.a.dennison@usace.army.mil Contract Specialist – Bradley J. Grothus, email at bradley.j.grothus@usace.army.mil

In the subject of the e-mail – the Solicitation and Project Name shall be provided. If the email submission is considered large please consider breaking it up into different emails. For example: W912EK22B0001 – Title – Email 1 of 2. If the email size exceeds 41 MB, the Bid shall be sent in more than one email to ensure delivery to the Government POC. The Contracting Officer or Contract Specialist will send an email acknowledging receipt. Please note, the Government Firewall can cause a delay in receipt of emails, so be sure to allow time for the delay.

The Bid Opening is currently scheduled for Wednesday, 04 May 2022 at 2:00 PM CST.

The Contracting Officer and Contract Specialist will begin downloading bids ONE HOUR BEFORE BID OPENING TIME, which is the bid receipt cutoff time.

All bids received after 1:00 PM CST on Wednesday, 04 May 2022 will be considered late.

Audio Teleconference Bid Opening Information:

Bid Opening will be held on Wednesday, 04 May 2022 at 2:00 PM CST. Please use the following call-in information to attend the meeting:

Toll-Free: 844-800-2712 Access Code: 1999 96 2853

Following the conclusion of the bid opening, the Bid Abstract will be uploaded to the SAM.gov website under this solicitation, within 24 hours.

Bid Bonds (Offer Guarantee) should be submitted electronically with the Bid Package.

Per Class Deviation 2020-O0016, Electronic signatures and electronic, mechanically-applied, or printed dates may be used and shall be considered original signatures and dates. In addition, a Corporate Seal is not required, the SF 28 need not be sworn and notarized and a written authorization of the release signed by the surety is acceptable in lieu of the notarized authorization of release by the surety. Original Certified Bonds need not be mailto:elizabeth.a.dennison@usace.army.mil mailto:bradley.j.grothus@usace.army.mil submitted at time of bid. The Rock Island District reserves the right to request the Original Certified Bonds, if deemed necessary to verify their authenticity.

The following deviation clauses now apply, in lieu of the corresponding FAR clauses:

• 52.228-11, Pledges of Assets (DEVIATION 2020-O0016), which removes the requirement for the Standard Form 28 to be sworn and notarized.

• 52.228-15, Performance and Payment Bonds—Construction (DEVIATION 2020-O0016), which removes the requirements for seals on Standard Forms.

• 52.228-16, Performance and Payment Bonds—Other than Construction (DEVIATION 2020-O0016), which removes requirements for seals on Standard Forms.

For any Questions please contact:

Contracting Officer – Elizabeth A. Dennison, email elizabeth.a.dennison@usace.army.mil Phone: 309-794-5293

Contract Specialist – Bradley J. Grothus, email bradley.j.grothus@usace.army.mil Phone: 309-794-5021

The following have been modified:

SCHEDULE OF PRICES

ITEM

NO.

SUPPLIES/SERVICES

QUANTITY

UNI

T

UNIT PRICE AMOUNT

0001 Mobilization and Demobilization 1 JOB XXXXXXXX

0002 Demolition 1 JOB XXXXXXXX $__________

0003 Temporary Traffic Control 1 JOB XXXXXXXX $__________

0004 Protection and Dewatering 1 JOB XXXXXXXX $__________

0005 Clearing, Grubbing, and Stripping 1 JOB XXXXXXXX $__________

0006 ACC Paving and Patching Work 1 JOB XXXXXXXX $__________

0007 PCC Paving and Patching Work 1 JOB XXXXXXXX $__________

0008 Closure Gate (Roller) 1 JOB XXXXXXXX $__________

0009 Seal Water Main Relocation and Casing Pipe Through Sheet Pile

1 JOB XXXXXXXX $__________

0010 Electrical/Communication Utility Work

1 JOB XXXXXXXX $__________

mailto:elizabeth.a.dennison@usace.army.mil mailto:bradley.j.grothus@usace.army.mil

0011 Gate Closure Monolith 1 JOB XXXXXXXX $__________

0012 Gate Storage Monolith 1 JOB XXXXXXXX $__________

0013 Flood Wall Construction 1 JOB XXXXXXXX $__________

0014 Concrete Stairs 1 JOB XXXXXXXX $__________

0015 Pavement Markings 1 JOB XXXXXXXX $__________

0016 Retaining Wall 1 JOB XXXXXXXX $__________

0017 Signage 1 JOB XXXXXXXX $__________

0018 Seeding and Site Restoration 1 JOB XXXXXXXX $__________

0019 Closure Gate Decorative Panels 1 JOB XXXXXXXX $__________

0020 Levee Embankment 850 CY $_________

0021 Structural Excavation 1,686

CY $_________

0022 Concrete Curb and Gutter 826 LF $_________

0023 Concrete Sidewalk 4,738

SF $_________

0024 Metal Sheet Piling 12,950

SF $_________

0025 Metal H-Piling 3,080

LF $_________

0026 Micro Piling 1,730

LF $_________

0027 RCP Storm Sewer 568 LF $_________

0028 Catch Basins 9 EA $_________

0029 Manhole 1 EA $_________

0030 Water Main Distribution 360 LF $_________

0031 Water Main Extended Performance Bond

1 JOB XXXXXXXX $__________

0032 Riprap

0032AA First 500 Tons 500 TN $_________

0032AB Over 500 Tons 228 TN $_________

0033 Bedding Stone

0033AA First 150 Tons 150 TN $_________

0033AB Over 150 Tons 62 TN $_________

0034 Railing 102 LF $_________

0035 River Trail 3,595

SF $_________

TOTAL OF ESTIMATED AMOUNTS

(ITEM NOS. 0001 THROUGH 0035, INCL.) $__________

CY = CUBIC YARD EA = EACH JOB = LUMP SUM

LF = LINEAR FOOT SF = SQUARE FOOT TN = TON

ENSURE UNIT PRICE AND AMOUNT LINES FOR ALL ITEMS ARE COMPLETED.

SECTION 00700 - CONTRACT CLAUSES

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 400 consecutive calendar days for Base Bid. The time stated for completion shall include final cleanup of the premises.

(End of clause)

SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS

WAGE RATES

"General Decision Number: IA20220081 02/25/2022

Superseded General Decision Number: IA20210081

State: Iowa

Construction Types: Heavy and Highway

Counties: Adair, Adams, Allamakee, Appanoose, Audubon, Benton, Black Hawk, Boone, Bremer, Buchanan, Buena Vista, Butler, Calhoun, Carroll, Cass, Cedar, Cerro Gordo, Cherokee, Chickasaw, Clarke, Clay, Clayton, Clinton, Crawford, Dallas, Davis, Decatur, Delaware, Des Moines, Dickinson, Dubuque, Emmet, Fayette, Floyd, Franklin, Fremont, Greene, Grundy, Guthrie, Hamilton, Hancock, Hardin, Harrison, Henry, Howard, Humboldt, Ida, Iowa, Jackson, Jasper, Jefferson, Johnson, Jones, Keokuk, Kossuth, Lee, Linn, Louisa, Lucas, Lyon, Madison, Mahaska, Marion, Marshall, Mills, Mitchell, Monona, Monroe, Montgomery, Muscatine, O'Brien, Osceola, Page, Palo Alto, Plymouth, Pocahontas, Polk, Pottawattamie, Poweshiek, Ringgold, Sac, Shelby, Sioux, Story, Tama, Taylor, Union, Van Buren, Wapello, Warren, Washington, Wayne, Webster, Winnebago, Winneshiek, Woodbury, Worth and Wright Counties in Iowa.

HIGHWAY CONSTRUCTION PROJECTS and HEAVY CONSTRUCTION PROJECTS

Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.

Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60).

|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $15.00 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2022. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $11.25 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2022. |

The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.

Additional information on contractor requirements and worker protections under the Executive Orders is available at https://www.dol.gov/agencies/whd/government-contracts.

Modification Number Publication Date 0 01/07/2022 1 02/25/2022

* SUIA2021-001 10/18/2017

Rates Fringes

Carpenter & Piledrivermen

ZONE 1......................$ 29.27 14.58

ZONE 2......................$ 27.48 14.73

ZONE 3......................$ 27.48 14.73

ZONE 4......................$ 26.85 12.30

ZONE 5**....................$ 25.75 10.70

CONCRETE FINISHER

ZONE 1......................$ 29.05 7.60

ZONE 2......................$ 29.05 7.60

ZONE 3......................$ 29.05 7.60

ZONE 4......................$ 25.95 6.95

ZONE 5......................$ 24.90 6.95

ELECTRICIAN (STREET AND

HIGHWAY LIGHTING AND TRAFFIC

SIGNALS)

ZONE 1, 2, AND 3............$ 30.40 9.80

ZONE 4......................$ 29.10 8.80

ZONE 5......................$ 26.95 7.80

IRONWORKER (SETTING OF

STRUCTURAL STEEL)

ZONE 1......................$ 32.25 11.60

ZONE 2......................$ 30.16 12.05

ZONE 3......................$ 30.16 12.05

ZONE 4......................$ 28.00 11.15

ZONE 5**....................$ 26.15 10.30

LABORER

ZONE 1, 2 AND 3

GROUP A....................$ 24.08 10.65

GROUP AA...................$ 26.46 10.65

GROUP B....................$ 22.23 10.65

GROUP C....................$ 19.15 10.65

ZONE 4

GROUP A....................$ 21.37 9.83

GROUP B....................$ 20.05 9.83

GROUP C....................$ 17.17 9.83

ZONE 5

GROUP A....................$ 21.77 8.38

GROUP B....................$ 19.27 8.38

GROUP C....................$ 18.42 8.38

POWER EQUIPMENT OPERATOR

ZONE 1

GROUP A....................$ 33.25 15.50

GROUP B....................$ 31.70 15.50

GROUP C....................$ 29.20 15.50

GROUP D....................$ 29.20 15.50

ZONE 2

GROUP A....................$ 32.55 15.50

GROUP B....................$ 30.95 15.50

GROUP C....................$ 28.40 15.50

GROUP D....................$ 28.40 15.50

ZONE 3

GROUP A....................$ 30.45 25.90

GROUP B....................$ 28.65 25.90

GROUP C....................$ 27.65 25.90

GROUP D....................$ 27.65 25.90

ZONE 4

GROUP A....................$ 31.35 13.85

GROUP B....................$ 30.21 13.85

GROUP C....................$ 28.13 13.85

GROUP D....................$ 28.13 13.85

ZONE 5

GROUP A....................$ 28.52 11.50

GROUP B....................$ 27.48 11.50

GROUP C....................$ 25.75 11.50

GROUP D....................$ 24.75 11.50

TRUCK DRIVER (AND PAVEMENT

MARKING DRIVER/SWITCHPERSON)

ZONE 1......................$ 25.25 11.45

ZONE 2

.................................$ 25.25 11.45

ZONE 3......................$ 25.25 11.45

ZONE 4......................$ 25.00 7.50

ZONE 5

.................................$ 23.05 7.50

ZONE DEFINITIONS

ZONE 1 The Counties of Polk, Warren, and Dallas for all Crafts, and Linn County Carpenters only.

ZONE 2 The Counties of Dubuque for all Crafts and Linn County for all Crafts except Carpenters.

ZONE 3 The Cities of Burlington (including West Burlington), Clinton, Fort Madison, Keokuk, and Middleton (including the Iowa Army Ammunition Plant) and Muscatine (and abutting municipalities of any such cities).

ZONE 4 Story, Black Hawk, Cedar, Jasper, Jones, Jackson, Louisa, Madison, and Marion Counties; Clinton County (except the City of Clinton), Johnson County, Muscatine County (except the City of Muscatine), the City of Council Bluffs, Lee County and Des Moines County.

ZONE 5 All areas of the state not listed above.

LABORER CLASSIFICATIONS - ALL ZONES

GROUP AA - {Skilled pipelayer (sewer, water and conduits) and tunnel laborers; asbestos abatement worker} (Zones 1, 2 and 3).

GROUP A - Carpenter tender on bridges and box culverts; curb machine (without a seat); deck hand; diamond & core drills;

drill operator on air tracs, wagon drills and similar drills; form setter/stringman on paving work; gunnite nozzleman; joint sealer kettleman; laser operator;

powderman tender; powderman/blaster; saw operator;

{pipelayer (sewer, water, and conduits); sign erector*;

tunnel laborer; asbestos abatement worker (Zones 4 and 5)}, sign erector.

GROUP B - Air, gas, electric tool operator; barco hammer;

carpenter tender; caulker; chain sawman; compressor (under 400 cfm); concrete finisher tender; concrete processing materials and monitors; cutting torch on demolition; drill tender; dumpmen; electric drills; fence erectors; form line expansion joint assembler; form tamper; general laborer;

grade checker; handling and placing metal mesh, dowel bars, reinforcing bars and chairs; hot asphalt laborer;

installing temporary traffic control devices;

jackhammerman; mechanical grouter; painter (all except stripers); paving breaker; planting trees, shrubs and flowers; power broom (not self-propelled); power buggyman;

rakers; rodman (tying reinforcing steel); sandblaster;

seeding and mulching; sewer utility topman/bottom man;

spaders; stressor or stretcherman on pre or post tensioned concrete; stringman on re/surfacing/no grade control;

swinging stage, tagline, or block and tackle; tampers;

timberman; tool room men and checkers; tree climber; tree groundman; underpinning and shoring caissons over twelve feet deep; vibrators; walk behind trencher; walk behind paint stripers; walk behind vibrating compactor; water pumps (under three inch); work from bosun chair.

GROUP C - Scale weigh person; traffic control/flagger, surveillance or monitor; water carrier.

POWER EQUIPMENT OPERATOR CLASSIFICATIONS - ALL ZONES

GROUP A - All terrain (off road) forklift; asphalt breakdown roller (vibratory); asphalt laydown machine; asphalt plant;

asphalt screed; bulldozer (finish); central mix plant;

concrete pump; crane; crawler tractor pulling scraper;

directional drill (60,000 (lbs) pullback and above);

dragline and power shovel; dredge engineer; excavator (over � cu. yd.); front end loader (4 cy and over); horizontal boring machine; master mechanic; milling machine (over 350 hp); motor grader (finish); push cat; rubber tired backhoe (over � cu. yd.); scraper (12 cu. yd. and over or finish);

Self-propelled rotary mixer/road reclaimer; sidebroom tractor; slipform portland concrete paver; tow or push boat; trenching machine (Cleveland 80 or similar) GROUP B - Articulated off road hauler, asphalt heater/planer;

asphalt material transfer vehicle; asphalt roller; belt loader or similar loader; bulldozer (rough); churn or rotary drill; concrete curb machine; crawler tractor pulling ripper, disk or roller; deck hand/oiler;

directional drill (less than 60,000 (lbs) pullback);

distributor; excavator (1/2 cu. yd. and under); form riding concrete paver; front end loader (2 to less than 4 cu.

yd.); group equipment greaser; mechanic; milling machine (350 hp. and less); paving breaker; portland concrete dry batch plant; rubber tired backhoe (1/2 cu. yd. and under);

scraper (under 12 cu. yd.); screening, washing and crushing plant (mobile, portable or stationary); shoulder machine;

skid loader (l cu. yd. and over); subgrader or trimmer;

trenching machine; water wagon on compaction.

GROUP C - Boom & winch truck; concrete spreader/belt placer;

deep wells for dewatering; farm type tractor (over 75 hp.)

pulling disc or roller; forklift; front end loader (under 2

cu. yd.); motor grader (rough); pile hammer power unit;

pump (greater than three inch diameter); pumps on well points; safety boat; self-propelled roller (other than asphalt); self-propelled sand blaster or shot blaster, water blaster or striping grinder/remover; skid loader (under 1 cu. yd.); truck mounted post driver.

GROUP D - Boiler; compressor; cure and texture machine; dow box; farm type or utility tractor (under 75 hp.) pulling disk, roller or other attachments; group greaser tender;

light plants; mechanic tender; mechanical broom; mechanical heaters; oiler; pumps (under three inch diameter); tree chipping machine; truck crane driver/oiler.

** CARPENTERS AND PILEDRIVERMEN, or IRONWORKERS (ZONE 5) Setting of structural steel; any welding incidental to bridge or culvert construction; setting concrete beams.

* ADDED CRAFT - SIGN ERECTOR

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour National Office because National Office has responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISIO"

(End of Summary of Changes)

B5CEDRPD202103 - Cedar Rapids FRM 12th Avenue Road Closure Cedar Rapids, IA SCHEDULE OF PRICES

Solicitation No. W912EK22B0001

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 Mobilization and Demobilization 1 JOB XXXXXXXX $

0002 Demolition 1 JOB XXXXXXXX $

0003 Temporary Traffic Control 1 JOB XXXXXXXX $

0004 Protection and Dewatering 1 JOB XXXXXXXX $

0005 Clearing, Grubbing, and Stripping 1 JOB XXXXXXXX $

0006 ACC Paving and Patching Work 1 JOB XXXXXXXX $

0007 PCC Paving and Patching Work 1 JOB XXXXXXXX $

0008 Closure Gate (Roller) 1 JOB XXXXXXXX $

0009 Seal Water Main Relocation and Casing Pipe Through Sheet Pile

1 JOB XXXXXXXX $

0010 Electrical/Communication Utility Work 1 JOB XXXXXXXX $

0011 Gate Closure Monolith 1 JOB XXXXXXXX $

0012 Gate Storage Monolith 1 JOB XXXXXXXX $

0013 Flood Wall Construction 1 JOB XXXXXXXX $

0014 Concrete Stairs 1 JOB XXXXXXXX $

0015 Pavement Markings 1 JOB XXXXXXXX $

0016 Retaining Wall 1 JOB XXXXXXXX $

0017 Signage 1 JOB XXXXXXXX $

0018 Seeding and Site Restoration 1 JOB XXXXXXXX $

0019 Closure Gate Decorative Panels 1 JOB XXXXXXXX $

Cedar Rapids, IA SCHEDULE OF PRICES (continued)

Solicitation No. W912EK22B0001

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0020 Levee Embankment 850 CY $ $

0021 Structural Excavation 1,686 CY $ $

0022 Concrete Curb and Gutter 826 LF $ $

0023 Concrete Sidewalk 4,738 SF $ $

0024 Metal Sheet Piling 12,950 SF $ $

0025 Metal H-Piling 3,080 LF $ $

0026 Micro Piling 1,730 LF $ $

0027 RCP Storm Sewer 568 LF $ $

0028 Catch Basins 9 EA $ $

0029 Manhole 1 EA $ $

0030 Water Main Distribution 360 LF $ $

0031 Water Main Extended Performance Bond

1 JOB XXXXXXXX $

0032 Riprap

0032AA First 500 Tons 500 TN $ $

0032AB Over 500 Tons 228 TN $ $

0033 Bedding Stone

0033AA First 150 Tons 150 TN $ $

0033AB Over 150 Tons 62 TN $ $

Cedar Rapids, IA SCHEDULE OF PRICES (continued)

Solicitation No. W912EK22B0001

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0034 Railing 102 LF $ $

0035 River Trail 3,595 SF $ $

CY = CUBIC YARD EA = EACH JOB = LUMP SUM

LF = LINEAR FOOT SF = SQUARE FOOT TN = TON

ENSURE UNIT PRICE AND AMOUNT LINES FOR ALL ITEMS ARE COMPLETED.

TOTAL OF ESTIMATED AMOUNTS

(ITEM NOS. 0001 THROUGH 0035, INCL.)

Solicitation No. W912EK22B0001

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 73 05 SPECIAL CONTRACT REQUIREMENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 22 00 PRICE AND PAYMENT PROCEDURES

01 32 16 CONSTRUCTION PROGRESS SCHEDULES

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 45 00 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 45 04 CONTRACTOR QUALITY CONTROL

01 50 02 TEMPORARY CONSTRUCTION CONTROLS

01 53 00 TEMPORARY RETAINING STRUCTURES

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 78 00 CLOSEOUT SUBMITTALS

DIVISION 02 - EXISTING CONDITIONS

02 21 00 SURVEYS

02 41 00 DEMOLITION

DIVISION 03 - CONCRETE

03 11 14 CONCRETE FORMWORK

03 15 14 JOINTS IN CONCRETE

03 15 15 GROUT AND ANCHOR BOLTS

03 20 01 CONCRETE REINFORCEMENT

03 31 00 CAST-IN-PLACE STRUCTURAL CONCRETE

03 41 00 PLANT-PRECAST STRUCTURAL CONCRETE

DIVISION 04 - MASONRY

04 43 00 STONE MASONRY - 12TH AVENUE CLOSURE

DIVISION 05 - METALS

05 50 14 STRUCTURAL METAL FABRICATIONS

05 50 15 CIVIL WORKS FABRICATIONS - 12TH AVENUE CLOSURE

05 59 20 FRACTURE CRITICAL HYDRAULIC STEEL STRUCTURES FABRICATION

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 42 13 ALUMINUM COMPOSITE PANELS

DIVISION 09 - FINISHES

09 97 02 PAINTING: HYDRAULIC STRUCTURES

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 05 22 GEOTEXTILES - 12TH AVENUE CLOSURE

31 09 06 VIBRATION MONITORING

31 41 16 METAL SHEET PILING

31 62 16 STEEL H-PILES

PROJECT TABLE OF CONTENTS Page 1 AMEND. 0002

08 APR 2022

31 63 33 MICROPILES

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 11 23 AGGREGATE BASE AND SURFACE COURSES

32 12 10 TACK COAT - 12TH AVENUE CLOSURE

32 12 16 HOT-MIX ASPHALT (HMA) PAVING - 12TH AVENUE CLOSURE

32 13 13 CONCRETE PAVEMENTS, SLABS, SIDEWALKS, AND CURB AND GUTTERS

32 17 23 PAVEMENT MARKINGS

32 31 19 DECORATIVE METAL FENCES AND GATES - 12TH AVENUE CLOSURE

32 92 19 SEEDING

DIVISION 33 - UTILITIES

33 11 00 WATER UTILITY DISTRIBUTION PIPING - 12TH AVENUE CLOSURE

33 40 00 STORM DRAINAGE UTILITIES

33 46 16 SUBDRAINAGE PIPING - 12TH AVENUE CLOSURE

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 20 16 CLOSURE GATES

35 31 19 STONE PROTECTION

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 2 AMEND. 0002

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 73 05

SPECIAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 ADDITIONAL COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

1.4 UNANTICIPATED HAZARDOUS MATERIAL

1.5 COORDINATION WITH OTHERS

1.6 ANTITERRORISM (AT) AND OPERATIONS SECURITY (OPSEC)

1.6.1 E-Verify Program

1.7 ACTIVITY REGULATIONS FOR CONTRACTOR ACCESS AND USE OF PREMISES

1.8 EVALUATION OF SUBDIVIDED ITEMS

1.9 VARIATIONS IN ESTIMATED QUANTITIES - SUBDIVIDED ITEMS

1.10 SUSTAINABILITY

1.11 PERMITS

1.12 CONDITION OF EXISTING STRUCTURES, ROADWAYS, LEVEES, AND OTHER

FACILITIES

1.13 U.S. ARMY CORPS OF ENGINEERS SAFETY AND HEALTH MANUAL (EM 385-1-1)

1.14 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE

1.15 PROGRESS MEETINGS

1.16 INSPECTION

1.17 DAMAGE TO WORK

1.18 SPECIAL SAFETY REQUIREMENTS

1.19 LOCATION OF PARKING, STAGING, AND STORAGE AREAS

1.20 ELECTRICAL POWER LINES

1.21 BARRICADES AND WARNING SIGNS

1.22 ONE CALL SYSTEMS FOR EXCAVATORS

1.23 ADDITIONAL PHYSICAL DATA CLAUSE INFORMATION

1.24 DELAYS DUE TO HIGH WATER

1.24.1 12th Avenue Closure

1.24.2 Deleted

1.25 HIGH WATER ACTION PLAN

1.25.1 12th Avenue Closure

1.25.2 Deleted

1.26 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

1.27 IOWA SALES AND USE TAX EXEMPTION CERTIFICATE

1.28 PROCESSING DAVIS-BACON ACT CERTIFIED LABOR PAYROLLS

1.29 AVAILABILITY AND USE OF UTILITY SERVICES

1.30 WORKING IN THE VICINITY OF STRUCTURES AND UTILITY CROSSINGS

1.31 DELETED

1.32 ATTACHMENTS

PART 2 PRODUCTS

PART 3 EXECUTION

ATTACHMENTS:

DOCUMENT 00 73 05 Page 1 AMEND. 0002

08 APR 2022

ATTACHMENT A - Flood Contingency Plan Form

ATTACHMENT B - Cedar River Temporary Flood Mitigation System

ATTACHMENT C - Deleted

ATTACHMENT D - Iowa DNR Floodplain Development Permit and City of Cedar Rapids Floodplain Development Permit

ATTACHMENT E - Deleted

-- End of Section Table of Contents --

DOCUMENT 00 73 05 Page 2 AMEND. 0002

08 APR 2022

SECTION 00 73 05

SPECIAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EP 1110-1-8 (2016) Construction Equipment Ownership and Operating Expense Schedule

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1926.106 Working Over or Near Water

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Company Enrollment in E-Verify; G, SO

Form I-9; G, SO

**NOTE: To protect the privacy of the Contractor, all Contractor employees, and all subcontractor employee's security information, submit with a cover page stating the Contract Number (e.g., W912EK21CXXXX), Contract Title, and the Contractor's point of contact information in a sealed envelope/container and mail to:

Security and Law Enforcement Office U.S. Army Corps of Engineers Rock Island District 1500 Rock Island Drive Rock Island, Illinois 61201

Permits; G

Pre-Construction Condition Survey; G

High Water Action Plan; G

Structures and Utility Crossings Plan; G

SD-11 Closeout Submittals

DOCUMENT 00 73 05 Page 3 AMEND. 0002

Post-Construction Condition Survey; G

1.3 ADDITIONAL COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

In addition to the requirements of Contract Clause 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK, comply with the following requirements:

a. Complete Base Bid Phase 1 work no later than November 1, 2022. The closure of 12th Avenue to traffic as part of Base Bid Phase 2 work is prohibited prior to July 5, 2022. A maximum of five calendar days will be allowed for temporary adjustments to the City's trail detour to complete Phase 3 work, reference sheet GC100 in the Base Bid plan set for delineation of phases.

b. Clearing of trees or disturbance of areas where roosting occurs or is showing signs of or having nests occupied is prohibited when bald eagles or red-shouldered hawks are present in the area. There are active nest(s) near the Cedar Lake along the Cedar River. If any nesting activity is observed, construction activities within 660 feet of the nest will be prohibited. Nesting activity may be anticipated between 15 January and 01 July, however, these dates are not all inclusive. Coordinate with the U.S. Fish and Wildlife Service and Iowa Department of Natural Resources through the Contracting Officer prior to any tree cutting.

c. In accordance with the "Bald and Golden Eagle Protection Act" and "Migratory Bird Treaty Act," limit construction activity near bald eagle roosting sites during the winter months unless otherwise approved. Conduct operations in a manner that minimizes the disturbance to the bald eagles. The Bald Eagle Management Guidelines and Conservation Measures found at http://www.fws.gov/midwest/MidwestBird/EaglePermits/baeatakepermit.html may be used to determine what constitutes a disturbance and to find information on minimizing impact to bald eagles. May also contact the U.S. Fish and Wildlife Service or appropriate state Department of Natural Resources for assistance.

d. Clearing of trees equal to or greater than 3 inches with exfoliating bark, cracks, crevices, cavities, or peeling bark is prohibited between April 1 and September 30 inclusive (during the Northern Long-Eared Bat summer maternity season and during the Indiana Bat breeding and rearing season). Coordinate with the U.S. Fish and Wildlife Service and Iowa Department of Natural Resources through the Contracting Officer prior to any tree cutting.

1.4 UNANTICIPATED HAZARDOUS MATERIAL

If a hazardous material(s) is encountered where it was not indicated, stop work and immediately notify the Contracting Officer of the located potential hazardous material(s) found. Upon direction from the Contracting Officer, the Contractor may be required to conduct sampling and testing of these suspect material(s) in accordance with an Industrial Hygienist's recommended procedures and the Contract Specification Section(s) required that will be provided to the Contractor as a Modification to the Contract.

Payment for this additional work will be handled under the Contract Clause

52.243-4 CHANGES.

DOCUMENT 00 73 05 Page 4 AMEND. 0002

08 APR 2022

1.5 COORDINATION WITH OTHERS

Schedule and coordinate operations affecting other Contractors, Government Personnel, utilities, and/or property occurring within the work limits.

Accomplish with lead time sufficient for coordination of all involved parties as necessary for timely completion of each Contract feature. At a minimum, establish coordination with each of the following point(s) of contact, as required:

a. Area Engineer Central Area Office U.S. Army Corps of Engineers 1910 E. Kimberly Road, Suite 105 Davenport, IA 52807 Telephone No.: 563-386-0572 (Collect calls not accepted.)

b. Mediacom Telephone No.: 319-395-9699 (Collect calls not accepted.)

c. IMUA Telephone No.: 318-360-5122 (Collect calls not accepted.)

d. Century Link/TerraTech Telephone No.: 847-812-2247 (Collect calls not accepted.)

e. Fiber-Utilites/ICN Telephone No.: 319-558-7427 (Collect calls not accepted.)

f. MidAmerican Telephone No.: 319-289-5162 (Collect calls not accepted.)

g. Windstream Telephone No.: 319-538-1985 (Collect calls not accepted.)

h. Alliant Telephone No.: 319-786-1921 (Collect calls not accepted.)

i. ITC Midwest Telephone No.: 319-297-6762 Telephone No.: 319-297-6765 ITC-Field Supervisor Telephone No.: 641-328-9894 (Collect calls not accepted.)

j. Im On Telephone No.: 319-261-4689 (Collect calls not accepted.)

k. City of Cedar Rapids Telephone No.: 319-286-5027 (Collect calls not accepted.)

DOCUMENT 00 73 05 Page 5 AMEND. 0002

l. City of Cedar Rapids Water Department Telephone No.: 319-286-5999 Telephone No.: 319-286-5773 (Collect calls not accepted.)

m. City of Cedar Rapids Planning Engineer Department Telephone No.: 319-286-5745 (Collect calls not accepted.)

n. City of Cedar Rapids Development Services Department Telephone No.: 319-286-5363 (Collect calls not accepted.)

1.6 ANTITERRORISM (AT) AND OPERATIONS SECURITY (OPSEC)

1.6.1 E-Verify Program

Pre-screen candidates using the E-Verify Program website ( http://www.uscis.gov/e-verify) to meet the established employment eligibility requirements. Ensure that the candidate has two valid forms of Government-issued identification prior to enrollment to ensure the correct information is entered into the E-Verify system. Submit documentation of company enrollment in E-Verify, via a print screen of the company profile within the E-Verify system, to the Security Office no later than 3 business days after receiving the Notice to Proceed.

*When Contracts are with individuals, the individuals will be required to complete a Form I-9, give/coordinate Employment Eligibility Verification with the Contracting Officer. This Form will be provided to the Security Office after Notice to Proceed is received.

1.7 ACTIVITY REGULATIONS FOR CONTRACTOR ACCESS AND USE OF PREMISES

Follow all current Army Security Regulations concerning strict visitor control and preservation of all Government assets. Immediately report all security concerns to the Contracting Officer, who will notify the Security Office.

Work may be affected by the following Force Protection Conditions levels:

FPCON NORMAL

When there is no discernible terrorist activity. Routine security posture.

FPCON ALPHA

When there is a general threat of possible threat activity against personnel and the installation, or both. There will be a limited impact on normal operations.

FPCON BRAVO

When there is an increased or more predictable threat. There will be an impact on normal operations but it will not cause undue

DOCUMENT 00 73 05 Page 6 AMEND. 0002 hardship to personnel, substantially affect operational capabilities, or cause aggravated relations with local authorities and civilians.

FPCON CHARLIE

When an incident occurs or intelligence is received indicating imminent terrorist action. If this lasts for more than a short period it will probably create hardships for personnel and affect the peacetime activities of units and personnel.

FPCON DELTA

When a terrorist attack has occurred or intelligence indicates likely terrorist action against a specific location. This is normally declared as a localized warning and requires implementation of mandatory security measures. This cannot be sustained for an extended period without causing significant hardships for personnel and affecting the peacetime activities of units and personal.

FPCON NORMAL through FPCON BRAVO will not affect the work. FPCON CHARLIE and FPCON DELTA will affect work. FPCON CHARLIE will subject the Contractor to a higher degree of inspection and may not be able to work on-site for short periods of time as decreed by the District Security Officer. FPCON DELTA as determined by the District Security Officer will close the site down and the Contractor will not be able to work on the site.

1.8 EVALUATION OF SUBDIVIDED ITEMS

Bid Item Nos. 0032 and 0033 subdivided into two or more estimated quantities and separately priced. The Government will evaluate each of these items on the basis of total price of the subitems.

1.9 VARIATIONS IN ESTIMATED QUANTITIES - SUBDIVIDED ITEMS

This variation in estimated quantities clause is applicable only to Bid Item Nos. 0032 and 0033.

a. Variation from the estimated quantity in the actual work performed under any second or subsequent sub-item or elimination of all work under such a second or subsequent sub-item will not be the basis for an adjustment in Contract unit price.

b. Where the actual quantity of work performed for Bid Item Nos. 0032 and 0033 is less than 85 percent of the quantity of the first sub-item listed under such item, it will be paid at the Contract unit price for that sub-item for the actual quantity of work performed and, in addition, an equitable adjustment will be made in accordance with Contract Clause 52.211-18, VARIATION IN ESTIMATED QUANTITIES.

c. If the actual quantity of work performed under Bid Item Nos. 0032 and 0033 exceeds 115 percent or is less than 85 percent of the total estimated quantity of the sub-item under that item and/or if the quantity of the work performed under the second sub-item or…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .