About this file

This notice provides a draft performance work statement for an advanced contract initiative regional contracts for debris management services. Key details include:

  • The document requests industry feedback on a draft PWS for emergency debris removal services prior to final solicitation. Interested contractors should review and submit technical inquiries to ProjNet by July 19, 2018.

  • The services include all aspects of debris management from removal to final disposal as tasked by USACE districts for natural or man-made disasters within CONUS and its territories. Contractors must mobilize assets within 24 hours of a task order.

  • The contractor will provide personnel, equipment, planning, hazard assessments and an automated debris management system to track loads from origin to disposal. Services also include dumpsite management and reduction through mechanical means, burning or air curtain incineration.

  • The contract period of performance is five years with task orders issued on a fixed-price basis delineating specific work areas. Contract awards will guarantee a minimum of $10,000 over the life of each contract.

View the file

Other files

File Type Posted
AUTOMATED_DEBRIS_MANAGEMENT_SYSTEM.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NOTIFICATION TO INDUSTRY

DRAFT PERFORMANCE WORK STATEMENT (PWS) W912EK18R0022 FOR

ADVANCED CONTRACT INITIATIVE (ACI) REGIONAL CONTRACTS FOR

DEBRIS MANAGEMENT SERVICES (RCDMS)

This notice does not constitute a solicitation but rather an announcement for DRAFT PWS W912EK18R0022, Advanced Contract Initiative (ACI), Regional Contracts for Debris Management Services (RCDMS).

DISCLAIMER: This is a DRAFT PWS to obtain industry feedback for the emergency debris removal effort. The information provided in this notice is subject to change and is not binding on the Government. This notice DOES NOT constitute a Request for Proposal (RFP) and is not a commitment by the U.S. Government to procure subject services.

The purpose of this announcement is to provide DRAFT PWS W912EK18R0022, for emergency debris removal services. The intent of this DRAFT PWS is to provide all interested contractors the opportunity to review the DRAFT PWS prior to the release of the final solicitation at a later date.

The Rock Island District requests interested contractors review the DRAFT PWS to provide feedback using the Bidder Inquiry information as the instructions provide below:

Technical inquiries and questions relating to this PWS are to be submitted via Bidder Inquiry in ProjNet at (https://www.projnet.org) No Later Than (NLT) July 19, 2018 by 2:00pm CST.

To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment will receive an acknowledgement of their comment via email.

The Bidder Inquiry Key is: 8P53CB-QP4Z6Q Specific Instructions for ProjNet Bid Inquiry Access:

1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

2. Identify the Agency. This should be marked as USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. Email. Enter the email address you would like to use for communication.

5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret

Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.

7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

Specific Instructions for Future ProjNet Bid Inquiry Access:

1. For future access to ProjNet, you will not be provided any type of password. You will utilize your Secret Question and Secret Answer to log in.

2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

3. Identify the Agency. This should be marked as USACE.

4. Key. Enter the Bidder Inquiry Key listed above.

5. Email. Enter the email address you used to register previously in ProjNet.

6. Click Continue. A page will then open asking you to enter the answer to your Secret

Question.

7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

The Government will NOT provide a response to the comments. However, the comment will be considered and will be reflected in the final solicitation, if applicable.

No funds are available to pay for preparation of responses to this notification. Any information submitted by respondents is strictly voluntary. No basis for a claim against the Government shall arise as a result from a response to this announcement.

Response to this notice is strictly voluntary. The Government will not reimburse any party attending or participating for costs incurred for this event or marketing efforts.

DISCLOSURE NOTIFICATION AND PROCEDURES

Do not submit proprietary information. Any information provided will not be held in confidence and may be incorporated into the design of the Project. Information submitted in response to this notice is subject to disclosure under the Freedom of Information Act.

Respondents are advised that the Government is under no obligation to acknowledge or provide feedback with respect to any information submitted under this notice. Any information whether written or oral, provided by a contractor will not be considered confidential and may be incorporated into the Project.

SEE ADDENDUM

(No Collect Calls)

W912EK18R0022

b. TELEPHONE NUMBER

309-794-XXXX

8. OFFER DUE DATE/LOCAL TIME

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA ARE

26. TOTAL AWARD AMOUNT (For Govt. Use Only)

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W912EK 9. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

SALLY A. DUNCAN

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

PAGE 1 OF

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR: SET ASIDE: UNRESTRICTED OR X

SMALL BUSINESS

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

CONTRACTING DIVISION

US ARMY CORPS OF ENGINEERS

1500 ROCK ISLAND DRIVE

ROCK ISLAND IL 61201

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A 13b. RATING

CODE 15. DELIVER TO CODE 16. ADMINISTERED BY

SEE SCHEDULE

12. DISCOUNT TERMS 11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFP X

--- --- ---- REF BLOCK 18A) FAX:

TEL: 309-794-xxxx (INVOICES SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

8(A)

HUBZONE SMALL

BUSINESS

SIZE STANDARD:

$38,500,000

NAICS:

562119

X

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICES ITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24. 22. 21. 19.

WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT 41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

Section B - Supplies or Services and Prices

SCHEDULE OF PRICES

SECTION B – Supplies or Services and Prices

The Contractor shall furnish all plant, labor, material, equipment, etc., necessary to perform all work in strict accordance with the terms and conditions set forth in the contract to include all attachments thereto.

The contract’s performance period shall begin upon contract award and proceed for five years. Each awarded contract will have a minimum guarantee of $10,000.00 over the life of the contract.

The rates shall be fully burdened with indirect cost and profit. All rates shall be binding and must be honored during the period of this contract on any resulting Firm Fixed Price task orders. This contract allows the Government to issue task orders as Firm Fixed Price. The schedule requires the offeror to propose binding rates for each Firm Fixed Price task order. Escalation rates shall be included in this offer to allow for “cost of doing business increases” during the years following the year of contract award. Escalation rates will be evaluated for price reasonableness.

Proposed Division:

Escalation Rate for Year 2:________________ Escalation Rate for Year 3:________________ Escalation Rate for Year 4:________________ Escalation Rate for Year 5:________________

Offerors shall provide a separate Schedule of Prices for each Proposed Region.

Further, if the proposed Region has a reach back assignment, the offeror shall include a Schedule of Prices for that assigned reach back Region. See Section F for reach back regions.

These prices will be contractually binding and cover each contract line item included in Section B of the solicitation.

The quantities in Section B represent a year of performance. Therefore, the Government will escalate the rates in accordance with proposals and evaluate the price offered over the life of the contract.

SUBCLIN Location Description Estimated Quantity

Unit Unit Price Amount

0001AA Operations Manager 84 Hour

0001AB Operations Planner 84 Hour

0001AC Environmental Health & Safety Manager

84 Hour

0001 AD QC Manager 84 Hour

0001AD Validate and Certify Automated Debris Management System (ADMS)

1 Each (EA)

0001 AE Management Team Training and Exercise

1 Each (EA)

0002AA Automated Debris Management System (ADMS) up to 500,000 CY

500,000 Cubic Yard

(CY)

0002AB Automated Debris Management System (ADMS) over 500,000 CY

2,500,000 CY

Debris Removal from Public Roads, Streets and ROWs And Hauling to Debris Management or Final Disposal Sites (Vegetative )

0002AC Urban Sector Hauling Distance 0-15 miles

560,000 CY

0002AD Urban Sector Hauling Distance 16-30 miles

40,000 CY

0002AE Urban Sector Hauling Distance 31-60 miles

4,000 CY

0002AF Non-Urban Sector Hauling Distance 0-15 miles

1,100,000 CY

0002AG Non-Urban Sector Hauling Distance 16-30 miles

60,000 CY

0002AH Non-Urban Sector Hauling Distance 31-60 miles

6,000 CY

Debris Removal from Public Roads, Streets and ROWs And Hauling to Debris Management or Final Disposal Sites (C&D)

0002AI Urban Sector Hauling Distance 0-15 miles

160,000 CY

0002AJ Urban Sector Hauling Distance 16-30 miles

80,000 CY

0002AK Urban Sector Hauling Distance 31-60 miles

8,000 CY

0002AL Non-Urban Sector Hauling Distance 0-15 miles

240,000 CY

0002AM Non-Urban Sector Hauling Distance 16-30 miles

120,000 CY

0002AN Non-Urban Sector Hauling Distance 31-60 miles

12,000 CY

Vegetative Debris Reduction at Debris Management Sites includes site management

0002AO Urban Sector Site Debris Reduction - Mechanical (chipping or grinding)

500,000 CY

0002AP Non-Urban Sector Site Debris Reduction - Mechanical (chipping or grinding)

400,000 CY

0002AQ Urban Sector Site Debris Reduction – Air Curtain Incineration

100,000 CY

0002AR Non-Urban Sector Site Debris Reduction – Air Curtain Incineration

800,000 CY

Final Disposal of Reduced Chips

0002AS From Urban Sector Site Hauling Distance 0-15 miles

100,000 CY

0002AT From Urban Sector Site Hauling Distance 16-30 miles

40,000 CY

0002AU From Urban Sector Site Hauling Distance 31-60 miles

10,000 CY

0002AV From Non-Urban Sector Site Hauling Distance 0-15 miles

80,000 CY

0002AW From Non-Urban Sector Site Hauling Distance 16- 30 miles

30,000 CY

0002AX From Non-Urban Sector Site Hauling Distance 31- 60 miles

10,000 CY

Testing of Ash and Disposal at Landfill

0002AY From Urban Sector Site Hauling Distance 0-15 miles

5,000 CY

0002AZ From Urban Sector Site Hauling Distance 16-30 miles

2,000 CY

0002BA From Urban Sector Site Hauling Distance 31-60 miles

1,000 CY

0002BB From Non-Urban Sector Site Hauling Distance 0-15 miles

40,000 CY

0002BC From Non-Urban Sector Site Hauling Distance 16- 30 miles

7,500 CY

0002BD From Non-Urban Sector Site Hauling Distance 31- 60 miles

2,500 CY

Removal of Freon Containing White Goods (Refrigerators, Freezers, Air Conditioners, etc.) includes Freon removal

0002BE Urban Sector Freon White Goods, 0-15 miles

2,000 Each (EA)

0002BF Urban Sector Freon White Goods, 16-30 miles

200 EA

0002BG Urban Sector Freon White Goods, 31-60 miles

10 EA

0002BH Non-Urban Sector Freon White Goods, 0-15 miles

700 EA

0002BI Non-Urban Sector Freon White Goods, 16-30 mile

100 EA

0002BJ Non-Urban Sector Freon White Goods, 31-60 mile

50 EA

Removal of Non-Freon Containing White Goods (Washers, Dryers, Water Heaters, Stoves, etc.)

0002BK Urban Sector Non-Freon White Goods, 0-15 miles

4,000 EA

0002BL Urban Sector Non-Freon White Goods, 16-30 miles

400 EA

0002BM Urban Sector Non-Freon White Goods, 31-60 miles

20 EA

0002BN Non-Urban Sector Non-Freon White Goods, 0-15 miles

1,500 EA

0002BO Non-Urban Sector Non- Freon White Goods, 16-30 mile

200 EA

0002BP Non Urban Sector Non-Freon White Goods, 31-60 mile

100 EA

0002BQ Inspection Tower 10 EA

0002BR Hazardous Waste Containment Area

4,000 Square Foot

0002BS Household Hazardous Waste Separation and removal Crew

30 Crew Day

0002BT Debris Separation Crew 30 Crew Day

0002BU Search and Rescue Support Crew

20 Crew Day

0002BV Emergency road clearance Crew

30 Crew Day

0002BW HTRW Separation Crew TBN Crew Day TBN TBN

0002BX RACM

0002BY Mobilization and Demobilization

TBN EA TBN TBN

TOTAL

Bid Schedule Notes:

1. If mobilization and demobilization pricing is identified in the task order and unless otherwise specified in the task order, the Contractor will be entitled to invoice for 60% of the mobilization and demobilization line item after all equipment is delivered to the designated work site. The remaining 40% will be due after all equipment is removed from the work site, all vehicle signs have been returned to the government and the Contracting Officer has received a proper invoice.

TBN means to be negotiated on the task order.

2. The Quality Control Program, and all costs associated therewith shall be included in the applicable unit prices.

3. All costs associated with ADMS execution shall be included in the applicable unit prices shown in the bid schedule items numbered 0002AA and 0002AB.

4. “Urban Sector” as used in this Bid Schedule is defined as an operationally designated sector as approved by the Contracting Officer within a geographic area containing a population density of at least 1000 people per square mile. Example of an Urban Sector: The operational “Sector” approved by the Contracting Officer is the entire City of Montgomery, AL. Using the 2006 population of 202,000 divided by the land area of 158.38 sq. mi. = 1300 people per square mile.

5. Crew Day unit of measure refers to a 12-hour day for a typical crew as defined in Section C of this solicitation.

6. Mileage will be rounded down to the whole mile and from point of Origin to the disposal site tower as determined by ADMS specifications.

U.S. ARMY CORPS OF ENGINEERS

ADVANCED CONTRACTING INITIATIVE, DEBRIS MANAGEMENT

PERFORMANCE WORK STATEMENT

TABLE OF CONTENTS

PART 1 - GENERAL INFORMATION

PART 2 - DEFINITIONS & ACRONYMS

PART 3 - SPECIFIC TASKS

PART 4 - ATTACHMENT / TECHNICAL EXHIBIT LISTING

Attachment 1 – Typical Truck / Trailer Measurement Form

Attachment 2 – Management / Operations Plan Minimum Requirements

Attachment 3 – Contractor Quality Control Specifications

Attachment 4 – Automated Debris Management System

Attachment 5 – Wage Determination Link

Attachment 6 – Report Requirements

Attachment 7 – Site Management Plan

PART 1

GENERAL

NFORMATION

The purpose of this contract is to provide debris removal after any natural or man-made disaster or catastrophe in which the remediation has been assigned to USACE.

1.1 Description of Services: The contractor shall provide all personnel, equipment, tools, materials, supervision, other items, and personnel necessary to perform debris removal services as defined in this Performance Work Statement (PWS) except as specified as government-furnished property and services. The contractor shall perform to the standards in this contract. To meet this requirement, all USACE assets, to include the contractor, must be able to mobilize and respond within 24 hours.

This is a non-personal services contract for managing disaster generated debris after any natural or man-made catastrophe or major disaster supported by the U.S. Army Corps of Engineers (USACE). The Government shall neither supervise contractor employees nor control the method by which the contractor performs the required tasks. Under no circumstances shall the Government assign tasks to, or prepare work schedules for, individual contractor employees. It shall be the responsibility of the contractor to manage its employees and to guard against any actions that are of the nature of personal services, or give the perception of personal services. If the contractor believes that any actions constitute, or are perceived to constitute personal services, it shall be the contractor's responsibility to notify the Procuring Contracting Officer (PCO) immediately.

1.2 Background: The required work shall include clearing and removing disaster generated debris.

Tasks will normally include: (1) separating debris, (2) loading the debris, (3) hauling the debris to an approved dumpsite, or (4) dumping the debris at a debris reduction site or as directed by the Contracting Officer (KO). When necessary, other materials such as sediment, storm surge over-wash materials, land slide materials, flood fight materials and other obstructions may be removed as directed by the KO. Curbside separation of debris may be required prior to removal when not previously accomplished by property owners, as directed by the KO. Typical separation categories include household garbage, construction debris, vegetative debris, household hazardous wastes, and regulated asbestos containing materials (RACM), white goods, and electronics. The contractor shall, whenever possible and efficient, process eligible debris for beneficial re-use and / or recycling of the material.

1.3 Objectives: The purpose of this PWS is to specify the requirements for managing disaster generated debris after any natural or man-made catastrophe or major disaster supported by USACE. This contract is an Indefinite Delivery/Indefinite Quantity (IDIQ) contract. The Government will issue task orders on a fixed price basis. The project locations will be designated in the task orders. The Government reserves the right to make multiple awards off a single solicitation and the right to award the scope of work in partial, if required. Each contract award will be for a pre-defined geographic region as detailed in Section F, Deliverables. It is important to note, that the Government may utilize contracts from outside the awarded, geographic region, if needed. Further, the Government may utilize this contract anywhere within the United States or its territories by bi-lateral modification of the contract.

1.4 Scope: Debris management services may be provided within the geographical boundaries of all USACE districts and their mission assignments which includes the continental United States (CONUS) and its territories and commonwealths. The contractor shall, unless otherwise directed by the KO, manage disaster generated debris from the point of origin to final disposal. All actions and processes used shall be in full compliance with all applicable local, state, and Federal policies, regulations, and laws. All debris management work shall be accomplished in the most efficient and effective manner appropriate for the applicable waste stream(s) in accordance with the performance work statement.

Other debris related mission specific requirements and/or tasks not specifically covered in the Schedule of Prices can be negotiated at the task order level.

1.5 Period of Performance: The contract period of performance will be 5 years with no options.

1.6 Mission Flow: The following is a standard mission flow to explain how FEMA, the state/territory/commonwealth, USACE and the contractor interrelate to execute an emergency debris removal mission. This section is not meant to be all inclusive as to every aspect of the emergency debris removal mission, but is intended to explain most of the process and how the various entities interrelate.

For “Notice” events (examples include hurricanes and ice storms), FEMA Regions may mobilize Federal assets into a state/territory/commonwealth in preparation of a potential disaster. Under this type of declaration, FEMA tasks USACE to mobilize resources, including the contractor, into an area in preparation to respond to a forecasted disaster. The KO shall issue a Not-to-Exceed (NTE) task order to the contractor for mobilization of agreed upon assets (personnel and/or equipment) to the pre-defined staging area. Under Pre-Disaster Declaration, Federal assets are not provided to the state/territory/commonwealth. This is FEMA’s opportunity to best align and prepare for response to the pending disaster.

Once an event (man-made or natural) is declared a “Disaster” by the President (this includes an Emergency Declaration or Major Disaster Declaration), FEMA is authorized to provide assistance to the impacted state/territory/commonwealth. FEMA will stand-up the Joint Field Office (JFO) in the capital city of the impacted state/territory/commonwealth from which to manage and execute the response and recovery efforts. All response and recovery efforts will be managed/executed from the JFO. The impacted state/territory/commonwealth will provide, via their own emergency management process, requests to FEMA. Once the validity of the request has been confirmed by FEMA, FEMA passes the request to the Action Officer (AO) located at the JFO. The requests are then forwarded to the Planning Response Team (PRT) located at a staging area. The staging area is located as close to the impacted area as possible and is where most of the personnel involved in the Mission Execution Phase of this PWS are located, including the contractor and all support personnel and equipment.

Once all debris has been removed and additional requests for emergency debris removal are not anticipated, the contractor will complete the de-mobilization process.

The ACI Debris contract can be utilized for other Federal response requirements. Examples of contract utilization include, assist EPA with hazardous waste type mission, or USDA for animal carcass removal. This is just an example of usage. The ACI Debris contracts can also be utilized for non-Stafford Act missions.

1.7 General Information: Disaster generated debris is defined as materials originating from the effects of any natural or man-made catastrophe or major disaster. Materials included are of both man-made and natural origins, and may include hazardous/toxic/radiological wastes (HTRW) and household hazardous waste (HHW). Man-made debris, construction/demolition (C&D) materials includes, but is not limited to, lumber, concrete, asphalt, masonry, metals, regulated asbestos containing material, and plastics. Debris of natural origins includes, but is not limited to, all vegetative debris (grass, shrubs, stumps, and trees, including trees on houses when specified by task order) and earthen materials or storm surge materials (clay, sand, gravel, rock, residual solids), waterway debris, and earth collected with the debris while loading trucks.

Debris may also include electronic wastes, appliances, vehicles, putrefied foods, flood fight materials, vessels, and dead animals. Removing materials such as sediment, storm surge over-wash materials, land slide materials, and other obstructions may be necessary to access disaster generated debris or to prepare the worksite for debris management work. Screening and sorting may be required to separate debris waste streams for processing or to remove earthen material prior to reduction.

1.7.1 Hours of Operation: Unless otherwise directed by the KO, the contractor shall work during daylight hours only, 7 days per week. The contractor shall maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential.

1.7.2 Quality Assurance (QA): The Government shall evaluate the contractor's performance under this contract in accordance with (IAW) the quality assurance surveillance plan (QASP).

This plan is primarily focused on what the Government must do to ensure the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rates.

1.7.3 Quality Control (QC): The contractor shall develop and maintain an effective QC program to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. As a minimum, the contractor shall develop QC procedures addressing the areas identified in the "Performance Requirements Summary." See Section 3.8.3 for submittal requirements. After acceptance of the QC plan, the contractor shall receive the KO's acceptance in writing of any proposed change to the QC plan.

1.7.4 Post Award Conference/Periodic Progress Meetings: The contractor agrees to attend any post award conference convened by the contracting activity or contract administration office. The KO, COR, and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the KO will apprise the contractor of how the government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.

1.7.5 Contracting Officer's Representative: The COR will be identified by separate letter for each individual task order. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is authorized to perform the following functions: assure that the contractor performs the technical requirements of the contract; perform inspections necessary in connection with contract performance; maintain written and oral communications with the contractor concerning technical aspects of the contract; issue written interpretations of technical requirements, including Government drawings, designs, specifications; monitor contractor's performance and notifies both the KO and contractor of any deficiencies; coordinate availability of Government furnished property, and provide site entry of contractor personnel. A letter of designation issued to the COR states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting contract. A copy of this designation letter will be provided to the contractor.

1.7.6 Contractor’s 24-Hour Emergency Contact: The contractor shall provide to the KO a list of personnel available 24 hours a day in the event a requirement for contract performance arises after regular working hours. At a minimum, this list will include personnel names, day and evening phone numbers (land and cellular, pager number), and e-mail addresses. The primary point of contact (POC) shall be clearly identified on the list. The standard for responding by voice communications shall be within 30 minutes. After issuance of a task order, the contractor shall maintain a task order specific personnel roster that is updated and submitted on a daily basis to the KO and COR. This ensures streamlined communications between the contractor and the

KO.

1.7.7 Identification of Contractor Employees: The contractor shall be responsible for furnishing an identification badge to all personnel (contractor and sub-contractors) prior to the employee working on-site. The contractor shall be responsible to ensure each employee engaged in the work displays identification. Identification shall consist of badges that include the name of the contractor or subcontractor, identification of working on this contract (i.e.

contract number), and the employee's name. At a minimum, a valid state driver's license or other Government-issued photo identification card is required for positive identification. All contract personnel attending meetings, answering Government telephones, and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. They must also ensure that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed.

1.7.8 Business Relations: The contractor shall successfully integrate and coordinate all activity needed to execute the requirement. The contractor shall manage the timeliness, completeness, and quality of problem identification. The contractor shall provide corrective action plans, proposal submittals, timely identification of issues, and effective management of subcontractors. The contractor shall seek to ensure customer satisfaction and professional and ethical behavior of all contractor personnel.

1.7.9 Personnel Administration: The contractor shall provide the management and support as required. The contractor shall provide for employees during designated Government non-work days or other periods where Government offices are closed due to weather or security conditions. The contractor shall maintain the currency of their employees by providing initial and refresher training as required to meet the PWS requirements. The contractor shall make necessary travel arrangements for employees. The contractor shall provide necessary equipment and personnel to support contract tasks. The contractor shall provide administrative support to employees in a timely fashion (time keeping, leave processing, pay, emergency needs).

1.7.10 Contract Management: The contractor shall establish clear organizational lines of authority and responsibility to ensure effective management of the resources assigned to the requirement. The contractor must maintain continuity between the support operations at the emergency debris removal site and the contractor's corporate offices.

1.7.11 Contract Administration: The contractor shall establish processes and assign appropriate resources to effectively administer the requirement. The contractor shall respond to Government requests for contractual actions in a timely fashion. The contractor shall have a single POC between the Government and contractor personnel assigned to support contracts or task orders. The contractor shall assign work effort and maintaining proper and accurate time keeping records of personnel assigned to work on the requirement.

1.7.12 Contractor Travel: Travel costs shall be included in the existing schedule of prices.

Travel will not be reimbursed as a separate cost.

1.7.13 Subcontract Management: The contractor shall provide to the KO a current and comprehensive list of all subcontractors at each tier below the prime with updated lists as conditions change. The prime contractor is responsible for payment of all subcontractors, and funds will be withheld from the prime contractor as is necessary to ensure payment of subcontractors.

1.7.14 Organizational Conflict of Interest (OCI): The contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCI. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may affect other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.

1.7.15 Measurement and Payment: The contractor will be paid based upon schedule of prices as specified in the task order. Debris removal will be paid to the nearest yard as validated by the KO or COR. Task order payments will be in accordance with Section B, Schedule of Prices and the appropriate payments clause list in Section I.

1.8 Security Requirements:

1.8.1 AT Level I Training. All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, controlled access areas, or require network access, shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the KO (if a COR is not assigned), within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: http://jko.jten.mil/courses/atl1/launch.html.

1.8.2 Access and General Protection/Security Policy and Procedures. All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DoD, Headquarters Department of Army and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition at any installation or facility change, the Government may require changes in contractor security matters or processes.

1.8.3 Contractors Requiring Common Access Card (CAC): Before CAC issuance, the contractor employee requires, at a minimum, a favorably adjudicated National Agency Check with Inquiries (NACI) or an equivalent or higher investigation in accordance with Army Directive 2014-05 and Homeland Security Presidential Directive-12. The contractor and all sub-contractors employees will be issued a CAC only if duties involve one of the following: (1) Both physical access to a DoD facility and access, via logon, to DoD networks on-site or remotely; (2) Remote access, via logon, to a DoD network using DoD-approved remote access procedures; or (3) Physical access to multiple DoD facilities or multiple non-DoD federally controlled facilities on behalf of the DoD on a recurring basis for a period of 6 months or more. At the discretion of the sponsoring activity, an interim CAC may be issued based on a favorable review of the FBI fingerprint check and a successfully scheduled NACI at the Office of Personnel Management.

1.8.4 Suspicious Activity Reporting Training: The contractor and all associated sub-contractors shall receive a brief/training on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity.

This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR not later than (NLT) 5 calendar days after the completion of the training.

1.8.5 Pre-screen candidates using E-Verify Program: The contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR NLT 3 business days after the initial contract award. *When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the KO and shall become part of the official contract file.

PART 2

DEFINITIONS & ACRONYMS

2.1 DEFINITIONS:

2.1.1. Contracting Officer Representative (COR). An employee of the U.S. Government appointed by the KO to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

2.1.2. CREW DAY. Unit of measure refers to a 12-hour day for typical crew.

2.1.3. Contracting Officer (KO). A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. The KO is the only individual who can legally bind the Government.

2.1.4. DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.

2.1.5. DELIVERABLE. Anything that can be physically delivered, but may include non‐ manufactured things such as meeting minutes or reports.

2.1.6. PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.

2.1.7. PRE-EXECUTION PHASE. The timeframe before a disaster occurs but after the disaster has been forecasted. If the nature of the disaster allows (hurricane tracking to a precise area), specific event planning may occur during the time approximately seven (7) days before an anticipated event, i.e. a hurricane. As the storm threatens a particular region, the SATOC contractors, will assist in the planning.

2.1.8. QASP. An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.9. QA. The Government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.10. QC. All necessary measures taken by the contractor to assure that the quality of an end product or service shall meet contract requirements.

2.1.11. SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.2 ACRONYMS:

AFAR Army Federal Acquisition Regulation Supplement AO Action Officer APP Accident Prevention Plan CAC Common Access Card C&D Construction / Demolition CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer Representative CY Cubic Yards DFARS Defense Federal Acquisition Regulation Supplement DOD Department of Defense EPA Environmental Protection Agency FAR Federal Acquisition Regulation FEMA Federal Emergency Management Agency FP Force Protection GDA Government Designated Authority GIS Geographic Information System GPS Global Positioning System HHW Household Hazardous Waste HTRW Hazardous/Toxic/Radiological Wastes IDIQ Indefinite Delivery Indefinite Quantity JFO Joint Field Office JTR Joint Travel Regulations KO Contracting Officer NLT No Later Than NTE Not to Exceed NTP Notice to Proceed OCI Organizational Conflicts of Interest OCONUS Outside the Continental United States PCO Procuring Contracting Officer PRT Planning Response Team POC Point of Contact PWS Performance Work Statement QA Quality Assurance QASP Quality Assurance Surveillance Plan QC Quality Control RACM Regulated Asbestos Containing Materials ROE Right-of- Entry ROW Right-of-Way TBN To Be Negotiated USACE U.S. Army Corps of Engineers

PART 3

SPECIFIC TASKS

3.1 Task Orders. All Government directed phases of work shall be accomplished at the direction of the KO through the issuance of a task order. Each task order will be issued as a “NTE” dollar value. There are instances where the Government will have the contractor adjust the assets initially deployed.

The KO will provide instructions on the commencement of work which will be authorized by Notice to Proceed (NTP).

3.2 Training and Preparedness. If requested by USACE, the contractor shall participate in training exercises. The responsibilities of the contractor will be to participate in a training exercise between the contractor and other local, state and federal stakeholders. Preparedness training shall be a target of 5 days per training exercise. The target number of training exercises will be one per calendar year. The contractor shall mobilize the Pre-Execution Planning Team, which consists of, (1) Operations Manager, (2) Operations Planner, (3) Environmental Health and Safety Manager, and (4) CQC Systems Manager, in order to participate in a training exercise.

3.3 Pre-Execution Phase. Upon notification by the KO, the contractor shall mobilize and deploy a

Pre-Execution Planning Team consisting of the members identified in paragraph 3.2. The team shall deploy to a location designated by the KO arriving within 24 hours of notification. The Government POC for the team, if not otherwise designated in the task order, will be the USACE

COR.

The Pre-Execution Planning Team shall function as part of an interagency debris planning team.

The Pre-Execution Planning Team will provide technical assistance which may include (but not limited to) the following tasks:

(1) Evaluation of the disaster area for efficient debris management

(2) Estimation of debris volumes,

(3) Sectoring disaster area for most efficient debris management,

(4) Locating temporary debris storage and reduction sites and disposal sites,

(5) Determining personnel and equipment resources (crews) required,

(6) Performing environmental health and safety evaluations

(7) Evaluating requirements to implement an automated debris management system. Decision authority remains with the Government. The contractor’s Pre- Execution Planning Team serves in an advisory capacity.

3.4 Execution Phase - Debris Removal Tasks. The contractor shall provide all labor, equipment, materials and services for all debris management operations which includes, but not limited to, emergency debris clearance, separation, removal, hauling, disposal, recycling, structural demolition on public, commercial, or private property, dumpsite management, and debris reduction operation.

3.4.1 The Operations Manager and team elements shall report to the USACE Debris COR within

24 hours of NTP unless otherwise directed by the KO. The contractor shall provide a minimum of 5 crews to commence debris removal operations within 24 hours of issuance of task order

NTP.

3.4.2 The contractor shall supervise and direct the work using skilled labor and proper equipment for all tasks. Safety of the contractors and subcontractor’s personnel and equipment is the responsibility of the contractor. Additionally, the contractor shall pay for all materials, personnel, taxes, and fees necessary to perform under the terms of this contract.

3.4.3 The contractor shall be duly licensed to perform the work in accordance with the statutory requirement of the affected state/territory/commonwealth. After award of base contract, provide proof of license to work in states within region awarded.

3.4.4 If required, the contractor shall obtain all applicable permits necessary to complete all

CONUS and OCONUS work. The contractor shall be responsible for determining what permits are necessary to perform under the contract. Copies of all permits shall be submitted to the KO prior to commencement of work.

3.4.5 If required, the contractor shall obtain all applicable Rights of Entry (ROE) for work to be performed in the affected area(s) to include Temporary Disposal/Staging areas. Copies of all ROE(s) shall be submitted to the KO prior to access and usage of property.

3.4.6 The contractor shall be responsible for correcting any notices of violations issued as a result of the Contractor’s or any subcontractor’s actions or operations during the performance of the contract.

3.4.7 The contractor shall be responsible for control of pedestrian and vehicular traffic in all work areas. All applicable laws, regulations, policies and USACE EM 385-1-1 requirements apply.

3.4.8 The contractor shall conduct the work so as not to interfere with other disaster response and recovery activities of federal, state, and local governments or agencies, or of any public utilities.

The contractor may be assigned to support other disaster and recovery activities.

3.4.9 The contractor shall not move from one designated work area to another designated work area without prior approval from the KO.

3.4.10 There will be no demolition, or removal of debris from private property without approval from the KO and a legally executed ROE agreement.

3.4.11 The contractor shall, when requested, participate within the Inter-Agency Debris

Management Task Force.

(This is a repeat of 3.4.8 above.)

3.4.12 Unless otherwise directed by the Contracting Officer, the Contractor shall work during daylight hours only, 7 days per week to accomplish emergency debris clearance, separation, removal, hauling, and structural demolition on public commercial, or private property.

3.4.13 The Contractor shall use only designated debris dumpsites including temporary debris storage and reduction sites (TDSR) as approved by the government.

3.4.14 All dumping operations at commercial landfills shall be directed by the landfill operator.

The Contractor shall cooperate with the landfill operator to facilitate effective dumping operations.

3.4.15 The contractor shall be responsible for final disposal of non-burnable debris and ash residue either through landfill operations or recycling/beneficial use. Tipping fees shall be reimbursed by the Government. Disposal of non-burnable debris and ash residue shall be made in accordance with current state, federal, and local regulations. Contractor shall return the reduction site to original conditions upon completion of reduction activities. This requirement includes post use environmental testing.

3.4.16 The Contractor shall construct all necessary and appropriate reduction sites, managing the operation of the reduction sites, performing debris reduction by burning, air curtain incineration and/or reduction by mechanical means using chippers, grinders, shredders as specified in the task order, separation of debris, and final debris disposal. This requirement includes baseline environmental testing.

3.4.17 The storage area and processing area for the debris reduction operation shall be approved by the Contracting Officer based upon the site opportunities and constraints. All proposed temporary debris storage and reduction sites (TDSR) and final disposal sites shall be approved by the Contracting Officer prior to Contractor use.

3.4.18 When included in a task order, the Contractor shall install an inspection tower for each

Reduction Site, Disposal Site, and all Temporary Debris Storage and Reduction (TDSR) sites.

Inspection Towers shall be designed and constructed to meet all applicable safety standards, withstand a 45mph wind load, provide adequate height to enable inspectors to view over the protective railing down into loaded debris hauling containers, and have a minimum covered working area of 8 feet X 12 feet. The design for the inspection tower must be certified by an engineer and construction must be consistent with the design. Inspection towers shall be installed on a level pad and protected from vehicle traffic. Inspection towers shall be supplied with adequate lighting and power, and work space furnishings, necessary to support tower operations.

This bid item includes all labor and materials costs associated with the design, installation, and supply of the inspection tower.

3.4.19 Hauling operations shall not be allowed into any reduction site, disposal site, or TDSR until an inspection tower is provided. A temporary mechanical lift may be used until a fixed tower can be constructed as approved by the Contracting Officer.

3.4.20 When included in a task order, the Contractor shall construct a…