BID SUMMARY SHEET

W912EK-11-B-0004 Chichaqua Wetland Mitigation Project, South Skunk River, Polk County, Iowa

FOUR AMENDMENTS

IFB NO: W912EK-11-B-0004

DATE: March 2, 2011

TIME: 2:00 PM

PLACE: Clock Tower Bldg.

NO: BIDDER & ADDRESS AMOUNT AMENDMENTS BID BOND

1. DS Contract Services, Inc. $331,327.07 X X Des Moines, IA

2. McHugh Excavating & Plumbing $475,578.50 X X Onalaska, WI

3. Next Phase Environmental, Inc. $524,227.90 X X Underwood, IA

4. Earthwerks Land Improvement & $246,580.00 X X

Development Corporation Batavia, IL

5. Aspen Construction Co. $407,775.32 X X

Hackensack, MN

6. Gator Excavating, Inc. $570,331.60 X X Grimes, IA

GOVERNMENT ESTIMATE: $318,847.19