Amendment 0002 W912EF22R0015 McNary DUE System Rehab.pdf
PDF 408 KB Posted
- Solicitation number
- W912EF22R0015
About this file
This solicitation requests offers for the McNary Drainage, Unwatering, and Equalization System Rehabilitation project. The scope of work includes removing, rebuilding, and reinstalling existing unwatering pumps with material and equipment upgrades. Offerors must demonstrate experience with similar industrial mechanical and electrical installation projects. The evaluation will consider technical experience, schedule, past performance, and small business participation. The contract type will be firm-fixed price. The solicitation includes submittal requirements, evaluation criteria, and instructions for the technical proposal and price proposal volumes. The closing date for offers is specified in block 13 of the SF1442 form.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to incorporate the changes outlined below .
1. CONTRACT ID CODE PAGE OF PAGES
1 14
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 19-Sep-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EF22R0015
X 9B. DATED (SEE ITEM 11)
18-Aug-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
19-Sep-2022
CODE
USAED, WALLA WALLA - CONTRACTING DIV.
HILLARY A. MORGAN
201 N. THIRD AVENUE
WALLA WALLA WA 99362
W912EF 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912EF22R0015
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Summary of changes for Amend - 0002
McNary Powerhouse Drainage, Unwatering, and Equalization System Rehabilitation
• Revised the following Specifications (See revised specification for details):
a. SECTION 22 11 00.01 28 PIPING AND VALVES
• Revised Paragraph 2.2.1 "Resilient Seat Wedge Gate Isolation Valves".
b. SECTION 43 23 31.13 28 POWERHOUSE UNWATERING PUMPS
• Revised Paragraph 2.1.2 "Existing Equipment".
• Revised the following solicitation sections:
a. SECTION 00 21 00 - INSTRUCTIONS
i. B. FACTORS TO BE EVALUATED, paragraph "3. Factor 2 Schedule".
See Yellow Highlights
SECTION 00 21 00 - INSTRUCTIONS
The following have been modified:
A. BASIS FOR AWARD
The award will be made based on the best overall (i.e., best value-tradeoff) proposal that is determined to be the most beneficial to the Government, based on an integrated assessment, with appropriate consideration given to the five (5) evaluation factors: Technical Experience; Schedule; Past Performance; Small Business Participation; and Price.
Factor 1, Technical Experience is more important than Factor 2, Schedule, Factor 3, Past Performance, and Factor 4, Small Business Participation. Factor 2, Schedule is equally as important as Factor 3, Past Performance and both are more important than Factor 4, Small Business Participation. When combined, the non-price factors (Factors 1, 2, 3, and 4) are significantly more important than Factor 5, Price.
The following paragraphs B through E cover the Factors to be evaluated, the evaluation approach for each Factor to include factor rating tables, proposal submission requirements and final discussion guidance.
B. FACTORS TO BE EVALUATED
The following evaluation factors will be used to evaluate each proposal.
1. FACTOR 1 – Technical Experience
Risk will be evaluated as one aspect of the technical evaluation, inherent in the technical evaluation factor ratings. Risk assesses the degree to which the offeror’s proposed technical approach for the requirements of the solicitation may cause disruption of schedule, increased price, degradation of performance, the need for increased Government oversight, or the likelihood of unsuccessful contract performance.
Evaluation of the offeror’s proposal shall address the factor as it applies to the scope of work. A detailed explanation of the criteria for the evaluation is set forth in the Evaluation Approach, Paragraph C of this section.
During evaluations of each proposal, the Government will assign each factor an adjectival rating and write a narrative evaluation reflecting the identified findings.
2. FACTOR 2 – Schedule
Risk will be evaluated as one aspect of the technical evaluation, inherent in the technical evaluation factor rating. Risk assesses the degree to which the offeror’s proposed technical approach for the requirements of the solicitation may cause disruption of schedule, increased price, degradation of performance, the need for increased Government oversight, or the likelihood of unsuccessful contract performance.
3. FACTOR 3 – Past Performance
Each offeror’s current and past performance will be reviewed to determine relevancy and confidence.
4. FACTOR 4 – Small Business Participation
The extent of Small Business Participation will be evaluated for unrestricted acquisitions.
5. FACTOR 5 – Price
The resulting award will be a firm-fixed price contract. Price reasonableness will be utilized in the evaluation of the proposal.
C. EVALUATION APPROACH
All proposals will be evaluated by the Source Selection Evaluation Board (SSEB). The following sections define the information to be provided and describe how the information for each factor and will be evaluated and rated.
1. The overarching evaluation approach for all factors is as follows:
a. Adequacy of Response. The proposal will be evaluated to determine whether the offerors methods and approach have adequately and completely considered, defined, and satisfied the requirements specified in the RFP. The proposal will be evaluated to determine the extent to which each requirement has been addressed in the proposal in accordance with the proposal submission section of the RFP. Marginal levels of overall detail could indicate a lack of understanding concerning the requirements and may result in the entire factor receiving an unfavorable rating and/or being eliminated from the competitive range.
2. Factor 1 Technical Experience
Proposals will be evaluated to determine experience with mechanical and electrical industrial installation relevant with the scope and complexity required in the solicitation. Offerors shall provide sufficient information to clearly demonstrate the breadth and depth of the Offeror’s (and major subcontractor’s) electrical and mechanical industrial installation experience. Major subcontractors are defined as members of an offeror’s overall team who are expected to perform ten (10) percent or more of the proposed effort. The Offeror shall also submit the written consent of its major subcontractors to allow the disclosure of its subcontractor’s technical experience to the Offeror. In addition, signed letters of commitment shall be included for all major subcontractors for their technical experience to be considered. Proposals shall conform to the solicitation requirements, to include all stated terms, conditions, representations, certifications, and all other information required of this solicitation.
Offerors shall submit the following for Factor 1:
Offerors must demonstrate electrical industrial installation experience and mechanical industrial installation experience by providing no more than five (5) projects performed within the last ten (10) years, which collectively demonstrate all the elements identified below. Individual projects that include all elements will be considered more favorable. If a subcontractor is proposed, the proposal will be considered more favorable if the proposal contains evidence of the prime and subcontractor working successfully together previously on relevant projects, than an offer with a prime and subcontractor with no prior experience working together on relevant projects. If a joint venture is proposed, the proposal will be considered more favorable if the proposal contains evidence of the firms working successfully together previously on relevant projects, than an offer with a joint venture with no prior experience working together on relevant projects.
I. Electrical Industrial Installation Experience Elements:
• At least 80% physically complete at the time of proposal submission. If project is not complete, provide documentation such as an invoice, letter from the owner, PPQ response or CPARS to demonstrate 80% physically complete.
• Complete equipment upgrade of at least a 500 KVA system that collectively include the following:
o 480V switchgear, motor control centers, panelboards and motors.
o Installation and programming of Human Machine Interface (HMI) and Programmable
Logic Controllers (PLC) for motor controls.
• Contractors shall be rated more favorably if work included the following:
o Medium voltage equipment removal or installation .
o Installation work involving temporary 480V motor power and control measures.
o Installation of 3 phase, medium voltage, dry-type transformers.
• Use Attached “Offeror Experience Form” to describe the projects in which the Offeror has relevant installation experience. Project experience shall include adequate detail to demonstrate the relevancy of the scope of work for comparison to that required in this solicitation.
II. Mechanical Industrial Installation Experience Elements:
• At least 80% physically complete at the time of proposal submission. If project is not complete, provide documentation such as an invoice, letter from the owner, PPQ response or CPARS to demonstrate 80% physically complete.
• Installation of vertical turbine or centrifugal pumps that have a minimum capacity of 3,500gpm.
• Installation of a minimum 12” diameter steel piping and isolation control valves.
• Contractors shall be rated more favorably if the installation included the following:
o Installation of work occurred in hazardous environments such as confined spaces or in the presence of fall hazards.
o Installation work that required diving within boat restricted zone of hydroelectric plant.
o Installation work involving water diversion and temporary pumping control measures.
• Use Attached “Offeror Experience Form” to describe the projects in which the Offeror has relevant installation experience. Project experience shall include adequate detail to demonstrate the relevancy of the scope of work for comparison to that required in this solicitation.
3. Factor 2 Schedule
This factor evaluates the offeror’s understanding of the required scope of work and evaluates the offeror’s ability to complete all requirements within the period of performance. Proposals shall conform to the solicitation requirements to include all stated terms, conditions, representations, certifications, and all other information required by this solicitation.
Offerors should assume for evaluation purposes, a Notice To Proceed (NTP) date of 31 January 2023.
Offerors shall submit the following for Factor 2:
I. Provide a schedule that shall reflect the planned activities, order of major tasks identified, task dependencies and durations proposed to successfully accomplish the entire project from notice to proceed to final commissioning, and contract close-out. At a minimum, the schedule shall include the following:
a. Pre-Construction Submittals submitted/approved within 60 calendar days from NTP being issued.
b. Compliance with Work and Operational Restrictions Specification (01 14 00.02 28) and acknowledgement of outage requirements in the 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK clause.
c. Discuss how work to complete one task may impact or be impacted by work to complete other tasks.
d. Major Activities:
i. Pre-construction submittals
ii. Outage duration needed for valve replacements, for each main unit
iii. Rehabilitation of the Unwatering Pumps
iv. Long lead fabrication and procurement items
v. Motor Control Center (MCC) demolition and replacement
vi. Rehabilitation of the Drainage System
vii. Contractor and Government Commissioning of Major Activities
II. Work plan addressing the following items:
a. Discuss how work to complete one task may impact or be impacted by work to complete other tasks.
b. Document capabilities and availability of resources (manufacturing, equipment and personnel) necessary to complete all required major tasks identified in the schedule.
c. List all major subcontractors with their respective role and responsibility to complete all major tasks.
Refer to the requirement for a letter of commitment for subcontractors in submission requirements for Factor 1.
d. Explain the communication process between different crews, subcontractors, and managers, including the superintendent, project manager, safety officer and quality control personnel. Include an organization chart to show the communication channels.
TECHNICAL FACTOR RATINGS: Ratings outlined below focus on strengths, deficiencies, weaknesses, risks and uncertainties of the offeror’s proposal. The rating depicts how well the offeror’s proposal meets the Technical subfactor requirements.
Technical Factor Ratings
Rating Definition
Outstanding Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is low.
Good
Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate.
Acceptable
Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.
Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.
Unacceptable
Proposal does not meet requirements of the solicitation, and thus, contains one or more deficiencies, and/or risk of unsuccessful performance is unacceptable. Proposal is non-awardable.
4. Factor 3 - Past Performance
There are three aspects to the past performance evaluation: Recency, Relevancy (including context of data) and Quality (including general trends in the contractor performance and source of information).
The Government will evaluate the offeror’s record of past and current performance to ascertain the probability of successfully performing the required efforts of the scope of work. Proposals shall conform to the solicitation requirements to include all stated terms, conditions, representations, certifications, and all other information required by this solicitation.
a. The Government will focus its inquiries on the offeror’s (and major subcontractor’s) record of performance as it relates to all solicitation requirements, including price, schedule, performance and management of sub-contractors. Major sub-contractors are defined as members of an offeror’s overall team who are expected to perform ten (10) percent or more of the proposed effort. The Offeror shall also submit the written consent of its major subcontractors to allow the disclosure of its subcontractor’s past performance information to the Offeror. In addition, signed letters of commitment shall be included for all major subcontractors for their past performance to be considered.
Offerors are reminded to include the most recent and relevant efforts (within the past ten years) in their proposal. Absent any recent and relevant past performance history or when the performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned, the offeror will be assigned a “neutral confidence rating” and its proposal will not be evaluated favorably or unfavorably on past performance. The Government may use data provided by the offeror in its proposal and data obtained from other sources, including data obtained through interviews with personnel familiar with the contractor and their current and past performance under Federal, State, or Local government or commercial contracts for same or similar services as compared to the North American Industry Classification System (NAICS) 237990, Other Heavy and Civil Engineering Construction. Data submitted by the offeror or gathered from other sources by the government in conducting performance risk assessments shall not extend past ten years prior to the issue date of the request for proposal, but may include performance data generated during the past ten years without regard to the contract award date. CPARS data is limited to the past 6 years.
Offeror’s shall provide additional performance data for projects beyond six years.
b. Offerors should submit all Government and/or commercial contract numbers and descriptions for the prime offeror and each major subcontractor in performance or awarded during the past ten years, from the issue date of this request for proposal, which are relevant to the efforts required by this solicitation.
c. The past performance factor considers each offeror’s demonstrated current and relevant past record of performance in supplying products and services that meet the contract requirements.
d. RECENCY: The Government will evaluate recency by examining the offerors’ record of past performance and to assess the time period during which the offeror’s past performance is considered relevant.
e. RELEVANCY: The Government will conduct a performance assessment based on the relevancy of the Offeror's current and past performance, as well as that of its major subcontractors, as it relates to the probability of successful accomplishment of the required effort. These efforts include all aspects of schedule, performance and customer support, including the Offeror’s submitted subcontracting plan for this project and the Offeror’s record of: 1) Conforming to specifications and standards of good workmanship; 2) Maintaining program execution within price; 3) Adherence to contract schedules, including the administrative aspects of performance; 4) Ability to resolve technical and manufacturing problems quickly and effectively; 5) Businesslike concern for the interest of its customers; 6) Establishing and maintaining adequate management of subcontractors; and 7) Compliance with subcontracting plans submitted on previous projects.
Past Performance Relevancy Ratings
Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.
Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.
Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
f. QUALITY: The third aspect of the past performance evaluation is to establish the overall quality of the offeror’s past performance. The quality past performance evaluations conducted gathers information from offeror’s customers to determine how well the offeror performed those past contracts. This quality assessment will be reflected in the overall confidence assessment described below.
g. PERFORMANCE CONFIDENCE ASSESSMENT: The final step is for the team to arrive at a single consensus performance confidence assessment for the offeror. Because this source selection requires a greater level of discrimination with the past performance evaluation, evaluators shall use the ratings in the chart below. This rating considers the assessed quality of the relevant/current efforts gathered (documented results from Past Performance Questionnaires, interviews, CPARS, and other sources form the support and basis for this assessment). Ensure the rationale for the conclusions reached are included.
Performance Confidence Assessments
Substantial Confidence Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Neutral Confidence
No recent/relevant performance record is available or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned. The offeror may not be evaluated favorably or unfavorably on the factor of past performance.
Limited Confidence Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.
5. Factor 4 – Small Business Participation Proposal
Other than small business offerors will be evaluated on the level of proposed participation of small business concerns in performance of this acquisition (as small business subcontractors) relative to the objectives and goals established herein. Small business contractors may achieve small business participation goals through their own performance/participation as a prime and also through a joint venture, teaming arrangement, and subcontracting to other small businesses.
The government will evaluate:
a. The extent to which such firms, as defined in FAR Part 19, are specifically identified in proposals;
b. The extent of commitment to use such firms. The proposal will be rated more favorably under this factor if it contains an enforceable commitment in the form of a signed letter of commitment (LOC);
c. Identification of the complexity and variety of the work small firms are to perform;
d. The extent past performance is in compliance with FAR 52.219-8 “Utilization of Small Business” and maximizing opportunities for U.S. Small Business Subcontractors.
e. The extent to which the offeror meets or exceeds the goals. The goals for this procurement are:
• Total Small Business (any type of small business) 5% of the total contract value (the sum of all CLINs);
• Subcategory Small Business o Small Disadvantaged Business (SDB) 0.5% of the total contract value;
o Woman-Owned Small Business (WOSB) 0.5% of the total contract value;
o Historically Underutilized Business Zone (HUBZone) 0.5% of the total contract value;
o Veteran Owned Small Business (VOSB) 1% of the total contract value;
o Service Disabled Veteran Owned Small Business (SDVOSB) 0.5% of the total contract value;
Small Business Participation Factor Rating Definitions:
Small Business Participation Factor Ratings
Outstanding Proposal indicates an exceptional approach and understanding of the small business objectives.
Good Proposal indicates a thorough approach and understanding of the small business objectives.
Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the small business objectives.
Marginal Proposal has not demonstrated an adequate approach and understanding of the small business objectives.
Unacceptable Proposal does not meet small business objectives. Proposal is non-awardable.
6. Factor 5 – Price
Offerors must submit completed Contract Line Item Numbers (CLINs) with unit price, quantity, and extended price.
All extensions of the unit prices shown will be subject to verification by the Government.
An evaluation will be performed on the proposed prices. The evaluation will not be assigned an adjectival rating.
However, it will be evaluated for completeness and reasonableness in accordance with FAR 15.305 and FAR 15.404.
a. Completeness - To be complete, the Offeror must provide all data that is requested and necessary to evaluate the price. The Government will assess the extent to which the proposed prices comply with the content and format requirements set forth in this solicitation.
b. Reasonableness - The Offerors proposal is evaluated through price analysis techniques as described in FAR
Subpart 15.305(a) (1) and 15.404-1(b). For price to be reasonable, it must represent a price that provides best value to the Government when consideration is given to prices in the market, (market conditions may be evidenced by other competitive proposals), and technical and functional capabilities of the Offeror. The Offerors price will be evaluated to determine if any are unreasonably high in relation to the anticipated work under the contract, as well as with current industry standards.
D. PROPOSAL SUBMISSION
1. Introduction. The offeror’s proposal shall be submitted electronically, as set forth below. The solicitation shall provide the Government address and receipt date for proposal submission. Files shall not contain classified data. The use of hyperlinks in proposals is prohibited.
The offeror’s proposal shall consist of two (2) volumes. The Volumes are:
Volume I - Technical, Past Performance Volume II – Small Business Participation Plan, Price, Solicitation, Offer and Award Documents and Certifications/Representations.
Offerors are cautioned that “parroting” of the Technical requirements with a statement of intent to perform does not reflect an understanding of the requirement or capability to perform. Offerors are responsible for including sufficient details to permit a complete and accurate evaluation of each proposal. Proprietary information shall be clearly marked.
2. Proposal Submission Requirements.
a. Each volume shall be submitted as a separate PDF or ZIP file. Any pages that are changed (as a result of negotiations or proposal revisions) should be of a different color and have changed information clearly marked by a vertical line in the right margin of the page. The revised pages shall be dated.
b. Printing shall be single spaced. Each paragraph shall be separated by at least one blank line. A standard, 12-point minimum font size applies. Arial or Times New Roman fonts are required. Tables and illustrations may use a reduced font size no less than 8-point and may be landscape.
c. The following volumes of material shall be submitted:
VOLUME TITLE PRINTED COPIES ELECTRONIC COPIES
Volume I Printed copies not required. 1 Volume II Printed copies not required. 1
d. Proposals may be rejected for failure to adhere to the proposal preparation requirements.
e. Proposals shall conform to the solicitation requirements to include all stated terms, conditions, representations, certifications, and all other information required of this solicitation.
f. To submit proposals electronically via DoD SAFE, email Contract Specialist, David Boone at david.c.boone@usace.army.mil, Hillary Morgan at hillary.a.morgan@usace.army.mil and Contracting Officer, Jani Long at jani.c.long@usace.army.mil for a unique code with valid email address and point of contact for your company. Mr. Boone will provide you with your unique code, then you will need to go to the following website: https://safe.apps.mil/
At the DoD SAFE website select “Drop-Off,” then enter your unique code and submit your proposal(s).
When your proposal is submitted via the DoD SAFE website, the website will provide notification of the submittal to the recipients. For this solicitation, the recipient will be: David C. Boone, david.c.boone@usace.army.mil and Hillary Morgan hillary.a.morgan@usace.army.mil
• When your files have been “picked-up,” you will receive an email notification. If you have not received a notification and it has been more than one business day since your “drop-off”
– please contact David Boone at david.c.boone@usace.army.mil and Hillary Morgan at hillary.a.morgan@usace.army.mil
For the purposes of determining whether the proposal was received “late” in accordance with FAR 15.208, the date and time the file(s) are uploaded into the DoD SAFE website as identified in the DoD SAFE email sent to the Contract Specialist(s)/Contracting Officer will be the time and date the Government received the proposal. Do not assume that electronic communication is instantaneous. Please make allowances for delays in transmittal.
NOTE: ONLY in the unusual case that the DoD SAFE website is “down” (not operational); the Offeror should email their proposal to the following individuals prior to the proposal due date and time: David Boone whose email address is david.c.boone@usace.army.mil and Hillary Morgan at hillary.a.morgan@usace.army.mil
SUBMISSION DEADLINE – Proposals shall be received by the USACE Contracting Activity no later than the time and date specified in Block 13 of Standard Form 1442. Official time will be established by the clock located in the area where proposals are received. Late proposals may not be accepted.
3. Proposal Files.
mailto:david.c.boone@usace.army.mil mailto:hillary.a.morgan@usace.army.mil mailto:jani.c.long@usace.army.mil https://safe.apps.mil/ mailto:hillary.a.morgan@usace.army.mil mailto:david.c.boone@usace.army.mil mailto:hillary.a.morgan@usace.army.mil mailto:david.c.boone@usace.army.mil mailto:hillary.a.morgan@usace.army.mil
a. Format. The submission shall be clearly indexed and logically assembled. Each volume shall be clearly identified and shall begin at the top of a page. All pages of each volume shall be appropriately numbered and identified by the complete company name, date and RFP number in the header and/or footer. Scans must be in color and at least 600 dpi. All files created in MS Word (doc) files shall use the following page setup parameters:
Margins – Top, Bottom, Left, Right – 1” From Edge – Header, Footer 0.5” Page Size, Width – 8.5” Page Size, Height – 11”
NOTE: 11X17 folded pages are acceptable for tables/graphic representations. The following additional restrictions apply:
File Packaging. All of the proposal files shall be compressed (zipped) into one file entitled proposal zip using WinZip version 6.2 or later, or as separate uploads in their native format, i.e. doc, xls, ppt, etc., and submitted electronically via DoD SAFE. Files shall be in read-only format, using PDF files. All price breakdown information to aid in the Price evaluation shall be submitted in Microsoft Office Excel Read/Write format. **Please note – Self extracting exe files are not acceptable.
b. Content Requirement. All information shall be confined to the appropriate file. The offeror shall confine submissions to essential matters, sufficient to define the proposal in a concise manner, to permit a complete and accurate evaluation of each proposal. Each file of the proposal shall consist of a Table of Contents, Summary Section, and the Narrative discussion. The Summary Section shall contain a brief abstract of the file. Proprietary information shall be clearly marked.
Sub-Contractor Identification:
a. Offerors should clearly identify the firm(s) that will be utilized during performance of the contract or work that will be self-performed. Ensure the proposal is clear as to which function the Offeror or subcontractor will be performing. If the prime contractor proposes to use a subcontractor, the offeror shall submit a signed Letter of Commitment from the subcontractor with the proposal.
a. If a subcontractor is proposed, the proposal will be considered more favorable if the proposal contains evidence of the prime and subcontractor working successfully together previously on relevant projects.
b. If a joint venture is proposed, the proposal will be considered more favorable if the proposal contains evidence of the joint venture entity working successfully together previously on relevant projects.
(i) VOLUME I, TAB 1 –Technical Experience
(i) VOLUME I, TAB 2 –Schedule
(iii) VOLUME I, TAB 3 – Past Performance. This tab shall contain current and past performance information regarding similar contracts. Offerors shall submit Government and/or commercial contracts for the prime offeror and each major contract currently in performance or awarded during the past ten (10) years, from the issue date of this RFP, which are relevant to the efforts required by this solicitation. Relevant efforts are defined as services/efforts that are the same as or similar to the effort required by the RFP. Data concerning the offeror shall be provided first, followed by each proposed major subcontractor, in alphabetical order. The Offeror shall also submit the written consent of its major subcontractors to allow the disclosure of its subcontractor’s past performance information to the Offeror. In addition, signed letters of commitment shall be included for all major subcontractors for their past performance to be considered. This tab shall be organized into the following sections:
(1) Section 1 – Contract Descriptions. This section shall include the following information in the following format. Ensure all information is current and accurate.
(a) Contractor/Subcontractor place of performance, CAGE Code and DUNS
Number. If the work was performed as a subcontractor, also provide the name of the prime contractor and Point of Contact (POC) within the prime contractor organization (name, and current address, e-mail address, and telephone and fax numbers).
(b) Government contracting activity, (or private firm) and current address, Procuring Contracting Officer’s name, e-mail address, telephone and fax numbers.
(c) Technical representative/COR and current email address, telephone and fax numbers.
(d) Government contract administration activity and the Administrative Contracting Officer’s name, current e-mail address, telephone and fax number.
(e) Government contract administration activity’s Pre-Award point of contact name, and current e-mail address, telephone and fax numbers.
(f) Contract Number and, in the case of Indefinite Delivery type contracts, GSA contracts, and Blanket Purchase Agreements, include Delivery Order/Task Order Numbers.
(g) Contract Type (specific type such as Fixed-Price (FP), Cost Reimbursement
(CR), Time & Material (T&M), etc.). In the case of Indefinite Delivery contracts, indicate specific type (Requirements, Definite Quantity, and Indefinite Quantity) and secondary contract type (FP, CR, T&M, etc.).
(h) Awarded price.
(i) Final or projected final price.
(j) Original delivery schedule, including dates of start and completion or work.
(k) Final or projected final, delivery schedule, including dates of start and completion of work.
(2) Section 2 – Performance. Offerors shall provide a specific narrative explanation of each contract listed in Section 1 - Contract Description, describing the objectives achieved and detailing how the effort is relevant to the requirement of this RFP.
(a) For any contracts that did not/do not meet original schedule or technical performance requirements, provide a brief explanation of the reason(s) for the shortcomings and any corrective action(s) taken to avoid recurrence. The offerors shall list each time the delivery schedule was revised and provide an explanation of why the revision was necessary. All Requests for Deviation and Requests for Waiver shall be addressed with respect to causes and corrective actions. The offerors shall also provide copy of any Cure Notices or Show Cause Letters received on each contract listed and a description of any corrective action implemented by the offeror or proposed subcontractor. The offerors shall indicate if any of the contracts listed were terminated and the type and reasons for the termination.
(b) For all contracts, the offeror shall provide data on all manufacturing warranty returns. Data shall delineate total number of warranty returns, number of Could Not Duplicate (CND), number of failures attributable to GFE component failures, and number and nature of failures attributable to the offeror’s delivered product.
(3) Section 3 – Subcontracts. Offerors shall provide an outline of how the effort required by the RFP will be assigned for performance within the offeror’s corporate entity and among the proposed subcontractors. The information provided for the prime offeror and each proposed major subcontractor shall include the entire company name, company address, CAGE Code, DUNS Number and type of work to be performed by citing the applicable Government technical specification. This includes all subcontractors and suppliers who will be providing critical hardware/services or whose subcontract is for more than 10% of the total proposed Price.
(4) Section 4 – New Corporate Entities. New corporate entities may submit data on prior contracts involving its officers and employees. However, in addition to the other requirements in this section, the offeror shall discuss in detail the role performed by such persons in the prior contracts cited to demonstrate the relevancy of experience and past performance with this solicitation. Information should be included in the files described in the sections above. Signed Letters of Commitment shall be included in the proposal for these employees in order to be considered. Letters of Commitment must be signed both by the company official and the employee.
(5) Section 5-Past Performance Questionnaire. For all contracts identified in Section 1 - Contract Descriptions, complete a Past Performance Questionnaire for any project that has not received a formal Contractor Performance Assessment Reporting System (CPARS) evaluation. The offeror shall complete Part I of the Past Performance Questionnaire and E-mail the questionnaire to the technical representative responsible for the current and past contract. The Point of Contacts (POCs) shall be instructed to electronically complete Part II of the questionnaire and e-mail the entire questionnaire to the Contracting Office no later than the proposal due date, to David.C.Boone@usace.army.mil and Hillary.a.morgan@usace.army.mil. The offeror shall submit, with its proposal, a list of all the POCs who were sent questionnaires. The POC List shall be submitted in Word for Windows Table Format to include the following fields:
Solicitation Number; Company Name; Contract Number; Government Agency; POC Last Name, First Name;
POC Title; POC Telephone Number; POC E-mail Address; and Date E-Mail to POC (month/day).
(6) Section 6-Submissions. Offerors are discouraged from providing points of contact with another contractors’ facility, i.e., in case an offeror (or one of his/her team members) is in a subcontract with another contractor who has submitted a proposal on the same requirement. Offerors shall provide and submit the prime contract number and all Governmental agency points of contact (POC) in lieu of subcontract numbers or prime contract POCs in situations as described above.
(iii) VOLUME II, TAB 1 – Price. This tab shall consist of all information, required to support proposed prices. Certified pricing data is not currently required; however, the Government reserves the right to request such data prior to award. There are no page limitations for this tab.
The offeror shall ensure that the information submitted in this tab is consistent with and fully supports the amounts set forth in the SF1442 and continuation sheets.
(iv) VOLUME II, TAB 2– Small Business Participation Plan. See Small Business Participation Plan.
Large business Offerors are required to complete a Small Business Participation Plan (form attached).
Offerors must propose the level of participation of small businesses (as small business subcontractors) in the performance of this acquisition relative to the objectives/goals set forth in the evaluation of this area.
(v) VOLUME II, TAB 3– SOLICITATIONS, OFFER AND AWARD DOCUMENTS AND
CERTIFICATIONS/REPRESENTATIONS
Certifications and Representations – Each offeror shall complete (fill-in and signatures) the solicitation sections indicated below using the file (without modification to the file) provided with the RFP. An authorized official of the firm shall sign the SF1442 and all certifications requiring original signature.
An Acrobat PDF file shall be created to capture the signatures for submission.
Section 00 21 00 – Standard Form 1442 Solicitation, Offer and Award Section 00 45 00 – Representations, Certification, and Other Statements of Offerors mailto:David.C.Boone@usace.army.mil mailto:Hillary.a.morgan@usace.army.mil
Solicitations, Offer and Award Documents and Certifications/Representations shall not be submitted separately from that submitted in VOLUME II – SOLICITATIONS, OFFER AND AWARD
DOCUMENTS AND CERTIFICATIONS /REPRESENTATIONS.
E. DISCUSSIONS
1. GENERAL INFORMATION. In accordance with FAR provision 52.215-1, the Government intends to evaluate proposals and award a contract without discussions with offerors. Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary.
(End of Summary of Changes)
MNA Powerhouse Drainage_Unwatering_Equalization System Rehab W912EF22R0015 Amend-0002
SECTION TABLE OF CONTENTS
DIVISION 22 - PLUMBING
SECTION 22 11 00.01 28
PIPING AND VALVES
PART 1 GENERAL
1.1 SCOPE
1.2 REFERENCES
1.3 SUBMITTALS
1.4 QUALITY ASSURANCE
1.5 PIPING DRAWINGS
PART 2 PRODUCTS
2.1 WATER PIPING
2.1.1 Galvanized Steel Piping
2.1.2 Stainless Steel Piping
2.2 VALVES
2.2.1 Resilient Seat Wedge Gate Isolation Valves
2.2.2 Equalizer Valves
2.2.2.1 Equalizer Valve Packing
2.2.3 Silent Check Valves
2.2.4 Double Wafer Check Valve
2.2.5 Unwatering Discharge Plug
2.2.6 Ball Valves
2.3 MISCELLANEOUS PIPING MATERIALS
2.3.1 Flanges and Gaskets
2.3.2 Mechanical Couplings
2.3.3 Threaded Fittings
2.3.4 Expansion Joints
2.3.5 Flanged Coupling Adapter
2.3.6 Welded Outlets
2.3.7 Pressure Gauges
2.3.8 Offset Pipe Clamps
2.3.9 Draft Tube Drain Tee
2.3.10 Custom Suction Bell
PART 3 EXECUTION
3.1 INSTALLATION
3.1.1 Pipe Plug Installation
3.1.2 Piping Joints
3.1.2.1 Threaded
3.1.2.2 Unions and Flanges
3.2 FIELD QUALITY CONTROL
3.2.1 Inspections
3.2.2 Field Testing
3.2.2.1 Water Piping Test Plan
3.3 WELD TESTING
3.4 IDENTIFICATION SYSTEMS
3.4.1 Identification Tags
3.4.2 Pipe Labels
ATTACHMENTS:
SECTION 22 11 00.01 28
G4EDHCMP
Line
McNary Piping Color Marker Identification and Label Scheme
-- End of Section Table of Contents --
SECTION 22 11 00.01 28
SECTION 22 11 00.01 28
PIPING AND VALVES
PART 1 GENERAL
1.1 SCOPE
This section specifies the materials and workmanship standards applicable to the fabrication, assembly, installation, and testing of the various items of piping work. These requirements are in addition to those contained in other sections or indicated on the drawings.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
AMERICAN WELDING SOCIETY (AWS)
AWS D1.1/D1.1M (2020; Errata 1 2021) Structural Welding Code - Steel
AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
ASME B1.20.1 (2013; R 2018) Pipe Threads, General Purpose (Inch)
ASME B16.3 (2016) Malleable Iron Threaded Fittings, Classes 150 and 300
ASME B16.42 (2016) Ductile Iron Pipe Flanges and Flanged Fittings, Classes 150 and 300
ASME B16.5 (2020) Pipe Flanges and Flanged Fittings NPS 1/2 Through NPS 24 Metric/Inch Standard
ASME B16.21 (2016) Nonmetallic Flat Gaskets for Pipe Flanges
ASME B16.34 (2017) Valves - Flanged, Threaded and Welding End
ASME B31.3 (2016) Process Piping
ASME B31.9 (2017) Building Services Piping
ASME B40.100 (2013) Pressure Gauges and Gauge Attachments
ASTM INTERNATIONAL (ASTM)
ASTM A 53 (1997) Pipe, Steel, Black and Hot-Dipped, Zinc-Coated Welded and Seamless
ASTM A 105/A 105M (2005) Carbon Steel Forgings for Piping Applications
ASTM A 516/A 516M (2004) Pressure Vessel Plates, Carbon Steel, for Moderate- and Lower-Temperature Service
ASTM A536 (1984; R 2014) Standard Specification for Ductile Iron Castings
ASTM A123/A123M (2017) Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products
ASTM A320/A320M (2015) Standard Specification for Alloy/Steel and Stainless Steel Bolting Materials for Low-Temperature Service
AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
ASME A13.1 (2020) Scheme for the Identification of Piping Systems
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA C110/A21.10 (2012) Ductile-Iron and Gray-Iron Fittings for Water
AWWA C116/A21.16 (2015) Protective Fusion-Bonded Coatings for the Interior and Exterior Surfaces of Ductile-Iron and Gray Iron Fittings
AWWA C515 (2009) Reduced-Wall, Resilient-Seated Gate Valves for Water Supply Service
AWWA C606 (2015) Grooved and Shouldered Joints
ASTM INTERNATIONAL (ASTM)
ASTM A312/A312M (2019) Standard Specification for Seamless, Welded, and Heavily Cold Worked Austenitic Stainless Steel Pipes
INTERNATIONAL CODE COUNCIL (ICC)
ICC Plumbing Code (2012) International Plumbing Code
MANUFACTURERS STANDARDIZATION SOCIETY OF THE VALVE AND FITTINGS
INDUSTRY (MSS)
MSS SP-25 (1998) Standard Marking System for Valves, Fittings, Flanges and Unions
MSS SP-110 (2010) Ball Valves Threaded, Socket-Welding, Solder Joint, Grooved and Flared Ends
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only. When used, a designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Identification Tags ; G, C
Valve Operator Color Schedule ; G, ME
SD-02 Shop Drawings
Piping Drawings ; G, ME
SD-03 Product Data
Resilient Seat Wedge Gate Isolation Valves ; G, ME
Silent Check Valves ; G, ME
Double Wafer Check Valve ; G, ME
Unwatering Discharge Plug ; G, ME
Ball Valves ; I, ME
Equalizer Valve Packing ; I, ME
Spare Equalizer Valves ; I, ME
Miscellaneous Piping Materials ; I, ME
SD-06 Test Reports
Water Piping Test Plan ; G, ME
Discharge Piping Weld Test ; I, ME
1.4 QUALITY ASSURANCE
Plumbing systems including fixtures, equipment, materials, installation, and workmanship shall be in accordance with the ICC Plumbing Code (referred to herein as Plumbing Code) except as modified herein. In the Plumbing Code the advisory provisions shall be considered to be mandatory, as though the word "shall" had been substituted for the word "should" wherever it appears; reference to the "authority having jurisdiction," the Administrative Authority, the Plumbing Official, and the Design Engineer shall be interpreted to mean the Contracting Officer.
1.5 PIPING DRAWINGS
The Contractor shall submit Piping Drawings for the pump discharge and inlet pipes, pump columns as well as all replaced drainage piping.
Drawings shall consist of plans drawn to scale, with elevations, sections and details to show clearly the location (by dimension to pertinent building features) of all piping. This includes but is not limited to, details of connections and size and type of piping and valves, all support types and locations, pipe thrust restraints, sway braces, and appurtenances.
PART 2 PRODUCTS
2.1 WATER PIPING
2.1.1 Galvanized Steel Piping
Steel pipe for the pump shaft columns and pump discharge pipes shall be galvanized steel pipe conforming to ASTM A 53 , Type S, Grade B, seamless pipe. For all nominal pipe sizes flanged connection and fittings shall be used according to ASME B16.5 and ASME B16.42 class 150 as applicable, unless noted otherwise. For nominal pipe sizes less than 4 inches in diameter that cannot be flanged due to existing conditions threaded connections and fittings shall be used according to ASME B16.3 class 150, unless noted otherwise. Fabricated piping shall be "hot-dip" galvanized in accordance with ASTM A123/A123M after all welding is complete. All welding and repairs to galvanizing shall be done according to
05 50 14.00 28 METALWORK AND METAL FABRICATION.
2.1.2 Stainless Steel Piping
Stainless steel pipe shall meet the requirements of ASTM A312/A312M , seamless, Grade TP304, TP304L, TP316, or TP316L, Schedule 10S with dimensions conforming to ASME B31.9 .
2.2 VALVES
Generally, valves shall conform to ASME B16.34 as applicable or unless specified otherwise. Valves of nominal sizes equal to or greater than 4 inches in diameter shall have flanged end connections conforming to ASME B16.42 class 150. Valves of nominal sizes less than 4 inches in diameter shall have threaded end connections according to ASME B16.3 class 150 with a union on all but one side of the valve, or solder end connections for connections between bronze valves and copper tubing. All new valves shall be provided with means to lock them in both the open and closed positions.