W912EF18R0012
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
Summary of changes for Amend -0001 Ice Harbor Station Service Transformers TJO and TWO Replacement
W912EF18R0012
Changes to Section L of the Solicitation:
Paragraph (iv) revised Changes to Section M of the solicitation:
Factor 3 – Past Performance, paragraph a revised to “within the past ten years”.
Updated Wage Determination
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 29-Mar-2018 02:00 PM to 04-Apr-2018 04:00 PM.
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS
The following have been modified:
D. PROPOSAL SUBMISSION
1. Introduction. The offeror’s proposal shall be submitted in hard copy, with accompanying digital copies, as set forth below. The RFP shall provide the Government address and receipt date for proposal submittal. The offeror’s proposal shall consist of two (2) volumes. The Volumes are:
Volume I - Technical, Past Performance Volume II –Price, Solicitation, Offer and Award Documents and Certifications/Representations.
Files shall not contain classified data. The use of hyperlinks in proposals is prohibited. Proposals must be submitted in hard copy AND in electronic format. The electronic files shall contain identical information to the hard copy files.
Offerors are cautioned that “parroting” of the Technical requirements with a statement of intent to perform does not reflect an understanding of the requirement or capability to perform. Offerors are responsible for including sufficient details to permit a complete and accurate evaluation of each proposal. Proprietary information shall be clearly marked.
2. Proposal Submission Requirements.
a. Each volume shall be submitted in a separate three-ring binder. Any pages that are changed (as a result of negotiations or proposal revisions) should be of a different color and have changed information clearly marked by a vertical line in the right margin of the page. The revised pages shall be dated. Each binder shall be clearly labeled with its Title and a copy number (e.g., copy 1 of 5).
b. Printing should be single spaced. Each paragraph shall be separated by at least one blank line. A standard, 12-point minimum font size applies. Arial or New Times Roman fonts are required.
Tables and illustrations may use a reduced font size no less than 8-point and may be landscape.
c. The following volumes of material shall be submitted:
VOLUME TITLE
PRINTED
COPIES
ELECTRONIC
COPIES
Volume I Original +4 1 Volume II Original + 1 1
3. Proposal Files.
a. Format. The submission shall be clearly indexed and logically assembled. Each volume shall be clearly identified and shall begin at the top of a page. All pages of each volume shall be appropriately numbered and identified by the complete company name, date and RFP number in the header and/or footer. All files created in MS Word (doc) files shall use the following page setup parameters:
Margins – Top, Bottom, Left, Right – 1” From Edge – Header, Footer 0.5” Page Size, Width – 8.5” Page Size, Height – 11”
NOTE: 11X17 folded pages are acceptable for tables/graphic representations
The following additional restrictions apply:
b. File Packaging. All of the proposal files shall be compressed (zipped) into one file entitled proposal zip using WinZip version 6.2 or later, and provided on CDs or DVDs. Zip disks are not permitted. Files shall be in read-only format, using PDF files. All price breakdown information to aid in the Price evaluation shall be submitted in Microsoft Office Excel Read/Write format and viewable in Microsoft Excel 2007. Each disc shall be externally labeled with the volume number, date, and the offeror’s name. **Please note – Self extracting exe files are not acceptable. **The electronic files shall contain identical information to the hard copy files.
c. Content Requirement. All information shall be confined to the appropriate file. The offeror shall confine submissions to essential matters, sufficient to define the proposal in a concise manner, to permit a complete and accurate evaluation of each proposal. Each file of the proposal shall consist of a Table of Contents, Summary Section, and the Narrative discussion. The Summary Section shall contain a brief abstract of the file.
Proprietary information shall be clearly marked. The following shall be included in the Narrative discussion:
(i) VOLUME I, TAB 1 -Technical. The volume shall be organized into the following sections:
Section 1: Factor 1: Transformer Design and Manufacturer Experience Section 2: Factor 2: Installation Experience
(ii) VOLUME I, TAB 2 – Factor 3: Past Performance. This tab shall contain current and past performance information regarding similar contracts. This volume shall not exceed 25 pages plus five pages for each major subcontractor, excluding Past Performance Questionnaire Forms. Offerors shall submit Government and/or commercial contracts for the prime offeror and each major contract currently in performance or awarded during the past ten (10) years, from the issue date of this RFP, which are relevant to the efforts required by this solicitation.
Relevant efforts are defined as services/efforts that are the same as or similar to the effort required by the RFP. Data concerning the offeror shall be provided first, followed by each proposed major subcontractor, in alphabetical order.
The Offeror shall also submit the written consent of its major subcontractors to allow the disclosure of its subcontractor’s past performance information to the Offeror. In addition, signed letters of commitment shall be included for all major subcontractors and fabricators for their past performance to be considered. This tab shall be organized into the following sections:
(1) Section 1 – Contract Descriptions. This section shall include the following information in the following format. Ensure all information is current and accurate.
(a) Contractor/Subcontractor place of performance, CAGE Code and DUNS Number. If the work was performed as a subcontractor, also provide the name of the prime contractor and Point of Contact (POC) within the prime contractor organization (name, and current address, e-mail address, and telephone and fax numbers).
(b) Government contracting activity, (or private firm) and current address, Procuring Contracting Officer’s name, e-mail address, telephone and fax numbers.
(c) Technical representative/COR and current email address, telephone and fax numbers.
(d) Government contract administration activity and the Administrative Contracting Officer’s name, current e-mail address, telephone and fax number.
(e) Government contract administration activity’s Pre-Award point of contact name, and current e-mail address, telephone and fax numbers.
(f) Contract Number and, in the case of Indefinite Delivery type contracts, GSA contracts, and Blanket Purchase Agreements, include Delivery Order/Task Order Numbers.
(g) Contract Type (specific type such as Fixed-Price (FP), Cost Reimbursement (CR), Time & Material (T&M), etc.). In the case of Indefinite Delivery contracts, indicate specific type (Requirements, Definite Quantity, and Indefinite Quantity) and secondary contract type (FP, CR, T&M, etc.).
(h) Awarded price.
(i) Final or projected final price.
(j) Original delivery schedule, including dates of start and completion or work.
(k) Final or projected final, delivery schedule, including dates of start and completion of work.
(2) Section 2 – Performance. Offerors shall provide a specific narrative explanation of each contract listed in Section 1 - Contract Description, describing the objectives achieved and detailing how the effort is relevant to the requirement of this RFP.
(a) For any contracts that did not/do not meet original schedule or technical performance requirements, provide a brief explanation of the reason(s) for the shortcomings and any corrective action(s) taken to avoid recurrence. The offerors shall list each time the delivery schedule was revised and provide an explanation of why the revision was necessary. All Requests for Deviation and Requests for Waiver shall be addressed with respect to causes and corrective actions. The offerors shall also provide copy of any Cure Notices or Show Cause Letters received on each contract listed and a description of any corrective action implemented by the offeror or proposed subcontractor. The offerors shall indicate if any of the contracts listed were terminated and the type and reasons for the termination.
(b) For all contracts, the offeror shall provide data on all manufacturing warranty returns.
Data shall delineate total number of warranty returns, number of Could Not Duplicate (CND), number of failures attributable to GFE component failures, and number and nature of failures attributable to the offeror’s delivered product.
(3) Section 3 – Subcontracts. Offerors shall provide an outline of how the effort required by the RFP will be assigned for performance within the offeror’s corporate entity and among the proposed subcontractors. The information provided for the prime offeror and each proposed major subcontractor must include the entire company name, company address, CAGE Code, DUNS Number and type of work to be performed by citing the applicable Government technical specification. This includes all subcontractors, fabricators, and suppliers who will be providing critical hardware/services or whose subcontract is for more than 10% of the total proposed Price.
(4) Section 4 – New Corporate Entities. New corporate entities may submit data on prior contracts involving its officers and employees. However, in addition to the other requirements in this section, the offeror shall discuss in detail the role performed by such persons in the prior contracts cited to demonstrate the relevancy of experience and past performance with this solicitation. Information should be included in the files described in the sections above. Signed Letters of Commitment shall be included in the proposal for these employees in order to be considered. Letters of Commitment must be signed both by the company official and the employee.
(5) Section 5-Past Performance Questionnaire. For all contracts identified in Section 1 - Contract Descriptions, complete a Past Performance Questionnaire for any project that has not received a formal Contractor Performance Assessment Reporting System (CPARS) evaluation. The offeror shall complete Part I of the Past Performance Questionnaire and E-mail the questionnaire to the technical representative responsible for the current and past contract. The Point of Contacts (POCs) shall be instructed to electronically complete Part II of the questionnaire and e-mail the entire questionnaire to the Contracting Office no later than the proposal due date, to Hillary.A.Morgan@usace.army.mil. The offeror must submit, with its proposal, a list of all the POCs who were sent questionnaires. The POC List shall be submitted in Word for Windows Table Format to include the following fields:
Solicitation Number; Company Name; Contract Number; Government Agency; POC Last Name, First Name; POC Title; POC Telephone Number; POC E-mail Address; and Date E-Mail to POC (month/day).
(6) Section 6-Submissions. Offerors are discouraged from providing points of contact with another contractors’ facility, i.e., in case an offeror (or one of his/her team members) is in a subcontract with another contractor who has submitted a proposal on the same requirement. Offerors shall provide and submit the prime contract number and all Governmental agency points of contact (POC) in lieu of subcontract numbers or prime contract POCs in situations as described above.
(iii) VOLUME II, TAB 1 – Price. This tab shall consist of all information, required to support proposed prices. Certified pricing data is not currently required; however, the Government reserves the right to request such data prior to award. There are no page limitations for this tab.
The offeror shall ensure that the information submitted in this tab is consistent with and fully supports the amounts set forth in the SF33 and continuation sheets.
(iv) VOLUME II, TAB 2– SOLICITATIONS, OFFER AND AWARD DOCUMENTS AND
CERTIFICATIONS/REPRESENTATIONS
Certifications and Representations – Each offeror shall complete (fill-in and signatures) the solicitation sections indicated below using the file (without modification to the file) provided with the RFP. An authorized official of the firm shall sign the SF33 and all certifications requiring original signature. An Acrobat PDF file shall be created to capture the signatures for submission.
Section A – Standard Form 33 Solicitation, Offer and Award Section K – Representations, Certification and Other Statements of Offerors
Solicitations, Offer and Award Documents and Certifications/Representations shall not be submitted separately from that submitted in VOLUME II – SOLICITATIONS, OFFER AND AWARD
DOCUMENTS AND CERTIFICATIONS /REPRESENTATIONS.
DISCUSSIONS
1. GENERAL INFORMATION. In accordance with FAR provision 52.215-1, the Government intends to evaluate proposals and award a contract without discussions with offerors. Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary.
The following have been modified:
EVALUATION FACTORS
A. BASIS FOR AWARD
The award will be made based on the best overall (i.e., best value-tradeoff) proposal that is determined to be the most beneficial to the Government, with appropriate consideration given to the four (4) factors: Transformer Design and Manufacturing Experience; Installation Experience; Past Performance; and Price.
Factor 1, Transformer Design and Manufacturing Experience is more important than Factor 2, Installation Experience. Factors 1 and 2 are more important than Factor 3, Past Performance. When combined, the non-price factors (Factors 1 through 3) are significantly more important than Factor 4, Price. As proposals become more equal in their technical (non-price) merit, the evaluated price becomes more important in determining the best value proposal.
B. FACTORS AND SUB-FACTORS TO BE EVALUATED
The following evaluation factors and sub-factors will be used to evaluate each proposal. Award will be made to the offeror whose proposal is most advantageous to the Government based upon an integrated assessment of the evaluation factors and sub-factors described below.
All non-price factors other than Factor 3, Past Performance, shall be rated using the combined technical/risk rating as follows:
RATING DESCRIPTION
Outstanding Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is low.
Good Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate.
Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.
Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.
Unacceptable Proposal does not meet requirements of the solicitation, and thus, contains one or more deficiencies, and/or risk of unsuccessful performance is unacceptable. Proposal is unawardable.
SECTION M - EVALUATION FACTORS FOR AWARD
FACTOR 1 – Transformer Design and Manufacturing Experience
Proposals will be evaluated to determine transformer design and manufacturer experience relevant with the scope and complexity required in the solicitation. Offerors shall provide sufficient information to clearly demonstrate the breadth and depth of the Offeror’s transformer design and manufacturer experience.
Offerors shall clearly identify the transformer manufacturing firm(s) that will be utilized during performance of the contract to design, manufacture and test the transformers. If the prime contractor proposes to self-perform manufacturing of the required transformer, ensure the proposal is clear that the Offeror will be performing this function. If the prime contractor proposes to use a subcontractor for the manufacturing of the required transformer, the offeror must submit a signed Letter of Commitment from the subcontractor with the proposal.
If a subcontractor is proposed, the proposal will be considered more favorable if the proposal contains evidence of the prime and subcontractor working successfully together previously on relevant projects, than an offer with a prime and subcontractor with no prior experience working together on relevant projects.
If a joint venture is proposed, the proposal will be considered more favorable if the proposal contains evidence of the joint venture entity working successfully together previously on relevant projects, than an offer with a joint venture with no prior experience working together on relevant projects.
Offerors must demonstrate transformer manufacturer experience by providing at least one example of each of the elements identified in the fully relevant definition below performed within the past six (6) years.
Fully relevant transformer manufacturing experience is defined as projects including all of the following:
a. Design and Manufacturing. Class I and Class II power transformers, as defined by IEEE standard C57.12.00, with a minimum of 500 kVA rating and larger.
b. Ratings. Transformer ratings (kVA, primary/secondary voltage, Basic Impulse Level (BIL), and temperature rise.
c. Transformer Design and Manufacture with Throats. Experience designing and manufacturing transformers with throats for bus ducts.
d. Transformer Design and Manufacture of Mineral Oil-Immersed Transformers with Dual Cooling Classes. Transformers with natural convection oil flow through cooling equipment and windings that are air cooled by either natural circulation air cooling or by forced air circulation
(ONAN/ONAF).
Use Attachment “Offeror Experience Form” to describe the projects in which the Offeror has relevant transformer manufacturing experience. Project experience shall include adequate detail such as configuration and dimensions to demonstrate the relevancy of the scope of work for comparison to that required in this solicitation.
Offerors with ISO 9001 Certification of Design and Manufacturing Facility certified as of the date of proposal submission will be rated more favorably.
Factor 2 - Installation Experience
Proposals will be evaluated to determine installation contractor experience relevant with the scope and complexity required in the solicitation. Offerors shall provide sufficient information to clearly demonstrate the breadth and depth of the Offeror’s installation experience.
Offerors shall clearly identify the installation firm(s) that will be utilized during performance of the contract. If the prime contractor proposes to self-perform installation of the required transformer, ensure the proposal is clear that the Offeror will be performing this function. If the prime contractor proposes to use a subcontractor for the installation of the required transformer, the offeror must submit a signed Letter of Commitment from the subcontractor with the proposal.
If a subcontractor is proposed, the proposal will be considered more favorable if the proposal contains evidence of the prime and subcontractor working successfully together previously on relevant projects, than an offer with a prime and subcontractor with no prior experience working together on relevant projects.
If a joint venture is proposed, the proposal will be considered more favorable if the proposal contains evidence of the joint venture entity working successfully together previously on relevant projects, than an offer with a joint venture with no prior experience working together on relevant projects.
Offerors must demonstrate installation experience by providing at least one example of each of the elements identified in the fully relevant definition below performed within the past of ten (10) years.
Each reference project used to demonstrate installation experience must include relevant scope of work, but it’s not required to involve all of the fully relevant elements defined in this subfactor. Fully relevant installation experience is defined as projects including all of the following:
Installation of Class I and/or Class II power transformers of a minimum of 500 kVA and larger that include:
a. Installation of 115kV high-voltage tubular bus systems; and
b. Installation that includes bus duct connections.
c. Installation involving a transformer manufacturer’s erecting engineer that provides continual on-site support during delivery, movement, assembly, oil-filling, and testing of transformers.
d. Installation involving a commissioning agent that coordinates commissioning activities and develops inspection and test plans for electrical equipment of comparable type and complexity.
Use Attachment “Offeror Experience Form” to describe the projects in which the Offeror has relevant installation experience. Project experience shall include adequate detail such as configuration and dimensions to demonstrate the relevancy of the scope of work for comparison to that required in this solicitation.
FACTOR 3 – Past Performance
There are three aspects to the past performance evaluation: Recency, Relevancy (including context of data) and Quality (including general trends in the contractor performance and source of information).
The Government will evaluate the offeror’s record of past and current performance to ascertain the probability of successfully performing the required efforts of the scope of work.
a. The Government will focus its inquiries on the offeror’s (and major subcontractor’s) record of performance as it relates to all solicitation requirements, including price, schedule, performance and management of sub-contractors. Major sub-contractor are define as members of an offeror’s overall team who are expected to perform ten (10) percent or more of the proposed effort. A significant achievement, problem or lack or relevant data in any element of the work can become an important consideration in the evaluation process.
Therefore, offerors are reminded to include the most recent and relevant efforts (within the past ten years) in their proposal. Absent any recent and relevant past performance history or when the performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned, the offeror will be assigned an “unknown confidence rating” and its proposal will not be evaluated favorably or unfavorably on past performance. The Government may use data provided by the offeror in its proposal and data obtained from other sources, including data obtained through interviews with personnel familiar with the contractor and their current and past performance under Federal, State, or Local government or commercial contracts for same or similar services as compared to the North American Industry Classification System (NAICS) 335311, Power Distribution, and Specialty Transformer Manufacturing. Data submitted by the offeror or gathered from other sources by the government in conducting performance risk assessments shall not extend past ten years prior to the issue date of the request for proposal, but may include performance data generated during the past ten years without regard to the contract award date. CPARS data is limited to the past 6 years. Offeror’s should provide additional performance data for projects beyond six years.
b. Offerors should submit all Government and/or commercial contract numbers and descriptions for the prime offeror and each major subcontractor in performance or awarded during the past ten years, from the issue date of this request for proposal, which are relevant to the efforts required by this solicitation.
c. The past performance factor considers each offeror’s demonstrated current and relevant past record of performance in supplying products and services that meet the contract requirements.
d. RELEVANCY: The Government will conduct a performance assessment based on the relevancy of the Offeror's current and past performance, as well as that of its major subcontractors and fabricators, as it relates to the probability of successful accomplishment of the required effort. These efforts include all aspects of schedule, performance and customer support, including the Offeror’s submitted subcontracting plan for this project and the Offeror’s record of: 1) Conforming to specifications and standards of good workmanship; 2) Maintaining program execution within price; 3) Adherence to contract schedules, including the administrative aspects of performance; 4) Ability to resolve technical and manufacturing problems quickly and effectively; 5) Businesslike concern for the interest of its customers; 6) Establishing and maintaining adequate management of subcontractors; and 7) Compliance with subcontracting plans submitted on previous projects.
Past Performance Relevancy Ratings
Rating Definition
Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.
Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.
Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
e. Quality: The third aspect of the past performance evaluation is to establish the overall quality of the offeror’s past performance. The quality past performance evaluations conducted gathers information from offeror’s customers to determine how well the offeror performed those past contracts. This quality assessment will be reflected in the overall confidence assessment described below.
f. PERFORMANCE CONFIDENCE ASSESSMENT: The final step is for the team to arrive at a single consensus performance confidence assessment for the offeror, selecting the most appropriate rating from the chart below. This rating considers the assessed quality of the relevant/current efforts gathered (documented results from Past Performance Questionnaires, interviews, CPARS, and other sources form the support and basis for this assessment). Ensure the rationale for the conclusions reached are included.
Performance Confidence Assessments
Rating Definition
Substantial Confidence Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Neutral Confidence
No recent/relevant performance record is available or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned. The offeror may not be evaluated favorably or unfavorably on the factor of past performance.
Limited Confidence Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.
Factor 4– Price
Offerors must submit completed Contract Line Item Numbers (CLINs) with unit price, quantity, and extended price.
All extensions of the unit prices shown will be subject to verification by the Government. In case of discrepancy between the unit price and the extended price, the unit price will govern.
An evaluation will be performed on the proposed prices. The evaluation will not be assigned an adjectival rating.
However, it will be evaluated for completeness and reasonableness as follows:
a. Completeness - To be complete, the Offeror must provide all data that is requested and necessary to evaluate the price. The Government will assess the extent to which the proposed prices comply with the content and format requirements set forth in this solicitation.
b. Reasonableness - The Offeror's proposal is evaluated through price analysis techniques as described in FAR Subpart 15.305(a) (1) and 15.404-1(b). For price to be reasonable, it must represent a price that provides best value to the Government when consideration is given to prices in the market, (market conditions may be evidenced by other competitive proposals), and technical and functional capabilities of the Offeror. The Offeror's price will be evaluated to determine if any are unreasonably high or low in relation to the anticipated work under the contract, as well as with current industry standards.
WAGE DETERMINATION
NOTE: This wage decision is only applicable to the onsite construction portion of the work.
General Decision Number: WA180085 02/23/2018 WA85
Superseded General Decision Number: WA20170085
State: Washington
Construction Type: Heavy including water and sewer line construction
County: Walla Walla County in Washington.
HEAVY CONSTRUCTION PROJECTS (including sewer/water construction).
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.35 for calendar year 2018 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.35 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2018. The EO minimum wage rate will be adjusted annually.
Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/05/2018
1 02/23/2018
ELEC0077-001 02/01/2013
Rates Fringes
Line Construction:
LINEMEN.....................$ 45.62 4%+12.90
ELEC0112-014 06/01/2017
Rates Fringes
ELECTRICIAN......................$ 40.90 20.06
* ENGI0370-010 06/01/2017
Rates Fringes
POWER EQUIPMENT OPERATOR
GROUP 1.....................$ 27.11 15.20
GROUP 2.....................$ 27.43 15.20
GROUP 3.....................$ 28.04 15.20
GROUP 4.....................$ 28.20 15.20
GROUP 5.....................$ 28.36 15.20
GROUP 6.....................$ 28.64 15.20
GROUP 7.....................$ 28.91 15.20
GROUP 8.....................$ 30.01 15.20
ZONE DIFFERENTIAL (Add to Zone 1 rate): Zone 2 - $2.00
Zone 1: Within 45 mile radius of Spokane, Pasco, Washington;
Lewiston, Idaho
Zone 2: Outside 45 mile radius of Spokane, Pasco, Washington; Lewiston, Idaho
POWER EQUIPMENT OPERATORS CLASSIFICATIONS
GROUP 1: Rollers, all types on subgrade, including seal and chip coatings
GROUP 2: Fork Lift
GROUP 3: Bulldozer (up to D-6 or equivalent)
GROUP 4: Loaders (overhead & front-end, under 4 yds. R/T);
Oiler; Drill (churn, core, calyx or diamond)
GROUP 5: Backhoe (Under 45,000 gw); Trackhoe/Excavator (under 3/4 yd.); Cranes (25 tons & under); Drilling equipment (8 unch bit and over) (robbins, reverse circulation and similar); Boom Truck (Under 25 tons)
GROUP 6: Asphalt Roller; Backhoe (45,000 gw and over to 110,000 gw); Trackhoe/Excavator (3/4 yd. to 3 yd.); Cranes (over 25 tons, to and including 45 tons), Bulldozer, 834 R/T & similar; Loader Operator (front-end & overhead, 4 yds. incl. 8 yds.); Mechanic
GROUP 7: Backhoe (Over 110,000); Trackhoe/Excavator (3 yds & over); Cranes (over 45 tons to but not including 85 tons);
Loaders (overhead & front-end, over 8 yds. to 10 yds.);
Grader/Blade
GROUP 8: Cranes (85 tons and over, and all climbing, overhead,rail and tower); Loaders (overhead and front-end, 10 yards and over)
BOOM PAY: (All Cranes, Including Tower) 180 ft to 250 ft $ .50 over scale Over 250 ft $ .80 over scale
NOTE:
In computing the length of the boom on Tower Cranes, they shall be measured from the base of the Tower to the point of the boom.
HAZMAT:
Anyone working on HAZMAT jobs, working with supplied air shall receive $1.00 an hour above classification.
IRON0014-001 07/01/2016
Rates Fringes
IRONWORKER (Reinforcing and Structural)......................$ 32.89 24.56
LABO0238-002 06/01/2017
Rates Fringes
LABORER (Spokane)
GROUP 1.....................$ 24.66 11.30
GROUP 2.....................$ 26.76 11.30
GROUP 3.....................$ 27.03 11.30
GROUP 4.....................$ 27.30 11.30
Zone Differential (Add to Zone 1 rates): Zone 2 - $2.00
BASE POINTS: Spokane, Pasco, Lewiston
Zone 1: 0-45 radius miles from the main post office.
Zone 2: 45 radius miles and over from the main post office
LABORERS CLASSIFICATIONS
GROUP 1: Flagger
GROUP 2: Common or General Laborer;
GROUP 3: Mason Tender-Cement/Concrete; Pipelayer; Chipping Guns
GROUP 4: Grade Checker
LABO0238-007 06/01/2017
Rates Fringes
Laborer, Mason Tender Brick......$ 26.76 11.30
PAIN0005-003 07/01/2017
Rates Fringes
PAINTER (Brush, Roller, and Spray.)..........................$ 25.19 11.10
SUWA2009-051 08/07/2009
Rates Fringes
CARPENTER........................$ 24.03 6.50
CEMENT MASON/CONCRETE FINISHER...$ 17.21 0.00
LABORER: Landscape..............$ 14.67 0.00
TRUCK DRIVER: Dump Truck........$ 19.67 0.00
TRUCK DRIVER: Water Truck.......$ 24.36 8.30
TRUCK DRIVER: 10 Yard Truck.....$ 24.61 8.34
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the
Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
(End of Summary of Changes)