TECHSPECS_Goose_FL_Cooling_Alt_Power.pdf
PDF 2 MB Posted
- Attached to
- Little Goose Fish Ladder Cooling Alternate Power
- Solicitation number
- W912EF18B0028
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Opening_Abstract.pdf | ||
| Site_Visit_Attendee_List.pdf | ||
| 18B0028_Plans.pdf | ||
| A.07.23_Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Little Goose Fish Ladder Cooling Alternate Power W912EF18B0028
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15.00 28 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00.00 28 GENERAL REQUIREMENTS
01 11 01.00 28 SUPPLEMENTARY REQUIREMENTS
01 14 00.10 28 PROJECT SITE RESTRICTIONS
01 14 00.90 28 INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY
(OPSEC)
01 22 00.00 28 MEASUREMENT AND PAYMENT
01 32 16.00 28 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
01 33 00 SUBMITTAL PROCEDURES
01 35 29.10 28 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 01.00 28 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 04.00 28 CONTRACTOR QUALITY CONTROL
01 51 00.00 28 TEMPORARY UTILITIES
01 55 10.00 28 CONTRACTOR WORK, ACCESS AND STORAGE AREAS
01 57 20.00 28 ENVIRONMENTAL PROTECTION
01 78 00.00 28 CLOSEOUT SUBMITTALS
01 78 23.00 28 OPERATION AND MAINTENANCE DATA
DIVISION 03 - CONCRETE
03 60 00.01 28 CONCRETE CORE DRILLING, REPAIR OF CONCRETE SURFACES
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.00 28 CYBERSECURITY
DIVISION 26 - ELECTRICAL
26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL
26 05 13.00 40 MEDIUM-VOLTAGE CABLES
26 05 19.10 10 INSULATED WIRE AND CABLE
26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT
26 05 70.00 40 HIGH VOLTAGE OVERCURRENT PROTECTIVE DEVICES
26 08 00 APPARATUS INSPECTION AND TESTING
26 18 29.00 28 MEDIUM-VOLTAGE ENCLOSED BUS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
This page intentionally left blank
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 01 15.00 28
LIST OF DRAWINGS
PART 1 GENERAL
1.1 SUMMARY
1.2 CONTRACT DRAWINGS
1.3 FOR INFORMATION ONLY DRAWINGS (FIO)
-- End of Section Table of Contents --
DOCUMENT 00 01 15.00 28 Page 1
SECTION 00 01 15.00 28
LIST OF DRAWINGS
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
FILE NUMBER SHEET
NUMBER
DESCRIPTION Revision Number
Date
GENERAL
LGG-1-0-1/424 G-001 COVER SHEET AND LOCATION
MAPS
LGG-1-0-1/425 G-002 INDEX TO DRAWINGS
ELECTRICAL
LGF-1-6-3/10 E-001 ELECTRICAL LEGEND
LGF-1-6-3/11 ED101 EL 634 GALLERY TO LSP2
ROOM - PLAN - REMOVAL
LGF-1-6-3/12 E-101 POWERHOUSE - GENERAL PLAN
- EL 621 / 634
LGF-1-6-3/13 E-102 EL 634 GALLERY TO LSP2
ROOM - PLAN - INSTALL
LGF-1-6-3/14 E-103 NAVIGATION LOCK - LSP2
ROOM - PLAN AND SECTIONS
LGF-1-6-3/15 E-201 XJ7 AND XJO1 - ELEVATION
- INSTALL
LGF-1-6-3/16 E-501 XJ8 AND XJO2 LAYOUT -
ELEVATION 621
LGF-1-6-3/17 E-502 XJ8 AND XJO2 LAYOUT -
PLAN VIEW AND SECTION
LGF-1-6-3/18 E-601 POWERHOUSE - MAIN ONELINE
DIAGRAM
LGF-1-6-3/19 E-602 SCHEMATIC - MAIN UNITS
4-6 - ANNUNCIATOR -
LGF-1-6-3/20 E-603 SCHEMATIC - XJ8
PROTECTION AND TRAPPED
LGF-1-6-3/21 E-604 SCHEMATIC - XJ8 CONTROLS
- INSTALL
LGF-1-6-3/22 E-605 WIRING DIAGRAM - 13.8 KV
SERVICE - INSTALL
DOCUMENT 00 01 15.00 28 Page 2
LGF-1-6-3/23 E-606 CONTROL SCHEMATIC - XJO2
AND ZJ5 - INSTALL
LGF-1-6-3/24 E-607 WIRING DIAGRAM -
SWITCHBOARD S5R2 - INSTALL
LGF-1-6-3/25 E-608 SCHEMATIC - GOVERNOR
INTERPOSING RELAYS -
LGF-1-6-3/26 E-609 SCHEDULE - GOVERNOR
INTERPOSING RELAYS -
LGF-1-6-3/27 E-610 WIRING DIAGRAM -
SWITCHBOARD S5R1 - SHEET
LGF-1-6-3/28 E-611 WIRING DIAGRAM -
SWITCHBOARD S5R1 - SHEET
LGF-1-6-3/29 E-612 WIRING DIAGRAM -
SWITCHBOARD S5R1 - SHEET
LGF-1-6-3/30 E-613 WIRING DIAGRAM -
SWITCHBOARD S5R1 - SHEET
LGF-1-6-3/31 E-614 DIAGRAM - MAIN UNITS 5-6
- ONE LINE - INSTALL
LGF-1-6-3/32 E-615 DIAGRAM - MAIN UNITS 5-6
- THREE LINE - INSTALL
LGF-1-6-3/33 E-616 SCHEDULE - CABLE AND
CONDUIT
LGF-1-6-3/34 E-617 WIRING - XJ8 - INSTALL
LGF-1-6-3/35 E-618 WIRING - XJ02 - INSTALL
LGF-1-6-3/36 E-901 ELECTRICAL - MAIN UNITS
1-3 - ISOMETRIC
LGF-1-6-3/37 E-902 ELECTRICAL - MAIN UNITS
4-6 - ISOMETRIC
LGF-1-6-3/38 E-903 ELECTRICAL - PHOTOGRAPHS 1
LGF-1-6-3/39 E-904 ELECTRICAL - PHOTOGRAPHS 2
LGF-1-6-3/40 E-905 ELECTRICAL - PHOTOGRAPHS 3
LGF-1-6-3/41 E-906 ELECTRICAL - PHOTOGRAPHS 4
Microstation V8 is the only CAD system used by Walla Walla District.
Contract drawings created on CAD in Microstation V8 will be available in electronic form for use by the Contractor. No For Information Only drawings are available on CAD. The Contractor assumes all risks associated in using electronic CAD drawings. The contract drawings shall govern if there are any discrepancies between the electronic copy and the contract drawing.
The Contractor shall promptly notify the Contracting Officer of any discrepancies. The Government will not be responsible to correct the electronic CAD drawing. If contract modifications are issued, the associated electronic CAD drawings will not be available to the Contractor. Electronic copies of CAD drawings are only available in Bentley MicroStation format. The Government will provide the files on CD
ROM.
1.3 FOR INFORMATION ONLY DRAWINGS (FIO)
These FIO drawings are included with the drawings for information. The
DOCUMENT 00 01 15.00 28 Page 3
Government does not warrant the accuracy of the FIO drawings. The Government recommends that the Contractor verify the accuracy of FIO drawings.
FIO drawings are as follows:
FILE NUMBER SHEET
NUMBER
DESCRIPTION Revision Number
Date
LGP-1.9-6-1G1/6 FIO-001 POWERHOUSE UNITS 4-6 - MAIN
UNIT GALLERY & INTAKE DECK
LGP-1.37-6-9A24 FIO-002 DIGITAL GOVERNOR UPGRADE -
STATION SERVICE XJO2
7683-18-1 FIO-003 13.8 KV STATION SERVICE XJO2
7683-23-1 FIO-004 13.8 KV STATION SERVICE TAP
NO 2
73918-1 FIO-005 OUTLNE DIAGRAM - LITTLE
GOOSE SUBSTATION - 13.8 KV
73918-2A FIO-006 SCHEMATIC DIAGRAM - LITTLE
GOOSE SUBSTATION - METERING
73918-4A FIO-007 WIRING DIAGRAM - LITTLE
GOOSE SUBSTATION - BUS
73918-4B FIO-008 WIRING DIAGRAM - LITTLE
GOOSE SUBSTATION - BREAKER
LPG-1.1-6-1A11/ FIO-009 EQUIPMENT INSTALLATION -
INTAKE GALLERY - EL 637
E-401 FIO-010 UC-1 - POWERHOUSE EL. 634 -
FLOOR PLAN AND SECTIONS
LGP-1-4-2/36 FIO-011 POWERHOUSE - GENERATOR BAYS
- CONCRETE - OUTLINE -
LGP-1-4-2/87 FIO-012 POWERHOUSE - GENERATOR BAYS
- REINFORCEMENT - INTAKE
LGP-1-4-2/88 FIO-013 POWERHOUSE - GENERATOR BAYS
- REINFORCEMENT - INTAKE
LGP-1.9-4-4/19 FIO-014 POWERHOUSE UNIT 4-6 -
REINFORCEMENT - INTAKE
LGP-6-0-0/5 FIO-015 POWERHOUSE - ARRANGEMENT -
GENERATOR BAY - PLAN
LGP-1.1-6-1A11/ FIO-016 POWERHOUSE - ELECTRICAL -
METAL TRAY SYSTEM -
LGP-1.9-6-1A11/ FIO-017 POWERHOUSE - UNITS 4-6 -
ELECTRICAL EQUIPMENT -
-- End of Document --
DOCUMENT 00 01 15.00 28 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 00.00 28
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
SECTION 01 00 00.00 28 Page 1
SECTION 01 00 00.00 28
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
Federal Veteran employment information at http://www.fedshirevets.gov/index.aspx
Department of Labor Veterans Employment Assistance http://www.dol.gov/vets/
Department of Veterans Affairs-VOW to Hire Heroes Act http://benefits.va.gov/vow/
Army Wounded Warrior Program -http://wtc.army.mil/modules/employers/index.html
U.S. Chamber of Commerce Foundation-Hiring Our Heroes http://www.hiringourheroes.org/
Guide to Hiring Veterans - Reference Material http://www.whitehouse.gov/sites/default/files/docs/white_house _business_council_-_guide_to_hiring_veterans_0.pdf
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section --
SECTION 01 00 00.00 28 Page 2
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 01.00 28
SUPPLEMENTARY REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 FIELD VERIFICATION OF SITE CONDITIONS
1.4 DEFINITIONS
1.5 REGULAR CLEANUP AND DEBRIS DISPOSAL
1.6 GOVERNMENT ISSUED ITEMS
1.7 EQUIPMENT LIST
1.8 TESTING OF EQUIPMENT
1.9 DISPOSITION OF REMOVED MATERIALS AND EQUIPMENT
1.10 PROTECTION AND RESTORATION OF EXISTING FACILITIES
1.11 PRE-WORK AND POST WORK SURVEYS
1.12 PROTECTION OF POWERHOUSE FLOORS
1.13 AIR PURITY CONTROL IN THE POWERHOUSE
1.14 FIRE CONTROL
1.15 TRAINING
1.16 PROJECT OPERATORS' TRAINING
1.17 PROJECT SUPERINTENDENT
1.18 KEY PERSONNEL SUBSTITUTION
1.19 POST AWARD MEETINGS
1.19.1 Pre-Work Meeting
1.19.2 Pre-Construction Meeting
1.19.2.1 Minutes
1.19.2.2 Demobilizing And Remobilizing
1.20 WEEKLY PRODUCTION MEETINGS
1.20.1 Minutes
1.21 WEEKLY PRODUCTION MEETINGS
1.21.1 Minutes
1.22 ADDITIONAL MEETINGS
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
ATTACHMENTS:
Weekly Meeting Agenda Template
Weekly Meeting Agenda
SECTION 01 11 01.00 28 Page 1
SECTION 01 11 01.00 28
SUPPLEMENTARY REQUIREMENTS
PART 1 GENERAL
The work covered by this section of the specifications consists of work common to more than one section of these TECHNICAL SPECIFICATIONS.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 Safety and Health Requirements Manual
Comply with the current edition and all changes posted on the web as of the effective date of this solicitation.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only. Designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit in accordance with SECTION
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Equipment List; I C
Pre-Work Survey Photos And Report; I C
Air Purity Control Program; I C
Project Superintendent; I C
SD-07 Certificates
Key Personnel Substitution; G C
SD-11 Closeout Submittals
Post-Work Survey Photos And Report; I C
Training Manuals; G C
Government Issued Items; G C
1.3 FIELD VERIFICATION OF SITE CONDITIONS
Field verify all elevations, dimensions, and coordinates of existing
SECTION 01 11 01.00 28 Page 2 features indicated on the contract drawings that affect new construction.
Any deviations shall be updated as per SECTION 01 78 00.00 28, CLOSEOUT SUBMITTALS, paragraph WORKING AS-BUILT CONTRACT DRAWINGS AND FIO DRAWINGS.
1.4 DEFINITIONS
a. Qualified Person.
As defined in EM 385-1-1; "DEFINITIONS", unless otherwise specified.
b. F.O.B.
An abbreviation for free on board, which means that a vendor or consignor will deliver goods on a railroad car, truck, vessel, or other conveyance without any expense to the purchaser or consignee.
1.5 REGULAR CLEANUP AND DEBRIS DISPOSAL
With the exception of materials specifically indicated or specified to be salvaged for reuse in construction, or turned over to the Government, all wastes and demolished materials shall become the property of the Contractor and shall be removed from the job site daily in accordance with Federal, State, and local regulations. The Contractor shall furnish waste containers. All small waste containers provided by the contractor shall be emptied daily, large bin containers shall be emptied when full or once a week.
1.6 GOVERNMENT ISSUED ITEMS
Return to the Government all items issued to the Contractor from the Government, including but not limited to the following: keys, ID and security badges, radios, pagers, and excess/unused Government Furnished Property/Equipment. Submit documentation signed by the Contractor and Contracting Officer indicating items have been returned or fully accounted for. Format of submittal will be discussed and agreed upon at the Pre-Work Meeting.
1.7 EQUIPMENT LIST
Furnish a complete list of all equipment to be used on the Project 30 days prior to commencement of on-site work. Submit a revised list in the event of change of equipment. Lists shall include rented equipment as well as lease-purchase or sale-leaseback equipment. The initial list and the revised lists shall indicate dates equipment is assigned to or removed from the Project and adequate identification or description of each item of equipment including manufacturer's name (abbreviated), model number, manufacturer's serial number, year of manufacture, and Contractor's assigned serial or record number.
1.8 TESTING OF EQUIPMENT
Before any machinery or mechanized equipment is put to use on the job, it shall be inspected and tested by a qualified person and determined to be in safe operating condition. Cranes or derricks shall be tested by the Contractor or a qualified testing agency in accordance with EM 385-1-1.
Equipment shall be large enough to safely handle proposed picks or tasks without exceeding the crane rating established by these tests.
SECTION 01 11 01.00 28 Page 3
1.9 DISPOSITION OF REMOVED MATERIALS AND EQUIPMENT
Unless otherwise specified in other sections of the specifications, all existing equipment removed and not reinstalled shall become the property of the Contractor, removed from the Project site, and disposed of in a legal manner. Materials that cannot be removed daily may be temporarily stored on-site at an approved area. Salvaged materials shall not be sold on the project site.
1.10 PROTECTION AND RESTORATION OF EXISTING FACILITIES
Reference FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984).
1.11 PRE-WORK AND POST WORK SURVEYS
Conduct a pre-work survey prior to start of on-site work and a post-work survey during project closeout, with the Contracting Officer Representative, of the Government facilities at the work areas. The results of the surveys shall be documented by digital photographs and descriptive narrative reports. A color copy of the survey photographs and narrative reports shall be submitted to the Contracting Officer within five
(5) days after survey has been completed.
1.12 PROTECTION OF POWERHOUSE FLOORS
a. Care shall be taken to prevent damage to all floors and curbs within the Powerhouse. Protection shall include a continuous layer of oil-impervious kraft paper over the existing floor surface with joints of the kraft paper joined with an appropriate tape. In addition, tongue and groove 3/4-inch-thick Oriented Strand Board (OSB) plywood shall be installed over the craft paper at all work and storage areas. Plywood joints shall be fastened to ensure edges of plywood sheets are, and remain, flush with each other and do not pose a tripping hazard during execution of this work. Minimum nominal 2"x4" wood shall be installed along existing curb features within the contractor work areas and along perimeters of the work areas. Wood used for curb protection shall be secured in place without anchoring into the existing floors or curbs.
b. Pipe trenches shall remain accessible even if covered. All designations relating to fire protection equipment that get covered shall be marked on the temporary floor covering. Provide additional blocking and wood supports when required. Also suitably protect other surfaces of work. Damage to floors or curbs caused by the Contractor's operations shall be repaired at no additional cost to Government.
Repairs shall match the surrounding area in material type, color, texture, and surface finish and are subject to approval. Work in the powerhouse shall not start until floor and curb protection is in place.
1.13 AIR PURITY CONTROL IN THE POWERHOUSE
Take all necessary precautions to maximize the control, and prevention, of all dust and fumes created by operations under this contract from escaping into the powerhouse. To the maximum extent possible, all dust and dirt shall be removed by vacuum cleaning. At least 30 working days prior to commencement of work in the powerhouse, submit for approval, in writing, a proposed Air Purity Control Program. Air Purity Control Program shall include, but not necessarily be limited to, the following:
SECTION 01 11 01.00 28 Page 4
(1) Adequate isolation and ventilation of air arcing, welding, burning, and grinding operations.
(2) Provision of exhaust ducts that shall discharge outside the powerhouse structure where mechanical ventilation is used.
(3) Controlled operation of power driven tools.
(4) Furnishing and removing of oiled sawdust or other dust preventatives in areas that cannot be properly rendered free from excessive dusting by vacuum cleaning or other methods.
(5) Vacuum cleaning of spaces within the work areas where dust accumulates.
(6) Air-, electrical-, or battery-driven equipment may be used inside the powerhouse.
(7) Internal-combustion engine powered equipment will not be permitted to operate inside the powerhouse unless exhausted to the exterior except for short periods of time (not to exceed 15 minutes in a 2 hour window) to unload materials and equipment.
Depending upon the Contractor's plant, equipment, and methods of operation, additional provisions for satisfactory air purity control will be required and shall be included in the proposed Air Purity Control Program.
1.14 FIRE CONTROL
Each piece of internal combustion engine driven equipment used at the work site shall be equipped with a fire extinguisher in accordance with National Fire Protection Association (NFPA) recommendations as appropriate. The minimum approved rating of extinguishers shall not be less than 5-B:C.
1.15 TRAINING
Provide the services of authorized start-up engineers (Manufacturer's Representatives) as necessary to provide training in programming, operation and maintenance of the medium-voltage switchgear, medium-voltage circuit breaker, medium-voltage bus duct, medium-voltage cable, and protective relays. Provide training for operators and maintenance personnel prior to project operation of the system. Provide two, eight-hour class sessions;
one class for operators and maintenance personnel and one for system managers and engineers. Each class session shall include approximately 6 employees. The Government will provide for the training location. Submit training manuals and documentation for approval 30 days prior to scheduled classes and furnish sufficient training materials at the training classes for all students plus a minimum of three (3) copies for project files.
Where audio/visual materials are used in training classes, three (3) copies of such materials shall be furnished to the Project for use in future training. It shall be the Contractor's responsibility to coordinate the training sessions with the Project to ensure minimum conflicts with ongoing Project work.
1.16 PROJECT OPERATORS' TRAINING
Provide the services of one or more authorized individuals for Project Operators' training. Contractor personnel shall be experienced in the operational requirements of all newly installed equipment, and control
SECTION 01 11 01.00 28 Page 5 features. Contractor personnel shall be present at the project and available for assistance for three (3) consecutive ten-hour work shifts following Government acceptance of newly installed features. Required work shifts shall be coordinated with the Contracting Officer and are likely to occur in August.
1.17 PROJECT SUPERINTENDENT
At all times during performance of this contract and until the work is completed and accepted, assign and have on the worksite, a competent superintendent as per FAR Clause 52.236-6 "Superintendence by the Contractor". Submit Superintendent name and contact information prior to start of on-site construction.
1.18 KEY PERSONNEL SUBSTITUTION
If the Contractor plans on replacing any Key personnel (Project Superintendent, CQC System Manager, or CQC staff Members) they must have the approval of the Contracting Officer. Personnel shall possess the qualifications that meet or exceed those stated in this contract for the position of the individual they are replacing. Submit qualifications of new personnel at least 15 calendar days in advance of date of replacement.
1.19 POST AWARD MEETINGS
1.19.1 Pre-Work Meeting
Within 10 calendar days after receipt of Notice to Proceed, attend a Pre-Work Meeting. Senior Level members of the Contractor's staff involved with this contract shall participate in this meeting to discuss the overall contract requirements. The Government will lead this meeting and take the meeting minutes.
1.19.2 Pre-Construction Meeting
Coordinate with the Contracting Officer and establish the date of the Pre-Construction Meeting. The meeting will be held at the Project site at least one (1) week prior to mobilizing to the job site. Lead the Pre-Construction Meeting discussing the Contractor's plan on executing the work at the project site, schedule, required clearances and timeframe for them, and plan for implementing safety and quality control. The Government will have key members from the Project staff to discuss environmental and clearance issues. Key members of the contractor staff shall attend this meeting including the Quality Control (QC) System Manager, Site Safety and Health Officer (SSHO) and any other members determined by the Government to be required.
1.19.2.1 Minutes
Contractor is responsible for taking the meeting minutes and shall send them electronically within 48 hours of the meeting to the Government's Project Engineer, Quality Assurance Representative, and Resident Engineer.
1.19.2.2 Demobilizing And Remobilizing
Anytime the Contractor demobilizes from the site and remobilizes at a later date, another Pre-Construction Meeting shall be held and shall follow the requirements listed above.
SECTION 01 11 01.00 28 Page 6
1.20 WEEKLY PRODUCTION MEETINGS
During all fabrication and onsite construction work, the Project Superintendent shall lead a weekly production meeting using the attached " Weekly Meeting Agenda Template" to brief the Government on the status of the project. All elements listed in the agenda shall be thoroughly discussed. For example, the Project Superintendent shall provide the Government a three (3) week "look-ahead" that describes all the planned construction activities, onsite and offsite, over the next three (3) weeks. These activities shall align to the overall construction schedule submitted under SECTION 01 32 16.00 28 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULE, and if the three (3) week "look-ahead" differs from the construction schedule, the construction schedule shall be updated to include these changes by the next scheduled update. Key members of the Contractor's staff shall attend this meeting, including the Quality Control System Manager, who is responsible for discussing QC aspects of the work as outlined under SECTION 01 45 04.00 28 CONTRACTOR QUALITY CONTROL and SSHO.
The Government reserves the right to require any person from the Contractor's staff, such as the Project Manager, Engineer, scheduler, etc., or key subcontractor personnel to attend this meeting, if Government determines their participation is required.
Submit each meeting agenda to the COR 24 hours prior to the meeting.
1.20.1 Minutes
The Project Superintendent shall be responsible for taking the meeting minutes and shall send them electronically within 24 hours of the meeting to the Government's Project Engineer, Quality Assurance Representative, and Resident Engineer.
1.21 WEEKLY PRODUCTION MEETINGS
During all fabrication and onsite construction work, hold a weekly production meeting to brief the Government on the status of the project.
a. Use the attached "Weekly Meeting Agenda" and discuss all elements of this agenda.
b. Provide a three (3) week 'look ahead'
1. Describe all planned construction activities, on-site and off-site over the next three (3) weeks.
2. ENSURE these activities align to the overall construction SCHEDULE submitted under SECTION 01 32 16.00 28 SMALL PROJECT
CONSTRUCTION PROGRESS SCHEDULE.
3. RECORD any changes to the Project Schedule AND INCLUDE IN the next scheduled update.
c. Key members of the Contractor's staff including the Quality Control System Manager and the SITE SAFETY AND HEALTH OFFICER shall attend.
d. The Quality Control System Manager shall discuss all QC aspects outlined in SECTION 01 45 04.00 28 CONTRACTOR QUALITY CONTROL.
e. The Government reserves the right to require any person from the Contractor's staff such as the Project Manager, Engineer, Scheduler or
SECTION 01 11 01.00 28 Page 7
Key Subcontractor Personnel to attend the meeting.
1.21.1 Minutes
The Contractor shall be responsible for taking the meeting minutes and shall send them electronically within 24 hours of the meeting to the Government's Project Engineer, Quality Assurance Representative, and Resident Engineer.
1.22 ADDITIONAL MEETINGS
Record the minutes of all meetings, including all conference calls, that occur between the Contractor and Government. Send minutes electronically within 24 hours of the meeting to the Contracting Officer for concurrence.
E-mail subject line shall include project name and meeting topic.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
SECTION 01 11 01.00 28 Page 8
Weekly Meeting agenda template
Schedule - Work scheduled over the next week Three week look ahead Overall Schedule Review
Submittals Review- Submittal Register Submittals approved by QC Outstanding Submittals RFI’s Letters
Coordination - Clearances required over the next week, include the following:
A description of the work to be performed under the Clearance.
Determine the correct energy isolation points needed to perform the work safely.
Physical barriers, protective grounds, piping blanks, or bulkheads that shall be used, including locations.
Determine the procedure and method of testing for stored energy if applicable.
The date and time the Clearance shall be required.
The estimated length of time the system or equipment shall be out of service and the time to return the system or equipment to service in an emergency.
Coordination issues
Safety- Review of AHA’s for ongoing work Pending AHA’s
Required for new work Status of Gov’t approval
Safety issues
QC -
Preparatory meetings Held over last week- status of meeting minutes
Required over the next week Initial meetings over the next week Follow up over the next week Rework list Review Deficiency tracking log
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00.10 28
PROJECT SITE RESTRICTIONS
PART 1 GENERAL
1.1 REFERENCES
1.2 SITE CONDITIONS AND OPERATIONAL RESTRICTIONS
1.3 OUTAGES
1.4 PROJECT SECURITY
1.4.1 Vehicle Access
1.4.2 Identification of Employees
1.4.3 Delivery of Equipment
1.5 FACILITY OCCUPANCY CLOSURE
1.6 WORK SCHEDULES
1.6.1 Contractor's Work Schedule
1.6.2 Government's Work Schedule
1.7 USE OF WALLA WALLA DISTRICT PARKS
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
SECTION 01 14 00.10 28 Page 1
SECTION 01 14 00.10 28
PROJECT SITE RESTRICTIONS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 Safety and Health Requirements Manual
Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.
1.2 SITE CONDITIONS AND OPERATIONAL RESTRICTIONS
1. Use of Government cranes (Government or Contrator operated) will not be available for this project. Government crane riggers will also not be available to support Contractor operations.
2. Keep one lane open for vehicle access across the dam at all times.
If a road blockage is necessary, it shall be coordinated and approved by the Government 48 hours in advance of the blockage. Immediate access shall be given in the event of an emergency.
1.3 OUTAGES
Several types of outages are required to perform the work. The Contractor shall request outages a minimum of 60 days prior to when the outage is needed. The request shall include the outage start date, expected duration, type of outage (i.e. line, unit, sectionalizing cabinet, station service transformer outage) and the work being performed that needs the outage. No line outage requests will be approved for Work Window 2.
Outage requirements will be discussed at the prework meeting.
1.4 PROJECT SECURITY
The Project site is a secured area and access onto the Project is restricted. The security measures affect all of the Contractor's vehicles and personnel. There will be delays when entering Projects due to locked gates, vehicle inspections, and personnel checks. Inspections and checks may include inspection of tool boxes, brief cases, lunch boxes, and other containers.
1.4.1 Vehicle Access
Project access roads on both sides of the dams are secured with locked gates. All vehicles that pass through the locked gates will be subject to being searched. No privately owned vehicles (POV's) will be allowed
SECTION 01 14 00.10 28 Page 2 through locked gates. Only Contractor's work vehicles and equipment that are essential to the conduct of the work will be allowed in the work areas. All Contractor vehicles shall display suitable permanent or temporary identification.
1.4.2 Identification of Employees
Responsible for furnishing an identification badge/card to each employee prior to the employee's work on the Project site, and for requiring each employee engaged on the work to display identification at all times.
Badges shall include photo identification, company name, and the individual's name and company identification number as a minimum. Badges shall be laminated plastic type. All prescribed identification shall immediately be delivered to the Contracting Officer for cancellation upon the release of the employee or project completion. If required by the Contracting Officer, employees will be photographed by the Government.
Employees who fail to submit to photographing will not be allowed on the Project site.
Every Contractor employee (prime or subcontractor) shall have a hard hat meeting the requirements of
EM 385-1-1. Hardhats shall display the Prime Contractor name, subcontractor name, and the employee's name. Contractor employee hardhats shall not be white with red markings. It shall be the responsibility of the Project Superintendent to enforce this requirement.
1.4.3 Delivery of Equipment
Contractor shall be responsible for delivery and receipt of all materials and equipment. Government personnel will not be available to assist the Contractor in these activities. To the maximum extent possible, deliveries shall arrive on the same side of the river as the Contractor's work area.
Delivery vehicles will be allowed to cross the river over the dam only with Government approval. Delivery vehicles arriving on the opposite side of the river as the work area shall be unloaded outside the locked gate, equipment shall be loaded onto Contractor's vehicles, and Contractor's vehicles will then be allowed to cross the dam to the work area.
1.5 FACILITY OCCUPANCY CLOSURE
Streets, walks, and other facilities occupied and used by the Government shall not be closed or obstructed without written permission from the Contracting Officer.
1.6 WORK SCHEDULES
1.6.1 Contractor's Work Schedule
At the Pre-Work Meeting, furnish a schedule of number of working days per week, shifts per day, and hours per shift for contract work. Furnish notification of any change of schedule of regular work hours, overtime work hours, and shifts of work crews and personnel at the site. This notification shall be provided a minimum of 48 hours prior to any schedule change to allow suitable scheduling of Government personnel and inspection. Exception to this requirement may be allowed in case of schedule change due to emergency conditions.
SECTION 01 14 00.10 28 Page 3
1.6.2 Government's Work Schedule
The maintenance crews at the dam work from 6:30 a.m. to 5:00 p.m., Monday through Thursday. Crews and staff do not work on weekends and Federal holidays. If a Federal holiday falls on a Friday, the crews and staff do not work on the preceding Thursday. A powerhouse operator is at the site 24 hours a day, 7 days a week, including Federal holidays but is not available to assist the Contractor.
If the Contractor requires Government support or assistance outside of normal work hours, the Contractor must make a formal written request to the Contracting Officer at least one week prior to the date that support/assistance is needed. The Government will review this request, but there is no guarantee that Government support or assistance can be provided.
1.7 USE OF WALLA WALLA DISTRICT PARKS
Special consideration for the use of the Walla Walla District Camping Grounds will not be given to the Contractor if camping at these sites. The Contractor's crew may not use Government parking lots near the Little Goose Lock and Dam for RV parking.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used) -- End of Section --
SECTION 01 14 00.10 28 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00.90 28
INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY (OPSEC)
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.2.1 Biographical Information (HC) Submittal
1.3 AT LEVEL 1 TRAINING
1.4 ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES
1.5 FOR CONTRACTORS WHO DO NOT REQUIRE CAC, BUT REQUIRE ACCESS TO A DOD
FACILITY OR INSTALLATION
1.6 SUSPICIOUS ACTIVITY REPORTING TRAINING (iWATCH And/Or CORPS WATCH
Training)
1.7 FOR CONTRACTS THAT REQUIRE OPSEC TRAINING
1.8 PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
SECTION 01 14 00.90 28 Page 1
SECTION 01 14 00.90 28
INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY (OPSEC)
PART 1 GENERAL
The work covered by this section of the specifications consists of work common to more than one section of these TECHNICAL SPECIFICATIONS. This contract does not require access to or handling of classified material.
This contract does not require access to sensitive information, or equipment. It does require access to restricted areas. Little Goose Dam is considered a restricted area.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY (DA)
AR 190-13 (2011) The Army Physicialc Security Program
Army Directive 2014-05 (2014) Policy and Implementation Procedures for Common Access Card Credentialing and Installation Access for Uncleared Contractors
Website for Department of the Army Regulations:
http://armypubs.army.mil/
Federal Acquisition Regulation (FAR)
FAR 52.204-9 (2015) Personal Identity Verification of Contractor Personnel
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only. The designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Anti Terrorism (AT) Level 1; I, C iWATCH And/Or CORPS WATCH Training; I, C
Level 1 OPSEC training; I, C
Pre-Screen Candidates Using E-Verify Program; I, C
Biographical Information (HC); G, C
SECTION 01 14 00.90 28 Page 2
1.2.1 Biographical Information (HC) Submittal
Biographical Information shall only be submitted to the address below.
Submit one hard copy. No electronic copies shall be submitted.
District Commander
ATTN: CENWW-EC-C
Walla Walla District Corps of Engineers 201 North Third Avenue Walla Walla, WA 99362-1876
See paragraph "ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES" for additional information and details on items to submit.
1.3 AT LEVEL 1 TRAINING
All contractor employees requiring access to Army installations, facilities and controlled access areas shall complete Anti Terrorism (AT) Level 1 awareness training within 30 days after Notice to Proceed and annually thereafter until project completion. Submit certificates of completion for each employee to the contracting officer within 5 calendar days after initial completion of training or annual refresher. The contractor shall retain employee training certificates for the duration of the contract and maintain a current roster of the names of employees who have completed the training with the most recent date that the training was completed. The contractor shall update the roster and resubmit to the contracting officer no later than 5 calendar days after completion of refresher training or a new employee completes certification. AT Level I awareness training can be completed in approximately two (2) hours and is available at the following website: http://jko.jten.mil/courses/atl1/launch.html
1.4 ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES
All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by the Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR 52.204-9, Personal Identity Verification of Contractor Personnel:
http://www.ecfr.gov/cgi-bin/text-idx?rgn=div8&node=48:2.0.1.1.1.2.1.28) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
For each individual that will be working at Little Goose, submit a copy of their driver's license to satisify the information required to conduct the background check. Background check must be approved for an individual before they can access the site.
SECTION 01 14 00.90 28 Page 3
1.5 FOR CONTRACTORS WHO DO NOT REQUIRE CAC, BUT REQUIRE ACCESS TO A DOD
FACILITY OR INSTALLATION
Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13:
https://login.us.army.mil/login/fcc/caclogin.fcc?TYPE=33554433&REALMOID=06-649cf860-c8b5 P%2b), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
1.6 SUSPICIOUS ACTIVITY REPORTING TRAINING (iWATCH And/Or CORPS WATCH Training)
The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program (iWATCH, CORPS WATCH, or SEE SOMETHING, SAY SOMETHING).
This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 60 calendar days of Notice to Proceed and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.
1.7 FOR CONTRACTS THAT REQUIRE OPSEC TRAINING
All new contractor employees will complete Level I OPSEC Training within 30 calendar days of their reporting for duty. Additionally, all contractor employees must complete annual OPSEC awareness training. The contractor shall submit Level 1 OPSEC training certificates of completion for each affected contractor and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training. OPSEC awareness training is available at the following websites: https://www.iad.gov/ioss/ or http://www.cdse.edu/catalog/operations-security.html; or it can be provided by the RA OPSEC Officer in presentation form which will be documented via memorandum.
1.8 PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM
The Contractor must pre-screen Candidates using the E-verify Program ( http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after Notice to Proceed." *When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.
SECTION 01 14 00.90 28 Page 4
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
SECTION 01 14 00.90 28 Page 5
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 28
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 RETAINAGE OF PAYMENT
1.2 CLIN 0001 LITTLE GOOSE FISH LADDER ALTERNATE POWER
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 22 00.00 28 Page 1
SECTION 01 22 00.00 28
MEASUREMENT AND PAYMENT
PART 1 GENERAL
In each instance, the contract price for an item shall constitute full compensation for furnishing all plant, labor, equipment, and materials, and for performing all operations required to complete the work included in the item as herein specified, or as otherwise approved.
1.1 RETAINAGE OF PAYMENT
Retainage in the amount of 10 percent of original contract award amount will be withheld until the final submittals, listed below, have been approved by the Government. The 10 percent retainage for final submittals will be held until such time as the Contractor has earned 90 percent of the original contract value. See SECTION 01 78 00.00 28 "CLOSEOUT SUBMITTALS" for additional information.
a. Final Approved Versions of Contractor Prepared Drawings.
b. As-built contract drawings and FIO drawings.
c. Return of Government Issued Items.
1.2 CLIN 0001 LITTLE GOOSE FISH LADDER ALTERNATE POWER
Little Goose Fish Ladder Alternate Power will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0001, "Little Goose Fish Ladder Alternate Power," which price and payment shall be full compensation for all work required for construction, complete, as specified and approved.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 22 00.00 28 Page 2
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 16.00 28
SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
PART 1 GENERAL
1.1 SUBMITTALS
1.2 ACCEPTANCE
1.3 SCHEDULE FORMAT
1.3.1 Network Analysis Schedule (NAS)
1.3.1.1 Primavera P6 Settings and Parameters
1.3.1.2 Microsoft Project 2010 Settings and Parameters
1.3.1.3 Cost Loading Microsoft Project 2010 Schedules
1.3.2 Schedule Submittals and Procedures
1.4 SCHEDULE MONTHLY UPDATES
1.5 CONTRACT MODIFICATION
1.6 3-WEEK LOOK AHEAD SCHEDULE
1.7 CORRESPONDENCE AND TEST REPORTS:
1.8 ADDITIONAL SCHEDULING REQUIREMENTS
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
SECTION 01 32 16.00 28 Page 1
SECTION 01 32 16.00 28
SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only. Designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit in accordance with SECTION
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Construction Schedule; G, C
SD-07 Certificates
Monthly Updates; G, C
1.2 ACCEPTANCE
Prior to the start of work, prepare and submit to the Contracting Officer for acceptance a construction schedule in the form of a Network Analysis Schedule (NAS) in accordance with the terms in Contract Clause "FAR 52.236-15, Schedules for Construction Contracts," except as modified in this contract.
The acceptance of a Baseline Construction Schedule is a condition precedent to:
a. The Contractor starting work on the demolition or construction stage(s) of the contract.
b. Processing Contractor's invoice(s) for construction activities/items of work.
c. Review of any schedule updates.
Submittal of the Baseline Schedule, and subsequent schedule updates, is understood to be the Contractor's certification that the submitted schedule meets all of the requirements of the Contract Documents, represents the Contractor's plan on how the work will be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced (as-built logic).
1.3 SCHEDULE FORMAT
1.3.1 Network Analysis Schedule (NAS)
Use the critical path method (CPM) to schedule and control project activities. Prepare and maintain project schedules using Primavera P6 or Microsoft Project 2010. Importing data into the scheduling program using data conversion techniques or third party software is cause for rejection
SECTION 01 32 16.00 28 Page 2 of the submitted schedule. Build the schedule as follows:
a. The Project Schedule must show pre-construction submittals, Government review periods, material/equipment delivery, utility outages, all on-site construction, inspection, testing, and closeout activities.
Government and Contractor on-site work activities must be driven by calendars that reflect Saturdays, Sundays and all Federal Holidays as non-work days.
b. With the exception of the Contract Award and End Contract milestone activities, no activities shall be open-ended; each activity must have predecessor and successor ties. No activity must have open start or open finish (dangling) logic. Minimize redundant logic ties. Once an activity exists on the schedule it must not be deleted or renamed to change the scope of the activity and must not be removed from the schedule logic without approval from the Contracting Officer. While an activity cannot be deleted, where said activity is no longer applicable to the schedule but must remain within the logic stream for historical record, it can be changed to a milestone. Document any such change in the milestone's "Notebook", including a date and explanation for the change. The ID number for a deleted activity must not be re-used for another activity.
c. Each activity must be assigned its appropriate Responsibility Code indicating responsibility to accomplish the work indicated by the activity, Phase Code and Work Location Code.
d. Date/time constraint(s) and/or lags, other than those required by the contract, are not allowed unless accepted by the Contracting Officer.
Include as the last activity in the contract schedule, a milestone activity named "Contract Completion Date".
1.3.1.1 Primavera P6 Settings and Parameters
Use the following Primavera P6 settings and parameters in preparing the Baseline Schedule. Deviation from these settings and parameters, without prior consent of the Contracting Officer, is cause for rejection of schedule submission.
a. General: Define or establish Calendars and Activity Codes at the "Project" level, not the "Global" level.
b. Admin Drop-Down Menu, Admin Preferences, Time Periods Tab:
(1) Set time periods for P6 to 8.0 Hours/Day, 40.0 Hours/Week, 172.0 Hours/Month and 2000.0 Hours/Year.
(2) Use assigned calendar to specify the number of work hours for each time period: Must be checked.
c. Project Level, Dates Tab:
(1) Set "Must Finish By" date to "Contract Completion Date".
d. Project Level, Defaults Tab:
(1) Duration Type: Set to "Fixed Duration & Units".
SECTION 01 32 16.00 28 Page 3
(2) Percent Complete Type: Set to "Physical".
(3) Activity Type: Set to "Task Dependent".
(4) Calendar: Set to "Standard 5 Day Workweek". Calendar must reflect Saturday, Sunday and all Federal holidays as non-work days.
Alternative calendars may be used with Contracting Officer approval.
e. Project Level, Calculations Tab:
(1) Activity percent complete based on activity steps: Must be Checked.
(2) Reset Remaining Duration and Units to Original: Must be Checked.
(3) Subtract Actual from At Completion: Must be Checked.
(4) Recalculate Actual units and Cost when duration percent(%) complete changes: Must be Checked.
(5) Link Actual to Date and Actual This Period Units and Cost: Must be Checked.
f. Project Level, Settings Tab:
(1) Define Critical Activities: Check "Total Float is less than or equal to" and add "0d".
g. No on-site construction activity may have durations in excess of 10 working days.
1.3.1.2 Microsoft Project 2010 Settings and Parameters
The Network must have a minimum of 30 construction activities. No on-site construction activity may have durations in excess of 10 working days.
1.3.1.3 Cost Loading Microsoft Project 2010 Schedules
Assign material, labor and equipment costs to their respective Construction Activities. Material and equipment costs for which payment will be requested in advance of installation must be assigned to their respective procurement activity (i.e. the material/equipment on-site activity).
Evenly disperse overhead and profit to each activity over the duration of the project. Cost loading must total to 100 percent of the value of the contract.
a. Submit an Earned Value Report with each schedule update showing activity budget, cost percent complete, earned amount and cost to complete as directed by the Contracting Officer.
b. With each schedule submission, provide a Schedule Variance control (SVC) diagram showing:
(1) Cash Flow S-Curves indicating planned project cost based on projected early and late activity finish dates.
(2…
This is the start of the file's text. The full file is on GovTribe.