W68SBV60285931

MCNARY 350-TON BRIDGE CRANE SKEW CORRECTION

KENT R BERNARD 509-527-7205

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

17-Jun-2016

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________Section 00700

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________4 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________20 Jul 2016 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

USAED, WALLA WALLA - CONTRACTING DIV.

KENT R. BERNARD 201 N. THIRD AVENUE

WALLA WALLA WA 99362-1876

W912EF

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

509-527-7802FAX:TEL: 509-527-7205 TEL: FAX:

W912EF-16-R-0026 66

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W912EF-16-R-0026

Section 00010 - Solicitation Contract Form

TABLE of CONTENTS

Section 00010, Solicitation Contract Form Section 00100, Bidding Schedule/Instructions to Bidders Section 00600, Representations and Certifications Section 00700, Contract Clauses Section 00800, Special Contract Requirements Technical Specifications Drawings, as listed in Section 00700

ATTENTION TO OFFERORS

Offeror(s) may be asked to provide the following information for the Government’s use in the determination of offeror(s) responsibility, pursuant to FAR Part 9. Do not include it with your offer.

1. Current Balance Sheet and latest Profit and Loss Statement prepared from the most recent fiscal/calendar year and certified by an officer of the company.

2. The name of your banking institution, telephone number and the name of the individual to contact for a line-of-credit reference. (If you are the apparent low bidder, please contact your bank reference to let him/her know our office will be calling for financial information.)

Bank Institution ________________________________ Telephone Number ______________________________ Contact ________________________________________ Email Address __________________________________

3. Tax Identification Number ________________________

4. List of present work to include agency or firm name, address, telephone number, and email address of primary point of contact responsible for inspection and acceptance of the work. (Attach list) Will performance of the present work inhibit your ability to perform this contract? ___________

5. Offeror’s email address: ____________________________________

Return completed form with all attachments to:

Email: Kent.R.Bernard@usace.army.mil

OR

Physical/Mailing Address: Walla Walla District Corps of Engineers, 201 North Third Avenue, Walla Walla, WA 99362-1876.

Section 00100 - Bidding Schedule/Instructions to Bidders

BID SCHEDULE

Walla Walla District Corps of Engineers McNary 350 Ton Bridge Crane Skew Correction

UNRESTRICTED COMPETITION

The estimated magnitude of construction will be between $1,000,000 and $5,000,000

ITEM

DESCRIPTION

QUANTITY

U/M

U/P

AMOUNT

Base Items

0001 North Crane 1 JOB XXXXX $________

0002 North Crane Crack Repair 1 JOB XXXXX $________

0003 South Crane 1 JOB XXXXX $________

0004 South Crane Crack Repair 1 JOB XXXXX $________

BASE ITEMS SCHEDULE TOTAL $__________

Optional Item

0005 Equalizer Pin Line Boring (Optional) NTE* 9 EA $_______ $________

OPTIONAL ITEM SCHEDULE TOTAL $__________

SCHEDULE TOTAL $__________

IMPORTANT See Section 01 22 00.00 28; MEASUREMENT AND PAYMENT; Paragraph; Retainage of Payment, for withholding of payment for final deliverables.

*NTE (Not To Exceed)

REQUIRED LIABILITY INSURANCE PURSUANT TO FAR 28.306

In accordance with the clause 52.228-5 Insurance – Work on a Government Installation, the Contractor shall procure and maintain during the entire period of his performance under this contract the following minimum insurance:

(i) Coverage complying with state laws governing insurance requirements pertaining to Workmen’s Compensation and Employers” Liability Insurance.

(ii) Bodily injury liability insurance with minimum limits of $500,000 per occurrence shall be required on the comprehensive form of policy.

(iii) Automobile bodily injury and property damage liability with minimum limits of $200,000 per person and $500,000 per occurrence for bodily injury liability; and $20,000 per occurrence for property damage liability shall be required.

(iv) The coverage required under Longshore and Harbor Workers Compensation Act, if applicable.

(v) The Insurance Certificate will name the Walla Walla District, U.S. Army Corps of Engineers, 201 N. Third Avenue, Walla Walla, Washington 99362 as the Certificate Holder.

ENVELOPE(S), PURSUANT TO FAR 14.201-5

Envelope (s) shall be plainly marked with the following information:

Solicitation No. __________________________________ Opening Date ___________________________________ Number of each amendment which has been received

CONTRACTOR RESPONSIBILITY, PREAWARD SURVEY

In order to determine a contractor’s responsibility for purposes of contract award the contractor is required to provide a statement regarding previous experience and past performance in performing comparable work, information related to the business organization, financial resources, and/or plant to be used in performing the work.

(See the Attention to Bidders form included in this solicitation.) In accordance with FAR 9.104-1, to be determined responsible, a prospective contractor must –

(a) Have adequate financial resources to perform the contract, or the ability to obtain them;

(b) Be able to comply with the required or proposed delivery or performance schedule, taking into consideration all existing commercial and governmental business commitments;

(c) Have a satisfactory performance record. (A prospective contractor shall not be determined responsible or non-responsible solely on the basis of a lack of relevant performance history except as provided in FAR 9.104-2);

(d) Have a satisfactory record of integrity and business ethics;

(e) Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them;

(f) Have the necessary production, construction, and technical equipment and facilities, or the ability to obtain them; and

(g) Be otherwise qualified and eligible to receive an award under applicable laws and regulations.

BIDDER INQUIRY:

Bidder/Offeror Solicitation Questions:

All inquiries regarding this solicitation are to be submitted via Bidder Inquiry. Telephone and email inquiries will not be accepted. Bidder Inquiry is a web-site that allows bidders to post questions regarding the solicitation and view all questions by other bidders and responses by USACE. Bidder Inquiry can be accessed through ProjNet at (https://www.projnet.org)

To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email. Another email to the same address will notify the prospective vendor once the reply is available for viewing.

The Bidder Inquiry Key is: 9SG8C3-S82A5G

Specific Instructions for ProjNet Bid Inquiry Access:

1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

2. Identify the Agency. This should be marked as USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. Email. Enter the email address you would like to use for communication.

5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.

7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

Instructions for Entering Questions:

1. After you are logged in click on the "post new inquiry", it is on the left side of the window under the Word "Submit" a.) This is the window where you will enter your questions b.) Comment Classification: Click on the down arrow to the right of the words “Please select from below”, select “Public” c.) Discipline: This is where you select who this question should be directed to. Example; if the question is about an electrical drawing or specification select: “Electrical” from the pull down list.

d.) Sheet. Enter the sheet number of the drawing you are asking about.

e.) Detail. Enter the detail name of the detail shown on the drawing that you are asking about.

f.) Specification. Enter the Specification number and paragraph number.

g.) File. Use this if you are going to attach a pdf file.

h.) Question. Enter your question here.

Specific Instructions for Future ProjNet Bid Inquiry Access:

1. For future access to ProjNet, you will not be provided any type of password. You will utilize your Secret Question and Secret Answer to log in.

2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

3. Identify the Agency. This should be marked as USACE.

4. Key. Enter the Bidder Inquiry Key listed above.

5. Email. Enter the email address you used to register previously in ProjNet.

6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.

7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

For questions about the ProjNet Bidder Inquiry, please contact the Call Center help desk toll free at 1-800-428- HELP, which operates from 8AM to 5PM (Central US time zone). Bidder inquiry help questions can also be emailed to the helpdesk at staff@projnet.info

BACKGROUND AND OBJECTIVES

The existing 350T bridge cranes were originally constructed in 1953. They have a 350 ton capacity with a span of 78 feet. Both cranes were rehabilitated in 2005 which included replacement of the existing CMAA A3 bridge drive configuration with a new CMAA A4-four corner configuration, including complete replacement of the drive and idler end trucks. The current drive arrangement on each crane includes two 40 HP Magnetek Impulse G+ Series-2 VFDs and four 20 HP SEW Eurodrive MC3PEHT05- DV160L4BMGHR gearmotor assemblies. One VFD drives two gearmotors on the A girder and a second VFD drives two gearmotors on the B girder. The VFDs are configured in open loop vector. The end truck drive wheel axle is directly inserted into the hollow shaft output of the gearmotor (i.e. direct drive). All driven wheels are 27” diameter taper tread (4 per crane) and all idler wheels are 27” diameter flat tread (12 per crane).

Both cranes experience excessive skewing problems due to the improperly designed bridge drives (two taper drive wheels being driven by one VFD configured in open loop vector). Some of the drive and idler crane wheel flanges have worn excessively, and the crane frame is visibly wracking during bridge travel.

Cracks have formed in the end-tie connections as a result of the crane frame wracking and the crane operating in a skewed state for an extended period. In order to improve the skewing condition of each crane, new VFDs will be installed for each drive motor to allow independent control of the bridge motors.

The new drive controllers must communicate with the existing Allen Bradley PLC and HMI system already installed on the crane. The communication interdependence will be met by installing new Magnetek Impulse G+ drives to be compatible with what is currently installed on the crane. Additionally, laser anti-skewing equipment and programming will be installed to assist with the proper tracking of the bridge crane along the rails. New flat tread drive and idler wheel-axle assemblies will be installed at each corner truck. New right-angle drive gearmotors will be installed with encoder motors and torque-arm assemblies. The end-tie beams will be reinforced.

A. BASIS FOR AWARD

The award will be made based on the best overall (i.e., best value-tradeoff) proposal that is determined to be the most beneficial to the Government, with appropriate consideration given to the four (4) technical evaluation factors: Experience, Past Performance, Work Plan, and Small Business Participation. Factor I Experience is approximately equal to Factor II Past Performance. Factor III Work Plan is approximately equal to Factor IV Small Business Participation. Factors I and II, when combined are significantly more important than Factors III and IV, when combined. When combined, the non-price factors (Factors I, II, III, and IV) are significantly more important than Factor V, Price. As proposals become more equal in their technical (non-price) merit, the evaluated price becomes more important in determining the best value proposal.

B. FACTORS TO BE EVALUATED

The following evaluation factors will be used to evaluate each proposal. Award will be made to the offeror whose proposal is most advantageous to the Government based upon an integrated assessment of the evaluation factors described below.

1. Volume I, FACTOR I – Experience - Risk assesses the degree to which the offeror’s proposed technical approach for the requirements of the solicitation may cause disruption of schedule, increased price, degradation of performance, the need for increased Government oversight, or the likelihood of unsuccessful contract performance. Risk will be evaluated as one aspect of the technical evaluation, inherent in the technical evaluation factor rating.

Evaluation of the offeror’s proposal shall address this factor as it applies to the scope of work defined in this solicitation. During evaluations of each proposal, the Government will assign this factor an adjectival rating and write a narrative evaluation reflecting the identified findings.

2. Volume I, FACTOR II – Past Performance - Each offeror’s current and past performance will be reviewed to determine relevancy and confidence.

3. Volume I, FACTOR III – Work Plan - The Offeror shall submit a work plan consisting of a detailed schedule and a project management plan.

4. Volume I, FACTOR IV – Small Business Participation – Offerors shall submit a Small Business Participation Plan.

5. Volume II, FACTOR V – Price - The resulting award will be a firm-fixed price contract. Price reasonableness will be utilized in the evaluation of the proposal.

C. EVALUATION APPROACH

All proposals will be evaluated by the Source Selection Evaluation Board (SSEB).

The overarching evaluation approach for all factors is as follows:

a. Adequacy of Response. The proposal will be evaluated to determine whether the offeror’s methods and approach have adequately and completely considered, defined, and satisfied the requirements specified in the RFP. The proposal will be evaluated to determine the extent to which each requirement has been addressed in the proposal in accordance with the proposal submission section of the

RFP.

b. Feasibility of Approach. The proposal will be evaluated to determine the extent to which the proposed approach is workable and the end results achievable. The proposal will be evaluated to determine the extent to which successful performance is contingent upon proven devices and techniques. The proposal will be evaluated to determine the extent to which the offeror is expected to be able to successfully complete the proposed tasks and technical requirements within the required schedule.

1. Volume I, Factor I – Experience

Offeror’s proposal will be evaluated on the breadth and depth of relevant project experience that is comparable in technical scope to what is required by this solicitation.

Submit information for those projects that affirmatively demonstrate the Offeror’s specialized training, expertise, and ability performing work similar in size, scope, and complexity to this project. This project will consist of design, fabrication, installation of new bridge drives and controls upgrades to correct skewing on two (2) 350 Ton powerhouse bridge cranes at McNary Lock and Dam.

Relevant experience is defined as follows:

A crane must have traveled on rails to be relevant. Fully Relevant projects that demonstrate the Offeror’s Experience should include the following:

1) Complete design, fabrication, installation, assembly, factory testing, and field testing/load testing aspects of new or rebuilt bridge drives and controls upgrades on bridge cranes with a capacity of at least 100 tons and a minimum span of 60 feet. Demonstrating bridge drive skewing/control measures similar in complexity as required in the solicitation. Demonstrate experience with designing measures to maintain crane alignment on rails (bridge drive open loop vs. close loop configurations, flat vs. taper tread wheel type, alignment tolerances for crane frame, anti-skewing measures etc). Experience on bridge drive control and machinery is considered more relevant.

2) Projects that required design calculations and drawings from a registered professional engineer(s) that incorporates many of the following items: motors, brakes, communication and control systems, electrical power, bridge drive equipment or machinery (including drive and idler trucks), using live, dead, and variable loads.

3) Crane frame, end truck and wheel alignment experience for new or rehabilitated bridge cranes including assessment of crane skewing conditions using alignment measurements, analysis of results, and modifications to end trucks similar in scope and complexity as required in the solicitation.

Offerors shall submit project experience information for at least two (2) projects and no more than four (4) COMPLETED within the past six (6) years that are similar in size, scope, and complexity to this project. If more than four projects are submitted, only the first four projects will be evaluated for experience.

Use Attachment “Offeror Experience Form” in Appendix C to describe the projects in which the Offeror has relevant crane design, fabrication, installation, assembly, factory testing, and field testing/load testing experience. Project experience shall include adequate detail such as equipment types, ratings, capacities, and configuration to demonstrate the relevancy of the scope of work for comparison to that required in this solicitation.

The Technical Factor Ratings, excerpted below focus on the strengths, deficiencies, weaknesses, risks and uncertainties of the offeror’s proposal. The rating depicts how well the offeror’s proposal meets the Experience Factor requirements.

Rating Description Outstanding Proposal meets requirements and indicates an exceptional approach and understanding of the requirements. Strengths far outweigh any weaknesses.

Risk of unsuccessful performance is very low.

Good Proposal meets requirements and indicates a thorough approach and understanding of the requirements. Proposal contains strengths which outweigh any weaknesses. Risk of unsuccessful performance is low.

Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements. Strengths and weaknesses are offsetting or will have little or no impact on contract performance. Risk of unsuccessful performance is no worse than moderate.

Marginal Proposal does not clearly meet requirements and has not demonstrated an adequate approach and understanding of the requirements. The proposal has one or more weaknesses which are not offset by strengths. Risk of unsuccessful performance is high.

Unacceptable Proposal does not meet requirements and contains one or more deficiencies.

Proposal is not awardable.

Offerors that claim the experience of the subcontractor or supplier, i.e. a firm that is not the prime contractor or part of the joint venture, shall submit a letter of commitment signed by the subcontractor and the prime contractor. The letter of commitment must be submitted even if the firm is in some way related to a joint venture partner (for example, the subcontractor is a subsidiary of a joint venture partner, or a subsidiary of a firm to which the joint venture partner is also a subsidiary). If an Offeror submits projects demonstrating experience by a subcontractor, a subsidiary, or a supplier, as opposed to the prime or one of the joint venture partners, the Offeror MUST submit a signed letter of commitment from the contractor who performed the completed work. If a letter of commitment is not submitted, the experience will not be considered or evaluated.

2. Volume I, Factor II – Past Performance

The Government will evaluate the offeror’s record of past and current performance to ascertain the probability of successfully performing the required efforts of the scope of work.

The Offeror shall provide past performance information for each project listed by the Offeror under Factor 1: Experience. Recent and relevant projects are those projects completed in the past six (6) years that are comparable in size, scope, and complexity with this project. Each offeror’s current and past performance will be reviewed to determine relevancy and confidence.

a. Evaluation of past performance shall be in accordance with this plan utilizing the forms and questionnaires set forth in Appendix D.

b. The Government will focus its inquiries on the offeror’s (and major subcontractors’) record of performance as it relates to all solicitation requirements, including price, schedule, performance and management of subcontractors. Major subcontractors are defined as members of an offeror’s overall team who are expected to perform ten (10) percent or more of the proposed effort or who will be providing critical hardware/services.

A significant achievement, problem, or lack of relevant data in any element of the work can become an important consideration in the evaluation process. Therefore, offerors will be reminded to include the most current and relevant past efforts (within the past six years) in their proposal. Absent any current and relevant past performance history or when the performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned, the offeror will be assigned an “unknown confidence rating” and its proposal will not be evaluated either favorably or unfavorably on past performance.

The Government may use data provided by the offeror in its proposal and data obtained from other sources, including data in Government files or data obtained through interviews with personnel familiar with the contractor and their current and past performance under Federal, State or Local government or commercial contracts for same or similar services as compared to the North American Industry Classification System NAICS 237990, Other Heavy and Civil Engineering Construction. Data used in conducting performance risk assessments shall not extend past six years prior to the issue date of the RFP, but may include performance data generated during the past six years without regard to the contract award date.

c. Offerors shall submit all Government and/or commercial contract numbers and descriptions for the prime offeror and each major subcontractor in performance or awarded during the past six years, from the issue date of this RFP, which are relevant to the efforts required by this RFP.

The Government may consider a wide array of information from a variety of sources, but is not compelled to rely on all of the information available.

d. The past performance factor considers each offeror’s demonstrated current and relevant past record of performance in supplying products and services that meet the contract requirements. There are two aspects to the past performance evaluation: relevancy and performance confidence assessment.

(i) RELEVANCY: The Government will conduct a performance assessment based on the relevancy of the Offeror's current and past performance, as well as that of its major subcontractors, as it relates to the probability of successful accomplishment of the required effort. These efforts include all aspects of schedule, performance and customer support, including the Offeror’s submitted subcontracting plan for this project and the Offeror’s record of: 1) Conforming to specifications and standards of good workmanship; 2) Maintaining program execution within price; 3) Adherence to contract schedules, including the administrative aspects of performance; 4) Ability to resolve technical and manufacturing problems quickly and effectively; 5) Businesslike concern for the interest of its customers; 6) Establishing and maintaining adequate management of subcontractors; and 7) Compliance with subcontracting plans submitted on previous projects.

Past Performance Relevancy Ratings

Rating Definition

Very Relevant Current/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.

Relevant Current/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.

Somewhat Relevant Current/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.

Not Relevant Current/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.

(ii) PERFORMANCE CONFIDENCE ASSESSMENT: The final step is for the team to arrive at a single consensus performance confidence assessment for the offeror, selecting the most appropriate rating from the chart below. This rating considers the assessed quality of the relevant/current efforts gathered (documented results from Past Performance Questionnaires, interviews, CPARS, and other sources form the support and basis for this assessment). Ensure the rationale for the conclusions reached are included.

Performance Confidence Assessments

Rating Definition

Substantial Confidence Based on the offeror’s relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.

Satisfactory Confidence Based on the offeror’s relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.

Limited Confidence Based on the offeror’s relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.

No Confidence Based on the offeror’s relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.

Unknown Confidence (Neutral) No relevant performance record is available or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.

3. Volume I, Factor III – Work Plan - This Factor evaluates the Offeror's capability (evaluating their approach and reasonableness) to prepare a work plan, including detailed schedule and project management plan, that covers all aspects and elements related to this project. The Offeror must demonstrate an understanding of the scope of work and capability to perform the required work.

a. The offeror should propose a Work Plan Schedule that includes the following:

A detailed schedule presented in Gantt chart format using Microsoft Office Project format (minimum accepted format).

o The schedule demonstrates a thorough comprehension of the

3.1.2 General Sequence of Work (Section 41 01 20.72 26)

needed to complete the project, realistic duration for each work task, and work task sequencing in a logical order. For evaluation purposes only, the Offeror should use the arbitrary, non-binding Notice to Proceed date of 8 September 2016.

b. The offeror should propose a Work Plan that includes the following:

Demonstrate an understanding of the scope of work and the capability to perform the required work.

Include a detailed narrative discussing design, existing crane inspection and surveying, shop fabrication and testing, field installation and alignment, and acceptance and load testing.

Identify risks and risk management for unforeseen issues and delays, for example manufacture and delivery of long lead items or items supplied by subcontractors, and describe a plan to mitigate risk and a plan for schedule recovery.

Identify tasks associated with the offeror, proposed vendors, and subcontractors.

Provide a list of major equipment and special tools to be used on this job (including mobile crane types, load ratings, jacking, etc).

The Technical Factor Ratings, excerpted below focus on the strengths, deficiencies, weaknesses, risks and uncertainties of the offeror’s proposal. The rating depicts how well the offeror’s proposal meets the Work Plan Factor requirements.

understanding of the requirements. Strengths far outweigh any weaknesses.

Risk of unsuccessful performance is very low.

Good Proposal meets requirements and indicates a thorough approach and understanding of the requirements. Proposal contains strengths which outweigh any weaknesses. Risk of unsuccessful performance is low.

Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements. Strengths and weaknesses are offsetting or will have little or no impact on contract performance. Risk of unsuccessful performance is no worse than moderate.

Marginal Proposal does not clearly meet requirements and has not demonstrated an adequate approach and understanding of the requirements. The proposal has one or more weaknesses which are not offset by strengths. Risk of unsuccessful performance is high.

4. Volume I, Factor IV – Small Business Participation - Offerors shall submit Attachment D, Small Business Participation Plan, for Factor 4 to address the Small Business Participation in this contract.

All offerors (both large and small businesses) will be evaluated on the level of proposed participation of small businesses in the performance of acquisition (as small business prime offerors or small business subcontractors) relative to the objectives and goals established herein. The government will evaluate:

a. The extent to which such firms, as defined in FAR Part 19, are specifically identified in proposals;

b. Identification of the complexity and variety of the work small firms are to perform;

c. The extent of past performance in compliance with FAR 52.219-8 “Utilization of Small Business” and maximizing opportunities for U.S. Small Business Subcontractors;

d. The extent of small business prime offerors and small business subcontractors in terms of the percentage of the value of the total acquisitions. The Government will evaluate the extent to which the offeror meets or exceeds the goals: Goals for this procurement are –

- Small Business: (8%) of the total contract value;

- Small Disadvantaged Business (SDB): (2%) of the total contract value;

- Woman Owned Small Business (WOSB): (1%) of the total contract value;

- Historically Underutilized Business Zone (HUB Zone) Small Business: (.5%) of the total contract value;

- Veteran Owned Small Business (VOSB): (1%) of the total contract value;

- Service Disabled Veteran Owned Small Business (SDVOSB): (1%) of the total contract value.

(Note, for example, that a participation plan that reflects (1%) of the contract value for WOSB would also count towards the overall Small Business Goal; and percentages for SDVOSB also count towards VOSB).

The Technical Factor Ratings, excerpted below focus on the strengths, deficiencies, weaknesses, risks and uncertainties of the offeror’s proposal. The rating depicts how well the offeror’s proposal meets the small business Factor requirements.

understanding of the requirements. Strengths far outweigh any weaknesses.

Risk of unsuccessful performance is very low.

Good Proposal meets requirements and indicates a thorough approach and understanding of the requirements. Proposal contains strengths which outweigh any weaknesses. Risk of unsuccessful performance is low.

Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements. Strengths and weaknesses are offsetting or will have little or no impact on contract performance. Risk of unsuccessful performance is no worse than moderate.

Marginal Proposal does not clearly meet requirements and has not demonstrated an adequate approach and understanding of the requirements. The proposal has one or more weaknesses which are not offset by strengths. Risk of unsuccessful performance is high.

5. Volume II - Factor V – Price - The contract will be a Firm Fixed-Price Contract. The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s). The Government will evaluate offers for award purposes by evaluating the prices proposed in the Bid Schedule. The Offeror must provide a price proposal by completing the Bid Schedule as instructed in Section 00100.

Firm Fixed Price Requirements

a. The RFP requires firm-fixed-price contract line items. A price reasonableness approach will be utilized by the Government to determine that the proposed prices offered are fair and reasonable and that a “buy-in” or unbalanced pricing between CLINs is not occurring.

b. The Government will examine price proposals for artificially low unit prices. Offers found to be unreasonably high, unrealistically low (an indication of “buy – in”), or unbalanced, may be considered unacceptable and may be rejected on that basis.

D. GENERAL PROPOSAL SUBMISSION REQUIREMENTS

1. Introduction. The offeror’s proposal shall be submitted in hard copy, with accompanying digital copies, as set forth below. The RFP shall provide the Government address and receipt date for proposal submittal.

The offeror’s proposal shall consist of two (2) volumes. The Volumes are:

Volume I – Experience, Past Performance, Work Plan, Small Business Participation Volume II - Price, and Solicitation, Offer and Award Documents and Certifications/Representations.

The Offeror’s proposal shall be organized into the following Volumes and separated by TABs as defined below.

REQUIRED TABS FOR VOLUME 1: TECHNICAL PROPOSAL

Table of Contents Factor 1 – Tab 01: Experience Factor 2 – Tab 02: Past Performance Factor 3 – Tab 03: Work Plan Factor 4 – Tab 04: Small Business Participation Plan

REQUIRED TABS FOR VOLUME 2: PRICE PROPOSAL

Table of Contents

Factor 5 – Tab 01: Price Proposal

Files shall not contain classified data. The use of hyperlinks in proposals is prohibited. Proposals must be submitted in hard copy AND electronically. The electronic files shall contain identical information to the hard copy files.

Offerors are cautioned that “parroting” of the Technical requirements with a statement of intent to perform does not reflect an understanding of the requirement or capability to perform. Offerors are responsible for including sufficient details to permit a complete and accurate evaluation of each proposal. Proprietary information shall be clearly marked.

2. General Submission Requirements.

a. Each volume shall be submitted in a separate three-ring binder. Any pages that are changed (as a result of negotiations or proposal revisions) should be of a different color and have changed information clearly marked by a vertical line in the right margin of the page. The revised pages shall be dated. Each binder shall be clearly labeled with its Title and a copy number (e.g., copy 1 of 4).

b. Printing should be single spaced. Each paragraph shall be separated by at least one blank line. A standard, 12-point minimum font size applies. Arial or New Times Roman fonts are required. Tables and illustrations may use a reduced font size no less than 8-point and may be landscape.

c. The following volumes of material shall be submitted:

VOLUME TITLE

PRINTED

COPIES

ELECTRONIC

COPIES

Volume I Original +4 1 Volume II Original 1

3. Proposal Files.

a. Format. The submission shall be clearly indexed and logically assembled. Each volume shall be clearly identified and shall begin at the top of a page. All pages of each volume shall be appropriately numbered and identified by the complete company name, date and RFP number in the header and/or footer. A Table of Contents should be created using the Table of Content feature in MS Word. MS Word (doc) files shall use the following page setup parameters:

Margins – Top, Bottom, Left, Right – 1” From Edge – Header, Footer 0.5” Page Size, Width – 8.5” Page Size, Height – 11”

NOTE: 11X17 folded pages are acceptable for tables/graphic representations

The following additional restrictions apply:

b. File Packaging. All of the proposal files shall be compressed (zipped) into one file entitled proposal zip using WinZip version 6.2 or later, or as separate uploads in their native format, i.e. doc, xls, ppt, etc., and provided on CDs or DVDs. Zip disks are not permitted. Files shall be in read-only format, using PDF files. All price breakdown information to aid in the Price evaluation shall be submitted in Microsoft Office Excel Read/Write format. Each disc shall be externally labeled with the volume number, date, and the offeror’s name. **Please note – Self extracting exe files are not acceptable. **Both electronic and hard copies must be the same.

c. Content Requirement. All information shall be confined to the appropriate file. The offeror shall confine submissions to essential matters, sufficient to define the proposal in a concise manner, to permit a complete and accurate evaluation of each proposal. Each file of the proposal shall consist of a Table of Contents, Summary Section, and the Narrative discussion. The Summary Section shall contain a brief abstract of the file. Proprietary information shall be clearly marked. The following shall be included in the Narrative discussion:

(i) VOLUME I –Technical. The volume shall be organized into the following sections:

(1) Factor I – Experience

(2) Factor II – Past Performance

(3) Factor III – Work Plan

(4) Factor IV – Small Business Participation

(ii) VOLUME I,– Past Performance This volume and TAB shall contain current and past performance information regarding similar contracts. This volume shall not exceed 25 pages plus five pages for each major subcontractor, excluding Past Performance Questionnaire Forms. Offerors shall submit all Government and/or commercial contracts for the prime offeror and each major contract currently in performance or awarded during the past six years, from the issue date of this RFP, which are relevant to the efforts required by this solicitation. Relevant efforts are defined as services/efforts that are the same as or similar to the effort required by the RFP. Data concerning the offeror shall be provided first, followed by each proposed major subcontractor, in alphabetical order. The Offeror shall also submit the written consent of its major subcontractors to allow the disclosure of its subcontractor’s past performance information to the Offeror. In addition, letters of commitment shall be included for all major subcontractors for their past performance to be considered. This volume shall be organized into the following sections:

(1) Section 1 – Contract Descriptions. This section shall include the following information in the following format. Ensure all information is current and accurate.

(a) Contractor/Subcontractor place of performance, CAGE Code and DUNS

Number. If the work was performed as a subcontractor, also provide the name of the prime contractor and Point of Contact (POC) within the prime contractor organization (name, and current address, e-mail address, and telephone and fax numbers).

(b) Government contracting activity, (or private firm) and current address, Procuring Contracting Officer’s name, e-mail address, telephone and fax numbers.

(c) Government’s Technical representative/COR and current email address, telephone and fax numbers.

(d) Government contract administration activity and the Administrative Contracting Officer’s name, current e-mail address, telephone and fax number.

(e) Government contract administration activity’s Pre-Award point of contact name, and current e-mail address, telephone and fax numbers.

(f) Contract Number and, in the case of Indefinite Delivery type contracts, GSA contracts, and Blanket Purchase Agreements, include Delivery Order Numbers.

(g) Contract Type (specific type such as Fixed-Price (FP), Cost Reimbursement

(CR), Time & Material (T&M), etc.). In the case of Indefinite Delivery contracts, indicate specific type (Requirements, Definite Quantity, and Indefinite Quantity) and secondary contract type (FP, CR, T&M, etc.).

(h) Awarded price.

(i) Final or projected final price.

(j) Original delivery schedule, including dates of start and completion or work.

(k) Final or projected final, delivery schedule, including dates of start and completion of work.

(2) Section 2 – Performance. Offerors shall provide a specific narrative explanation of each contract listed in Section 1 - Contract Description, describing the objectives achieved and detailing how the effort is relevant to the requirement of this RFP.

(a) For any contracts that did not/do not meet original schedule or technical performance requirements, provide a brief explanation of the reason(s) for the shortcomings and any corrective action(s) taken to avoid recurrence. The offerors shall list each time the delivery schedule was revised and provide an explanation of why the revision was necessary. All Requests for Deviation and Requests for Waiver shall be addressed with respect to causes and corrective actions. The offerors shall also provide copy of any Cure Notices or Show Cause Letters received on each contract listed and a description of any corrective action implemented by the offeror or proposed subcontractor. The offerors shall indicate if any of the contracts listed were terminated and the type and reasons for the termination.

(b) For all contracts, the offeror shall provide data on all manufacturing warranty returns. Data shall delineate total number of warranty returns, number of Could Not Duplicate (CND), number of failures attributable to GFE component failures, and number and nature of failures attributable to the offeror’s delivered product.

(3) Section 3 – Subcontracts. Offerors shall provide an outline of how the effort required by the RFP will be assigned for performance within the offeror’s corporate entity and among the proposed subcontractors. The information provided for the prime offeror and each proposed major subcontractor must include the entire company name, company address, CAGE Code, DUNS Number and type of work to be performed by citing the applicable Government technical specification. This includes all subcontractors who will be providing critical hardware/services or whose subcontract is for more than 10% of the total proposed Price. This section will further include written consent of major subcontracts to allow the disclosure of their subcontractor’s past performance information to the Offeror. In addition, letters of commitment shall be included for all major subcontractors.

(4) Section 4 – New Corporate Entities. New corporate entities may submit data on prior contracts involving its officers and employees. However, in addition to the other requirements in this section, the offeror shall discuss in detail the role performed by such persons in the prior contracts cited. Information should be included in the files described in the sections above.

Letters of Commitment shall be included in the proposal for these employees in order to be considered. The letters of Commitment have to be signed by the officer or employee and the President or equivalent managing member to be considered.

(4) Section 4-Past Performance Questionnaire. For all contracts identified in Section 1 - Contract Descriptions, a Past Performance Questionnaire, Appendix D, must be completed and submitted. The offeror shall complete Part I of the Past Performance Questionnaire and e-mail the questionnaire to both the Government contracting activity and technical representative responsible for the current and past contract. The Point of Contacts (POCs) shall be instructed to electronically complete Part II of the questionnaire and e-mail the entire questionnaire to the Contracting Office no later than the proposal due date, to Kent.R.Bernard@usace.army.mil.

The offeror must submit, with its proposal, a list of all the POCs who were sent questionnaires.

The POC List shall be submitted in Word for Windows Table Format to include the following fields: Solicitation Number; Company Name; Contract Number; Government Agency; POC Last Name, First Name; POC Title; POC Telephone Number; POC E-mail Address; and Date E-Mail to POC (month/day).

Section 5-Submissions. Offerors are discouraged from providing points of contact with another contractors’ facility, i.e., in case an offeror (or one of his/her team members) is in a subcontract with another contractor who has submitted a proposal on the same requirement.

Offerors shall provide and submit the prime contract number and all Governmental agency points of contact (POC) in lieu of subcontract numbers or prime contract POCs in situations as described above.

(iii) VOLUME II –Price This volume shall consist of all information, required to support proposed prices. Certified pricing data is not currently required; however, the Government reserves the right to request such data prior to award. There are no page limitations for this volume.

The offeror shall ensure that the information submitted in this volume is consistent with and fully supports the amounts set forth in the SF1442 and continuation sheets.

(II) VOLUME II – SOLICITATIONS, OFFER AND AWARD DOCUMENTS AND

CERTIFICATIONS/REPRESENTATIONS

Certifications and Representations – Each offeror shall complete (fill-in and signatures) the solicitation sections indicated below using the file (without…