Amendment 1 Answers questions from industry and updated Performance Work Statement to reinforce answers.

View the file

Other files for this federal contract opportunity

Other files attached to MNA Crane Inspection, newest first.
File Type Posted
W912EF-16-Q-0177_Crane_Inspection.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Annual Mobile Crane Inspection Service, McNary Lock and Dam.

Purpose of this amendment is to:

1.) Address Questions and Answ ers 2.) Revise Performance Work Statement.

If you are submitting an offer, ensure that you acknow ledge receipt of the amendment (16-Q-0177) by completing Block 8 and 15A. The signed SF30 and amendment shall be included in proposal submission. Please note there are now tw o individual line items. The Line Items must be filled out and submitted in submission package.

The required response date/time has changed from 15-Sep-2016 02:00 PM to 20-Sep-2016 02:00 PM.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 7

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 14-Sep-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EF-16-Q-0177

X 9B. DATED (SEE ITEM 11)

01-Sep-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Sep-2016

CODE

USAED, WALLA WALLA - CONTRACTING DIV.

LEANNE WALLING

201 N. THIRD AVENUE

WALLA WALLA WA 99362-1876

W912EF 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912EF-16-Q-0177

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

QUESTION AND ANWERS

Questions and Answers

Q-1. You specify that the inspectors need to be certified NCCO inspectors. Why is this? We are certified by Federal OSHA to inspect all cranes and have been inspecting for other Army Corp of Engineers sites for many years. It is much harder to become OSHA certified than NCCO certified. Can that requirement be changed?

A-1. Performance Work Statement are now updated to clarify the certification as OSHA certification not NCCCO certification.

Q-2. Also you specify that the inspectors also are required to lubricate and make certain other adjustments. Why is that? We, or any other inspectors would then be put in the awkward and not wise position of inspecting and certifying our own work.

A-2. Performance Work Statement are now updated to clarify the lubrication and adjustments is not a requirement.

Should there need to be an adjustment or part needing to be "greased" etc. the inspector can tell the crane operator, who will see that "on the spot maintenance" is performed to facilitate the inspection process.

Sections changed in Instruction to Offerors section ADDENDUM TO FAR 52.212-1 INSTRUCTIONS TO OFFERORS – COMMERCIAL ITEMS #5, and in the Performance Work Statement sections 5. SCHEDULE;

5.3, 5.4, and 5.5 and section 10. Performance Requirement Summary matrix – Visual Inspection section.

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

SOLICITATION/CONTRACT FORM

The required response date/time has changed from 15-Sep-2016 02:00 PM to 20-Sep-2016 02:00 PM.

SUPPLIES OR SERVICES AND PRICES

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job

Annual Mobile Crane Inspection Service

FFP

Per Technical Specifications FOB: Destination

NET AMT

CLIN 0002 is added as follows:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Job OPTION Optional Re inspection

FFP

Should parts need to be replaced, the Contractor shall return for a re inspection of the area(s) that required replacing. This is an optional line that will not be exercised unless necessary.

FOB: Destination

NET AMT

The following have been added by reference:

52.217-7 Option For Increased Quantity-Separately Priced Line Item MAR 1989

The following have been modified:

INSTRUCTION TO OFFERORS

This acquisition is 100 percent set – aside for small business concerns.

This is a requirement to provide a service for the annual inspection and certification of three (3) mobile cranes at McNary Lock and Dam.

This solicitation will result in a firm-fixed price award.

If you have any questions or concerns regarding the Request for Quote, please contact LeAnne Walling (Telephone 509-527-7230) or send an email to leanne.r.walling@usace.army.mil).

Offerors are cautioned to clearly print prices for all line items. Be especially careful placing decimal points, as a mistake in your offer may render it unresponsive. Your quote must be good for 30 days. Please include shipping costs in the quoted price of each item.

Registration at www.sam.gov is required. If not registered, please do so. Step-by-step help information on how to register is detailed on the website, along with frequently asked questions (FAQs). Lack of registration in the SAM database may make an offeror ineligible for award.

Completion of the required FAR 52.212-3 Alt. I, Offeror Representations and Certifications – Commercial Items is required. When you complete your SAM registration, the link to complete your Reps and Certs is also available.

Please do not hesitate to contact me or the SAM web site if you need assistance or have questions.

In accordance with FAR 52.229.3, State and Local Taxes, and per Title 4 of the US Code 104-107, the Government is exempt from paying local and state taxes. Exempt Tax Identification Number 91-0828090.

Quote must be valid for thirty (30) days.

Please be sure to also complete Blocks 17a, 30a, 30b, and 30c on page 1 and other pages that require information.

General Contract Information:

Delivery Date________________________________________________

Offeror’s Name (Printed) _________________________________________

Offeror’s Contact Telephone Number_______________________________

Offeror’s Email Address___________________________________________

Federal Tax Identification No. ____________________________________________

CAGE Code __________________ DUNS No. ______________________________

Is your company registered on-line in SAM (www.sam.gov)? YES NO

To ensure receipt of your quote, please send to the attention of LeAnne Walling at:

Email: leanne.r.walling@usace.army.mil

ADDENDUM TO FAR 52.212-1 INSTRUCTIONS TO OFFERORS – COMMERCIAL ITEMS

Submission of Price Quote – Contractor shall submit the following in 1 copy:

1. Signed and dated Standard Form 1449 ((Solicitation / Contract / Order for Commercial Items).

2. Signed and dated Standard Form 30, if applicable, for any Amendments to the Solicitation

3. Completed schedule (pricing information) for all line items listed in the solicitation / amendments.

4. Completed Clause 52.212-3 and Alt I, “Offeror Representations and Certifications – Commercial Item’s”

As noted above.

5. The following shall be submitted with the quote:

Copies of certificate(s) showing that the inspector is a OSHA certified inspector.

Proof of experience and knowledge in performing inspections on mobile cranes of similar size and capacity.

Proof of current employment as a qualified crane inspector and certifier by a firm specializing in crane inspection and/or certification work.

All quotes shall include descriptive materials that demonstrate the capabilities of the contractor to perform the requirement as specified in the Performance Work Statement. The Government reserves the right to make an award based on initial quote submissions.

BASIS FOR AWARD

The Government will award one contract resulting from this solicitation in accordance with FAR 13.106 to the responsible offeror meeting or exceeding all solicitation requirements and representing the lowest price technically acceptable.

PERFORMANCE WORK STATEMENT

PERFORMANCE WORK STATEMENT

MCNARY LOCK AND DAM

INSPECTION AND CERTIFICATION OF MOBILE CRANES

1. INTENT

The following specifications pertain to the annual inspection and certification of three (3) mobile cranes at McNary Lock and Dam.

2. SCOPE

The successful quoter shall be required to perform annual inspection and certification of three (3) mobile cranes in accordance with the most recent version of the US Army Corps of Engineers Safety and Health Requirements Manual EM 385-1-1 and other relevant ASME/ANSI B30 specifications. In addition, the Contractor shall lubricate and adjust the hydraulic booms sections and wear pads on each crane. The Government will provide a crane operator.

3. CRANE INFORMATION:

3.1 Linkbelt mobile crane

Model: RTC-8030 Series II Capacity: 30-ton Serial #E8J2-6282

3.2 Linkbelt mobile crane

Model: HTC-8690 Capacity: 90-ton Serial # N3J9-1146

3.3 Drott Shuttlelift

Model: 330D Capacity: 8 ½-ton Serial # 12751293 LMI Model: DS150

4. QUALIFICATIONS AND SUBMITTALS

SEE: ADDENDUM TO FAR 52.212-1 INSTRUCTIONS TO OFFERORS – COMMERCIAL ITEMS

5. SCHEDULE

5.1 The Contractor shall complete the inspections no later than 14 calendar days after date of contract award.

5.2 The Contractor shall give five (5) days notification of the inspection dates and times to the POC.

5.3 Records shall be kept of the findings of the inspections. Should parts need to be replaced, the Contractor shall provide a parts/material list. Once the parts have been replaced/installed the contractor will need to re inspect those areas.

5.4 Should an adjustment, or lubrication need to happen, the contractor is to let the crane operator know; so that it can be taken care of on the spot – to facilitate the inspection process.

5.5 The Government shall be notified of any deficiencies noted under this contract.

5.6 A completed inspection report for each crane shall be submitted within 14 days of inspection completion.

6. POINT OF CONTACT (POC) on site.

6.1 The Contractor can arrange a site visit with the POC.

7. ACCESS TO MCNARY LOCK & DAM WAREHOUSE:

7.1 General: The current access to McNary Lock & Dam is limited due to heighten security at all USACE facilities. Contractor will need to coordinate with the POC for accessing the warehouse and warehouse secured parking area where these 3 cranes will be located for their inspections.

7.2 Contractor/vendor Access is only allowed during normal business hours of Monday-Thursday 6:30AM-4:00PM, excluding holidays. Contractor is to coordinate with the POC of proposed arrival dates and times to avoid any unnecessary site security issues.

7.3 Project Security. The project site is a secured area and access onto the project is restricted. The security measures affect all of contractors’ vehicles and personnel. There will be delays when entering projects due to locked gates, vehicle inspections, and personnel checks. Inspections and checks may include inspection of toolboxes, brief cases, lunch boxes, and other containers.

7.4 Vehicle Access. Project access roads are secured with locked gates. All vehicles that pass thru the locked gates will be subject to being searched. No privately owned vehicles (POV’s) will be allowed thru locked gates except to access designated parking areas. Only the contractors work vehicles and equipment that are essential to conduct the work will be allowed in the work area.

7.5 Pre-screen candidates using E-Verify Program. "The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award." *When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative.

This Form will be provided to the Contracting Officer and shall become part of the official contract file.

8. SAFETY STANDARDS - The contractor shall comply with applicable occupational safety and health act (OSHA ) standards, the U.S. Army Corps of Engineers safety manual, EM 385-1-1, dated 15 sep 2008.

Compliance with the accident prevention and safety requirements by subcontractors shall be the responsibility of the contractor.

9. ACCIDENT REPORTING – The Contractor shall immediately notify the POC by the quickest means available of any accident which does or may result in damage to Government property regardless of amount of damage.

10. Performance Requirements Summary Matrix

Performance Objective Specification reference

Acceptable Quality Level Surveillance Method

Contractor must follow the applicable safety provisions of EM 385-1-1.

2.0 & 8.0 100% Random Periodic Surveillance

Contractor must follow applicable ANSI/ASME B30 specifications for cranes

2.0 100% Random Periodic Surveillance

Contractor must inspect and certify three mobile cranes at McNary Lock and Dam, should parts need replaced, the Contractor shall provide a part/materials list. Once part have been replaced/installed, the Contractor will reinspect those areas. Should an adjustment or lubrication be needed, the Contractor is to let the Crane Operator know so it can be taken care of on the spot – to facilitate the inspection process.

2.0 100% Visual Inspection

Contractor must submit inspector qualifications

4.1 100% Submittal Review

Contractor must submit inspection report for each crane within 14 days of inspection completion

5.5 100% Submittal Review

11. Veterans Employment Emphasis for U.S. Army Corps of Engineers Contracts

In addition to complying with the requirements outlined in FAR Part 22.13, DFARS 222.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, and Department of Labor regulations; U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract; USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:

Federal Veteran employment information at http://www.fedshirevets.gov/index.aspx Department of Labor Veterans Employment Assistance http://www.dol.gov/vets/ Department of Veterans Affairs – VOW to Hire Heros Act http://benefits.va.gov/vow/ Army Wounded Warrior Program – http://wtc.army.mil/modules/employers/index.html Guide to Hiring Veterans – Reference Material http://www.whitehouse.gov/sites/default/files/docs/white_house_business_council_- _guide_to_hiring_veterans_0.pdf

(End of Summary of Changes)