- RECOVERY--Z--Ice Harbor Charbonneau and Fishhook Parks Electrical Upgrades, Walla Walla County, Washington
- Solicitation number
- W912EF-09-B-0020
About this file
Amendment 0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Opening Results.pdf | ||
| Site Visit Attendees List.pdf | ||
| W912EF-09-B-0020.pdf | ||
| Site Visit Information.pdf | ||
| Plans - Volume 1.zip | ZIP file | |
| Downloading and viewing drawings.pdf | ||
| Plans - Volume 2.zip | ZIP file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W68SBV91763351
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
TITLE: Ice Harbor Charbonneau and Fishhook Parks Electrical Upgrade
The purpose of this amendment is to change FAR Clause 52.228-1 from reference to full text to display the bid guarantee requirement, and to revise specifications and draw ings as indicated in the Summary of Changes.
Revised specification sections and draw ing sheets are included.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 10-Sep-2009
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EF-09-B-0020
X 9B. DATED (SEE ITEM 11)
18-Aug-2009
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
10-Sep-2009
CODE
USAED, WALLA WALLA - CONTRACTING DIV.
JANI C. LONG
201 NORTH 3RD AVE
WALLA WALLA WA 99362-1876
W912EF 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912EF-09-B-0020
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
Changes to Drawings:
Volume 1
1. Sheet E-101
a. added note, see brackets lower left hand corner.
b. Revised legend, see brackets
c. Changed note regarding Vault, see brackets
d. New note for directional drilling, see brackets
2. Sheet E-501
a. Multiple changes to Detail “Side Elevation: Typical Transformer and panelboard installation for campsite power “See brackets”
3. Sheet E-601
a. Corrected PPA2/PPA3 Feeders, see brackets
4. Sheet ED-101
a. Changed note regarding Vault, see brackets
Volume 2
1. Sheet E-101
a. added note and revised legend, see brackets
b. Changed note regarding Vault, see brackets
c. New note for directional drilling, see brackets
2. Sheet E-102
a. added note 1 and revised detail A, see brackets
3. Sheet E-501
a. Multiple changes to Detail “Side Elevation: Typical Transformer and panelboard installation for campsite power “See brackets”
4. Sheet E-103
a. New note for directional drilling, see brackets
5. Sheet ED-101
a. Changed note regarding Vault, see brackets
Changes to Technical Specs
1. Section 01 11 00.00 28 “Summary of Work” paragraph 1.1 Summary of work:
a. Changed the following: 6 additional R.V. campsite pedestals to has been reduced to 5.
b. Added the following to paragraph 1.1 Summary of work:
Work effort included at both locations are: trenching, backfilling and excavation to assist the local Utility Service Provider “See Section 01 11 01.00 28 paragraph Local Utility Coordination”
2. Section 01 11 01.00 28 “Supplementary Requirements” added the following paragraph:
1.5 LOCAL UTILITY COORDINATION
The Contractor shall coordinate work with the local Utility Service Provider. The local electric utility is Columbia REA in Dayton, Washington. Point of Contact is Dan Andrews,
509.526.4041. The utility service provider will be under separate contract with the Government.
The utility service provider will provide transformers, meters and feeder conductors. Contractor shall provide all trench and backfill for utility feeders per plans. Contractor is responsible for secondary conductors past the meters, including meterbases and panelboards.
3. Section 26 05 00.00 28 “General Electrical Work” paragraph Primary Conductors Title has been changed to Utility Feeders and the paragragh has been revised to read as follows:
Utililty Feeders
Primary service conductors will be furnished and installed by Columbia REA.COOP in Dayton, Washington. See Section 01 11 01.00 28 paragraph Local Utility Coordination. The Contractor shall provide the trenching and backfilling for the primary service indicated on the drawings.
4. Section 31 00 00.00 28 “Earthwork”
a. Deleted paragraph 3.10.7 “Trench Backfill”
b. Revised paragraph 3.4.1 “Support to Columbia REA to read as follows:
The Contractor shall provide all backhoe trench excavation for the portion of the work conducted by the Columbia REA as indicated on the drawings and as specified in paragraph: Select Backfill for Columbia REA. After installation of the vaults and ground sleaves, the Contractor shall backfill to the existing slopes and grades. The Contractor shall coordinate with Columbia REA to minimize delays and standby time for REA crews. See Section 01 11 01.00 28, paragraph Local Utility Cooridination for more details.
c. Added paragraph “Jacking, Boring, and Tunneling” to part 3
Unless otherwise indicated, provide excavation by open cut except that sections of a trench at paved road ways may be jacked, bored, or tunneled if, in the opinion of the Contracting Officer, the pipe, cable, or duct can be safely and properly installed and backfill can be properly compacted in such sections.
d. Revised paragraph “Excavation for Appurtenances” to read as follows:
Provide excavation for vaults, sleeves, or similar structures sufficient to leave at least 12 inches clear between the outer structure surfaces and the face of the excavation or support members.
Clean rock of loose debris and cut to a firm surface either level, stepped, or serrated, as shown or as directed. Remove loose disintegrated rock and thin strata.
5. Section 03 30 50.00 28 “Concrete”
a. added paragraph 3.2.2 “Sawcutting Concrete Slab”
Sawcutting shall be performed at the locations and to the depths shown on the contract drawings.
The sawcuts shall be done using a diamond-bladed saw. Sawcuts shall be straight and uniform.
Excess concrete shall be disposed of as specified.
SECTION 00700 - CONTRACT CLAUSES
The following have been modified:
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.
The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000.00, whichever is less.-
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of clause)
(End of Summary of Changes)
Charbonneau Fishook Electrical Upgrades W912EF-09-B-0020 Amend-1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00.00 28
SUMMARY OF WORK
PART 1 GENERAL
1.1 SUMMARY OF WORK
1.1.1 Location of Work
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section Table of Contents --
SECTION 01 11 00.00 28
G4EDDRJR
Line
SECTION 01 11 00.00 28
SUMMARY OF WORK
PART 1 GENERAL
This summary of work is a generalized description of work and is not all inclusive.
1.1 SUMMARY OF WORK
Demolition Work at Charbonneau & Fish Hook Parks - Remove existing electrical equipment such as, but not limited to, equipment brackets, supports, enclosures, transformers, panel boards, fittings, wires, receptacles, breakers, mounts, cement pads, protruding ground rods, pedestals that will not be used by the new service. Abandon in-place original buried electrical lines.
Construction Work at Charbonneau & Fish Hook Parks - The Contractor shall provide all material, equipment and labor necessary to supply electrical service from the secondary distribution transformer side to the final R.V. campsite pedestals, which includes:
(1) At Charbonneau - 54 R.V. campsite pedestals; electrical receptacle service for a group shelter; and, electrical service, and lighting at the Pavilion, as well as 5 additional R.V. Campsite pedestals around the Pavillion area.
(2) At Fish Hook - 41 R.V. campsite pedestals. The pedestals with water taps and line are to be left in place.
Work effort included at both locations are: trenching, backfilling and excavation to assist the local Utility Service Provider See Section 01 11 01.00 28 paragraph Local Utility Coordination for installation of primary lines to the transformer and installation of the transformer vaults, and for the Contractor's installation of the secondary lines to the pedestals; as well as using horizontal directional drilling for installation of conduits under paved roads, and seeding or sodding of disturbed areas. The Contractor shall coordinate energizing and de-energizing electrical power with the local electrical utility.
1.1.1 Location of Work
The work is located upstream of Ice Harbor Dam, on the left(eastern)side of the Snake River in Walla Walla County, Washington State.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used) -- End of Section --
SECTION 01 11 00.00 28
G4EDDRJR
Line
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 01.00 28
SUPPLEMENTARY REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 WORK SCHEDULES
1.3.1 Contractor's Schedule
1.4 SANITATION FACILITIES
1.5 LOCAL UTILITY COORDINATION
1.6 CONTRACTORS STORAGE AND STAGING AREA.
1.7 TRAFFIC CONTROL AND PUBLIC ACCESS
1.8 REGULAR CLEANUP AND DEBRIS DISPOSAL
1.9 EQUIPMENT LIST
1.10 TESTING OF EQUIPMENT
1.11 DISPOSITION OF REMOVED EQUIPMENT
1.12 PROTECTION AND RESTORATION OF EXISTING FACILITIES
1.13 POST AWARD MEETINGS
1.13.1 Pre-Work Meeting
1.13.2 Pre-Construction Meeting
1.14 WEEKLY PRODUCTION MEETINGS
1.15 USE OF WALLA WALLA DISTRICT PARKS
1.16 MAINTAIN WORKING AS-BUILT CONTRACT DRAWINGS
1.17 KEY PERSONNEL SUBSTITUTION
1.18 DAILY VISITORS AND PUBLIC USE.
1.19 DUST CONTROL PLAN
1.20 ARRA PROJECT SIGNAGE
1.20.1 Construction Project Identification Sign Legend
1.20.2 Sign Locations
1.20.3 Installation and Removal
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section Table of Contents --
SECTION 01 11 01.00 28
SECTION 01 11 01.00 28
SUPPLEMENTARY REQUIREMENTS
PART 1 GENERAL
The work covered by this section of the specifications consists of work common to more than one section of these TECHNICAL SPECIFICATIONS.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2008) Safety and Health Requirements Manual
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Equipment List
Pre-Work Survey Photos And Report
Dust Control Plan; G C
Public Use Control Plan; G C
ARRA Project Signage Submit proposed signage layout prior to fabrication of the project signs.
SD-11 Closeout Submittals
Post-Work Survey Photos And Report
As-Built Contract Drawings; G C
1.3 WORK SCHEDULES
1.3.1 Contractor's Schedule
At the prework meeting, the Contractor shall furnish a Schedule for the complete project in accordance with Section 01 32 01.00 28 PROJECT SCHEDULE, and the proposed working hours and days of the week for contract work. The Contractor shall furnish notification of any change of schedule of regular work hours, overtime work hours, and shifts of work crews and personnel at the site. This notification shall be provided a minimum of 48 hours prior to any schedule change to allow suitable scheduling of Government personnel and inspection. Exception to this requirement may be allowed in case of schedule change due to emergency conditions.
The Contractor shall not plan working on any Federal holidays. If the need arises to work on a Federal Holiday, the Contractor shall submit a letter to the Contracting Officer at least one (1) week prior to that date requesting permission. The Government reserves the right to deny this request.
1.4 SANITATION FACILITIES
Public restrooms at Charbonneau and Fishhook parks may be used, if open;
the Parks are not scheduled to be open until 1 May, and are closed by 13 September at Fishhook Park, and 31 Oct at Charbonneau Park. Otherwise, the Contractor shall furnish sanitation facilities in accordance with EM 385-1-1.
The location of all facilities will be subject to Contracting Officer approval. Sanitary wastes shall be removed from the area and disposed of in a legal manner a minimum of once per week during the contract period. The Contractor shall provide freeze protection during the months October through March to prevent any spillage.
1.5 LOCAL UTILITY COORDINATION
The Contractor shall coordinate work with the local Utility Service Provider. The local electric utility is Columbia REA in Dayton, Washington. Point of Contact is Dan Andrews, 509.526.4041. The utility service provider will be under separate contract with the Government. The utility service provider will provide transformers, meters and feeder conductors. Contractor shall provide all trench and backfill for utility feeders per plans. Contractor is responsible for secondary conductors past the meters, including meterbases and panelboards.
1.6 CONTRACTORS STORAGE AND STAGING AREA.
The Contractor's storage and staging area shall be at the locations indicated. The storage and staging area may be used for setup of an office trailer, parking of vehicles, and for storage of materials and equipment.
Security at the storage and staging site shall be the Contractor’s responsibility. The contractor is responsible for securing any required storage and staging areas on and off-site. Temporary security fencing may be installed in around the storage and staging area in a manner approved by the Contracting Officer.
1.7 TRAFFIC CONTROL AND PUBLIC ACCESS
Existing public roads and access roads shall be kept open to vehicle traffic at all times. The Contractor shall conduct his work in such a manner as will obstruct and inconvenience traffic as little as possible.
When necessary for the Contractor to operate on or cross existing highways or roads, the Contractor shall furnish signs lights, and/or other necessary safe guards to safely control and direct the flow of traffic. The Contractor shall obtain any and all required permits for such operations from the appropriate private or public authority at no additional cost to the Government.
SECTION 01 11 01.00 28
1.8 REGULAR CLEANUP AND DEBRIS DISPOSAL
All debris resulting from the work regardless of size, such as packing cases, scrap lumber, metal grindings, and all other debris shall be collected and removed from the project site daily and disposed of in a legal manner. All costs for removing debris shall be incidental to the work, and no separate payment will be made therefore. The Government's trash cans, dumpsters, etc. shall not be used.
1.9 EQUIPMENT LIST
The Contractor shall furnish a complete list of all equipment to be used on the project, in duplicate, within 15 days after date of receipt of Notice to Proceed. The Contractor shall submit a revised list in the event of change of equipment. Lists shall include rented equipment as well as lease-purchase or sale-leaseback equipment. The initial list and the revised lists shall indicate dates equipment is assigned to or removed from the project and adequate identification or description of each item of equipment including manufacturer's name (abbreviated), model number, manufacturer's serial number, year of manufacture, and Contractor's assigned serial or record number.
1.10 TESTING OF EQUIPMENT
Before any machinery or mechanized equipment is put to use on the job, it shall be inspected and tested by a qualified person and determined to be in safe operating condition. Cranes or derricks shall be tested by the Contractor or a qualified testing agency in accordance with EM 385-1-1.
Equipment shall be large enough to safely handle proposed picks or tasks without exceeding the crane rating established by these tests.
1.11 DISPOSITION OF REMOVED EQUIPMENT
All existing equipment removed and not reinstalled shall become the property of the Contractor, removed from the Project site, and disposed of in a legal manner.
1.12 PROTECTION AND RESTORATION OF EXISTING FACILITIES
The Contractor shall take precautions to prevent damage to existing facilities while performing work under this contract. Upon completion of the work, all the existing facilities not included as a portion of the work shall be left in a condition better than or equal to the condition existing at time of contract award. Costs for maintenance, repair and restoration of any facilities shall be considered as incidental to and included in The Schedule prices.
The Contractor shall conduct a pre-work survey and a post-work survey of the Government facilities at the proposed work areas. The results of the surveys shall be documented by digital photographs and descriptive narrative reports. A color copy of the survey photographs and narrative reports shall be submitted to the Contracting Officer.
1.13 POST AWARD MEETINGS
1.13.1 Pre-Work Meeting
Within 10 days of receipt of Notice to Proceed, the Contractor shall attend a Pre-Work meeting. Senior Level members of the Contractor's staff involved with this contract shall participate in this meeting to discuss the overall contract requirements. The Government will lead this meeting and take the meeting minutes.
1.13.2 Pre-Construction Meeting
The Project Superintendent shall coordinate with the Contracting Officer and establish the date of the Pre-Construction Meeting. The meeting will be held at the project site at least one (1) week prior to mobilizing to the job site. The Project Superintendent shall lead the Pre-Construction meeting discussing the Contractor's plan on executing the work at the project site, schedule, required clearances and timeframe for them, and plan for implementing safety and quality control. The Government will have key members from the Project staff to discuss environmental and clearance issues. Key members of the contractor staff shall attend this meeting including the Quality Control (QC) System Manager, Site Safety Officer and any other members determined by the Government to be required.
The Project Superintendent shall be responsible for taking the meeting minutes and shall send them electronically within 48 hours of the meeting to the Government's Project Engineer, Quality Assurance Representative, and Resident Engineer.
Anytime the Contractor demobilizes from the site and remobilizes at a later date, another Pre-Construction meeting shall be held and shall follow the requirements listed above.
1.14 WEEKLY PRODUCTION MEETINGS
During all onsite construction work the Project Superintendent shall lead a weekly production meeting using the attached agenda to brief the Government on the status of the project. All elements listed in the agenda shall be thoroughly discussed. For example, the Project Superintendent shall provide the Government a three (3) week "look-ahead" that describes all the planned construction activities, onsite and offsite, over the next three
(3) weeks. These activities shall align to the overall construction schedule submitted under SECTION 01 32 01.00 28 PROJECT SCHEDULE, and if the three (3) week "look-ahead" differs from the construction schedule, the construction schedule shall be updated to refer these changes by the next scheduled update. Key members of the Contractor's staff shall attend this meeting, including the Quality Control System Manager, who is responsible for discussing QC aspects of the work as outlined under SECTION 01 45 02.00 28 CONTRACTOR QUALITY CONTROL and Site Safety Officer. The Government reserves the right to require any person from the Contractor's staff, such as the Project Manager, Engineer, scheduler, etc., or key subcontractor personnel to attend this meeting, if Government feels their participation is required.
The Project Superintendent shall be responsible for taking the meeting minutes and shall send them electronically within 24 hours of the meeting to the Contracting officer's Representative, the Government's Quality Assurance Representative, and Resident Engineer.
A Weekly Production Meeting template is included at the end of this SECTION.
1.15 USE OF WALLA WALLA DISTRICT PARKS
Special consideration for the use of the Walla Walla District Camping Grounds will not be given to the Contractor if they plan on camping at these sites.
The Contractor's crew may not use parking lots near the Ice Harbor Lock and Dam for RV parking. Government services such as water and power will not be provided. The Contractor shall be responsible for removing all of their RV's, including any debris, prior to demobilization. Demobilization shall not be considered complete until this is completed.
1.16 MAINTAIN WORKING AS-BUILT CONTRACT DRAWINGS
The Contractor shall maintain a current and accurate record of the work as actually constructed in the form of working as-built drawings by marking as-built conditions on the contract drawings. All As-Built drawings prepared by the Contractor for this contract shall conform dimensionally to Drawing No. WWD-40-33-01. As-built drawings shall incorporate all deviations from the design and modifications to the contract, however minor. Blue pencil shall be used to mark information added to the drawings and red pencil shall be used to mark information deleted from the drawings. Contract drawings shall be maintained on-site during construction.
The completeness and accuracy of the marked as-built drawings must be verified by Government Quality Assurance personnel prior to submission of progress payment requests. The working as-built drawings shall be submitted to the Contracting Officer after all as-built conditions have been marked on the working as-built contract drawings.
1.17 KEY PERSONNEL SUBSTITUTION
If the Contractor plans on replacing any Key personnel (Project Superintendent, CQC System Manager, or CQC staff Members) they must have the approval of the Contracting Officer and the new personnel qualifications must meet or exceed the personnel they are replacing.
1.18 DAILY VISITORS AND PUBLIC USE.
Charbonneau and Fish Hook parks are used extensively by the public, particularly on weekends, and may be open to the public during performance of the work. For protection of the public, 30 days prior to commencement of construction, the Contractor shall submit a public use control plan for the work areas. The plan shall conform to the requirements of Engineering Manual 385-1-1, “Safety and Health Requirements Manual,” and additional requirements as follows:
a. Plastic mesh safety fencing, orange in color, 48 inches tall, shall be installed at locations to limit access by the public to the work areas.
b. Public access to areas of the park outside the work areas shall be maintained during the work.
1.19 DUST CONTROL PLAN
The Contractor shall be responsible during dust generating activities to prevent the dust from spreading. Contractor shall submit a written dust control plan for approval.
1.20 ARRA PROJECT SIGNAGE
The Contractor shall furnish and install ARRA project signs at each of the sites listed below. All signs shall be self-standing, post holes will not be allowed. The signs shall conform to the attachment at the end of this SECTION (this information may also be found at the following website;
http://140.194.76.129/publications/eng-pamphlets/ep310-1-6a/s-16.pdf), except as otherwise specified. All signs shall have the ARRA logo placed as shown. The following US Army Corps of Engineers sign shops are available to produce these signs: UNICOR sign shop (POC: Mike Fleming, 805-735-6211); Tully Lake sign shop (POC: Jeff Mangum, 978-318-8282); and, Harry S. Truman Lake sign shop (POC: Lisa Freshler, 660-438-7317).
1.20.1 Construction Project Identification Sign Legend
The following information shall be printed on each sign following the guidelines in the attached sheets CONSTRUCTION PROJECT IDENTIFICATION SIGN.
Legend Group 1: Corps Relationship, the wording shall read:
Construction Supervised by:
Legend Group 2 Division/District Name:
Walla Walla District
Legend Group 3: Project Title:
Ice Harbor Lock & Dam, Arra Charbonneau-Fishhook Electrical Upgrades
1.20.2 Sign Locations
The Project signs shall be installed at both Charbonneau and Fishhook Parks at locations directed by the Contracting Officer.
1.20.3 Installation and Removal
The signs shall be installed 10 days before work on the site begins. All signs shall be removed at the end of the demobilization period.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section --
SECTION TABLE OF CONTENTS
DIVISION 03 - CONCRETE
SECTION 03 30 50.00 28.00 28
CONCRETE
PART 1 GENERAL
1.1 Concrete Work
1.2 REFERENCES
1.3 CONSTRUCTION TOLERANCES
1.3.1 Construction Tolerances
1.4 SUBMITTALS
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 Materials and Mix Design
2.1.2 Concrete Materials
2.1.3 Membrane-forming curing compound
2.1.4 Burlap
2.1.5 Water
2.2 STEEL WELDED WIRE FABRIC
2.3 MIXTURE PROPORTIONING AND PERFORMANCE
2.3.1 Concrete Requirements
2.3.2 Strength Evaluation
PART 3 EXECUTION
3.1 BATCHING AND MIXING CONCRETE
3.1.1 General
3.1.2 Batch Ticket Information
3.2 PREPARATIONS
3.2.1 Embedded Items
3.2.2 Sawcutting Concrete Slabs
3.3 CONVEYING
3.4 PLACING
3.4.1 General
3.4.2 Time Interval Between Mixing and Placing
3.4.3 Cold-Weather Placing
3.5 CONSOLIDATION
3.6 FINISHING
3.7 CURING AND PROTECTION
-- End of Section Table of Contents --
SECTION 03 30 50.00 28
SECTION 03 30 50.00 28.00 28
CONCRETE
PART 1 GENERAL
1.1 Concrete Work
The concrete related work specified in this section shall conform to the requirements of ASTM C 94 unless otherwise specified below. Concrete work includes preparations, formwork, placement, finishing, and curing of concrete for concrete pads for the panelboards, and meter cabinets, at both Charbonneau and Fishhoook Parks.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM C 33 (2003) Concrete Aggregates
ASTM C 94 (2000) Ready-Mixed Concrete
ASTM C 143 (2000) Slump of Hydraulic Cement Concrete
ASTM A 185/A 185M (2002) Steel Welded Wire Reinforcement, Plain, for Concrete
ASTM C 309 (1994) Standard Specification for Liquid Membrane-Forming Compounds for Curing Concrete
ASTM A 497/A 497M (2005) Steel Welded Wire Reinforcement, Deformed, for Concrete
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO)
AASHTO M 182 (2005) Burlap Cloth Made from Jute or Kenaf
U.S. ARMY CORPS OF ENGINEERS (USACE)
COE CRD-C 400 (1963) Requirements for Water for Use in Mixing or Curing Concrete
1.3 CONSTRUCTION TOLERANCES
1.3.1 Construction Tolerances
Variation in alignment, grade, and dimensions of the structures from the established alignment, grade, and dimensions shown on the drawings shall be as follows:
TABLE 1-1
SECTION 03 30 50.00 28
TOLERANCES
(1) Length, width, thickness | | Max 1/4 inch | | | Min 1/8 inch |
(2) Surface variations | In 5 feet | plus/minus | | | 1/8 inch |
(3) Top elevation | deviation from design line | plus/minus | | | Max 1/4 inch |
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-05 Design Data
Materials and Mix Design; G, GT (See submittal requirements in paragraph: Materials)
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 Materials and Mix Design
Submit the materials and mix design. The submittal shall include:
a) aggregate source data and laboratory report verifying properties, including: aggregate source identification, specific gravity, and gradations used in the mixes, absorption values, and fineness modulus used in mixes;
b) mill and manufacturer's certifications for all concrete materials;
c) concrete mixture proportions including: batch quantities of fine aggregate, coarse aggregate, admixtures, water, and cement per cubic yard based on saturated surface dry aggregate conditions;
d) material test properties, and performance information including:
compressive strengths at 7 and 28 days for the mixtures; slump; air content; and temperature of the mix that will be allowed in the field under quality control and actual slump, air content, and temperature of the mixtures measured during actual field placements;;
e) product data for all proposed admixtures;
f) sample batch ticket information;
g) membrane-forming curing materials.
2.1.2 Concrete Materials
Concrete materials shall conform to the applicable requirements of ASTM C 94.
Portland cement shall be a Type I or II, low alkali. Laboratory testing of aggregates proposed for use, showing compliance with ASTM C 33 shall have been performed within the last two (2) years. The course aggregate for concrete shall be a 3/4-inch or 1 inch maximum size aggregate (coarse aggregate grading 57 or 67). Entrained air content shall be measured at the discharge end of the transit mixer, or if a pump is used, at the discharge end of the pumpline.
2.1.3 Membrane-forming curing compound
Provide membrane-forming curing compound conforming to ASTM C 309 pigmented or nonpigmented. Nonpigmented compound shall contain a fugitive dye and shall have the reflective requirements in ASTM C 309 waived.
2.1.4 Burlap
Burlap used for curing shall conform to AASHTO M 182
2.1.5 Water
Water for mixing and curing shall be fresh, clean, potable, and free of injurious amounts of oil, acid, salt, or alkali, except that nonpotable water may be used if it meets the requirements of COE CRD-C 400.
2.2 STEEL WELDED WIRE FABRIC
Steel welded wire fabric (reinforcement) shall comply with the requirements of ASTM A 185/A 185M or ASTM A 497/A 497M with wire sizes and spacings as shown. For wire with a specified yield strength (fy) exceeding 60,000 psi, fy shall be the stress corresponding to a strain of 0.35 percent.
2.3 MIXTURE PROPORTIONING AND PERFORMANCE
2.3.1 Concrete Requirements
The Mix Design shall be the responsibility of the Contractor. The concrete mixture shall meet the performance requirements shown in Table 2-1. Mix No. 1 shall be used for all concrete structures. The Government may suggest revisions to a proposed mix and may reject the submittal if it is inadequate or incomplete. The Contractor shall provide established history from previous mixes, used within the last 3 years. Mixes must utilize the same materials proposed for this project. Fly ash may be included at a rate up to 15 percent of the volume of cementitious materials. Mixes shall be designed for a critical strength (f'cr) equal to f'c plus overdesign strength. See ASTM C 94 Table 4 for appropriate overdesign strength values. The slump shall be determined in accordance with ASTM C 143. Where the use of high range water reducing chemical admixture is approved, the slump shall not exceed 8 inches.
TABLE 2-1
SUMMARY OF CONCRETE REQUIREMENTS
Mix | Specified | Age | Max | ASTM C 33 | Slump | Air | ID | f'c 1 | | W/C | Grading No.| Range |Content | | | | Ratio | | | Range |
Mix No.1 | 4000 psi |28 days| 0.45 | 57 or 67 | 3-6 inch | 5-7 % |
2.3.2 Strength Evaluation
The strength of the concrete will be considered satisfactory so long as the average of all sets of three (3) consecutive test results equals or exceeds the specified strength and no individual test result (or average of two (2) cylinders) falls below the specified strength by more than 200 psi.
PART 3 EXECUTION
3.1 BATCHING AND MIXING CONCRETE
3.1.1 General
The batching and mixing equipment and procedures shall conform to the applicable provisions of ASTM C 94, except as otherwise specified. These requirements apply to both off-site and on-site measuring, batching, and mixing of concrete. The mixers shall not be charged in excess of the capacity recommended by the manufacturer. The mixers shall be operated at the drum or mixing blade speed designated by the manufacturer. The mixers shall be maintained in satisfactory operating condition, and the mixer drums shall be kept free of hardened concrete. Should any mixer at any time produce unsatisfactory results, its use shall be promptly discontinued until it is repaired.
3.1.2 Batch Ticket Information
The producer shall record the batching information for the concrete in accordance with ASTM C 94, Section 16, "Batch Ticket Information." The ticket must accompany the representative batch of concrete to the point of placement and be given to the Contracting Officer prior to placement of that batch of concrete. In the event the Contracting Officer or Contracting Officer's Representative is not at the site at the time of delivery, the batch tickets must be delivered or mailed to the Contracting Officer within 24 hours after delivery of the concrete.
3.2 PREPARATIONS
Surfaces against which concrete is to be placed shall be clean, damp, and free from frost, ice, and standing or running water. Gravel or aggregate foundations shall be compacted prior to placement of concrete.
3.2.1 Embedded Items
Before placing concrete, care shall be taken to determine that all embedded items are firmly and securely fastened in place as indicated on the drawings, or required. Embedded items shall be free of oil and other foreign matter such as loose coatings of rust, paint, and scale. The embedding of wood in concrete will be permitted only when specifically authorized or directed. Voids in sleeves, inserts, and anchor slots shall be filled temporarily with readily removable materials to prevent the entry of concrete into the voids.
3.2.2 Sawcutting Concrete Slabs
Sawcutting shall be performed at the locations and to the depths shown on
SECTION 03 30 50.00 28
the contract drawings. The sawcuts shall be done using a diamond-bladed saw. Sawcuts shall be straight and uniform. Excess concrete shall be disposed of as specified.
3.3 CONVEYING
Concrete shall be conveyed from mixer to forms as rapidly as practicable and within the time interval in paragraph: Time Interval Between Mixing and Placing by methods which will prevent segregation or loss of ingredients. Any concrete transferred from one conveying device to another shall be passed through a hopper which is conical in shape and shall not be dropped vertically more than 5 feet, except where suitable equipment is provided to prevent segregation and where specifically authorized.
3.4 PLACING
3.4.1 General
Concrete placement will not be permitted when, in the opinion of the Contracting Officer, weather conditions prevent proper placement and consolidation. Concrete shall be deposited as close as possible to its final position in the forms, and in so depositing there shall be no vertical drop greater than 5 feet except where suitable equipment is provided to prevent segregation and where specifically authorized.
Depositing of the concrete shall be so regulated that it may be effectively consolidated in horizontal layers 16 inches or less in thickness with a minimum of lateral movement. The amount deposited in each location shall be that which can be readily and thoroughly consolidated. Free water shall be removed prior to placement of concrete. Sufficient placing capacity shall be provided so that concrete placement can be kept plastic and free of cold joints while concrete is being placed.
3.4.2 Time Interval Between Mixing and Placing
Concrete shall be placed within 30 minutes after discharge into nonagitating equipment. When concrete is truck mixed or when a truck mixer or agitator is used for transporting concrete mixed by a concrete plant mixer, the concrete shall be delivered to the site of the work and discharge shall be completed within 1-1/2 hours after introduction of the cement to the aggregates. When the concrete temperature exceeds 85 F, the placement shall be completed within 45 minutes, except if an approved dosage of retarder is used, then placement shall be completed within 1-1/2 hours
3.4.3 Cold-Weather Placing
The ambient temperature of the space adjacent to the concrete placement and surfaces to receive concrete shall be above 32 F. The placing temperature of the concrete having a minimum dimension less than 304.8mm (12 inches) shall be between 60 F. and 75 F. The placing temperature of the concrete having a minimum dimension greater than 12 inches shall be between 50 F and 75 F. Heating of the mixing water or aggregates will be required to regulate the concrete placing temperatures. Materials entering the mixer shall be free from ice, snow, or frozen lumps. Salt, chemicals, or other materials shall not be mixed with the concrete to prevent freezing. An approved non-corrosive, non-chloride accelerator may be used.
SECTION 03 30 50.00 28
3.5 CONSOLIDATION
Immediately after placing, concrete shall be consolidated by a combination of rodding, spading, and internal vibrating. Vibrators shall not be used to transport concrete within the forms. Rodding and hand spading shall be performed along formed surfaces permanently exposed to view. Form or surface vibrators shall not be used. Vibrators of the proper size, frequency, and amplitude shall be used for the type of work. The vibrator shall be inserted vertically at uniform spacing over the entire area of placement. The distance between insertions shall be approximately one and one-half times the radius of action of the vibrator. The vibrator shall penetrate rapidly to the bottom of the layer and at least 6 inches into the preceding layer if such exists. It shall be held stationary until the concrete is consolidated and then withdrawn slowly. Care shall be taken to avoid contact with the form liner with the vibrator head.
3.6 FINISHING
Concrete shall be edged with an edging tool around the perimeter of the slab, the edges of the access path, and the top edges of the footing or pedestal. After the concrete has been placed, concrete shall be floated using a magnesium float or other approved float. The surface shall be dense, uniform, and show no voids. Unless otherwise shown on the contract drawings, all exterior concrete surfaces shall receive a light-broom finish. After the surface has been floated, the surface shall be finished with a fiber-bristle brush. Unless otherwise directed by the Contracting Officer, the deformations from brushing shall be 1/16 inch, and the direction of brushing shall be transverse to the direction of traffic.
3.7 CURING AND PROTECTION
All concrete shall be membrane cured for a minimum of 7 days. Membrane curing compound shall conform to ASTM C 309 and shall be applied in accordance with the manufacturer's recommendations. During the specified cure time, the curing concrete shall not be loaded with external forces, moved or disturbed. All concrete shall be adequately protected from damage. After placement, concrete shall be protected from the damaging effects of rain for 12 hours. All concrete shall be maintained above 40 degrees F. for the duration of the curing period. NO fire or excessive heat shall be permitted near or in direct contact with concrete at any time.
-- End of Section --
SECTION TABLE OF CONTENTS
DIVISION 26 - ELECTRICAL
SECTION 26 05 00.00 28
GENERAL ELECTRICAL WORK
PART 1 GENERAL
1.1 UNDERGROUND UTILITIES
1.2 REFERENCES
1.3 SUBMITTALS
1.4 PREVENTION OF CORROSION
1.5 GENERAL REQUIREMENTS
1.5.1 Departures from Drawings
1.5.2 Code
1.5.3 Coordination
1.5.4 Special Environments
1.5.4.1 Weatherproof Locations
1.5.5 Materials and Equipment
1.5.6 Standard Products
1.5.7 UL Listing
1.5.8 Identification Nameplates
1.5.9 As Built Drawings
1.6 WORKMANSHIP
PART 2 PRODUCTS
2.1 CONDUIT
2.1.1 Rigid-Steel Conduit (RSC)
2.1.2 Fiberglass Conduit
2.1.3 Rigid Nonmetallic Conduit
2.1.4 Bends
2.2 ABOVE GROUND BOXES AND ENCLOSURES
2.2.1 Steel Cabinets and Boxes
2.2.2 Concentric ring knockouts
2.2.3 Doors, Covers, Cabinet Trim and Hardware
2.2.4 INSULATED WIRE AND CABLE
2.2.5 General
2.2.6 Governing Standard
2.2.7 Type
2.2.8 Conductors
2.2.9 RECEPTACLES
2.2.10 Campsite Receptacles
2.2.11 Campsite Power Receptacle
2.2.12 MISCELLANEOUS ELECTRICAL EQUIPMENT
2.2.13 Utilities
2.2.14 Service Entrance Equipment
2.2.15 Utililty Feeders
PART 3 EXECUTION
3.1 REPAIR OF EXISTING WORK
SECTION 26 05 00.00 28
3.1.1 Workmanship
3.1.2 Existing Concealed Wiring to be Removed
3.1.3 Removal of Existing Electrical Distribution System
3.1.4 Continuation of Service
3.2 PAINTING AND FINISHING
3.2.1 Factory-Applied Paint
3.3 FIELD TESTING
3.3.1 General
3.3.2 Continuity Test
3.3.3 Acceptance
3.4 SPARE PARTS
-- End of Section Table of Contents --
SECTION 26 05 00.00 28
GENERAL ELECTRICAL WORK
PART 1 GENERAL
Contractor shall furnish all necessary labor and materials required for removal of all above grade camp ground pedestal system components (abondon in-place existing buried service), supplying and installing the new meter bases, NEMA 4 enclosures for panelboards, new campsite electrical pedestals, conduits in sleeves at road crossings, panelboards with associated concrete pads, and appurtenant wiring and electrical conduit required for supplying power to the campsites and Visitor Pavilion. This shall include, but not be limited to, disconnecting and re-connecting circuits as required, excavation, trenching, backfilling, and asphalt concrete pavement repair, as well as supporting the medium voltage installation requirements of the serviing utility company.
1.1 UNDERGROUND UTILITIES
The parks have existing underground sprinklers, water lines and electrical system, but there are no drawings that show their exact locations.
Approximate Sprinkler and Water lines are shown in the "For Information Only" drawings. The existing underground electrical system shall be abandoned in-place. The Contractor shall be responsible for repairing or replacing damaged sprinklers and water lines with new to equal or better condition that may be damaged during work under this contract.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ANSI/NECA 1 (2000) Standard Practices for Good Workmanship in Electrical Contracting
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE C2 (2005) National Electrical Safety Code
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2005) National Electrical Code
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
NEMA WC 70 (1999 Errata 2001) Standard for Non-Shielded Power Cable 2000 V or Less
UNDERWRITERS LABORATORIES (UL)
UL 1684 (2000) Reinforced Thermosetting Resin Conduit (RTRC) and Fittings
UL 44 (2005) Thermoset-Insulated Wires and Cables
UL 83 (2003; Rev thru Mar 2004) Thermoplastic-Insulated Wires and Cables
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Fiberglass Conduit;G EL
SD-06 Test Reports
Continuity Test
1.4 PREVENTION OF CORROSION
Protect metallic materials against corrosion. Provide equipment enclosures with the standard finish by the manufacturer when used for most indoor installations. Do not use aluminum when in contact with earth or concrete and, where connected to dissimilar metal, protect by approved fittings and treatment. Ferrous metals such as, but not limited to, anchors, bolts, braces, boxes, bodies, clamps, fittings, guards, nuts, pins, rods, shims, thimbles, washers, and miscellaneous spare parts not of corrosion-resistant steel must be hot-dip galvanized except where other equivalent protective treatment is specifically approved in writing.
1.5 GENERAL REQUIREMENTS
1.5.1 Departures from Drawings
The contract drawings constitute the working drawings for construction and for purchase of required materials, and indicate the extent and general location and arrangement of equipment, conduit, and wiring. The Contractor shall become familiar with all details of the work and verify all dimensions in the field so that the outlets and equipment shall be properly located and readily accessible. If any departures from the contract drawings are deemed necessary by the Contractor, details of such departures and reasons therefore shall be submitted to the Contracting Officer for approval as soon as practicable but not later than 30 days before installation. No such departure shall be made without the prior written approval of the Contracting Officer.
1.5.2 Code
The installation shall be in accordance with the National Electrical Code ( NFPA 70) and National Electrical Safety Code (IEEE C2) except where more stringent requirements are indicated herein or shown on the contract drawings. Omission of details on the drawings or in the specifications shall not be construed as permitting deviations from Code requirements.
1.5.3 Coordination
The Contractor shall coordinate the electrical requirements of the mechanical work and provide all power related circuits, wiring, hardware and structural support, even if not shown on the drawings.
1.5.4 Special Environments
1.5.4.1 Weatherproof Locations
Wiring and equipment shall conform to NFPA 70 requirements for installation in damp or wet locations.
1.5.5 Materials and Equipment
Materials and equipment shall be approved based on the manufacturer's published data. All electrical materials shall be new and unused.
Defective equipment or equipment damaged in the course of installation shall be replaced or repaired without cost to the Government in a manner meeting the approval of the Contracting Officer. Insofar as practicable, equipment for the same, similar, or allied service shall be of the same make and type, and when of the same rating it shall be interchangeable.
1.5.6 Standard Products
Unless otherwise indicated, the materials and equipment to be furnished under this specification shall be the standard products of manufacturers regularly engaged in the production of such items and shall be the manufacturer's latest standard marketed design.
1.5.7 UL Listing
The materials and equipment to be furnished under this specification shall be UL listed. The label or listing of the Underwriters Laboratories, Inc., shall be accepted as evidence that the materials or equipment conform to the applicable standards of that agency. In lieu of this label or listing, a statement from a nationally recognized, adequately equipped testing laboratory indicating that the items have been tested in accordance with required procedures and that the materials and equipment comply with all requirements of the governing authority will be accepted.
1.5.8 Identification Nameplates
Major items of electrical equipment and major components shall be…