Amend 0003.pdf
PDF 259 KB Posted
- Solicitation number
- W912EF-09-B-0017
About this file
Amendment 0003
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Results W912EF-09-B-0017.pdf | ||
| Vol2-Amend3-Plans_C-403_C-501.pdf | ||
| Vol1-Amend3-Plans_C-402.pdf | ||
| Amend 0002.pdf | ||
| Amend 0001 Volume 3 drawings.zip | ZIP file | |
| Amendment 0001.pdf | ||
| Amend 0001 Volume 4 drawings.zip | ZIP file | |
| Amend 0001 Volume 1 drawings.zip | ZIP file | |
| Amend 0001 Volume 2 drawings.zip | ZIP file | |
| Solicitation 09-B-0017.pdf | ||
| Vol-3.zip | ZIP file | |
| Vol-4.zip | ZIP file | |
| Downloading and viewing drawings.pdf | ||
| Vol-2.zip | ZIP file | |
| Vol-1.zip | ZIP file | |
| Vol-5.zip | ZIP file | |
| Site visit info.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W68SBV91914291
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
Changes are made to the bid schedule, draw ings, and technical specifications as indicated on the attached sheets. Bid opening remains unchanged at: September 9, 2009, 2:00pm, local time.
ARRA (Recovery Act) Project: Road repair/paving at Ice Harbor Dam, Little Goose Dam, Low er Granite Dam, Mill Creek Dam, and Dw orshak
1. CONTRACT ID CODE PAGE OF PAGES
J
FAR (48 CFR) 53.243
1 16
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 31-Aug-2009
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EF-09-B-0017
X 9B. DATED (SEE ITEM 11)
30-Jul-2009
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
31-Aug-2009
CODE
USAED, WALLA WALLA - CONTRACTING DIV.
PHYLLIS L. BUERSTATTE
201 NORTH 3RD AVE.
WALLA WALLA WA 99362-1876
W912EF 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912EF-09-B-0017
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
1. Bid opening remains unchanged at: 2:00 pm, local time, on September 9, 2009
2. Bidders must acknowledge receipt of this amendment. See Block No. 11 of Standard Form 30 for methods of acknowledging solicitation amendments.
3. The following changes are made to the solicitation as a result of this amendment:
A. Changes to the Bid Schedule
Volume 1
1. Bid Item 0012 has been changed from 6, 000 Sq Ft. to 3,000 Sq Ft Bid Item 0013 has been changed from 30 LF to 600 LF.
Volume 2
2. Bid Item 0050 has been changed from 1,500 Sq Ft to 4,000 Sq Ft Bid Item 0051 Pavement Markings has been added.
Volume 3
2. All bid item numbers after 0050 have changed as a result of the addition of Bid Item 0051 in Volume 2.
Bid Item 0055, was numbered “0054”, has been changed from 16,976 Sq Yd to 14,000 Sq Yd Bid Item 0056, was numbered “0055”, has been changed from 7,300 LF to 6,300 LF.
B. Changes to Contract Clauses
1. 252.236-7001 CONTRACT DRAWINGS, MAPS, AND SPECIFICATIONS
Added amend number and date to the revised drawings.
C. Changes to Drawings:
Volume 1
1. Revised sheet C-402, Revised Note 3, see brackets.
Volume 2
2. Revised sheet C-501, Detail 4 Title has been changed form Little Goose Crest Road Asphalt Paving to “Little Goose Crest Road and Willow Landing Asphalt Paving”
D. Changes to Technical Specifications
1. Section 01 22 00.00 28, “MEASUREMENT AND PAYMENT”, the following changes have been made:
a. 1.7, AGGREGATE SURFACE COURSE; changed bid item number from 0063 to 0064.
b. 1.8 DITCH CLEANING; changed bid item numbers from 0064 and 0068 to 0065 and 0069
2. Section 32 12 16.00 28 “ASPHALT PAVING”, the following paragraph has been revised:
a. 1.1, SCOPE OF WORK; added the following: and also the Little Goose project, Willow Landing site to the paragraph. It now reads
The work covered by this SECTION shall consist of constructing an asphalt concrete pavement on a prepared surface for the Lower Granite Project Lewiston/Clarkston Bike Paths including the Naves and Chestnut parking lots and also the Little Goose project, Willow Landing site. The Contractor shall provide all necessary equipment, materials, and personnel to supply, place, and compact an asphalt concrete surface in accordance with these specifications and conforming to the lines, grades, thicknesses, and typical cross sections shown on the contract drawings.
3. Section 32 15 00.10 28 “AGGREGATE SURFACE COURSE”, the following paragraph has been revised:
a. 3.1, COMPACTION: Changed 100 percent to 95 percent in the second to last sentence.
Degree of compaction is a percentage of the maximum density obtained by the test procedure presented in ASTM D 1557 abbreviated herein as present laboratory maximum density. Compact each layer of the aggregate surface course with approved compaction equipment and as required in the following paragraphs. The water content during the compaction procedure shall be maintained at optimum or at the percentage specified by the Contracting Officer. In locations not accessible to the rollers, the mixture shall be compacted with mechanical tampers. Compaction shall continue until each layer through the full depth is compacted to at least 95 percent of laboratory maximum density. Remove any materials that are found to be unsatisfactory and replace them with satisfactory material or rework them to produce a satisfactory material.
SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS
BID SCHEDULE
ARRA MULTIPLE PROJECT ROAD REPAIR/PAVING
Magnitude of construction for all locations combined is between $1,000,000 and $5,000,000 Volume 1
Ice Harbor Project
Franklin and Benton County, Washington
Magnitude of construction is between $500,000 and $1,000,000
ITEM
DESCRIPTION
QUANTITY
U/M
U/P
AMOUNT
North Shore Access Road
Estimated 0001 Single Bituminous Surface Treatment 5,925 Sq Yd _______ _________ Estimated 0002 Sealing of Cracks in Asphalt Pavement 5,540 LF _______ _________ Estimated 0003 Asphalt Concrete Pavement Repair 100 Sq Ft _______ _________ Estimated 0004 Pavement Markings 0004AA Pavement Markings 600 LF _______ _________ 0004AB Life Jacket Graphic 1 LS _______ _________
North Shore Access Road SCHEDULE SUB-TOTAL $__________
Charbonneau Park
0005 Single Bituminous Surface Treatment 17,894 Sq Yd _______ _________ Estimated 0006 Sealing of Cracks in Asphalt Pavement 15,900 LF _______ _________ Estimated 0007 Asphalt Concrete Pavement Repair 40 Sq Ft _______ _________ Estimated 0008 Parking Bumper Curbs 85 Each _______ _________ Estimated 0009 Pavement Markings 0009AA Pavement Markings 5,625 LF _______ _________ 0009AB Life Jacket Graphic 1 LS _______ _________
Charbonneau Park SCHEDULE SUB-TOTAL $__________
Charbonneau Park Day Use Parking Optional Items
0010 Single Bituminous Surface Treatment 7,533 Sq Yd _______ _________ Estimated 0011 Sealing of Cracks in Asphalt Pavement 5,100 LF _______ _________ Estimated 0012 Asphalt Concrete Pavement Repair 3,000 Sq Ft _______ _________ Estimated 0013 Tree Root Barriers 600 LF Estimated 0014 Parking Bumper Curbs 150 Each _______ _________
0015 Pavement Markings 4,000 LF _______ _________
Charbonneau Park Day Use Parking Optional Items SCHEDULE SUB-TOTAL $__________
Fishhook Park
0016 Single Bituminous Surface Treatment 19,745 Sq Yd _______ _________ Estimated 0017 Sealing of Cracks in Asphalt Pavement 9,100 LF _______ _________ Estimated 0018 Asphalt Concrete Pavement Repair 1,500 Sq Ft _______ _________ Estimated 0019 Parking Bumper Curbs 120 Each _______ _________ Estimated 0020 Pavement Markings 0020AA Pavement Markings 7,500 LF _______ _________ 0020AB Life Jacket Graphic 1 LS _______ _________
Fishhook SCHEDULE SUB-TOTAL $__________
Natural Resource Access Road and Parking Lot
0021 Single Bituminous Surface Treatment 4,800 Sq Yd _______ _________ Estimated 0022 Sealing of Cracks in Asphalt Pavement 5,200 LF _______ _________ Estimated 0023 Asphalt Concrete Pavement Repair 50 Sq Ft _______ _________
0024 Pavement Markings 800 LF _______ _________
Natural Resource Access Road and Parking Lot SCHEDULE SUB-TOTAL $__________
South Abutment Visitor Center Parking Lot
0025 Single Bituminous Surface Treatment 3,177 Sq Yd _______ _________ Estimated 0026 Sealing of Cracks in Asphalt Pavement 3,100 LF _______ _________ Estimated 0027 Asphalt Concrete Pavement Repair 50 Sq Ft _______ _________
0028 Pavement Markings 900 LF _______ _________
South Abutment Visitor Center Parking Lot SCHEDULE SUB-TOTAL $__________
Levey Park
0029 Single Bituminous Surface Treatment 14,338 Sq Yd _______ _________ Estimated 0030 Sealing of Cracks in Asphalt Pavement 3,150 LF _______ _________ Estimated 0031 Asphalt Concrete Pavement Repair 1,110 Sq Ft _______ _________ Estimated 0032 Parking Bumper Curbs 80 Each _______ _________ Estimated 0033 Pavement Markings 0033AA Pavement Markings 3,950 LF _______ _________ 0033AB Life Jacket Graphic 1 LS _______ _________
Levey SCHEDULE SUB-TOTAL $__________
Windust Park
0034 Single Bituminous Surface Treatment 9,296 Sq Yd _______ _________ Estimated 0035 Sealing of Cracks in Asphalt Pavement 3,530 LF _______ _________ Estimated 0036 Asphalt Concrete Pavement Repair 440 Sq Ft _______ _________ Estimated 0037 Parking Bumper Curbs 150 Each _______ _________
0038 Pavement Markings 2,400 LF _______ _________
Windust SCHEDULE SUB-TOTAL $__________
ICE HARBOR PROJECT SCHEDULE TOTAL $__________
Volume 2
Little Goose Project Columbia, Whitman and Garfield Counties, Washington
Magnitude of construction is between $250,000 and $500,000
Little Goose Areas
0039 Single Bituminous Surface Treatment 41,500 Sq Yd _______ _________ Estimated 0040 Sealing of Cracks in Asphalt Pavement 19,000 LF _______ _________ Estimated 0041 Asphalt Concrete Pavement Repair 3,000 Sq Ft _______ _________ Estimated 0042 Parking Bumper Curbs 50 Each _______ _________
0043 Pavement Markings 9,500 LF _______ _________
Little Goose Areas SCHEDULE SUB-TOTAL $__________
Little Goose Dam Crest
0044 Asphalt Paving 2,500 Sq Yd _______ _________ Estimated 0045 Sealing of Cracks in Asphalt Pavement 3,000 LF _______ _________ Estimated 0046 Asphalt Concrete Pavement Repair 1,000 Sq Ft _______ _________
0047 Pavement Markings 9,100 LF _______ _________
Little Goose Dam Crest SCHEDULE SUB-TOTAL $__________
Willow Landing
0048 Asphalt Paving 5,700 Sq Yd _______ _________ Estimated 0049 Sealing of Cracks in Asphalt Pavement 2,500 LF _______ _________ Estimated 0050 Asphalt Concrete Pavement Repair 4,000 Sq Ft _______ _________
0051 Pavement Markings 3,000 LF _______ _________
Willow Landing SCHEDULE SUB-TOTAL $__________
LITTLE GOOSE PROJECT SCHEDULE SUB-TOTAL $__________
Volume 3
Lower Granite Project Asotin County, Washington and Nez Pierce County, Idaho
Clearwater River Lewiston Levee Bike Path Repair
0052 Asphalt Paving 12,000 Sq Yd _______ _________ Estimated 0053 Sealing of Cracks in Asphalt Pavement 3,750 LF _______ _________
0054 Asphalt Concrete Pavement Repair 2,360 Sq Ft _______ _________
Clearwater River Lewiston Levee Bike Path Repair SCHEDULE SUB-TOTAL $__________
Snake River Greenbelt Segment Paving Repair
0055 Asphalt Paving 14,000 Sq Yd _______ _________ Estimated 0056 Sealing of Cracks in Asphalt Pavement 6,300 LF _______ _________ Estimated 0057 Asphalt Concrete Pavement Repair 390 Sq Ft _______ _________ Estimated 0058 Parking Bumper Curbs 55 Each _______ _________
0059 Pavement Markings 1,400 Sq Ft _______ _________
Snake River Greenbelt Segment Paving Repair SCHEDULE SUB-TOTAL $__________
LOWER GRANITE PROJECT SCHEDULE TOTAL $__________
Volume 4
Mill Creek Project Walla Walla County, Washington
Magnitude of construction is between $25,000 and $100,000
0060 Single Bituminous Surface Treatment 13,100 Sq Yd _______ _________
0061 Sealing of Cracks in Asphalt Pavement 8,000 LF _______ _________
0062 Asphalt Concrete Pavement Repair 1,200 Sq Ft _______ _________
0063 Pavement Markings 16,000 LF _______ _________
MILL CREEK PROJECT SCHEDULE TOTAL $__________
Volume 5
Dworshak Project Clearwater County, Idaho
Dworshak Reservoir Work Sites
0064 Aggregate Surface Course 63,000 Sq Yd _______ _________
0065 Ditch Cleaning 3,500 LF _______ _________
Dworshak Reservoir Work Sites SCHEDULE SUB-TOTAL $__________
Dworshak Dent Acres Campground Access Road
0066 Single Bituminous Surface Treatment 9,330 Sq Yd _______ _________
0067 Sealing of Cracks in Asphalt Pavement 5,000 LF _______ _________
0068 Asphalt Concrete Pavement Repair 2,000 Sq Ft _______ _________
0069 Ditch Cleaning 3,500 LF _______ _________
0070 Pavement Markings 7,000 LF _______ _________
Dworshak Dent Acres Campground Access Road SCHEDULE SUB-TOTAL $__________
ARRA MUTIPLE PROJECT ROAD REPAIR/PAVING SCHEDULE TOTAL $_____________
In accordance with Contract Clause: 52.228-5 Insurance -- Work on a Government Installation, the Contractor shall procure and maintain the following minimum insurance:
(i) Coverage complying with state laws governing insurance requirements pertaining to Workmen’s Compensation and Employers” Liability Insurance.
(ii) Bodily injury liability insurance with minimum limits of $500,000 per occurrence shall be required on the comprehensive form of policy.
(iii) Automobile bodily injury and property damage liability with minimum limits of $200,000 per person and $500,000 per occurrence for bodily injury liability; and $20,000 per occurrence for property damage liability shall be required.
SECTION 00700 - CONTRACT CLAUSES
The following have been modified:
252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)
(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.
(b) The Contractor shall--
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
(3) Promptly notify the Contracting Officer of any discrepancies;
(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and
(5) Reproduce and print contract drawings and specifications as needed.
(c) In general--
(1) Large-scale drawings shall govern small-scale drawings; and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:
FILE NUMBER SHEET
NUMBER TITLE REVISION
NUMBER DATE
ICE HARBOR - VOLUME 1
IHG-1-0-1/395 G-001 ICE HARBOR PROJECT - COVER SHEET
AND LOCATION MAPS
IHG-1-0-1/396 G-002 ICE HARBOR PROJECT - INDEX TO
DRAWINGS
NUMBER DATE
IHG-1-9-6/1 C-101 ICE HARBOR PROJECT - PAVING KEY PLAN
IHG-1-9-6/2 C-401 ICE HARBOR DAM VICINITY - NEW
SURFACE TREATMENT - PLAN A 8/24/09
IHG-1-0-10/239 C-402 CHARBONNEAU PARK - NEW SURFACE
TREATMENT - PLAN B 8/28/09
IHG-1-0-10/240 C-403 LEVEY PARK - NEW SURFACE TREATMENT
- PLAN A 8/24/09
IHG-1-0-10/241 C-404 FISHHOOK PARK - NEW SURFACE
TREATMENT - PLAN A 8/24/09
IHG-1-0-10/242 C-405 WINDUST PARK - NEW SURFACE
TREATMENT - PLAN A 8/24/09
IHG-1-0-10/243 C-501 MISCELLANEOUS DETAILS
LITLE GOOSE - VOLUME 2
LGG-1-0-1/299 G-001 LITTLE GOOSE PROJECT - COVER SHEET
AND LOCATION MAPS
LGG-1-0-1/300 G-002 LITTLE GOOSE PROJECT - INDEX TO
DRAWINGS
LGG-1-0-5/60 C-101 LITTLE GOOSE PROJECT - PAVING KEY
PLAN
LGG-1-0-5/61 C-401 DAM AND RECREATION AREAS - NEW
SURFACE TREATMENT - PLAN A 8/24/09
LGG-1-0-5/62 C-402 LITTLE GOOSE DAM - NEW SURFACE
TREATMENT - PLAN A 8/24/09
LGG-1-0-10/73 C-403
LITTLE GOOSE RECREATION AREAS - NEW
SURFACE TREATMENT - WILLOW LANDING
PLAN
A 8/28/09
LGG-1-0-5/63 C-501 MISCELLANEOUS DETAILS B 8/28/09
NUMBER DATE
LOWER GRANITE - VOLUME 3
GDG-1-0-1/515 G-001 LOWER GRANITE PROJECT - COVER
SHEET AND LOCATION MAPS
GDG-1-0-1/516 G-002 LOWER GRANITE PROJECT - INDEX TO
DRAWINGS
GDG-1-0-5/109 C-101
LOWER GRANITE PROJECT - LEWISTON-
CLARKSTON BIKE PATHS - AREAS OF NEW
PAVING
A 8/24/09
GDG-1-0-5/110 C-401 CLEARWATER R. LEWISTON LEVEE - BIKE
PATH SEGMENT 4 - PLAN VIEW
GDG-1-0-5/111 C-402 CLEARWATER R. LEWISTON LEVEE - BIKE
PATH SEGMENTS 1,2,3 - PLAN VIEW A 8/24/09
GDG-1-0-5/112 C-403 SNAKE RIVER GREENBELT - SEGMENTS 3-6
- PLAN VIEWS A 8/24/09
GDG-1-0-5/113 C-404 SNAKE RIVER GREENBELT - SEGMENTS 7
& 8 - PLAN VIEW A 8/24/09
GDG-1-0-5/114 C-405 SNAKE RIVER GREENBELT - SEGMENT 9 -
PLAN VIEW A 8/24/09
GDG-1-0-5/115 C-501 MISCELLANEOUS DETAILS
MILL CREEK - VOLUME 4
MC-1-123/1 G-001 MILL CREEK PROJECT - COVER SHEET
AND LOCATION MAPS
MC-1-123/2 G-002 MILL CREEK PROJECT - INDEX TO
DRAWINGS
MC-1-123/3 C-101 MILL CREEK PROJECT - AREAS TO BE
PAVED
MC-1-123/4 C-501 MISCELLANEOUS DETAILS
DWORSHAK - VOLUME 5
DWG-1-0-1/382 G-001 DWORSHAK PROJECT - COVER SHEET AND
LOCATION MAPS
DWG-1-0-1/383 G-002 DWORSHAK PROJECT - INDEX TO
DRAWINGS
DWG-1-0-10/229 C-101 DWORSHAK PROJECT - KEY PLAN
NUMBER DATE
DWG-1-0-10/230 C-401
GRANDAD (W/CAMPGROUND). CAMP X,
AND BREAKFAST CREEK ROADS - AREAS
OF NEW GRAVEL
DWG-1-0-10/231 C-402 LITTLE MEADOW CREEK ROAD AND ORMV
CAMP - AREAS OF NEW GRAVEL
DWG-1-0-10/232 C-403 DENT ACRES CAMPGROUND - ACCESS
ROAD - NEW SURFACE TREATMENT PLAN
DWG-1-0-10/236 C-501 MISCELLANEOUS DETAILS
(End of drawing list) (End of Clause)
Contract drawings created on CADD will be available in electronic form for use by the Contractor. No For Information Only drawings are available on CADD. The Contractor assumes all risks associated in using electronic CADD drawings. The contract drawings shall govern if there are any discrepancies between the electronic copy and the contract drawing. The Contractor shall promptly notify the Contracting Officer of any discrepancies. The Government will not be responsible to correct the electronic CADD drawing. If contract modifications are issued, the associated electronic CADD drawings will not be available to the Contractor. Electronic copies of CADD drawings are only available in Bentley MicroStation format. The Government will provide the files on CD ROM. If the Contractor requires different media, such as floppy disks, the Contractor shall be responsible for all conversions required for their use and associated conversion inaccuracies.
(End of Summary of Changes)
Multible Project Road Repair/Paving W912EF-09-B-0017 Amend 3
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 28
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SINGLE BITUMINOUS SURFACE TREATMENT
1.2 SEALING OF CRACKS IN ASPHALT PAVEMENT
1.3 ASPHALT CONCRETE PAVEMENT REPAIR
1.4 PAVEMENT MARKINGS
1.4.1 Pavement Markings
1.4.2 Life Jacket Graphic
1.5 PARKING BUMPER CURBS
1.6 ASPHALT PAVING
1.7 AGGREGATE SURFACE COURSE
1.8 DITCH CLEANING
1.9 CHARBONNEAU PARK DAY USE AREA OPTIONAL ITEMS
1.9.1 SINGLE BITUMINOUS SURFACE TREATMENT
1.9.2 SEALING OF CRACKS IN ASPHALT PAVEMENT
1.9.3 ASPHALT CONCRETE PAVEMENT REPAIR
1.9.4 Tree Root Barriers
1.9.5 Parking Bumper Curbs
1.9.6 Pavement Markings
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section Table of Contents --
SECTION 01 22 00.00 28
G4EDDRJR
Line
SECTION 01 22 00.00 28
MEASUREMENT AND PAYMENT
PART 1 GENERAL
In each instance, the contract price for an item shall constitute full compensation for furnishing all plant, labor, equipment, and materials, and for performing all operations required to complete the work included in the item as herein specified, or as otherwise approved.
1.1 SINGLE BITUMINOUS SURFACE TREATMENT
Single bituminous surface treatment will be measured for payment as the number of Square Yards (Sq Yd) of surface treatment completed. Payment will be made at the unit price for each Item Nos. titled, "Single Bituminous Surface Treatment," which price and payment shall be full compensation for all work of this type required for each work area, complete, as specified and approved.
1.2 SEALING OF CRACKS IN ASPHALT PAVEMENT
Sealing of cracks in asphalt pavement will be measured for payment as the number of Linear Feet (LF) of cracks sealed. Payment will be made at the unit price for each Item Nos. titled, "Sealing Of Cracks In Asphalt Pavement," which price and payment shall be full compensation for all work of this type required for each work area, complete, as specified and approved.
1.3 ASPHALT CONCRETE PAVEMENT REPAIR
Asphalt concrete pavement repair will be measured for payment as the number of Square Feet (Sq Ft) of pavement repair completed. Payment will be made at the unit price for each Item Nos. titled, "Asphalt Concrete Pavement Repair," which price and payment shall be full compensation for all work of this type required for each work area complete, as specified and approved.
1.4 PAVEMENT MARKINGS
1.4.1 Pavement Markings
Pavement markings will be measured for payment as the number of Linear Feet (LF) of marking completed. Payment will be made at the unit price for each Item Nos. titled, "Pavement Markings," which price and payment shall be full compensation for all work of this type required for each work area complete, as specified and approved.
1.4.2 Life Jacket Graphic
Life Jacket Graphic will be measured for payment as a lump sum (LS) item for painting the life jacket graphic. Payment will be made at the lump sum price for each Item Nos. titled, "Life Jacket Graphic," which price and payment shall be full compensation for all work of this type required for each work area, complete, as specidied and approved.
1.5 PARKING BUMPER CURBS
Parking bumper curbs will be measured for payment as the number of existing parking curbs (EA) moved at each work area. Payment will be made at the unit price for each Item Nos. titled, "Parking Bumper Curbs," which price and payment shall be full compensation for all work involved to handle parking curbs at each work area, complete, as specified and approved.
1.6 ASPHALT PAVING
Asphalt Paving will be measured for payment as the number of Square Yards (Sq Yd) of paving completed. Payment will be made at the unit price for each Item Nos. titled, "Asphalt Paving," which price and payment shall be full compensation for all work of this type required for each work area complete, as specified and approved.
1.7 AGGREGATE SURFACE COURSE
Aggregate Surface Course will be measured for payment as the number of Square Yards (Sq Yd) of surface course completed. Payment will be made at the unit price for Item No. 0064, "Aggregate Surface Course," which price and payment shall be full compensation for all work of this type required for each work area complete, as specified and approved.
1.8 DITCH CLEANING
Ditch Cleaning will be measured for payment as the number of Linear Feet (LF) of ditch cleaned. Payment will be made at the unit price for Item Nos. 0065 and 0069 "Ditch Cleaning," which price and payment shall be full compensation for all work required for ditch cleaning, complete, as specified and approved.
1.9 CHARBONNEAU PARK DAY USE AREA OPTIONAL ITEMS
1.9.1 SINGLE BITUMINOUS SURFACE TREATMENT
Single bituminous surface treatment will be measured for payment as the number of Square Yards (Sq Yd) of surface treatment completed. Payment will be made at the unit price for Item No. 0010, "Single Bituminous Surface Treatment," which price and payment shall be full compensation for all work, complete, as specified and approved.
1.9.2 SEALING OF CRACKS IN ASPHALT PAVEMENT
Sealing of cracks in asphalt pavement will be measured for payment as the number of Linear Feet (LF) of cracks sealed. Payment will be made at the unit price for Item No. 0011, "Sealing Of Cracks In Asphalt Pavement," which price and payment shall be full compensation for all work, complete, as specified and approved.
1.9.3 ASPHALT CONCRETE PAVEMENT REPAIR
Asphalt concrete pavement repair will be measured for payment as the number of Square Feet (Sq Ft) of pavement repair completed. Payment will be made at the unit price for Item No 0012, "Asphalt Concrete Pavement Repair," which price and payment shall be full compensation for all work, complete, as specified and approved.
SECTION 01 22 00.00 28
1.9.4 Tree Root Barriers
Tree root barriers will be measured for payment as the number of Linear Feet (LF) of tree root barrier installed. Payment will be made at the unit price for Item No 0013, "Tree Root Barriers," which price and payment shall be full compensation for all work involved to install the root barriers, complete, as specified and approved.
1.9.5 Parking Bumper Curbs
Parking bumper curbs will be measured for payment as the number of existing parking curbs (EA) moved at each work area. Payment will be made at the unit price for Item No 0014, "Parking Bumper Curbs," which price and payment shall be full compensation for all work involved to handle parking curbs, complete, as specified and approved.
1.9.6 Pavement Markings
Pavement markings will be measured for payment as the number of Linear Feet (LF) of marking completed. Payment will be made at the unit price for Item No 0015, "Pavement Markings," which price and payment shall be full compensation for all work, complete, as specified and approved.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section --
SECTION TABLE OF CONTENTS
DIVISION 32 - EXTERIOR IMPROVEMENTS
SECTION 32 12 16.00 28
ASPHALT PAVING
PART 1 GENERAL
1.1 SCOPE OF WORK
1.2 REFERENCES
1.3 TOLERANCES
1.3.1 Asphalt Cement Content
1.3.2 Weights of Aggregates
1.3.3 Asphalt Concrete Surface Parallel to the Roadway
1.3.4 Asphalt Concrete Surface Perpendicular to the Roadway
1.4 SUBMITTALS
1.5 CONTRACTOR QUALITY CONTROL
1.5.1 Aggregate Source Approval
1.5.2 Nuclear Gauge Submittal
1.5.3 Job Mix Formula
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 Aggregates
2.1.1.1 General
2.1.1.2 Durability
2.1.1.3 Fracture Requirements
2.1.1.4 Sand Equivalent
2.1.1.5 Wood Waste
2.1.1.6 Gradation
2.1.2 Mineral Filler
2.1.3 Asphalt Cement
2.1.4 Antistripping Additive
2.1.5 Tack Coat
2.2 COMPOSITION AND PROPORTIONS
2.2.1 Job Mix Formula
2.2.2 State-Approved Job Mix Formula
2.3 PRODUCTION
2.3.1 Mixing Plants
2.3.2 Materials During Production
2.3.2.1 Asphalt Cement
2.3.2.2 Water Content
2.3.2.3 Temperature
2.3.2.4 Storage of Mixture
PART 3 EXECUTION
3.1 CONVEYING AND PLACEMENT EQUIPMENT
3.1.1 Hauling Equipment
3.1.2 Pavers
3.1.3 Rollers
SECTION 32 12 16.00 28
3.2 PLACING
3.2.1 General
3.2.1.1 Asphalt Concrete Mixture
3.2.1.2 Internal Temperature
3.2.2 Joints
3.2.2.1 General
3.2.2.2 Transverse Joints
3.2.3 Tack Coat
3.3 COMPACTION
3.3.1 Uniform Compaction
3.3.2 Compaction
3.3.3 Rolling
3.3.4 Prevention of Adhesion to the Rollers
3.3.5 Compaction of Asphalt Concrete
3.4 WEATHER LIMITATIONS
3.4.1 Wet or Damp Surfaces
3.5 PROTECTION
3.6 CONTRACTOR QUALITY CONTROL
3.6.1 Surface Smoothness
3.6.2 Asphalt Temperature
3.6.3 Asphalt Cement Content and Gradation
3.6.3.1 Additional Tests
3.6.3.2 Materials for Testing
3.6.4 Core Removal for Density Determinations
3.6.5 Quality Control Laboratory
-- End of Section Table of Contents --
SECTION 32 12 16.00 28
SECTION 32 12 16.00 28
ASPHALT PAVING
PART 1 GENERAL
1.1 SCOPE OF WORK
The work covered by this SECTION shall consist of constructing an asphalt concrete pavement on a prepared surface for the Lower Granite Project Lewiston/Clarkston Bike Paths including the Naves and Chestnut parking lots and also the Little Goose project, Willow Landing site. The Contractor shall provide all necessary equipment, materials, and personnel to supply, place, and compact an asphalt concrete surface in accordance with these specifications and conforming to the lines, grades, thicknesses, and typical cross sections shown on the contract drawings.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO)
AASHTO M 320 (2003) Performance-Graded Asphalt Binder
ASTM INTERNATIONAL (ASTM)
ASTM C 117 (2004) Materials Finer than 75 Micrometer (No. 200) Sieve in Mineral Aggregates by Washing
ASTM C 131 (1996) Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine
ASTM C 136 (2004) Test Method for Sieve Analysis of Fine and Coarse Aggregates
ASTM D 4643 (2000) Determination of Water (Moisture) Content of Soil by the Microwave Oven Method
ASTM D 4959 (2000) Determination of Water (Moisture) Content of Soil by Direct Heating
ASTM D 242 (1995) Mineral Filler for Bituminous Paving Mixtures
ASTM D 979 (1996) Sampling Bituminous Paving Mixtures
ASTM D 1188 (1996; R 2002e1) Bulk Specific Gravity and Density of Compacted Bituminous Mixtures Using Paraffin-Coated Specimens
SECTION 32 12 16.00 28
ASTM D 2172 (1995) Quantitative Extraction of Bitumen from Bituminous Paving Mixtures
ASTM D 2397 (1998) Cationic Emulsified Asphalt
ASTM D 2419 (1995) Sand Equivalent Value of Soils and Fine Aggregate
ASTM E 329 (2007) Standard Specification for Agencies Engaged in the Testing and/or Inspection of Materials Used in Construction
IDAHO STATE DEPARTMENT OF TRANSPORTATION
ITD-04 (2004) Standard Specifications for Highway Construction
WASHINGTON STATE DEPARTMENT OF TRANSPORTATION (WSDOT)
WSDOT M 41-10 (2008) Standard Specifications for Road, Bridge, and Municipal Construction
1.3 TOLERANCES
1.3.1 Asphalt Cement Content
The asphalt-cement content shall not vary more than plus-or-minus 0.2 percent of the quantity required.
1.3.2 Weights of Aggregates
Batch weights of aggregates shall be computed and recorded to the nearest 10 pounds.
1.3.3 Asphalt Concrete Surface Parallel to the Roadway
Unless otherwise designed, the asphalt concrete surface parallel to the roadway centerline or to the direction of placement shall not vary more than 1/8 inch from the lower edge of a 10-foot straightedge.
1.3.4 Asphalt Concrete Surface Perpendicular to the Roadway
Unless otherwise designed, the asphalt concrete surface perpendicular to the roadway centerline or to the direction of placement shall not vary more than 1/8 inch from the lower edge of a 10-foot straightedge.
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Aggregate Source; G GT
Job Mix Formula; G GT
Nuclear Gauge
SD-06 Test Reports
Asphalt Material Testing Report Submit within one (1) day of asphalt completion at work areas.
1.5 CONTRACTOR QUALITY CONTROL
Unless otherwise stated in THIS SPECIFICATION, all test results for Contractor Quality Control performed prior to placement of asphalt concrete shall be reported and delivered to a designated representative of the Contracting Officer prior to beginning placement of the asphalt concrete.
1.5.1 Aggregate Source Approval
The Contractor shall submit all data and test reports for the aggregate source. The test reports shall have been completed within the last two (2) years and show compliance to the specifications for durability, sand equivalent and wood waste. With the test reports, the Contractor shall confirm and submit in writing the proposed source located by Section, Township and Range, pit name, owner, operator using the pit, phone number for the operator, and if the source is approved by the State's Department of Transportation, the State's identification number.
1.5.2 Nuclear Gauge Submittal
To determine the in-place density of the asphalt concrete for quality control purposes, not acceptance, the Contractor may use a nuclear gauge.
The Contractor shall submit a copy of the State license authorizing the use of a nuclear gauge and manufacturer certification that operators have completed an approved safety and gage operation training session. For each gauge to be used on site, the date of last calibration, the individual or organization performing calibration, list of calibration standards, and the calibration curve shall be submitted.
1.5.3 Job Mix Formula
The Contractor shall submit the state-approved job mix formula as specified in paragraph below. In addition, the Contractor shall submit a manufacturer's statement certifying compliance to the specifications for:
(1) Asphalt cement.
(2) Cationic emulsified asphalt, CSS-1.
(3) Antistripping additive when required.
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 Aggregates
2.1.1.1 General
Aggregate shall consist of crushed or partially crushed granular rock manufactured from ledge rock, talus or gravels.
2.1.1.2 Durability
Percentage of loss shall not exceed 40 after 500 revolutions, as determined in accordance with ASTM C 131.
2.1.1.3 Fracture Requirements
Crushed gravel retained on the No. 4 sieve and each coarser sieve shall contain at least 75 percent by weight of crushed pieces having one or more fractured faces with the area of each face equal to at least 75 percent of the smallest midsectional area of piece. When two fractures are contiguous, the angle between planes of fractures shall be at least 30 degrees to count as two fractured faces.
2.1.1.4 Sand Equivalent
Sand equivalent shall conform to the requirements of ASTM D 2419 and shall be a minimum of 45 percent. Testing for sand equivalent will not be required when the percentage of material passing the No. 200 sieve is less than 5 percent after crushing and screening.
2.1.1.5 Wood Waste
Wood waste shall not exceed 0.10 percent by weight of oven-dried, processed material retained on a 1/4-inch sieve.
2.1.1.6 Gradation
Gradation testing shall conform to the requirements of ASTM C 117 and ASTM C 136. The values given in the specification bands are acceptable percentages by weight of material passing a given sieve size.
GRADATION REQUIREMENTS
Sieve Size Gradation Limits
5/8" Sieve 100 1/2" Sieve 90-100 3/8" Sieve 75-90 1/4" Sieve 55-75 U.S. No. 10 Sieve 32-48 U.S. No. 40 Sieve 11-24 U.S. No. 80 Sieve 6-15 U.S. No. 200 Sieve 3.0-7.0 Mineral Filler 0-2
2.1.2 Mineral Filler
Mineral filler shall conform to the requirements of ASTM D 242.
2.1.3 Asphalt Cement
Asphalt cement shall meet the requirements of AASHTO M 320 and WSDOT M 41-10, Section 9-02.1(4,) or ITD-04, as applicable. The performance grade of asphalt cement used shall be as required by the Washington State Department of Transportation or the State of Idaho Transportation Department, as applicable.
2.1.4 Antistripping Additive
Antistripping additive shall be from a commercial supplier and specifically designated as an antistripping additive for asphalt cement.
2.1.5 Tack Coat
Tack coat shall be a cationic emulsified asphalt meeting the requirements of ASTM D 2397 for CSS-1. The tack coat may be a mixture of CSS-1 and water not to exceed a ratio of one to one (1:1).
2.2 COMPOSITION AND PROPORTIONS
2.2.1 Job Mix Formula
The job-mix formula shall be the responsibility of the Contractor and shall be submitted in writing to the Contracting Officer a minimum of 30 days prior to placement. Asphalt concrete placement for a specified mix shall not proceed until the job-mix formula is approved by the Contracting Officer. The submittal shall show all the calculations, proportions of materials by weight, manufacturer of asphalt cement and antistripping admixture, and the source of materials.
2.2.2 State-Approved Job Mix Formula
The Contractor shall submit a State-approved job mix formula for asphalt concrete meeting the requirements of WSDOT M 41-10, paragraph 5-04 or ITD-04, as applicable.
2.3 PRODUCTION
2.3.1 Mixing Plants
All mixing plants shall be capable of producing a uniform mixture and conform to the requirements listed in WSDOT M 41-10 or ITD-04, as applicable.
2.3.2 Materials During Production
2.3.2.1 Asphalt Cement
Asphalt cement furnished under these specifications shall not have been distilled at a temperature high enough to injure by burning or to produce flecks of carbonaceous matter, and upon arrival at the batch site, shall show no signs of separation into lighter and heavier components as determined by the Contracting Officer. At no time shall the temperature of the asphalt cement exceed 350-degrees F, nor shall the temperature exceed 300-degrees F at the time the asphalt cement is introduced to the aggregates.
2.3.2.2 Water Content
Water content of the aggregate shall be reduced by drying operations to less than 0.75 percent when tested tested in accordance to ASTM D 4959 or ASTM D 4643. For testing, the weight of the sample shall exceed 1.5 pounds.
2.3.2.3 Temperature
Temperature of the aggregates and mineral filler in the mixer shall not exceed 325-degrees F when the asphalt cement is introduced. After mixing, asphalt cement shall cover a minimum of 95 percent of the aggregate's surface area.
2.3.2.4 Storage of Mixture
In no case shall the mixture be stored more than four (4) hours after introduction of the asphalt cement to the aggregates.
PART 3 EXECUTION
3.1 CONVEYING AND PLACEMENT EQUIPMENT
3.1.1 Hauling Equipment
Trucks used for hauling plant mix shall have tight, clean, smooth metal beds. Each truck shall have a cover of canvas or other suitable material over the asphalt concrete when the air temperature is below 50-degrees F, or during periods of rain.
3.1.2 Pavers
Pavers shall be self-propelled units, provided with an activated heated screed. Only screed extensions which produce a satisfactory end result equal to the rest of the screed will be allowed. The paver shall be operated at a speed consistent with the delivery of plant mix which provides for a smooth, uniform forward travel with the least number of stops.
3.1.3 Rollers
Rollers shall be of the steel wheel, vibratory, or pneumatic-tired type, in good condition, capable of reversing without backlash, and shall be operated at speeds slow enough to avoid displacement of the mixture.
Rollers with steel-wheel drums shall be equipped with spray bars to distribute water. The number and weight of rollers shall be sufficient to compact the mixture as specified in paragraph 3.3.5 COMPACTION OF ASPHALT CONCRETE. The use of equipment which results in excessive crushing of the aggregate will not be permitted. Rollers producing pickup, washboard, uneven compaction of the surface, or other undesirable results shall be removed from the work area.
3.2 PLACING
3.2.1 General
3.2.1.1 Asphalt Concrete Mixture
The asphalt concrete mixture shall be placed on an approved surface, spread and struck off to the grade and elevation shown in the contract drawings.
Unless otherwise directed by the Contracting Officer or specified elsewhere in the contract documents, the compacted depth of any one course shall not exceed three (3) inches.
3.2.1.2 Internal Temperature
The internal temperature of the mixture shall not drop more than 20-degrees F between the hot plant and the paver and shall not be less than 185-degrees F upon achieving density requirements in accordance with paragraph 3.3.5 COMPACTION OF ASPHALT CONCRETE.
3.2.2 Joints
3.2.2.1 General
Joints between old and new pavements, between successive days' work, or joints that have become cold (less than 175-degrees F) shall be made to ensure continuous bond between the old and new sections of the course. All joints shall have the same texture, smoothness, grade, and density as required for other sections of the course. Contact surfaces shall be cleaned by brushing or shall be cut back, as directed. The surface against which new material is placed shall be sprayed with a thin, uniform tack coat. Material shall be applied far enough in advance of placement of a fresh mixture to ensure adequate curing. Care shall be taken to prevent damage or contamination of the sprayed surface. Public traffic shall not be permitted on the prepared surface after the tack coat application.
Placement of the pavement mix shall be completed within four (4) hours after application of the tack coat.
3.2.2.2 Transverse Joints
The roller shall pass over the unprotected end of a strip of freshly placed material only when placing is discontinued or delivery of the mixture is interrupted to the extent that the material in place may become cold. In all cases, prior to continuing placement, the edge of previously placed pavement shall be cut back to expose an even vertical surface for full thickness of the course.
3.2.3 Tack Coat
A tack coat shall be applied in a manner that provides full coverage of the applied surface. A minimum applied rate of 0.04 gallons per square yard of retained asphalt shall be applied. The Contracting Officer will direct the application of additional tack coat if full coverage is not observed. All costs associated with tack coating shall be incidental to the cost of asphalt concrete paving.
3.3 COMPACTION
3.3.1 Uniform Compaction
Immediately after the asphalt concrete mixture has been spread, struck off, and surface irregularities adjusted, it shall be thoroughly and uniformly compacted. The completed course shall be free from ridges, ruts, humps, depressions, objectionable marks, or irregularities and in conformance with line, grade, and cross section as shown in the contract drawings or as specified.
3.3.2 Compaction
Compaction shall take place when the mixture is in the proper condition so that no undue displacement, cracking or shoving occurs. All compaction units shall be operated at the speed, within specification limits, that will produce the required compaction. Areas inaccessible to large compaction equipment shall be compacted by mechanical or vibratory hand compactors. Any asphalt concrete that becomes loose, broken, contaminated, shows an excess or deficiency of asphalt, or is in any way defective, shall be removed and replaced at no additional cost to the Government with fresh hot mix which shall be immediately compacted to conform with the surrounding area.
3.3.3 Rolling
Unless otherwise directed by the Contracting Officer, rolling shall begin at the edge of the pavement and proceed longitudinally with the direction of laydown, working to the highest point of the pavement template with each pass overlapping one-half the roller width of the previous pass. When paving in echelon or abutting a previously placed lane, the longitudinal joint should be rolled first followed by the regular rolling procedure.
3.3.4 Prevention of Adhesion to the Rollers
To prevent adhesion of the mixture to the rollers, the wheels shall be kept properly moistened with water or water mixed with very small quantities of detergent or other approved materials. Excessive moisture shall not be left on the asphalt concrete.
3.3.5 Compaction of Asphalt Concrete
The asphalt concrete pavement shall be compacted to a density of 91.0 percent of the theoretical maximum density as determined by the Superpave Mix Design Method.
3.4 WEATHER LIMITATIONS
3.4.1 Wet or Damp Surfaces
Asphalt concrete shall not be applied to wet or damp surfaces or before any imminent storms that might damage the final results. The Contracting Officer will have the discretion as to whether the conditions are unsuitable to proceed with construction.
(1) The average surface temperature of the media to be overlayed shall be a minimum of 45-degrees F.
(2) The air temperature shall be a minimum of 50-degrees F and be expected to be maintained or rise as work proceeds.
3.5 PROTECTION
Should irregularities or contamination develop in the asphalt concrete, or in materials supporting the asphalt concrete, during or after placement until the work is accepted, the Contractor shall correct the defects to meet the requirements of this specification. Any additional materials, labor, or equipment necessary to make the repairs shall be furnished by the Contractor at no expense to the Government.
3.6 CONTRACTOR QUALITY CONTROL
3.6.1 Surface Smoothness
The Contractor shall check surface smoothness for compliance to the specifications and make available for use by the Contracting Officer a manufactured 10-foot straight edge. Surface smoothness shall be checked in the transverse and longitudinal directions at intervals not more than 50 feet.
3.6.2 Asphalt Temperature
A probe thermometer shall be used to determine the internal temperature of the asphalt concrete. A minimum of one (1) temperature reading shall be recorded for each required density check.
3.6.3 Asphalt Cement Content and Gradation
3.6.3.1 Additional Tests
In addition to tests prior to production, the asphalt concrete shall be tested for asphalt cement content and gradation each day that production takes place. Test results for asphalt concrete pavement placed at the work area shall be submitted to the Contracting Officer prior to asphalt concrete placement the following day.
3.6.3.2 Materials for Testing
The sample of materials for testing shall be taken from the roadway prior to compaction and in accordance with ASTM D 979. The asphalt concrete mix shall be tested in accordance with ASTM D 2172 to determine the asphalt cement content and in accordance with ASTM C 136 to determine the aggregate gradation. The Contractor shall submit test result for asphalt cement content and aggregate gradation as part of the Asphalt Material Testing Report.
3.6.4 Core Removal for Density Determinations
At the completion of asphalt concrete paving operations, the Contractor shall remove drilled cores not less than four (4) inches in diameter from the pavement. One (1) core shall be removed per 5,000 square feet of pavement placed. Core locations will be directed by the Contracting Officer. Density of cores shall be determined in accordance with ASTM D 1188. The Contractor shall submit the density determinations as part of the Asphalt Material Testing Report. The Contractor shall repair all core holes within four (4) hours after drilling the core. The asphalt concrete patch shall be compacted to create a uniform texture matching the surrounding asphalt concrete.
3.6.5 Quality Control Laboratory
The laboratory used for quality control testing shall be a recognized testing laboratory meeting the requirements of ASTM E 329 to test the asphalt concrete. The Contractor shall telephone all test results to the Contracting Officer on the same day as the testing was performed and submit all test reports as part of the Asphalt Material Testing Report.
-- End of Section --
SECTION TABLE OF CONTENTS
DIVISION 32 - EXTERIOR IMPROVEMENTS
SECTION 32 15 00.10 28
AGGREGATE SURFACE COURSE
PART 1 GENERAL
1.1 DWORSHAK PROJECT WORK AREAS
1.1.1 Grandad Bridge Road
1.1.2 Camp X Road
1.1.3 Breakfast Creek Road
1.1.4 Grandad Campground Road
1.2 REFERENCES
1.3 SUBMITTALS
1.3.1 Aggregate Source Approval
1.4 QUALITY ASSURANCE
1.4.1 Sampling
1.4.2 Testing
1.4.2.1 Gradation
1.4.2.2 Liquid Limit and Plasticity Index
1.5 ENVIRONMENTAL REQUIREMENTS
PART 2 PRODUCTS
2.1 AGGREGATE SURFACE COURSE
2.1.1 Coarse Aggregates
2.1.2 Fine Aggregates
2.1.3 Gradation Requirements
2.2 LIQUID LIMIT AND PLASTICITY INDEX REQUIREMENTS
PART 3 EXECUTION
3.1 COMPACTION
3.2 PREPARATION OF UNDERLYING COURSE SUBGRADE
3.3 GRADE CONTROL
3.4 MIXING AND PLACING MATERIALS
3.5 LAYER THICKNESS
3.6 SMOOTHNESS TEST
3.7 THICKNESS CONTROL
3.8 DENSITY TESTS
3.9 WEAR TEST
3.10 MAINTENANCE
-- End of Section Table of Contents --
SECTION 32 15 00.10 28
SECTION 32 15 00.10 28
AGGREGATE SURFACE COURSE
PART 1 GENERAL
The work covered by this SECTION consists of furnishing all plant, labor, equipment, and materials, and performing all necessary operations for placing aggregate surface course (gravel) at the work areas indicated.
Gravel to be placed shall be four (4) inches thick, unless otherwise specified.
1.1 DWORSHAK PROJECT WORK AREAS
1.1.1 Grandad Bridge Road
The haul distance for the gravel is approximately 64 miles one way from Orofino, Idaho.
1.1.2 Camp X Road
The haul distance for the gravel is approximately 66 miles one way from Orofino, Idaho.
1.1.3 Breakfast Creek Road
The haul distance for the gravel is approximately 68 miles one way from Orofino, Idaho.
1.1.4 Grandad Campground Road
The haul distance for the gravel is approximately 68 miles one way from Orofino, Idaho.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM C 117 (2004) Standard Test Method for Materials Finer than 75-um (No. 200) Sieve in Mineral Aggregates by Washing
ASTM C 131 (2006)Standard Test Method for Resistance to Degradation of Small-Size Coarse Aggregate…