B.08.Amendment W912EE25RA007-001_Specs.pdf
PDF 740 KB Posted
- Attached to
- Tensas Parish, LA, Point Pleasant-Yucatan, LA, Levee Enlargement and Berms, MRL Item 409-R, FC/MR&T, WBMRL
- Solicitation number
- W912EE25RA007
About this file
This document is a comprehensive specification for the Tensas Parish, Louisiana Levee Enlargement and Berms project (Solicitation Number W912EE25RA007), prepared by the U.S. Army Corps of Engineers Engineering District Vicksburg. The specifications detail multiple contract line items (CLINs) for levee construction work, including mobilization and demobilization, clearing and grubbing, erosion control, gravel surfacing, environmental protection, mowing and turfing, traverses, ramps, culverts, ditches, levee embankment, and surfacing. The work involves semicompacted and uncompacted embankment placement, with precise requirements for material placement, compaction, testing, and environmental controls.
The contract uses firm fixed pricing for job-based items, with unit pricing for earthwork quantities measured in cubic yards and ton miles. Key technical specifications cover excavation methods, borrow area management, material handling, compaction standards, and erosion control techniques. The project requires detailed submittals including excavation plans, quality control documentation, environmental protection plans, and certifications for materials like fertilizer, seed, and erosion control matting. The solicitation is restricted to specific MATOC (Multiple Award Task Order Contract) holders for Mississippi River Levee construction, limiting proposal submissions to four pre-qualified contractors: Affolter Contracting Company, B&K Construction Company, Circle LLC, and Tarpan Construction.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section 00 10 00 - Solicitation, Contract Line Item Number (CLIN) Schedule
Additional Information/Notes
Item Supplies/Service Quantity Unit Unit Price Amount
0001 MOBILIZATION AND DEMOBILIZATION
Pricing Arrangement: Firm Fixed Price
1 Job
CLEARING ANG GRUBBING
Claimant Program Code: C2 Pricing Arrangement: Firm Fixed Price
1 Job
0003 EROSION CONTROL
Pricing Arrangement: Firm Fixed Price
1 Job
0004 GRAVEL SURFACING, EXISTING
Pricing Arrangement: Firm Fixed Price
1 Job
0005 ENVIRONMENTAL PROTECTION FEATURES
Pricing Arrangement: Firm Fixed Price
1 Job
0006 MOWING AND TURFING
Pricing Arrangement: Firm Fixed Price
1 Job
0007 TRAVERSES
Pricing Arrangement: Firm Fixed Price
1 Job
0008 RAMPS
Pricing Arrangement: Firm Fixed Price
1 Job
0009 CULVERTS
Pricing Arrangement: Firm Fixed Price
1 Job
0010 DITCHES
1 Job
W912EE25RA007
MOWING, TURFING, AND EROSION CONTROL MATTING
Revised By Amendment 0001
B4EDGDML
Cross-Out
B4EDGDML
Cross-Out
B4EDGDML
Cross-Out
B4EDGDML
Cross-Out
B4EDGDML
Cross-Out
B4EDGDML
Cross-Out
B4EDGDML
Cross-Out
B4EDGDML
Cross-Out
B4EDGDML
Cross-Out
Pricing Arrangement: Firm Fixed Price
0011 LEVEE EMBANKMENT, SEMICOMPACTED
Pricing Arrangement: Firm Fixed Price
665,500 Cubic Yard
MAINTENANCE BERM EMBANKMENT,
UNCOMPACTED
Pricing Arrangement: Firm Fixed Price
6,200 Cubic Yard
0013 SEEPAGE BERM EMBANKMENT, UNCOMPACTED
Pricing Arrangement: Firm Fixed Price
299,100 Cubic Yard
0014 LEVEE SURAFCING, CRUSHED STONE
Pricing Arrangement: Firm Fixed Price
10,130 Ton Miles
W912EE25RA007
Revised By Amendment 0001
B4EDGDML
Cross-Out
B4EDGDML
Cross-Out
B4EDGDML
Cross-Out
B4EDGDML
Cross-Out
W912EE25RA007
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 80 00.00 09 SPECIAL CONTRACT REQUIREMENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00.00 09 GENERAL CONTRACT REQUIREMENTS
01 22 00.00 09 MEASUREMENT AND PAYMENT
01 32 01.00 09 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 09 QUALITY CONTROL
01 45 00.15 09 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 57 20.00 09 ENVIRONMENTAL PROTECTION
01 57 23.01 09 STORM WATER POLLUTION PREVENTION PLAN
DIVISION 31 - EARTHWORK
31 11 00.00 09 CLEARING AND GRUBBING
31 23 00.00 09 EXCAVATION
31 24 00.00 09 EMBANKMENT
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 15 00.00 09 LEVEE SURFACING
32 92 00.00 09 EXISTING TURF MAINTENANCE AND NEW TURF ESTABLISHMENT
32 92 02.00 09 EROSION CONTROL
DIVISION 33 - UTILITIES
33 42 29.01 09 CULVERTS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
32 92 04.00 09 EROSION CONTROL MATTING
Revised By Amendment 0001
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 3 PAGES
MRL Item 409-R
01 22 00.00 09 SD-01 Preconstruction Submittals
1.1.3 G ROSchedule Of Values
01 32 01.00 09 SD-01 Preconstruction Submittals
1.3 GProject Scheduler Qualifications
3.4.1 GPreliminary Project Schedule
3.4.2 GInitial Project Schedule
3.6.2 GPeriodic Schedule Update
01 35 26 SD-01 Preconstruction Submittals
1.8 GAccident Prevention Plan (APP)
SD-06 Test Reports
1.12.2 GAccident Reports
1.12.3 FIOLHE Inspection Reports
1.5 GMonthly Exposure Reports
SD-07 Certificates
1.9 GActivity Hazard Analysis (AHA)
1.12.4 FIOCertificate of Compliance
1.13 FIOHot Work Permit
FIOLicense Certificates
GPortable Gauge Operations
Planning Worksheet
GRadiography Operation Planning
Work Sheet
1.12.4 GStandard Lift Plan
01 45 00.00 09 SD-01 Preconstruction Submittals
1.4.2 GContractor Quality Control (CQC)
Plan
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
Revised By Amendment 0001
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 3 PAGES
01 45 00.00 09 SD-06 Test Reports
1.11.3 FIOVerification Statement
01 57 20.00 09 SD-01 Preconstruction Submittals
1.3.1 G GAEnvironmental Protection Plan
01 57 23.01 09 SD-07 Certificates
2.2.2 FIOFilter Fabric
31 23 00.00 09 SD-01 Preconstruction Submittals
3.2.2.1 GExcavation Plan
31 24 00.00 09 SD-06 Test Reports
3.4.1 GQC Test Report
32 15 00.00 09 SD-06 Test Reports
3.6 FIOMaterial Testing
2.1.4 FIOEvaluation Tests
SD-07 Certificates
2.1.1 FIOCrushed Stone
2.1.4 FIOLaboratory
32 92 00.00 09 SD-03 Product Data
2.5.1 GBermuda Grass Cultivar
SD-06 Test Reports
3.2.2 FIOSoil Testing
SD-07 Certificates
2.1 FIOFertilizer
2.3 FIOLime
2.5.2 FIOBermuda grass sprigs
2.5.3 FIOBermuda grass seed
32 92 04.00 09 SD-03 Product Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 3 PAGES
32 92 04.00 09 2.1.1 FIOErosion Control Matting
SD-07 Certificates
2.1.1 FIOErosion Control Matting
33 42 29.01 09 SD-07 Certificates
2.1.1 FIOCorrugated Metal Pipe
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 09
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 JOB PAYMENT ITEMS
1.1.1 General
1.1.2 Job Items
1.1.3 Schedule of Values
1.2 UNIT PRICE PAYMENT ITEMS
1.2.1 General
1.2.2 Unit Price Items
1.3 SUBMITTALS
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section Table of Contents --
SECTION 01 22 00.00 09 Page 1
SECTION 01 22 00.00 09
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 JOB PAYMENT ITEMS
1.1.1 General
Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, shall be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, submittal procedures, storm water pollution prevention, environmental protection, meeting safety requirements, tests and reports, providing as-built drawings, for using the Government-furnished software (RMS) and providing all labor and equipment necessary for electronic exchange of information and management of the contract as specified in Section 01 45 00.15 09 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM), and for performing all work required for which separate payment is not otherwise provided.
1.1.2 Job Items
a. "Mobilization and Demobilization"
(1) Payment will be made for all costs associated with mobilization and demobilization, as defined in Section 00 80 00.00 09 SPECIAL CONTRACT REQUIREMENTS, paragraph PAYMENT
FOR MOBILIZATION AND DEMOBILIZATION.
(2) Unit of measure: job.
b. "Clearing and Grubbing"
(1) Payment will be made for all costs associated with clearing and grubbing (including vegetation removal) of the areas as specified herein or indicated on the drawings, removing and disposing of all cleared and grubbed materials, filling holes resulting from clearing and grubbing operations, placing embankment to replace earthen materials removed as a result of clearing and grubbing operations, and all work incidental thereto.
(2) Unit of measure: job.
c. "Erosion Control"
(1) Payment will be made for all costs associated with performing erosion control, including grading and dressing, fertilizing, disking and harrowing, seeding, compacting, mulching, and all work incidental thereto.
SECTION 01 22 00.00 09 Page 2
(2) Unit of measure: job.
dc. "Gravel Surfacing, Existing"
(1) Payment will be made for all costs associated with salvaging, stockpiling, hauling, placing, spreading, compacting, and dressing the existing gravel surfacing as required, and all work incidental thereto.
(2) Unit of measure: job.
ed. "Environmental Protection Features"
(1) Payment will be made for all costs associated with furnishing, installing, and maintaining all temporary environmental protection features including silt fencing, straw bales hay wattles , diversion dikes, temporary grassing, construction entrance and exit, and other measures as necessary for compliance with all associated specifications, control plans and permits, and all work incidental thereto. Maintenance of these features includes, but is not limited to, removal of silt and contaminates, grading, repairs to silt fencing and other features, reseeding of temporary cover, and replacement of silt fencing, straw bales hay wattles, and other features when necessary due to damage, storm events, contractor activities, or deterioration of silt fence fabric, straw bales hay wattles , or other temporary materials.
(2) For progress payment purposes, payment for this lump sum item will occur in accordance with the following breakdown:
(a) A maximum of 50% of this bid item amount will be paid for work associated with the initial installation of all temporary environmental protection features identified on the contract documents, permits, and submitted plans. This includes, but is not limited to, silt fencing, straw bales hay wattles , diversion dikes, and construction entrance/exit.
(b) A minimum of 50% of this bid item amount is reserved for payment for work associated with the maintenance, repairs, and necessary improvements to temporary environmental protection features throughout the life of the contract. Payment for this work will be made in three (3) incremental, partial payments at 50% complete, 75% complete, and 100% complete, based on overall contract completion status. Completion status shall be calculated by comparing contract earnings less stored materials, to the current contract amount at the time of payment.
(3) Unit of measure: job.
f e. " Mowing and Turfing Mowing, Turfing, and Erosion Control Matting "
(1) Payment will be made for all costs associated with establishment and maintenance of new turf; providing erosion control matting on levee ramps; maintenance of existing turf, which includes mowing of undisturbed levee and berm embankment surfaces and all other existing turf within the rights-of-way during the life of the contract; and all work incidental thereto.
After seeding and mulching is completed, the Contractor may
SECTION 01 22 00.00 09 Page 3 request partial payment only. Material certification and invoices must be provided to authorize the initial 60% payment when seeding is completed and 100% when turf is established and finally accepted in accordance with paragraph ESTABLISHMENT Section
32 92 00.00 09 EXISTING TURF MAINTENANCE AND NEW TURF
ESTABLISHMENT, paragraph ESTABLISHMENT .
(3) Unit of measure: job.
gf . "Traverses"
(1) Payment will be made for all costs associated with constructing the traverses from the levee to the riverside construction borrow area including excavating, hauling, placing, compaction, dressing the material, removing material, furnishing and installing corrugated metal pipes, performing moisture control and field density testing; and all work incidental thereto.
(2) Unit of measure: job.
hg. "Ramps"
(1) Payment will be made for all costs associated with constructing the levee ramps (not includibng crushed stone surfacing); including performing foundation preparation;
excavating, hauling, placing, compacting and dressing the material; determining optimum moisture and maximum dry density;
performing moisture control and field density testing; and all work incidental thereto.
(2) Unit of measure: job.
i h. "Culverts"
(1) Payment will be made for all costs associated with installation of the culverts as indicated on the drawings including furnishing and installing the corrugated metal pipes, excavation the pipe trench, hauling, placing, and compacting backfill and the area fill, determining optimum moisture and maximum density, performing moisture control and field density testing, control of water and all work incidental thereto.
(2) Unit of measure: job.
j i . "Ditches"
(1) Payment will be made for all costs associated with constructing the ditches, including excavating and disposal of excavated material, and all work incidental therrto.
(2) Unit of measure: job.
1.1.3 Schedule of Values
Submit a list of pay activities, (Schedule of Values) to breakdown bid for each job CLIN. The Schedule of Values shall be submitted for Government approval with the baseline schedule submittal (see Section 01 32 01.00 09 PROJECT SCHEDULE). An unbalanced Schedule of Values and Pay Activity Schedule will be returned for revision. If this contract contains either
SECTION 01 22 00.00 09 Page 4 the Continuing Contracts clause or the Continuing Contracts (Alternate) clause, the Contractor should take into account the amount reserved for contract payments when preparing the construction schedule.
1.2 UNIT PRICE PAYMENT ITEMS
1.2.1 General
Payment items for the work of this contract on which unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, submittal procedures, storm water pollution prevention, environmental protection, meeting safety requirements, tests and reports, providing as-built drawings, for using the Government-furnished software (RMS) and providing all labor and equipment necessary for electronic exchange of information and management of the contract as specified in Section 01 45 00.15 09 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM), and for performing all work required for each of the unit price items.
1.2.2 Unit Price Items
a. "Levee Embankment, Semicompacted, and Seepage Berm Embankment, Uncompacted," and "Maintenance Berm Embankment, Uncompated"
(1) Payment will be made at the applicable contract unit price for all costs associated with constructing the semicompacted material placed as required in levee embankment including additional semicompacted levee material placed by reason of foundation settlement and including additional semicompacted levee placed by reason of soft material in the foundation being forced outward from the section during construction; and the uncompacted material placed as required in uncompacted berm embankment including additional uncompacted berm embankment material placed by reason of soft material in the foundation being forced outward from the section during construction. That price and payment shall constitute full compensation for performing foundation preparation; excavating, hauling, placing, compacting and dressing the material; determining optimum moisture and maximum dry density; performing moisture control and field density testing;
and all work incidental thereto. No separate measurement or payment will be made for placing embankment to replace material removed as a result of removal of existing gravel surfacing, and all costs therefor shall be included in the contract unit price for "Levee Embankment, Semicompacted". No separate payment will be made for grading, land leveling, and dressing of the excavated portion of the borrow area to the required tolerance and slope.
Three (3%) of the final quantity of the embankment material under this bid items will be retained by the Government until final dressing of the borrow area is satisfactorily completed.
(1a) If the Contractor elects to use settlement gages as specified in Section 31 24 00.00 09 EMBANKMENT, paragraph SETTLEMENT GAGES, the cost of furnishing, installing and maintaining the gages during embankment constructionk including measurements required to be made by the Contractor, shall be at the expense of the Contractor. No separate payment will be made for additional effort required for compaction of fill around and
SECTION 01 22 00.00 09 Page 5 over the settlement gages or for interference with the Contractor's operations resulting from the settlement gage installations.
(1b) If the Contractor elects to use settlement gages, failure to utilize settlement gages in strict accordance with the specifiactions and drawings will result in a total forfeiture of any payment which may otherwise be due the Contractor for settlement of foundation. In each case of (1) failure to recover any settlement gage, (2) construction of embankment over a settlement gage in excess of required construction lines plus the tolerance permitted in Section 31 24 00.00 09 EMBANKMENT, paragraph GRADE TOLERANCE, or (3) failure to comply with the 72 hour requirement for determining gage elevations as specified in Section 31 24 00.00 09 EMBANKMENT, paragraph SETTLEMENT GAGES, payment will be totally forfeited for the reach attributable to each gage so affected.
(1c) No separate payment will be made for additional berm material placed by reason of foundation settlement.
(1d) Payment for material in ramps will be included in the contract jpb price for "Ramps".
(1e) Surveys will be available upon request.
(2) Unless otherwise specified, semicompacted fill and uncompacted fill, as specified in Section 31 24 00.00 09 EMBANKMENT (including the material placed in ramps), including fill placed by reason of soft material in the foundation being forced outward from the section during construction will be measured for payment by the cubic yard. The basis for the measurement will be original surveys of the areas to be filled taken by the Government prior to CONTRACT AWARD, clearing, grubbing and vegetation removal operations, and prior to removal of existing gravel surfacing operations, and the theoretical gross cross section of the completed levee constructed within the specified tolerance. Quantities will be computed by the Government using the surface to surface method. There will be no separate measurement and payment for tolerances.
(2a) The basis for measurement of fill which replaces soft material in the foundation of the berms which is forced outward from the section will be a survey of the area outside the berm toe taken prior to the filling operations and a second survey of the same area after completion of the filling operations.
(2b) If the Contractor elects to use settlement gages, measurement of additional levee embankment fill material placed in each settlement measurement range by reason of foundation settlement, will be based on measurements on the respective settlement gage installed as specified in Section 31 24 00.00 09 EMBANKMENT, paragraph SETTLEMENT OF FOUNDATION and will be determined as follows:
(i) The settlement measured at each settlement gage will be considered to apply to the foundation area throughout the length of the settlement ranges specified herein in which the gage is located. No measurement for payment for settlement will be made in
SECTION 01 22 00.00 09 Page 6 the event that embankment over a settlement gage is constructed to a height in excess of specified gross construction grade plus the tolerance permitted under Section 31 24 00.00 09 EMBANKMENT, paragraph GRADE TOLERANCES. In instances where settlement plates have been set and cannot be found after completion of the embankment, no payment for settlement will be made for the reach of the plate.
(ii) The foundation settlement under the embankment at each transverse cross section within a settlement range will be considered to vary uniformly between break points in the cross section. At each breakpoint, the settlement allowance will be based upon the proportion that the specified fill height at the break point bears to the specified fill height at the settlement gage, in accordance with the following formula: S = (h X sm) / hm, where S is settlement to be computed at a break point; h is specified gross fill height at S; sm is measured for adjusted settlement at settlement gage; and, hm is specified gross fill height above settlement gage. Except as provided above and in Section 31 24 00.00 09 EMBANKMENT, paragraph SUDDEN FAILURE, no measurement for payment for additional fill material placed by reason of foundation settlement will be made.
(3) Unit of measure: cubic yard.
b. "Levee Surfacing, Crushed Stone"
(1) Payment will be made at the contract unit price for all costs associtated with constructing the new crushed stone levee and ramp surfacing, which price and payment shall constitute full compensation for blading and shaping levee crown and ramps;
furnishing, hauling, placing, spreading, performing moisture control, compacting and dressing the finished surfacing;
performing all required testing; furnishing scales and weighing for measurement; and all work incidental thereto.
(2) Crushed stone surfacing material for levee crown and ramps shall be measured for payment by being weighed by the Contractor on approved scales before being placed into the work. Each truck load shall be weighed to the nearest 0.1 ton and the final quantity rounded to the nearest whole ton. The Contractor shall furnish the scales and shall weigh the surfacing material in the presence of the Government representative, who will certify to the correctness thereof. Scales shall be of sufficient length to permit simultaneous weighing of all axle loads and shall be inspected, tested and sealed as directed by the Contracting Officer to assure an accuracy within 0.5 percent throughout the range of the scales. The scale's accuracy shall be checked and certified by an acceptable scales company representative prior to weighing any surfacing material and rechecked and recertified whenever a variance is suspected. The scales shall be located at the site of work. If commerical scales are readily available in close proximity (within 40 miles) of site of work, the Contracting Officer may approve the use of the scales. The Contracting Officer may elect to accept certified weight certificates furnished by a public weigh master in lieu of scales weights at the jobsite. Quarry weights will not be accepted. In any event, the Contractor shall not dump any load until it has been inspected and accepted by an authorized Government representative. If a load
SECTION 01 22 00.00 09 Page 7 is dumped without this inspection and measurement, the Contractor shall reload the material as directed by the Government representative and remove it from the jobsite until proper inspection and measurement can be made at not additional cost to the Government. The Contractor shall not allow the accumulation of material deposits in the trailer, i.e., lodged dirt, mud, gravel or stone.
(3) Unit of measure: ton.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Schedule Of Values; G, RO
Provide a breakdown of lump sum items into proposed pay activities as part of the initial project schedule. Schedule of Values will become basis for CLIN and Pay Activity data in the RMS-CM payment.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section --
SECTION 01 22 00.00 09 Page 8
DIVISION 31 - EARTHWORK
SECTION 31 23 00.00 09
EXCAVATION
PART 1 GENERAL
1.1 SUBMITTALS
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 HAUL ROADS
3.2 EXCAVATION IN BORROW AREAS
3.2.1 General
3.2.1.1 Equipment
3.2.2 Borrow Areas
3.2.2.1 Requirements
3.2.2.2 Riverside Borrow Area Locations
3.3 DISPOSITION OF MATERIALS
3.3.1 Suitable Materials
3.3.2 Unsuitable Materials
3.3.3 Temporary Stockpiles
3.4 EXCAVATION IN OTHER AREAS
3.4.1 General
3.4.2 Drainage Ditches
3.4.2.1 Excavation
3.4.3 Acceptance
3.5 DEGRADING EXISTING LEVEES
3.5.1 Embankments Not to be Disturbed
3.5.2 Unauthorized Excavation of Existing Levee or Berm
3.6 TRAVERSES
-- End of Section Table of Contents --
SECTION 31 23 00.00 09 Page 1
SECTION 31 23 00.00 09
EXCAVATION
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Excavation Plan; G
The Contractor shall prepare and submit a detailed plan for borrow area excavation for accceptance prior to beginning excavation.
The plan shall include the Contractor's proposed haul road location/s from borrow area and for embankment operations. The location of the haul roads will require review and approval of the Contracting Officer, prior to commencing work. Refer to paragraph BORROW AREAS within this Section for additional details.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 HAUL ROADS
Haul roads between borrow areas and fill areas shall meet the minimum requirements specified herein. At no additional cost to the Government, the Contractor shall increase the minimum specified requirements as necessary, due to job site conditions, to assure safe operations.
Whenever practical, one-way haul roads shall be used. Haul roads used for this work shall comply with the following:
(a) One-way haul roads for off-the-road haulage equipment; (e.g., belly dumps, scrapers, and off-the-road trucks) shall have a minimum usable width of 25 feet. One-way haul roads for over-the-road haulage equipment (e.g., dump trucks, etc.) shall have a minimum usable width of 15 feet.
When it is impractical to obtain the specified minimum widths for one-way haul roads (e.g., a road on top of a levee), a usable width of not less than 10 feet may be approved, provided a positive means of traffic control is implemented. Such positive means shall include signs, signals, or signalmen and an effective means of speed control.
(b) Two-way haul roads for off-the-road haulage equipment shall have a minimum usable width of 60 feet. Two-way haul roads for over-the-road haulage equipment shall have a minimum usable width of 30 feet.
SECTION 31 23 00.00 09 Page 2
(c) Haul roads shall be maintained to keep the surface free from potholes, ruts and similar conditions that could result in unsafe conditions. Haul roads shall be maintained free of all construction related debris, including loose riprap.
(d) Curves and changes in grade shall allow a minimum sight distance of 200 feet for one-way haul roads and 300 feet for two-way haul roads. Sight distance is defined as the centerline distance an equipment operator (4.5 feet above the road surface) can see an object
4.5 feet above the road surface. When conditions make it impractical to obtain the required minimum sight distances (e.g., ramps over levees), a positive means of traffic control shall be implemented.
(e) Dust abatement shall permit observation of objects on the roadway at a minimum distance of 300 feet.
(f) Haul roads shall have the edges of the usable portion marked with posts at intervals not greater than 50 feet on curves and not greater than 200 feet elsewhere. Such markers shall extend 6 feet above the road surface, and for nighttime haulage shall be provided with reflectors in both directions.
(g) Haul roads shall not block or impede drainage in or through the right-of-way. The Contractor is responsible for any damages resulting from haul roads blocking or impeding drainage. (See the Contract Clause PERMITS AND RESPONSIBILITIES.)
3.2 EXCAVATION IN BORROW AREAS
3.2.1 General
The rights-of-way and earth materials for constructing the work will be furnished without cost to the Contractor, at locations specified herein and shown on the drawings. Notwithstanding any other provision of this contract, the Contractor is required to obtain all borrow material from the Government furnished borrow areas, ditches and other required excavations. Contractor furnished borrow areas will not be permitted.
3.2.1.1 Equipment
The Contractor shall provide the types of equipment as necessary to perform the required excavation according to the in situ conditions of the borrow area.
3.2.2 Borrow Areas
3.2.2.1 Requirements
Borrow areas shall conform to requirements prescribed herein and as shown on the drawings. The material necessary for the construction of the embankments shall be procured from borrow areas and required excavations by haulage or otherwise. The permissible excavation depths in the borrow areas are indicated on the drawings, but the right is reserved, in accordance with the Contract Clause CHANGES, to modify the permissible depths in accordance with subsurface conditions determined as the work proceeds. Excavation to the permissible depths may require excavation below the ground water table. The bottom of the borrow areas excavated under this contract shall be dressed to the extent necessary to provide a reasonably smooth surface that can readily be traversed by a 50 to
SECTION 31 23 00.00 09 Page 3
60-horsepower farm tractor pulling a rotary-type pasture mower and sloped to provide surface drainage to the low side of the borrow area as soon as all usable materials have been removed or the Contractor has completed the use of the borrow area. Abrupt changes in grade shall be avoided.
Unsuitable material wasted in the borrow areas shall be sloped to drain.
Any excavation below the depths and slopes specified herein or shown on the drawings shall be backfilled by the Contractor, at no cost to the Government, to the specified permissible excavation line, with suitable material placed and compacted in accordance with Section 31 24 00.00 09 EMBANKMENT, paragraph SEMICOMPACTED EMBANKMENT. The borrow areas excavated under this contract shall be drained of water regardless of its source, including subsurface water, and kept free of water during excavation, as excavation will not be permitted in water nor shall excavated material be scraped, dragged or otherwise moved through water.
Drainage of borrow areas shall be accomplished by ditching, sump pumping or other approved methods. The borrow areas excavated under this contract and inundated from high river stages shall be drained and allowed to dry to a workable condition as quickly as practicable after the high river stage has passed. No additional payment will be made for keeping the borrow areas drained and free of water during excavation. The contractor shall not use rights-of-way for drainage of the borrow areas other than those rights-of-way furnished by the government. Except as required by variable right-of-way widths, abrupt changes in borrow area alignment shall be avoided. To conserve arable land and make optimum use of available borrow, the excavation of the borrow areas shall be made continuous throughout the length of the borrow areas to the permissible borrow depths, and at the width necessary to provide the required quantity of suitable material, and in such manner that all suitable available material within the required width between the leveeward limits of the borrow areas and the back of the borrow areas will be utilized. The Contractor shall submit an excavation plan for approval by the Contracting Officer and shall not begin excavation until the Contracting Officer's approval has been received. The plan shall contain, as a minimum, the following:
a. The Contractor's proposals for implementing Section 01 57 20.00 09 ENVIRONMENTAL PROTECTION insofar as that section applies to borrow areas.
b. The Contractor's proposed methods for draining and keeping the borrow areas free of water during excavation under this contract.
c. The Contractor's proposed methods for draining borrow areas excavated under this contract which may be inundated by high river stages.
d. A statement indicating whether the Contractor proposes to use:
(1) Government-furnished rights-of-way for drainage;
(2) Contractor-furnished rights-of-way for drainage; or
(3) A combination of Government-furnished and Contractor-furnished rights-of-way for drainage.
e. For Contractor-furnished rights-of-way for drainage, the plan shall contain all of the information required by paragraph REQUIREMENTS and the Contractor's proposals for implementing Section 01 57 20.00 09 ENVIRONMENTAL PROTECTION, insofar as that section
SECTION 31 23 00.00 09 Page 4 applies to rights-of-way for drainage.
f. The Contractor's proposals for conserving arable land and for making optimum use of available borrow, including the Contractor's proposed methods for smoothing the bottom of the borrow areas after having completed use of the borrow areas.
g. Drainage
h. The Contractor's proposal of haul road locations under this contract.
i. The Contractor's proposal of materials placement locations under this contract.
3.2.2.2 Riverside Borrow Area Locations
Riverside borrow areas shall be located as shown on the drawings.
3.3 DISPOSITION OF MATERIALS
3.3.1 Suitable Materials
Excavated materials which are suitable for incorporation in the levee embankment, and berm embankment, or other required fill or backfill, shall either be placed directly therein, or stockpiled and subsequently used in the levee embankment and berm embankment or other required fill or backfill.
3.3.2 Unsuitable Materials
Materials from required excavation which, as defined in Section 31 24 00.00 09 EMBANKMENT, paragraph UNSUITABLE MATERIALS, are unsuitable for levee embankment, and berm embankment or other required fill or backfill material will be ordered wasted and shall be disposed of in abandoned portions of borrow areas. This unsuitable material shall be shaped so that its surface is free from abrupt changes in grade and shall be sloped to drain. Where possible, unsuitable materials in borrow areas shall not be removed.
3.3.3 Temporary Stockpiles
No material shall be stockpiled on the existing levee or berm. Temporary stockpile areas shall be approved by the Contracting Officer before being used.
3.4 EXCAVATION IN OTHER AREAS
3.4.1 General
Excavation from other areas shall consist of removal of material in preparing the levee embankment and berm embankment foundations to the lines and grades shown on the drawings, removal of materials from ditches , and removal of unsuitable materials as defined in Section 31 24 00.00 09 EMBANKMENT, paragraph UNSUITABLE MATERIALS. Whenever unsuitable foundation material is encountered, the unsuitable material shall be removed to the depth directed by the Contracting Officer. Care shall be exercised by the Contractor in excavating to the lines and grades shown and in removing unsuitable materials so as not to excavate below the
SECTION 31 23 00.00 09 Page 5 grades specified or depth directed. Excavation below the lines and grades specified or the depth directed shall be backfilled by the Contractor at no cost to the Government. Such backfill shall be brought to grade with suitable material with each layer placed and compacted as specified in Section 31 24 00.00 09 EMBANKMENT, paragraph SEMICOMPACTED EMBANKMENT .
Excavated materials shall be disposed of as specified in paragraph
DISPOSITION OF MATERIALS.
3.4.2 Drainage Ditches
3.4.2.1 Excavation
Drainage ditches shall be excavated to the cross sections, lines, and grades shown on the drawings. Suitable material excavated from these ditches shall be used in the embankment(s). Any excess material or material unsuitable for use in the embankment and berm embankment shall be wasted and disposed of in excavated portions of the borrow area. In addition to the drainage ditch shown in plans, the right is reserved to require such other ditching as is deemed desirable and which can be performed without unreasonable difficulty by the equipment on the job.
Suitable material excavated from such ditching may, at the option of the Contractor, be used in the embankment. Material not so used shall be wasted in the borrow area. No separate payment will be made for this work.
3.4.3 Acceptance
Prior to the acceptance of the work, the Contractor shall excavate sediments from ditches as necessary to restore them to grade and section. Disposal of such material shall be as directed by the Contracting Officer. No separate payment will be made for this work.
3.5 DEGRADING EXISTING LEVEES
3.5.1 Embankments Not to be Disturbed
Existing levees, parts of levees, sublevees, spurs, or other embankments shall not be disturbed .
3.5.2 Unauthorized Excavation of Existing Levee or Berm
Excavation of any portion of the existing levee or berm without written authorization by the Contracting Officer is expressly prohibited. Should such unauthorized excavation occur, the Contractor will be required to cease construction operations and to restore the levee or berm to its original grade and section before further construction operations will be permitted. The restoration shall be made with suitable levee embankment material, placed and compacted as provided in Section 31 24 00.00 09 EMBANKMENT, paragraph SEMICOMPACTED EMBANKMENT, and by and at the expense of the Contractor.
3.6 TRAVERSES
The Contractor shall construct traverses as necessary for his operations.
The Contractor shall remove, and return the site to its pre-construction condition, all traverses and haul roads after completing his use of the borrow area. The Contractor shall construct traverses as necessary for his operations. The Contractor shall remove, and return the site to its pre-construction condition, unless noted otherwise on the plans, all traverses and haul roads after completing his use of the borrow area.
SECTION 31 23 00.00 09 Page 6
-- End of Section --
SECTION 31 23 00.00 09 Page 7
DIVISION 32 - EXTERIOR IMPROVEMENTS
-- End of Section Table of Contents --
SECTION 32 92 02.00 09 Page 1 Deleted By Amendment 0001
SECTION 32 92 02.00 09
EROSION CONTROL
PART 1 GENERAL
1.2 SUBMITTALS
Government approval is required for all submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Fertilizer
The Contractor shall submit signed copies of invoices from suppliers which show quantities and the percentages of nitrogen, phosphorous, and potash.
1.3 AREAS TO RECEIVE EROSION CONTROL
All disturbed areas within the contract rights-of-way, except areas to receive other types of surfacing, shall receive erosion control as specified herein.
PART 2 PRODUCTS
2.1 FERTILIZER
Fertilizer shall meet the requirements of the State of Louisiana for commercial fertilizer. Fertilizer shall have a minimum analysis of 13 percent nitrogen, 13 percent phosphorus, and 13 percent potash (13-13-13). Duplicate signed copies of invoices from suppliers shall be furnished to the Contracting Officer upon delivery to the worksite.
Invoices shall show quantities and percentages of nitrogen, phosphorus, and potash.
2.2 SEED
Grass seeds shall be labeled in accordance with the U.S. Department of Agriculture Rules and Regulations under the Federal Seed Act in effect on the date of purchase. The seed shall have a minimum purity of 90 percent and a minimum germination rate of 80 percent. Seeding mixtures shall be in accordance with the following:
2.2.1 Alternative A
If seeding is done during the period of 1 March through 30 September, the seeding mixture shall consist of a uniform mixture of 20 pounds of Bahia and 20 pounds of Bermuda Grass (hulled) seed per acre.
SECTION 32 92 02.00 09 Page 2
2.2.2 Alternative B
If seeding is done during the period of 1 October through 28 February, the seeding mixture shall consist of a uniform mixture of 50 pounds of Rye grass seed and 35 pounds of Bermuda Grass (unhulled) seed per acre.
2.3 MULCH
The mulch shall be a vegetative mulch consisting of grain straw (oats, wheat, or rice) or grass hay.
PART 3 EXECUTION
3.1 EROSION CONTROL
3.1.1 Grading and Dressing
The areas to receive erosion control shall be graded and dressed by the cutting off of high points and the filling of depressions to the extent necessary to provide a reasonably smooth surface that can be readily traveled by a farm tractor pulling a rotary type mower.
3.1.2 Application
After grading and dressing, the areas to receive erosion control shall be fertilized and seeded. Fertilizer shall be uniformly distributed at a rate of 250 pounds per acre over areas to be seeded and shall be incorporated into the soil to a depth of approximately 4 inches by disking, harrowing, or other acceptable methods. After dressing has been completed and fertilizer incorporated, surfaces shall be seeded by uniformly distributing the applicable mixture of grass seed specified in paragraph SEED per each acre. After the seed has been distributed, the entire finished surface shall be compacted by two passes of a conventional tractor-drawn cultipacker.
3.2 MULCHING
Mulching shall be performed within 24 hours after seeding. Mulch shall be applied uniformly on the soil surface at the rate of 1-1/2 tons (approximately 60 bales) per acre. The mulch shall be anchored into the soil with a mulch crimper. The mulch crimping equipment shall have straight, notched, dull blades no more than 10 inches apart and shall be equipped with scrapers. The mulching material shall be anchored at least 1 inch into the soil. Anchoring the mulch shall be performed along the contour of the ground surface. The mulch shall be applied by means of approved equipment suitable for such work.
-- End of Section --
SECTION 32 92 02.00 09 Page 3
DIVISION 32 - EXTERIOR IMPROVEMENTS
SECTION 32 92 04.00 09
EROSION CONTROL MATTING
PART 1 GENERAL
1.1 GENERAL DESCRIPTION
1.2 SUBMITTALS
PART 2 PRODUCTS
2.1 EROSION CONTROL MATTING MATERIALS
2.1.1 General
2.1.2 Anchor Pins or Staples
PART 3 EXECUTION
3.1 EROSION CONTROL MATTING
-- End of Section Table of Contents --
SECTION 32 92 04.00 09 Page 1 Added By Amendment 0001
SECTION 32 92 04.00 09
EROSION CONTROL MATTING
PART 1 GENERAL
1.1 GENERAL DESCRIPTION
Erosion control matting shall be provided as a ditch liner at levee ramps as specified herein. All costs associated with providing erosion control matting and all work incidental thereto shall be included in the contract lump sum price for "Mowing, Turfing, and Erosion Control Matting".
1.2 SUBMITTALS
Government approval is required for all submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Erosion Control Matting
The Contractor shall submit signed copies of invoices from suppliers which show quantities and identify the material and manufacturer.
SD-07 Certificates
Erosion Control Matting
Certificates of compliance attesting that the erosion control matting meets specification requirements shall be submitted to the Contracting Officer.
PART 2 PRODUCTS
2.1 EROSION CONTROL MATTING MATERIALS
2.1.1 General
The erosion control matting shall be a nominal 3/8-inch thick blanket of excelsior, wheat straw or other natural fiber bonded to a photo degradable mesh. The mats shall be rated by the manufacturer for use in vegetated channels having flow velocities of up to 5 feet per second.
2.1.2 Anchor Pins or Staples
Anchor pins or staples for erosion control matting shall be as recommended by the manufacturer.
SECTION 32 92 04.00 09 Page 2
PART 3 EXECUTION
3.1 EROSION CONTROL MATTING
The erosion control matting at levee ramps shall be installed along the full length of each ramp in a single 5 feet width centered in the shallow ditch required at the intersection of the ramp surface and the levee slope. In accordance with Section 32 92 00.00 09 EXISTING TURF MAINTENANCE AND NEW TURF ESTABLISHMENT, the areas to be covered shall be restored, prepared, fertilized, and seeded or sprigged. The matting shall be installed not more than 24 hours after completion of the required turfing operations. The matting shall be installed by unrolling it in the direction of water flow and draping it loosely, without folds or stretching, so that continuous ground contact is maintained. The mulch material shall be omitted from areas receiving erosion control matting.
The end of the material at the beginning and ending of each area to be covered shall be folded and placed in a vertical anchor trench at least six inches deep, and pinned or stapled into the trench on six inch centers, backfilled with suitable embankment material, and tamped to at least the density of the surrounding embankment. On the upgrade end, reinforce with a row of pins or staples on 6 inch centers about one foot below the anchor trench. Laps shall be avoided, but where two or more lengths are necessary to cover the ramp ditch, the ends shall overlap at least 6 inches with the upgrade section on top. Erosion control matting shall be anchored with pins or staples placed approximately 6 feet apart along each side of the matting, and with one row along the center placed at 6 feet intervals between the side pins. At overlap ends, pins shall be placed in a row with 6 inch spacing.
-- End of Section --
SECTION 32 92 04.00 09 Page 3
DIVISION 33 - UTILITIES
SECTION 33 42 29.01 09
CULVERTS
PART 1 GENERAL
1.1 REFERENCES
1.2 GENERAL
1.3 SUBMITTALS
1.4 REGULATORY REQUIREMENTS
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 Corrugated Metal Pipe
2.1.1.1 Pipe Ends
2.1.1.2 Lifting Lugs
2.1.1.3 Pipe Gage
2.1.1.4 Pipe Lengths
2.2 CULVERTS
2.2.1 Connecting Bands
2.2.1.1 Pipe All Sizes
2.2.1.2 Pipe 30 Inches In Diameter or Less
2.2.1.3 Tank Rods
2.2.1.4 Bands
2.3 TEST REPORTS AND BILLS OF LADING
PART 3 EXECUTION
3.1 INSTALLATION
3.1.1 Delivery and Handling of Pipe
3.1.2 Connecting Bands Gasket
3.1.3 Touch-up
3.2 PIPE TRENCH EXCAVATION
3.2.1 General
3.2.2 Disposition of Materials
3.2.2.1 Suitable Materials
3.2.2.2 Unsuitable Materials
3.3 PLACING OF PIPES
3.4 BACKFILL FOR PIPES
3.4.1 General
3.4.2 Compaction
-- End of Section Table of Contents --
SECTION 33 42 29.01 09 Page 1
SECTION 33 42 29.01 09
CULVERTS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
AMERICAN WELDING SOCIETY (AWS)
AWS D1.1/D1.1M (2015; Errata 1 2015; Errata 2 2016) Structural Welding Code - Steel
ASTM INTERNATIONAL (ASTM)
ASTM A123/A123M (2017) Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products
ASTM A762/A762M (20015) Standard Specification for Corrugated Steel Pipe, Polymer Precoated for Sewers and Drains
ASTM A780/A780M (2009; R 2015) Standard Practice for Repair of Damaged and Uncoated Areas of Hot-Dip Galvanized Coatings
ASTM D1056 (2014) Standard Specification for Flexible Cellular Materials - Sponge or Expanded Rubber
ASTM D6938 (2017a) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)
ASTM D698 (2012; E 2014; E 2015) Laboratory Compaction Characteristics of Soil Using Standard Effort (12,400 ft-lbf/cu. ft.
(600 kN-m/cu. m.))
1.2 GENERAL
The Contractor shall verify all measurements and shall take all field measurements necessary before fabrication. Welding to or on corrugated metal pipe shall be in accordance with the applicable provisions of AWS D1.1/D1.1M , except that the limitations on types of base metal shall not apply where other types are specified or shown.
1.3 SUBMITTALS
Government approval is required for all submittals with a "G" designation;
SECTION 33 42 29.01 09 Page 2 submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-07 Certificates
Corrugated Metal Pipe
Certificates of compliance shall be submitted attesting that the materials meet the specified requirements.
1.4 REGULATORY REQUIREMENTS
The regulation requirements listed below form a part of this specification to the extent referenced. The regulatory requirements are referred to in the text by basic designation only.
LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT (LA DOTD)
LOUISIANA DEPARTMENT OF ENVIRONMENTAL QUALITY (LDEQ)
LA DOTD, Water Resource Section P.O. Box 94245 Baton Rouge, Louisiana 70804
The Contractor or subcontractor installing the well system shall be licensed by the State of Louisiana and shall comply with Louisiana Water Well Rules, Regulations, and Standards (Nov. 1985) and Construction of Geotechnical Boreholes and Groundwater Monitoring Systems Handbook (Dec.
2000), except that only the top 10 feet of the riser pipe is required to be sealed by grout.
Measurement and payment provisions within the above referenced standard specifications will not apply. Measurement and payment shall be in accordance with Section 01 22 00.00 09 MEASUREMENT AND PAYMENT.
PART 2 PRODUCTS
2.1 MATERIALS
2.1.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .