About this file

This is a solicitation for an Indefinite Delivery Indefinite Quantity (IDIQ) construction contract for stone repairs to revetments and dikes along the Mississippi River. The U.S. Army Corps of Engineers Vicksburg District is seeking a contractor to perform stone repair work between river miles 616 and 326, with a total contract capacity of $30 million and a minimum guaranteed amount of $8 million.

The project involves furnishing all plant, labor, materials, and equipment to repair and restore stone revetments and dikes. Work includes grading, earth and sand fill, stone paving, subaqueous stone placement, removing and rearranging existing pavement, and environmental protection. The repairs will be conducted in varying water depths and river currents ranging from one to six miles per hour. The contract will be awarded on an unrestricted basis under NAICS code 237990 for Other Heavy and Civil Engineering Construction, with task orders to be issued from the contract award date until March 31, 2027.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION No. W912EE25BA004001

DATE: 21 March 2025

SPECIFICATIONS

FOR

MS RIVER MI 616-326

STONE REPAIRS TO REVETMENTS AND DIKES, FY25

FC/MR&T, MS RIVER BASIN, CHANNEL

IMPROVEMENT PROGRAM

THIS PROCUREMENT IS UNRESTRICTED.

♦Building Strong® ♦Serving the Army ♦Serving the Nation

VICKSBURG DISTRICT

4155 CLAY STREET

VICKSBURG, MS 39183-3435 CEMVK-CTC

INQUIRIES

REGARDING THIS SOLICITATION SHOULD

BE MADE TO THE FOLLOWING:

https://www.projnet.org

Plans and specifications will be available on the Web Page at:

https://sam.gov/ https://sam.gov/

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR

INFORMATION CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

CODE

6. PROJECT NUMBER

8. ADDRESS OFFER TO

4. CONTRACT NUMBER

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

INVITATION FOR BID

NEGOTIATED (RFP)

REQUEST FOR PROPOSAL

3. DATE ISSUED PAGE OF PAGES

W912EE25BA0040001 21 MAR 2025 1 139

PANMVD-25-P-0000 002191

W07V ENDIST VICKSBURG

KO CONTRACTING DIVISION, 4155 CLAY STREET

VICKSBURG, MS 39183-3435

UNITED STATES

KASEY DAVIS, EMAIL: KASEY.T.DAVIS@USACE.ARMY.MIL TELEPHONE: 601-631-

W912EE

W07V ENDIST VICKSBURG

KO CONTRACTING DIVISION, 4155 CLAY STREET

VICKSBURG, MS 39183-3435

UNITED STATES

KASEY DAVIS 601-631-7243

PROJECT TITLE: MS RIVER MI 616-326 STONE REPAIRS TO REVETMENTS AND DIKES, FY25 FC/MR&T, MS RIVER BASIN, CHANNEL IMPROVEMENT PROGRAM

INDEFINITE DELIVERY/INDEFINITE QUANTITY, (IDIQ)

PROJECT LOCATION: MS RIVER BETWEEN MILE 616 AND 326 A.H.P.

DESCRIPTION OF WORK: THE WORK CONSISTS OF FURNISHING ALL PLANT, LABOR, MATERIALS, AND EQUIPMENT, AND PERFORMING STONE REPAIRS TO REVETMENTS AND DIKES AT VARIOUS LOCATIONS ON THE MISSISSIPPI RIVER BETWEEN MILES 616 AND 326 A.H.P. PRINCIPAL FEATURES OF WORK INCLUDE GRADING; EARTH OR SAND FILL, AND SUBGRADE EXCAVATION; STONE PAVING, STONEFILL & SUBAQUEOUS STONE PLACEMENT; REMOVING PAVEMENT;

BREAKING OUT PAVING; REARRANGING DISARRANGED CONCRETE PAVING; DEGRADING OF STONE ALONG REVETMENTS AND/OR STONE BENDWAY WEIRS;

REPAIR TO DIKES, INCLUDING PLACEMENT OF STONE FILL IN SPECIFIED AREAS OF MINOR DAMAGE AND STONE PAVING PROTECTION; AND ENVIRONMENTAL PROTECTION. IN ADDITION, SOME STONE DIKE LOCATIONS WILL REQUIRE EXTENSIVE STONE REPAIRS. THIS WORK WILL BE PERFORMED IN THE MISSISSIPPI RIVER AND VARYING WATER DEPTHS AND CURRENTS MAY BE ENCOUNTERED. CURRENTS USUALLY ENCOUNTERED AT THE SITES OF THE WORK DURING LOW

WATER PERIOD MAY VARY FROM ABOUT ONE MILE PER HOUR TO SIX MILES PER HOUR.

THIS REQUIREMENT IS BEING OFFERED FOR FULL AND OPEN COMPETITION ON AN UNRESTRICTED BASIS. NAICS CODE 237990 OTHER HEAVY AND CIVIL ENGINEERING CONSTRUCTION. THE INTENT IS TO AWARD ONE (1) SINGLE AWARD TASK ORDER CONTRACT (SATOC) WITH A TOTAL CAPACITY OF $30M. THE

MINIMUM GUARANTEE FOR THE CONTRACT IS $8M.

10 730

FAR 52.211-10

1 02:00 PM

22 APR 2025

AWARD (To be completed by Government)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES

CODE AT

27. PAYMENT WILL BE MADE BY

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

27 MAR 2025

Section 00 00 00 - Procurement and Contracting Requirements

MS River MI 616-326 AHP, Stone Repairs to Revetments and Dikes, FY25, FC/MR&T, Channel Improvement Program, Indefinite Delivery/Indefinite Quantity (ID/IQ)

FY25 FC/MR&T, MS RIVER BASIN, CHANNEL IMPROVEMENT STONE REPAIRS TO REVETMENTS AND DIKES, MS RIVER MI 616-326

Bid Package Requirements

Bidders Shall Submit with their Bid Package:

1) A Complete and with Amendments Acknowledged.Signed SF-1442

2) A Complete , with the Bidders Unit Price, and Total Line Item Bid $ Amounts.Bid Schedule

3) A Complete , with The , and other required bidder identification Contractor Information Sheet Total Summation $ Amount of the Bid information.

4) The Bidder's Original Bid Guarantee (Ref Clause 52.228-1 Bid Guarantee).

5) An accurately completed copy of the Bidders (Ref. FAR Clause 52.204-8 Annual Representations and Representations and Certifications Certifications for required information).

In lieu of the completed FAR 52.204-8 Offeror Representations and Certifications, the bidder may certify in their bid package that their Online Representations and Certifications are available electronically at www.sam.gov. (Ref. FAR Clause 52.204-7 System for Award Management).

W912EE25BA004

Section 00 01 15 - List of Drawing Sheets

Attachments - Table of Contents

Identifier Attachment Name Attachment Description Reference Identifier

Date Line Item

# Of Pages

Provided Under Separate Cover

0001 BID SCHEDULE BID SCHEDULE

Mar

No

0002 PUBLISH Specification Mar

No

Wage Determination_Arkansas

Wage Determination

Davis Bacon Wage Deter mination

AR20240045

Feb

No

Wage Determination_Mississippi

Wage Determination

Davis Bacon Wage Deter mination

MS20240071

Feb

No

Wage Determination_Mississippi

Wage Determination

Davis Bacon Wage Deter mination

MS20240072

Feb

No

Wage Determination_Mississippi

Wage Determination

Davis Bacon Wage Deter mination

MS20240073

Feb

No

Wage Determination_Mississippi

Wage Determination

Davis Bacon Wage Deter mination

MS20240074

Feb

No

Wage Determination_Mississippi Warren

Wage Determination Davis Bacon Wage Deter mination

Feb

No

B.04.Wage Determination_Louisiana

Wage Determination Davis Bacon Wage Deter mination LA

Mar

No

Section 00 10 00 - Solicitation, Contract Line Item Number (CLIN) Schedule

Additional Information/Notes

Item Supplies/Service Estimated Quantity

Unit Unit Price Amount

0001 FY25 MS River Stone Repairs

Pricing Arrangement: Firm Fixed Price

1 Job

W912EE25BA004

$30,000,000.00 Capacity

$30,000,000.00 Capacity

ITEM DESCRIPTION

EST

QTY U/M UNIT PRICE AMOUNT

MOBILIZATION AND

DEMOBILIZATION 1 JOB FOR $

GRADED STONE “A” (MILE 616-

494) 25,000 TN $ $

GRADED STONE “A” (MILE 494-

326) 25,000 TN $ $

GRADED STONE “B” WITHOUT

FINES (MILE 616-494)

10,000 TN $ $

GRADED STONE “B” WITHOUT

FINES (MILE 494-326)

10,000 TN $ $

GRADED STONE “C” (MILE 616-

494)

PAINT (WHITE)

20,000 TN $ $

GRADED STONE “C” (MILE 494-

326)

PAINT (DOUBLE YELLOW)

20,000 TN $ $

INSTALLATION OF RAISED

LARGE DIKE BANKHEAD

EXCAVATION

1 EA $ $

SMALL BANKHEAD EXCAVATION

1 EA $ $

UPSTREAM TOWING

100 MI $ $

DOWNSTREAM TOWING

100 MI $ $

MS RIVER MI 616-326

STONE REPAIRS TO REVETMENTS AND DIKES, FY23

FC/MR&T, MS RIVER BASIN, CHANNEL IMPROVEMENT PROGRAM

INDEFINITE DELIVERY/INDEFINITE QUANTITY, (IDIQ)

TOTAL

BID SCHEDULE

Attachment 1

Section 00 20 00 - Instructions for Procurements

CONTRACTOR INFORMATION SHEET

TOTAL BID AMOUNT: $____________________________________________________________

CONTRACTOR'S ADDRESS: _____________________________________________________________

CAGE CODE: _____________________________________________________________

UEI NUMBER: _____________________________________________________________

POINT OF CONTACT: _____________________________________________________________

TELEPHONE NUMBER: _____________________________________________________________

EMAIL: _____________________________________________________________

DATE: _____________________________________________________________

Section 00 21 00 - Instructions

Instructions to Bidders:

NOTES:

(A) Reference Limitations on Subcontracting FAR 52.219-14. This procurement is unrestricted under NACIS Code 237990- Other Heavy and Civil Engineering Construction. The small business size standard is $45,000,000. The awardee of this contract shall comply with all requirements up to and including the following:

Services (except construction): Contractor will not pay more than 50 percent of the amount paid by the Government for contract performance to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded. When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract.

Supplies (other than procurement from a nonmanufacturer of such supplies): Contractor will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded. When a contract includes both supplies and services, the 50 percent limitation shall apply only to the supply portion of the contract.

General construction: Contractor will not pay more than 85percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 85 percent subcontract amount that cannot be exceeded.

Construction by special trade contractors: Contractor will not pay more than 75 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 75 percent subcontract amount that cannot be exceeded.

Upon the Contracting Officer's request, the Contractor shall submit a report to the Contracting Officer documenting compliance with FAR 52.219-14.

If the Contractor is using Similarly Situated Entities, it must be clearly identifiable in the submitted reports. If the required percentage is not being met the Contractor shall also include, with the semiannual report, a plan to meet the required percentage before the contract end date.

The below calculation for FAR 52.219-14 is for example only and not representative of this solicitation or any contract that may be awarded as a result of this solicitation.

1. Total value of contract award = $5,000,000.00

2. Cost of materials = $3,000,000.00

3. Adjusted amount (contract award value less cost of materials): $2,000,000.00 ($5,000,000.00 - $3,000,000.00)

4. 85% of $2,000,000.00 may be paid to non-similarly situated entities ($1,700,000.00)

5. 15% of $2,000,000.00 must be paid to a similarity situated entity ($300,000.00) What is similarly situated and what does it mean for the prime?

i. 1st tier subcontractor that has the same small business program status of the qualified prime contractor (i.e. HUBZone prime contractor, any HUBZone subcontractor is similarly situated).

ii. Any 1st tier subcontracts to similarly situated entities can count towards the prime contractor's self-performance requirements.

iii. Example: HUBZone Set-Aside Contract, 1st Tier is a HUBZone Small Business subcontractor. This meets the similarly situated requirement and the work performed by the HUBZone subcontractor will count towards the HUBZone prime contractor's self-performance requirement.

iv. Example: SDVOSB Set-Aside Contract, 1st Tier is a WOSB subcontractor only, this does not meet the "similarly situated" requirement and the WOSB subcontractor performance does not count towards the SDVOSB prime contractor's self-performance requirement.

Partnering With Us, in all solicitation notices posted at the Governmentwide point of https://www.usace.army.mil/Business-With-Us/Partnering/, entry for construction contracts anticipated to be awarded to a small business pursuant to FAR Part 19 to be in compliance with FAR 36.211(b).

(B) All technical inquiries and questions relating to this solicitation are to be submitted via bidder inquiry in ProjNet at https://www.projnet.org /project. See special notices to bidder's page entitled "Technical Inquiries and Questions"

(C) Stone tonnage placement rates will increase significantly, for specific stone dike repair sites. All dike sites with extensive repairs, requiring supplementary plans and specifications, will have the horizontal and vertical control furnished prior to issuance of task order/NTP (Section 01 00

00.00 09, paragraph 1.47 LAYOUT OF WORK.

W912EE25BA004

https://www.usace.army.mil/Business-With-Us/Partnering/,

(D) Bidders shall furnish unit prices for all items listed on the schedule of bid items which require unit prices. If the bidder fails to insert a unit price in the appropriate blank for required items, but does furnish an extended total or an estimated amount for such items, the Government will deem the unit price to be the quotient obtained by dividing the extended estimated amount for that line item by the quantity. IF THE BIDDER OMITS BOTH THE UNIT PRICE AND THE EXTENDED ESTIMATED AMOUNT FOR ANY ITEM, THE BID WILL BE DECLARED

NONRESPONSIVE.

(E) All quantities shown on the BIDDING SCHEDULE are estimated quantities and are provided only as a basis to establish unit prices for the contract line items. Actual quantities required will vary based upon the actual work required, based upon actual task orders issued, and as determined in the field. Refer to paragraph 1.4 PERIOD OF SERVICE regarding the minimum and maximum amounts of work to be performed under this contract..

(F) If a bid or modification to a bid based on unit price is submitted which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment to the unit price in the schedule must be stated. If it is not stated, the bidder agrees that the lump sum adjustment shall be applied on a pro rata basis to the unit price in the Bid Schedule.

(G) All extensions of the unit price shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the bid.

(H) Award will be made, as a whole to the lowest responsive, responsible bidder as may bein the best interest of the Government.

(I) The contract period is from contract award until 31 March 2027.

(J) At the time of this solicitation, dike and revetment sites have not been identified. Stone dike and revetment sites will be determined after award of the IDIQ contract. Bidders should anticipate both large and small dike repairs when determining their interest and completing their bid.

(K) The Contractor shall anticipate completing about 20 multibeam surveys.

(L) The contractor should be aware of the additional surveying requirements for this contract. See Section 01 00 00.00 09 for more information.

(M) THE NOTICE TO PROCEED (NTP): The successful bidder is advised that performance and payment bonds shall be submitted in accordance with the time frame in block 12B of SF1442. The NTP will be issued immediately after verification of acceptable performance and payment bonds.

Within seven (7) calendar days after issuance of the NTP, the Contractor shall initiate a meeting to discuss the submittals process with the Administrative Contracting Officer (ACO), or the Contracting Officer's Representative (COR), or their authorized representative. Physical work cannot start until the Accident Prevention Plan, Contractor Quality Control Plan, and other submittals which may be required, have been submitted and approved and all preliminary meetings called for under the contract, have been conducted. Contract performance time has been included in the specifications for the preparation, submittal, and approval of Plans, Submittals and Pre-Construction Conferences."

(N) Lack of registration in the WWW.SAM.gov database will make an offeror ineligible for award. See contract clause 52.204-7 entitled, "system for award management".

(O) The SF-1442, Bidding Schedule, and Bidder Representations and Certifications must be accurately completed and returned with your bid, or it may be rejected as nonresponsive. An offeror may also submit, in lieu of the completed FAR Clause52.204- 8 Representations and Certifications, certifications with their bid package that their online Representations and Certifications from www.sam.gov. See FAR Clauses 52.204-7 is available.

(P) All work under these specifications shall be performed in accordance with the most recent provisions of EM 385-1-1 "Corps of Engineers Safety and Health Requirements Manual", dated 15-March-2024.

(Q) The government reserves the right, as the interests of the government may require, to postpone or delay the date and/or time set for opening bids. Revisions or amendments to the bid opening date and/or time, if any, will be announced by amendment or amendments to this invitation for bids.

GENERAL NOTICES:

1. AUTHORITY & APPROPRIATION INFORMATION PROGRAM DATA

AUTHORITY: Flood Control Acts of 1928 (Sec 1), 1936 (Sec1), 1938 (Sec 4), 1941 (Sec 3), 1944 (Sec 10), 1962 (Sec 203), 1965 (Sec 201,204), 1966 (Sec 202, 203), and 1968 (Sec 207)

APPROPRIATION: 3112

FUNDING CITATION: Operation and Maintenance, 96 X 3123

2. NEGOTIATIONS AFTER SEALED BIDDING.

The Government has the option to reject all bids received in response to the sealed bid advertisement and initiate negotiation. Negotiations will include soliciting offers from each responsible bidder that submits a bid in response to the Invitation for Bids. If, after bid opening, the Contracting Officer determines that negotiations are in the best interest of the Government, the following steps will be followed:

(a) An amendment to the sealed bid advertisement will be issued to each responsible bidder changing the Invitation for Bids Number to Request for Proposals Number. The amendment will also make any necessary changes to the scope of the work.

(b) A cover letter signed by the negotiator will accompany the amendment explaining the procedures to be followed during negotiations.

3. BID, PERFORMANCE AND PAYMENT BONDS.

A bid guarantee/bond is required with the bid package and is to be executed on Standard Form SF24. Performance and payment bonds with be required after award. See Section 00700, Contract Clauses 52.228-1, BIDGUARANTEE and 52.228-15, PERFORMANCE AND PAYMENT

BONDS -- CONSTRUCTION

4. AMENDMENTS PRIOR TO DATE SET FOR OPENING BIDS.

The right is reserved, as the interest of the Government may require, to revise or amend the specifications and/or drawings prior to the date set for opening bids. Such revisions or amendments, if any, will be announced by amendment or amendments to this Invitation for Bids. Copies of such amendments as may be issued will be furnished to all prospective bidders. If the revision or amendments are of a nature which require material changes in quantities or prices bid or both, the date set for opening bids may be postponed by such number of days as in the opinion of the District Engineer will enable bidders to revise their bids. In such case, the amendments will include an announcement of the new date for opening bids.

5. BUSINESS INTEGRITY.

The apparent successful bidder as a condition for award of any contract resulting from this solicitation may be required to execute a certificate related to Business Integrity.

6. CONDITIONS AFFECTING THE WORK.

Bidders should visit the site and take such other steps as may be reasonably necessary to ascertain the nature and location of the work, and the general and local conditions which can affect the work or the cost thereof. Failure to do so will not relieve bidders from responsibility for estimating properly the difficulty or cost of successfully performing the work. The Government will assume no responsibility for any understanding or representations concerning conditions made by any of its officers or agents prior to the execution of the contract, unless included in the Invitation for Bids, the specifications, or related documents.

7. BIDDER'S QUALIFICATIONS.

A determination of contractor responsibility will be made. A determination of non-responsibility may be cause for the rejection of a prospective contractor's bid. In accordance with FAR 9.104-1 - General Standards, before a bid is considered for award, the bidder may be requested by the Government to submit a statement regarding their previous experience in performing comparable work, their business and technical organization, financial resources, the plant available to be used in performing the work and/or other information necessary to make the determination of contractor responsibility.

8. SITE OF THE WORK.

Bidders are advised that for purpose of applicability of the Davis-Bacon Act and other contract labor standard provisions, "the site of the work" under the contract to be awarded pursuant to this Invitation may not be limited to the physical place(s) where the construction called for in the contract will remain when work on it has been completed. The "site of the work" may include other adjacent or nearby property used by the Contractor or Subcontractors during such construction. For example, fabrication plants, mobile factories, batch plants, borrow pits, job headquarters, tool yards, etc., will be considered part of the site of the work provided they are dedicated exclusively or nearly so to performance on the contract and are so located in proximity to the actual construction location that it would be reasonable to include them.

9. INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE, AND BONDS.

a. Specifications, Bidding Schedule, Pre-award Information/Description of Work/Bid Evaluation, Equipment Schedule, Construction Contract Clauses, and Wage Determination Decisions of the Secretary of Labor, are parts of this Invitation for bids.

b. (1) An offeror (bidder) electing to use individual sureties for either bid guarantees or performance and payment bonds must submit, concurrently with the bonds and required affidavits, a statement of both the business and personal names of the persons and financial institution through whom the bonds or the guarantees are held, together with the address and telephone number of the persons and/or financial institution authorized to commit the surety.

(2) Offerors or bidders should note that some individual sureties have been debarred or suspended from offering themselves or others as sureties to the Government. Offerors or bidders are responsible for ascertaining the current status of their sureties.

(3) Failure to provide the required information or the submission of bid guarantees obtained from debarred or suspended sureties or brokers may cause rejection of the offer (bid).

10. DEFINITIONS

(a) The term "head of the agency" or "Secretary" as used herein means the Secretary of the Army; and the term "his duly authorized representative" means the Chief of Engineers, Department of the Army, or an individual or board designated by him.

(b) "Contracting Officer" means a person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings. The term includes certain authorized representatives of the Contracting Officer acting within the limits of their authority as delegated by the Contracting Officer.

(c) The agency board of contract appeals having jurisdiction over all appeals from final decisions of the Contracting Officer under the Contract Disputes Act ofl978 is the Armed Services Board of Contract Appeals, addressed as follows: Recorder, Armed Services Board of Contract Appeals, Skyline 6, 7th Floor, 5109Leesburg Pike, Falls Church, Virginia 22041-3208.

(d) "Small business concern" means a concern including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria and size standards in 13 CFR 121.

11. Size Standards for Construction and Special Trades.

(a) Construction. A concern is small if its average annual receipts for its preceding 3 fiscal years did not exceed $45 million.

SPECIAL NOTICES:

1. Bids shall be mailed to the Vicksburg district headquarters building, room 120, 4155 clay street, Vicksburg, Mississippi39183-3435. Bids sent by commercial carrier shall be clearly marked on the as containing a "Sealed Bid". Bids must be received prior to the exact time set for outer envelope bid opening.

Bids may also be submitted by hand at the Vicksburg district headquarters building lobby (4155 clay street, Vicksburg, MS) on the day of bid opening, and may not be submitted sooner than (2) hours prior to the time of the scheduled bid opening. Bidders will only have access to the main lobby. You must enter, hand off your bid package to a representative of the Vicksburg Contracting Office. Prior to opening of bids, bidders attending in person will be escorted to the bid opening room.

No electronic receipt of bids will be allowed for this invitation for bids. The bid opening may be viewed online through" youtube live at the below link; https://www.youtube.com/channel/UC8aGwLzGsYAHHISJg31RFOw

Users should stay on the home page. Once the live stream starts, a new streaming video section will appear above all the existing videos and it will say "live" on the bottom right corner. Users may need to refresh the page to make that section appear and for the video to start playing.

The youtube live link may also be found by going to the USACE Vicksburg district web page; HTTPS://WWW.MVK.USACE.ARMY.MIL/click "business with us" and then "contracting" where the link will be available under "bid openings"

2. Sealed bids for the work described herein will be received until date and time of bid opening.

3. Your attention is directed to section 00100-bid schedule/instructions to bidders' clause 52.214-5 entitled "submission of bids". It is the bidder's responsibility to ensure that bids sent by commercial carrier are clearly identified as containing a sealed bid on the outermost envelope. This includes, but is not limited to, bids sent via: Federal Express, Express Mail - U.S. Postal Service, or United Parcel Service.

4. Note the affirmative action requirement of the equal opportunity clause which may apply to the contract resulting from this solicitation.

5. See section 00 80 00.00 09, special contract requirements, clause entitled "commencement, prosecution, and completion of work".

6. See section 01 00 00.00 09, general contract requirements clause, entitled, "payment invoices" which will apply to the contract resulting from this solicitation. The federal acquisition regulation requires that the "remit to" address of the invoice match the "remit to" address on the contract or a proper notice of assignment.

7. In accordance with FAR 42.1502(e), Past performance evaluations shall be prepared for each construction contract of $750,000 or more, and for each construction contract terminated for default regardless of contract value. Past performance evaluations may also be prepared for construction contracts below $750,000.Past performance evaluations will be prepared by the MVK at least annually and at the time the work under a contract or order is completed and will be entered into the Contractor Performance Assessment Reporting System (CPARS), the Governmentwide evaluation reporting tool for all past performance reports on contracts located at http://www.cpars.gov/

8. Electronic Funds Transfer (EFT)

All vendor direct deposit and Electronic Funds Transfer (EFT) information must be entered/maintained in the System for Award Management(SAM) located at www.SAM.gov. UFC Form 23,previously required for direct deposits/EFT payments by the Vicksburg District(MVK) is obsolete. To receive direct deposits/EFT payments, routing and banking information must be entered and maintained in the SAM. Failure to update/maintain this information in the SAM will result in vendors receiving payments via Treasury checks distributed by U.S. mail. The below links are provided for your information.

How do I update the banking information on my Sam.gov entity registration? https://www.fsd.gov/gsafsd_sp?

id=gsafsd_kb_articles&sys_id=003e5979dbe1259494439f95f39619cd

What is an Electronic Funds Transfer (EFT) indicator and how do I create one? https://www.fsd.gov/gsafsd_sp?

id=gsafsd_kb_articles&sys_id=83629ecadb69e99494439f95f3961958

If you have further questions, please visit the Federal Service Desk (FSD) at www.FSD.gov.

W912EE25BA004

https://www.youtube.com/channel/UC8aGwLzGsYAHHISJg31RFOw https://www.fsd.gov/gsafsd_sp?id=gsafsd_kb_articles&sys_id=003e5979dbe1259494439f95f39619cd https://www.fsd.gov/gsafsd_sp?id=gsafsd_kb_articles&sys_id=003e5979dbe1259494439f95f39619cd https://www.fsd.gov/gsafsd_sp?id=gsafsd_kb_articles&sys_id=83629ecadb69e99494439f95f3961958 https://www.fsd.gov/gsafsd_sp?id=gsafsd_kb_articles&sys_id=83629ecadb69e99494439f95f3961958

9. Bids will not be accepted, nor shall bids be withdrawn electronically or by telephone.

Prior to bid opening, in accordance with federal acquisition regulation part 14.303 (b) modification or withdrawal of bids, "a bid maybe withdrawn in person by a bidder or its authorized representative if, before the exact time set for opening of bids, the identity of the person requesting withdrawal is established and that person signs a receipt for the bid."

The following steps will be required by the Vicksburg Contracting Office:

1. Contractor must present a letter verifying they are a representative of the company.

2. Contractor must show valid, government issued picture id.

3. Vicksburg district contracting office will have the representative sign a receipt forbid.

10. All Technical inquiries and questions related to this solicitation shall be submitted via ProjNet.

Technical inquiries and questions relating to this solicitation are to be submitted via bidder inquiry in ProjNet at (https:www.projnet.org).

Bidders are encouraged to submit questions 5 days prior to bid opening to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary. To submit and review inquiry items, prospective vendors will need to use the bidder inquiry key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email, followed by an answer to the comment/question after it has been processed by our technical team.

All timely questions and approved answers will be made available through ProjNet.

The solicitation number is: W912EE25BA004

The bidder inquiry key is: IPGAQV-6HYIZ4

Specific instructions for ProjNet bid inquiry access:

1. From the ProjNet home page linked above, click on quick add on the upper right side of the screen.

2. Identify the agency. This should be marked as USACE.

3. Key. Enter the bidder inquiry key listed above.

4. Email. Enter the email address you would like to use for communication.

5. Click continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

6. Enter your first name, last name, company, city, state, phone, email, secret question, secret answer, and time zone. Make sure to remember your secret question and answer as they will be used from this point on to access the ProjNet system.

7. Click add user. Once this is completed you are now registered within ProjNet and are currently logged into the system.

Specific instructions for future ProjNet bid inquiry access:

1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your secret question and secret answer to log in.

2. From the ProjNet home page linked above, click on quick add on the upper right side of the screen.

3. Identify the agency. This should be marked as USACE.

4. Key. Enter the bidder inquiry key listed above.

5. Email. Enter the email address you used to register previously in ProjNet.

6. Click continue. A page will then open asking you to enter the answer to your secret question.

7. Enter your secret answer and click login. Once this is completed you are now logged into the system.

11. Tax on Foreign Purchases FAR provision 52.229-11 and FAR clause 52.229-12

FAR provision 52.229-11 and FAR clause 52.229-12 are included in this solicitation. This provision and clause concern the imposition of a 2 percent Federal excise tax withholding on any resultant contract award or payment request. This rule applies to Federal Government contracts for goods or services that are awarded to foreign persons - such as foreign contractors. It implements the Department of the Treasury's final regulations published in the Federal Register at 81 FR 55133 on August 18, 2016, under section 5000C of the Internal Revenue Code relating to the 2 percent tax on payments made by the U.S. Government to foreign persons pursuant to certain contracts. Pursuant to the FAR 52.229-3 Federal, State, and Local Taxes, taxes imposed under 26 U.S.C.5000 C may not be included in the contract price or reimbursed.

W912EE25BA0040001

Exemptions from this excise tax must be claimed by an Offeror when it submits, with its offer, a U.S. Department of Treasury Internal Revenue Service (IRS) Form W-14, Certificate of Foreign Contracting Party Receiving Federal Procurement Payments, available via the internet at www.irs.

gov/W14. If not submitted with the offer, exemptions will not be applied to any resulting contract and the Government will withhold a full 2 percent on each contract payment. Failure to submit an IRS Form W-14 with each payment request will also result in an automatic withholding of 2 percent from the payment request.

When filling out the IRS Form W-14 the following information may be used to complete Part I, Lines 6 and 7. Line 6 Contract/reference number:

[W912EE25BA004]

Line 7 "Name and address of the acquiring agency":[USACE, Vicksburg District, 4155 Clay Street, Vicksburg MS. 39180]

Any exemption claimed and self-certified is subject to audit by the IRS. Any disputes concerning this tax are adjudicated by the IRS because the Section 5000C tax is a tax matter not a contract issue.

Offerors are encouraged to seek guidance from their own tax professionals for advice concerning the provision, clause, and exclusions exclusion /submission of IRS Form W-14. Additional information is also available at:

Notwithstanding the above, the USACE does not have a means of withholding this excise tax at this time. As a result, contractors are expected to comply with the instructions above and to properly complete and return the W-14 at proposal submission, and with each pay application. Whether the contractor sets the money aside for future payment to the IRS, or makes payment to the IRS, is the contractor's discretion, based on its analysis of the regulations regarding the excise tax. In the event that USACE is able to withhold during contract performance, it will notify the contractor and make such a withholding (including any catch up withholdings); no advance notice is required to the contractor prior to the withholding. Under no circumstances is USACE liable for any tax not paid by the contractor. The contractor is liable for the tax, to the extent required by law, regardless of whether USACE makes a withholding.

FAR 29.204 expressly states that "[a]gencies merely withhold the tax (section 5000C tax) for the Internal Revenue Service (IRS).All substantive issues regarding the underlying section 5000C tax, e.g., the imposition of, and exemption from the tax, are matters under the jurisdiction of the IRS."

Therefore, we cannot help you determine how the tax law applies to you. We strongly recommend that you contact the IRS and/or a tax professional should you have any questions of this nature. To be clear, this information does not constitute tax advice or a representation of your tax liability.

Furnishing this information does not create liability for the USACE for any Federal, state, or local taxes applicable to the above-referenced contract or any other contract.

For submission requirements and basis of evaluation:

Executed FAR Provision 52.229-11.

Completed IRS Form W-14, Certificate of Foreign Contracting Party Receiving Federal Procurement Payments, if applicable. If not submitted with the offer, exemptions will not be applied to any resulting contract and the Government will withhold a full 2 percent on each payment.

Veterans Employment Emphasis for U.S. Army Corps of Engineers Contracts:

In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause52.222- 37, DFARS 222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:

- U.S. Department of Labor Veterans' Employment and Training Service (VETS): https://www.dol.gov/vets/

- Federal Veteran Employment Information: https://www.fedshirevets.gov/

- Veterans Opportunity to Work (VOW) Program: https://www.benefits.va.gov/vow/

- U.S. Army Warrior Transition Command Employment Index:https://wct.army.mil/modules/employers/index.html

- Hiring Our Heroes: https://www.uschamberfoundation.org/hiring-our-heroes

FAR Clauses Incorporated by Full Text

52.204-7 System for Award Management. (Nov 2024)

As prescribed in 4.1105(a)(1), use the following provision:

System for Award Management (Nov 2024)

(a) Definitions. As used in this provision-

"Electronic Funds Transfer (EFT) indicator means a four-character suffix to the unique entity identifier. The suffix is assigned at the discretion of the commercial, nonprofit, or Government entity to establish additional System for Award Management records for identifying alternative EFT accounts (see subpart 32.11) for the same entity.

Registered in the System for Award Management (SAM) means that-

(1) The Offeror has entered all mandatory information, including the unique entity identifier and the EFT indicator, if applicable, the Commercial and Government Entity (CAGE) code, as well as data required by the Federal Funding Accountability and Transparency Act of 2006 (see subpart 4.14) into SAM

(2) The offeror has completed the Core, Assertions, and Representations and Certifications, and Points of Contact sections of the registration in SAM;

(3) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS). The offeror will be required to provide consent for TIN validation to the Government as a part of the SAM registration process; and

(4) The Government has marked the record "Active".

Unique entity identifier means a number or other identifier used to identify a specific commercial, nonprofit, or Government entity. See www.sam.

gov for the designated entity for establishing unique entity identifiers.

(b)

(1) An Offeror is required to be registered in SAM when submitting an offer or quotation and at time of award (see FAR clause 52.204-13, System for Award Management Maintenance, for the requirement to maintain SAM registration during performance and through final payment).

(2) The Offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation "Unique Entity Identifier" followed by the unique entity identifier that identifies the Offeror's name and address exactly as stated in the offer. The Offeror also shall enter its EFT indicator, if applicable. The unique entity identifier will be used by the Contracting Officer to verify that the Offeror is registered in the SAM.

(c) If the Offeror does not have a unique entity identifier, it should contact the entity designated at www.sam.gov for establishment of the unique entity identifier directly to obtain one. The Offeror should be prepared to provide the following information:

(1) Company legal business name.

(2) Tradestyle, doing business, or other name by which your entity is commonly recognized.

(3) Company physical street address, city, state, and Zip Code.

(4) Company mailing address, city, state and Zip Code (if separate from physical).

(5) Company telephone number.

(6) Date the company was started.

(7) Number of employees at your location.

(8) Chief executive officer/key manager.

(9) Line of business (industry).

(10) Company headquarters name and address (reporting relationship within your entity).

(d) Processing time should be taken into consideration when registering. Offerors who are not registered in SAM should consider applying for registration immediately upon receipt of this solicitation. See https://ww.sam.gov for information on registration.

(End of provision)

52.204-22 Alternative Line Item Proposal. (Jan 2017)

As prescribed in 4.1008 , insert the following provision:

Alternative Line Item Proposal (Jan 2017)

(a) The Government recognizes that the line items established in this solicitation may not conform to the Offeror's practices. Failure to correct these issues can result in difficulties in acceptance of deliverables and processing payments. Therefore, the Offeror is invited to propose alternative line items for which bids, proposals, or quotes are requested in this solicitation to ensure that the resulting contract is economically and administratively advantageous to the Government and the Offeror.

(b) The Offeror may submit one or more additional proposals with alternative line items, provided that alternative line items are consistent with subpart 4.10 of the Federal Acquisition Regulation. However, acceptance of an alternative proposal is a unilateral decision made solely at the discretion of the Government. Offers that do not comply with the line items specified in this solicitation may be determined to be nonresponsive or unacceptable.

(End of provision)

52.222-5 Construction Wage Rate Requirements-Secondary Site of the Work. (May 2014)

As prescribed in 22.407(h), insert the following provision:

Construction Wage Rate Requirements-Secondary Site of the Work (May 2014)

(a)

(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of provision)

52.233-2 Service of Protest. (Sep 2006)

As prescribed in 33.106 , insert the following provision:

Service of Protest (Sept 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from Contracting Officer 4155 Clay St., Vicksburg, MS 39180-0601 601-631-7243. [Contracting Officer designate the official or location where a protest may be served on the Contracting Officer.]

(b) The copy of any protest shall be received in the office designated above within oneday of filing a protest with the GAO.

(End of provision)

52.236-27 Site Visit (Construction). (Feb 1995)

As prescribed in 36.523 , insert a provision substantially the same as the following:

Site Visit (Construction) (Feb 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) Site visits may be arranged during normal duty hours by contacting:

Name: Mr. Robin Blake

Address: 100 Advocate Row Vidalia, LA 71373-3032

Telephone: 318-336-5226

(End of Provision)

52.252-1 Solicitation Provisions Incorporated by Reference. (Feb 1998)

As prescribed in 52.107(a), insert the following provision:

Solicitation Provisions Incorporated by Reference (Feb 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.govhttps://www.acquisition.gov/dfars____[Insert one or more Internet addresses]

(End of provision)

52.252-5 Authorized Deviations in Provisions. (Nov 2020)

As prescribed in 52.107(e), insert the following provision in solicitations that include any FAR or supplemental provision with an authorized deviation. Whenever any FAR or supplemental provision is used with an authorized deviation, the contracting officer shall identify it by the same number, title, and date assigned to the provision when it is used without deviation, include regulation name for any supplemental provision, except that the contracting officer shall insert "(DEVIATION)" after the date of the provision.

Authorized Deviations in Provisions (Nov 2020)

(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.

(b) The use in this solicitation of any Federal Acquisition Regulation (FAR)[insert regulation name](48 CFR Chapter1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

(End of provision)

DFARS Clauses Incorporated by Full Text

252.204-7019 Notice of NIST SP 800-171 DoD Assessment Requirements.