This document is an Amendment/Modification to Solicitation Number W912EE24Q0049 for the procurement of 23,100 lbs of Oxalic Acid in 55 lb bags. The key changes are:

The bidder inquiry key is revised to 56D5W3-692FAW. The scope of work is revised, requiring the contractor to ship the Oxalic Acid to a specified location in Vicksburg, MS by September 5, 2024. The evaluation factors are price and technical acceptability, with the lowest-priced technically acceptable bid considered first for award. Sustainability requirements regarding EPA and USDA BioPreferred designations may apply. Payment terms specify invoicing to designated USACE email addresses upon completion.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Reference Solicitation Number W912EE24Q0049 is hereby amended as follow s:

The bidder inquiry key is revised and replaced w ith 56D5W3-692FAW.

The scope of w ork is revised and replaced in its entirely.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 09-Aug-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912EE24Q0049

X 9B. DATED (SEE ITEM 11)

31-Jul-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

09-Aug-2024

CODE

VICKSBURG CONTRACTING OFFICE

4155 CLAY ST

VICKSBURG MS 39183-3435

W912EE 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912EE24Q0049

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been modified:

SCOPE OF WORK

OXALIC ACID FOR RELIEF WELL TREATMENT

Scope of Work OXALIC ACID FOR WELL TREATMENTS – GEOTECHNICALResearch:

Geotechnical Branch will require 23,100 lbs of the Oxalic Acid to be available to use by the 05 September 2024, to complete scheduled relief well projects. The government requires 55lb bags.

Transportation The contractor will ship Oxalic Acid to 2449 Haining Rd Vicksburg Ms. 39183

Evaluation Factors

Price The contractor bid with the lowest price will be considered for award first. 2) Technical Acceptability. The second evaluation factor will consist of determining whether the contractor’s bid is technically acceptable. Is the contractor’s bid indicates that they will be able to perform all aspects of the contract requirements, their bid will be deemed technically acceptable. The contractor must be able to deliver the Oxalic Acid as required by the scope of work. The contractor must be able to meet the required period of performance as required by the scope of work. The contractor must also meet all dealer qualifications listed above.

Payment Upon completion of work, the invoice(s) shall be emailed to the finance center (CEFC- B4Invoices@usace.army.mil) and to Jarsh Lepard, (Jarsh.L.Lepard@usace.army.mil.

Sustainability Requirements The contractor shall consider all Corps of Engineers Sustainability requirements:

• The contractor may be required to use materials as determined by EPA regulations. The following link can be used to determine which products (need to complete the SOW) are required to be EPA‐designated: http://www3.epa.gov/epawaste/conserve/tools/cpg/products/ • The contractor may be required to use materials as specified under BioPreferred Program requirements as determined by the USDA. The following link lists which products must contain biobased content:

http://www.biopreferred.gov/BioPreferred/faces/pages/ProductCategories.xhtml

W912EE24Q0049

(End of Summary of Changes)