This amendment modifies a solicitation for a federal construction contract. The work consists of levee enlargement in Washington County, Mississippi, including mobilization and demobilization, clearing and grubbing, embankment construction, ramps, borrow source development and reclamation, gravel and stone surfacing, turfing, erosion control, and environmental protection. Plans and specifications are available online. The issue date for the solicitation is 9 July 2021, with bids due by 2:00 PM Central time on 10 August 2021. This is a total small business set-aside issued by the U.S. Army Corps of Engineers Vicksburg District under NAICS 237990 and FSC YIPZ for a firm fixed-price contract.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B06_Official_Bid_Abstract_W912EE21B0017.pdf | ||
| A02_Drawings_W912EE21B0017.pdf | ||
| A02_Specifications_W912EE21B0017.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Solicitation No. W912EEB0017, for Washington County, Mississippi Levee Enlargement, ITEMS 526-L FC/MR&T, EBMRL, is amended.
SEE CONTINUATION PAGE FOR SUMMARY OF CHANGES
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 06-Aug-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912EE21B0017
X 9B. DATED (SEE ITEM 11)
09-Jul-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
06-Aug-2021
CODE
VICKSBURG CONTRACTING OFFICE
4155 CLAY ST
VICKSBURG MS 39183-3435
W912EE 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912EE21B0017
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SPECIFICATIONS: Section 08 00 00.00 09 is revised and replaced.
Specifications revised by this amendment have the notation "Revised by Amendment 0001" at the bottom of the page. Text added by this amendment is shown as underlined. Text deleted by this amendment is shown as overstruck.
W912EE-21-B-0017
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 80 00.00 09
SPECIAL CONTRACT REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
1.2.1 Notice To Proceed
1.3 LIQUIDATED DAMAGES-CONSTRUCTION
1.4 EXCEPTION TO LIQUIDATED DAMAGES
1.5 CONTRACT DRAWINGS AND SPECIFICATIONS
1.6 CORRESPONDENCE AND ELECTRONIC COMMUNICATION
1.7 (S-102) CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR
PROCESSING DAVIS-BACON ACT CERTIFIED LABOR PAYROLLS
1.8 PERFORMANCE OF WORK BY THE CONTRACTOR
1.9 WORK TO BE PERFORMED BY CONTRACTOR'S OWN ORGANIZATION
1.10 PHYSICAL DATA
1.11 PAYMENT FOR MOBILIZATION AND DEMOBILIZATION
1.12 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
1.13 I-WATCH
1.14 OPSEC TRAINING
1.15 PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section Table of Contents --
DOCUMENT 00 80 00.00 09 Page 1 Revised By Amendment 0001
SECTION 00 80 00.00 09
SPECIAL CONTRACT REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP 1110-1-8 (2016) Construction Equipment Ownership and Operating Expense Schedule
1.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
The Contractor shall be required to (a) commence work under this Contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 400 calendar days after the date the Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises. (FAR 52.211-10)
1.2.1 Notice To Proceed
The notice to proceed will be issued after receipt and Government verification of the required performance and payment bonds. The Contract also requires submission of various pre-work plans and Government approval of those plans as well as various preconstruction meetings prior to commencement of physical work at the site. Notice to proceed will not be delayed to await receipt of these plans. The Contract performance time includes adequate time for submission and Government review of the required pre-work plans and all required preconstruction meetings to be conducted after notice to proceed. The Notice to Proceed will not be issued any earlier than 01 October 2020 01 November 2021 .
1.3 LIQUIDATED DAMAGES-CONSTRUCTION
(a) If the Contractor fails to complete the work within the time specified in the Contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,051 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause. (FAR 52.211-12)
1.4 EXCEPTION TO LIQUIDATED DAMAGES
Since the Contractor's obligations specified in Section 32 92 00.00 09 EXISTING TURF MAINTENANCE AND NEW TURF ESTABLISHMENT may extend beyond the completion time specified in paragraph COMMENCEMENT, PROSECUTION, AND
DOCUMENT 00 80 00.00 09 Page 2
COMPLETION OF WORK, these periods and the additional work, if required, will be exempt from liquidated damages provided all other work has been completed.
1.5 CONTRACT DRAWINGS AND SPECIFICATIONS
(a) The Government will provide to the Contractor, without charge, one set of Contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.
(b) The Contractor shall --
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
(3) Promptly notify the Contracting Officer of any discrepancies;
(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and
(5) Reproduce and print Contract drawings and specifications as needed.
(c) In general --
(1) Large-scale drawings shall govern small scale drawings; and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the Contract drawings as required.
(DFARS 252.236-7001)
1.6 CORRESPONDENCE AND ELECTRONIC COMMUNICATION
For ease and speed of communications, both the Government and Contractor shall exchange correspondence and all other documents duplicate in both hard paper copy and electronic format. Inclusion of an electronic copy is in addition to any other parts of the Contract that may specify a minimum number of hard copies to be submitted, such as for shop drawing transmittals. Electronic submission can be accomplished by one of the following methods: e-mail, file upload to the following website https://safe.amrdec.army.mil/SAFE , or through the Resident Management System - Contractor Mode (RMS CM). Format for electronic submissions will be in portable document format (.pdf). File naming will be determined by the Contracting Officer and presented at the Preconstruction Conference.
DOCUMENT 00 80 00.00 09 Page 3
Documents include all general correspondence, administrative plans, all material submittals including shop drawings, progress schedules, submittal registers, requests for information (RFIs), Quality Control (QC) test results, pay requests, etc. Paper documents will govern, in the event of discrepancy with the electronic version. Generally, paper documents will also govern where effective receipt dates are required, such as Contractor claims submitted under the Disputes clause of the Contract and progress payment requests. However in the case of administrative plans, shop drawings and other submittals transmitted for Government review, both the electronic and hard copies are required to begin the review process, so the effective date of receipt will be the date when both the electronic and hard copies are received by the Government.
1.7 (S-102) CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR
PROCESSING DAVIS-BACON ACT CERTIFIED LABOR PAYROLLS
The Contractor is encouraged to use a commercially-available electronic system to process and submit certified payrolls electronically to the Government. The requirements for preparing, processing and providing certified labor payrolls are established by the Davis-Bacon Act as stated in FAR 52.222-8, PAYROLLS AND BASIC RECORDS and FAR 52.222-13, COMPLIANCE
WITH DAVIS-BACON AND RELATED ACT REGULATIONS.
If the Contractor elects to use an electronic Davis-Bacon payroll processing system, then the Contractor shall be responsible for obtaining and providing for all access, licenses, and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the Contractor to comply with Davis-Bacon and related Act regulations.
When the Contractor uses an electronic Davis-Bacon payroll system, the electronic payroll service shall be used by the Contractor to prepare, process, and maintain the relevant payrolls and basic records during all work under this construction Contract and electronic payroll service shall be capable of preserving these payrolls and related basic records for the required 3 years after Contract completion. If the Contractor chooses to use an electronic Davis-Bacon payroll system, then the Contractor shall obtain and provide electronic system access to the Government, as required to comply with the Davis-Bacon and related Act regulations over the duration of this construction Contract. The access shall include electronic review access by the Government Contract administration office to the electronic payroll processing system used by the Contractor.
The Contractor's provision and use of an electronic payroll processing system shall meet the following basic functional criteria: commercially available; compliant with appropriate Davis Bacon Act payroll provisions in the FAR; able to accommodate the required numbers of employees and subcontractors planned to be employed under the Contract; capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records (format at ) for export in an Excel spreadsheet to be imported into the Contractor's version of Resident Management System - Contractor Mode (RMS CM), that in turn shall export payroll data to the Government's Resident Management System (RMS); demonstrated security of data and data entry rights; ability to produce Contractor-certified electronic versions of weekly payroll data; ability to identify erroneous entries and track the data/time of all versions of the certified Davis Bacon payrolls submitted to the Government over the life of the Contract;
capable of generating a durable record copy, that is, a CD or DVD and PDF file record of data from the system database at end of the Contract closeout. This durable record copy of data from the electronic Davis-Bacon
DOCUMENT 00 80 00.00 09 Page 4 payroll processing system shall be provided to the Government during Contract closeout.
All Contractor-incurred costs related to the Contractor's provision and use of an electronic payroll processing service shall be included in the Contractor's price for the overall work under the Contract. The costs for Davis-Bacon Act compliance using electronic payroll processing services shall not be a separately bid/proposed or reimbursed item under this Contract. FAR 52.222-8 and FAR 52.222-13
1.8 PERFORMANCE OF WORK BY THE CONTRACTOR
The Contractor shall perform on the site and with its own organization, work equivalent to at least twenty (20) percent of the total amount of work to be performed under the Contract. This percentage may be reduced by a supplemental agreement to this Contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government. (FAR 52.236-1)
1.9 WORK TO BE PERFORMED BY CONTRACTOR'S OWN ORGANIZATION
Within 10 days after award, the successful Bidder/Contractor must furnish the Contracting Officer a description of the items of work which will be performed with its own forces and the estimated cost of those items. (See Contract Clause NOTICE OF TOTAL HUBZONE SET-ASIDE.)
1.10 PHYSICAL DATA
Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by surveys and borings.
(b) Weather Conditions. Information with respect to temperatures and precipitation may be obtained from the National Weather Service.
(c) Transportation Facilities.
(1) Roads. Mississippi State Highway No. 1, MS-438, and local roads serve the general area.
(2) Railroads. The Contractor is responsible for determining the availability of railroad service.
(d) Floods.
(1) High water stages or events are not to be considered a "flood," and damages resulting there from are not compensable underSection 01 00 00.00 09 GENERAL CONTRACT REQUIREMENTS, paragraph DAMAGE TO WORK unless river or stream stages exceed channel capacity and overtop the natural or artificial banks. High water stages and/or high water events at stages below ordinary top bank of a river or stream are not floods, even if such water reaches
DOCUMENT 00 80 00.00 09 Page 5 the project. For example, water flowing through or over low points in the river or stream bank, such as drains, are not floods.
(e) Additional Data. Additional data consisting of additional cross sections, records of borings, and boring samples are available for inspection at:
U.S. Army Engineer District, Vicksburg 4155 Clay Street
Vicksburg, Mississippi 39183-3435
(FAR 52.236-4)
1.11 PAYMENT FOR MOBILIZATION AND DEMOBILIZATION
(a) The Government will pay all costs for the mobilization and demobilization of all of the Contractor's plant and equipment at the Contract job price for this item.
(1) Sixty percent of the job price upon completion of the Contractor's mobilization at the work site.
(2) The remaining forty percent upon completion of demobilization.
(b) The Contracting Officer may require the Contractor to furnish cost data to justify this portion of the bid if the Contracting Officer believes that the percentages in subparagraphs (a)(1) and (2) of this clause do not bear a reasonable relation to the cost of the work in this Contract.
(1) Failure to justify such price to the satisfaction of the Contracting Officer will result in payment, as determined by the Contracting Officer, of--
(i) Actual mobilization costs at completion of mobilization;
(ii) Actual demobilization costs at completion of demobilization; and
(iii) The remainder of this item in the final payment under this Contract.
(2) The Contracting Officer's determination of the actual costs in paragraph (b)(1) of this clause is not subject to appeal.
(DFARS 252.236-7004)
1.12 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
(a) This special Contract requirement does not apply to terminations.
See 52.249-500, Basis for Settlement of Proposals and FAR Part 49.
(b) Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a Contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the Contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the
DOCUMENT 00 80 00.00 09 Page 6
Contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8 , Construction Equipment Ownership and Operating Expense Schedule, Region III.
Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the Contracting Officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.
(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36, Rental Costs. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.
(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the SAT, the Contracting Officer shall request the Contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.
(USACE Acquisition Instruction ("UAI") 31.105-101)
NOTE: EP 1110-1-8 , "Construction Equipment Ownership and Operating Expense Schedule" is available on the Internet at http://www.publications.usace.army.mil/USACEPublications/EngineerPamphlets.aspx , then search for EP 1110-1-8 , then click on the link and then choose EP_1110-1-8_Vol-03.pdf or may be purchased from the Government Printing Office on CD-ROM by calling (202) 512-1800.
1.13 I-WATCH
The Contractor and all associated subcontractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of Contract award and within 30 calendar days of new employees commencing performance with the results reported to the Contracting Officer NLT 5 calendar days after the completion of the training.
1.14 OPSEC TRAINING
All new Contractor employees will complete Level I OPSEC Training within 30 calendar days of their reporting for duty. Additionally, all Contractor employees must complete annual OPSEC awareness training. The Contractor shall submit certificates of completion for each affected
DOCUMENT 00 80 00.00 09 Page 7
Contractor and subcontractor employee, to the COR or to the Contracting Officer (if a COR is not assigned), within 5 calendar days after completion of training. OPSEC awareness training is available at the following websites:
https://www.iad.gov/ioss/ or http://www.cdse.edu/catalog/operations-security.html ; or, it can be provided by the Requiring Agency OPSEC Officer in presentation form which will be documented via memorandum.
1.15 PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM
The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the Contracting Officer no later than 3 business days after the initial Contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting Officer and shall become part of the official Contract file.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Document --