This document is an amendment to a solicitation for channel improvement work in Tallahatchie County, Mississippi. The amendment revises the specifications and notes sections of the solicitation, provides additional details on the pre-bid site visit and submission requirements, and extends the period for exercise of optional work items from 300 to 320 days after NTP issuance. Affected specifications and notes sections are replaced in their entirety. The work consists of channel excavation, disposal area development, and environmental protection features to improve drainage in the project area. Bidders are required to attend the pre-bid site visit on July 24, 2020 and meet submission deadlines for the accident prevention plan and other documents prior to the preconstruction conference.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Reference Solicitation No. W912EE20B0008, for FC/MR&T, YAZOO RIVER BASIN TALLAHATCHIE COUNTY, MISSISSIPPI UPPER YAZOO PROJECTS, ITEM 7D CHANNEL IMPROVEMENT, is amended as follow s:

Please see continuation pages for changes1

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 15-Jul-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912EE20B0008

X 9B. DATED (SEE ITEM 11)

07-Jul-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

15-Jul-2020

CODE

VICKSBURG CONTRACTING OFFICE

4155 CLAY ST

VICKSBURG MS 39183-3435

W912EE 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912EE20B0008

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

A prebid site visit will be conducted on Friday, July 24, 2020 at 10:00 a.m.at Disposal Area 7D- V1-1. For any further information regarding directions to the locattion of the site visit please contact Mr. Jason Overstreet, Area Engineer at telephone (662) 453-5531 or by Email at Jason.T.Overstreet@usace.army.mil.

NOTES sections is revised and replaced in its entirety.

SPECIFICATIONS: Section 00 80 00.00 09, and Section 01 00 00.00 09 are revised and replaced.

Specifications revised by this amendment have the notation "Revised by Amendment 0001" at the bottom of the page. Text added by this amendment is shown as underlined. Text deleted by this amendment is shown as overstruck.

W912EE20B0008

NOTES:

(A) PLAN ORGANIZATION. FOR CLARITY WITH DISTINGUISHING BETWEEN

THE BASE CONTRACT BID ITEMS AND OPTIONAL CONTRACT BID ITEMS, THE

PLANS HAVE BEEN SPLIT INTO TWO VOLUMES. VOLUME 1 OF THE PLAN SET

COVERS ALL WORK ASSOCIATED WITH THE BASE CONTRACT. VOLUME 2 OF

THE PLAN SET COVERS ALL WORK ASSOCIATED WITH OPTIONAL WORK 1.

(B) OPTIONAL WORK ITEMS. THE GOVERNMENT MAY REQUIRE THE DELIVERY

OF THE NUMBERED LINE ITEM(S), IDENTIFIED IN THE BID SCHEDULE AS

OPTIONAL WORK ITEMS, IN THE QUANTITIES AND PRICES STATED IN THE

SCHEDULE. THE CONTRACTING OFFICER MAY EXERCISE THE OPTIONAL WORK

ITEMS BY WRITTEN NOTICE TO THE CONTRACTOR. THE GOVERNMENT WILL

EXERCISE OW 1 NO LATER THAN 300 240 DAYS AFTER ISSUANCE OF THE

ORIGINAL NTP. BIDDERS SHALL BID ON ALL ITEMS INCLUDING OPTIONAL

ITEMS (SEE “EVALUATION OF OPTIONS” FAR 52.217-5). FAILURE TO BID

ON ALL ITEMS WILL RESULT IN A NON-RESPONSIVE BID.

(C) EVALUATION OF OPTIONS (FAR 52.217-5 JUL 1990). EXCEPT WHEN IT

IS DETERMINE IN ACCORDANCE WITH FAR 17.206(B) NOT TO BE IN THE

GOVERNMENT’S BEST INTERESTS, THE GOVERNMENT WILL EVALUATE OFFERS

FOR AWARD PURPOSES BY ADDING THE TOTAL PRICE FOR ALL OPTIONS TO

THE TOTAL PRICES FOR THIS BASIC REQUIREMENT. EVALUATION OF

OPTIONS WILL NOT OBLIGATE THE GOVERNMENT TO EXERCISE THE

OPTION(S). IF AN OPTIONS IS TO BE EXERCISED AT THE TIME OF

CONTRACT AWARD IN ACCORDANCE WITH FAR 17.208, FAR CLAUSE 52.217-4

SHALL BE USED IN PLACE OF FAR CLAUSE 52.217-5.

(D) TIME ADJUSTMENT IN THE EVENT OF THE EXERCISE OF OPTIONAL

WORK. IN THE EVENT THAT OPTIONAL WORK ITEMS (ITEMS 0006 THROUGH

0012) ARE EXERCISED UNDER THE TERMS OF THE CONTRACT, THE TIME

REQUIRED FOR COMPLETION OF THE CONTRACT WILL BE EXTENDED BY A

DURATION OF 260 320 CALENDAR DAYS.

(E) THIS PROCUREMENT IS TOTAL SMALL BUSINESS SET-ASIDE.

(F) ALL TECHNICAL INQUIRIES AND QUESTIONS RELATING TO THIS

SOLICITATION ARE TO BE SUBMITTED VIA BIDDER INQUIRY IN PROJECT AT

HTTP://WWW.PROJNET.ORG/PROJECT. SEE SNTB PAGE ENTITLE

“TECHNICAL INQUIRIES AND QUESTIONS”

(G) BIDDERS SHALL FURNISH UNIT PRICES FOR ALL ITEMS LISTED ON

THE SCHEDULE OF BID ITEMS WHICH REQUIRE UNIT PRICES. IF THE

BIDDER FAILS TO INSERT A UNIT PRICE IN THE APPROPRIATE BLANK FOR

REQUIRED ITEMS, BUT DOES FURNISH AN EXTENDED TOTAL OR AN

ESTIMATED AMOUNT FOR SUCH ITEMS, THE GOVERNMENT WILL DEEM HIS

Revised By Amendment 0001 http://www.projnet.org/project

B4EDGDML

Cross-Out

B4EDGDML

Cross-Out

UNIT PRICE TO BE THE QUOTIENT OBTAINED BY DIVIDING THE EXTENDED

ESTIMATED AMOUNT FOR THAT LINE ITEM BY THE QUANTITY. IF THE

BIDDER OMITS BOTH THE UNIT PRICE AND THE EXTENDED ESTIMATED

AMOUNT FOR ANY ITEM, HIS BID WILL BE DECLARED NONRESPONSIVE.

(H) ALL QUANTITIES SHOWN ON THE BIDDING SCHEDULE ARE ESTIMATED

QUANTITIES EXCEPT WHEN THE UNIT OF MEASURE IS SHOWN AS "LUMP

SUM", "JOB" OR "EACH".

(I) IF A BID OR MODIFICATION TO A BID BASED ON UNIT PRICE IS

SUBMITTED WHICH PROVIDES FOR A LUMP SUM ADJUSTMENT TO THE TOTAL

ESTIMATED COST, THE APPLICATION OF THE LUMP SUM ADJUSTMENT TO

THE UNIT PRICE IN THE SCHEDULE MUST BE STATED. IF IT IS NOT

STATED, THE BIDDER AGREES THAT THE LUMP SUM ADJUSTMENT SHALL BE

APPLIED ON A PRO RATA BASIS TO THE UNIT PRICE IN THE BID

SCHEDULE.

(J) ALL EXTENSIONS OF THE UNIT PRICE SHOWN WILL BE SUBJECT TO

VERIFICATION BY THE GOVERNMENT. IN CASE OF VARIATION BETWEEN

THE UNIT PRICE AND THE EXTENSION, THE UNIT PRICE WILL BE

CONSIDERED TO BE THE BID.

(K) AWARD WILL BE MADE AS A WHOLE TO THE LOWEST RESPONSIVE,

RESPONSIBLE BIDDER AS MAY BE IN THE BEST INTEREST OF THE

GOVERNMENT.

(L) LACK OF REGISTRATION IN THE SAM DATABASE WILL MAKE AN

OFFEROR INELIGIBLE FOR AWARD. SEE CONTRACT CLAUSE 52.204-7

ENTITLED, "SYSTEM FOR AWARD MANAGEMENT".

(M) THE SF1442, BIDDING SCHEDULE, AND SECTION 00600

(REPRESENTATIONS AND CERTIFICATIONS) MUST BE ACCURATELY

COMPLETED AND RETURNED WITH YOUR BID OR IT MAY BE REJECTED AS

NONRESPONSIVE. AN OFFEROR MAY ALSO SUBMIT, IN LIEU OF THE

COMPLETED SECTION 00600, A COMPLETE HARD COPY OF THEIR ONLINE

REPRESENTATIONS AND CERTIFICATIONS APPLICATIONS (ORCA)

REGISTRATION. SEE FAR CLAUSES 52.204-7 AND 52.204-8 FOR

REQUIREMENT INFORMATION. THE WEBSITE FOR ORCA IS WWW.SAM.GOV.

(N) THE NOTICE TO PROCEED (NTP): THE SUCCESSFUL BIDDER IS

ADVISED THAT PERFORMANCE AND PAYMENT BONDS SHALL BE SUBMITTED IN

ACCORDANCE WITH THE TIME FRAME IN BLOCK 12B OF SF1442. THE NTP

WILL BE ISSUED IMMEDIATELY AFTER VERIFICATION OF ACCEPTABLE

PERFORMANCE AND PAYMENT BONDS. WITHIN SEVEN (7) CALENDAR DAYS

AFTER ISSUANCE OF THE NTP, THE CONTRACTOR SHALL INITIATE A

MEETING TO DISCUSS THE SUBMITTAL PROCESS WITH THE AREA OR

Revised by Amendment 0001

RESIDENT ENGINEER OR HIS AUTHORIZED REPRESENTATIVE. PHYSICAL

WORK CANNOT START UNTIL THE ACCIDENT PREVENTION PLAN, CONTRACTOR

QUALITY CONTROL PLAN, AND OTHER SUBMITTALS WHICH MAY BE

REQUIRED, HAVE BEEN SUBMITTED AND APPROVED AND ALL PRELIMINARY

MEETINGS CALLED FOR UNDER THE CONTRACT, HAVE BEEN CONDUCTED.

(O) ALL WORK UNDER THESE SPECIFICATIONS SHALL BE PERFORMED IN

ACCORDANCE WITH THE PROVISIONS OF EM 385-1-1 "CORPS OF ENGINEERS

SAFETY AND HEALTH REQUIREMENTS MANUAL", DATED NOVEMBER 2014.

(P) THE GOVERNMENT RESERVES THE RIGHT, AS THE INTERESTS OF THE

GOVERNMENT MAY REQUIRE, TO POSTPONE OR DELAY THE DATE AND/OR

TIME SET FOR OPENING BIDS. REVISIONS OR AMENDMENTS TO THE BID

OPENING DATE AND/OR TIME, IF ANY, WILL BE ANNOUNCED BY AMENDMENT

OR AMENDMENTS TO THIS INVITATION FOR BIDS.

(Q) VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS

CONTRACTS

IN ADDITION TO COMPLYING WITH THE REQUIREMENTS OUTLINED IN FAR

PART 22.13, FAR PROVISION 52.222-38, FAR CLAUSE 52.222-35, FAR

CLAUSE 52.222-37, DFARS 222.13 AND DEPARTMENT OF LABOR

REGULATIONS, U.S. ARMY CORPS OF ENGINEERS (USACE) CONTRACTORS

AND SUBCONTRACTORS AT ALL TIERS ARE ENCOURAGED TO PROMOTE THE

TRAINING AND EMPLOYMENT OF U.S. VETERANS WHILE PERFORMING UNDER

A USACE CONTRACT. WHILE NO SET-ASIDE, EVALUATION PREFERENCE, OR

INCENTIVE APPLIES TO THE SOLICITATION OR PERFORMANCE UNDER THE

RESULTANT CONTRACT, USACE CONTRACTORS ARE ENCOURAGED TO

SEEK OUT HIGHLY QUALIFIED VETERANS TO PERFORM SERVICES UNDER

THIS CONTRACT. THE FOLLOWING RESOURCES ARE AVAILABLE TO ASSIST

USACE CONTRACTORS IN THEIR OUTREACH EFFORTS:

- U.S. DEPARTMENT OF LABOR VETERANS’ EMPLOYMENT AND TRAINING

SERVICE (VETS):

HTTPS://WWW.DOL.GOV/VETS/

- FEDERAL VETERAN EMPLOYMENT INFORMATION:

HTTPS://WWW.FEDSHIREVETS.GOV/

- VETERANS OPPORTUNITY TO WORK (VOW) PROGRAM:

HTTPS://WWW.BENEFITS.VA.GOV/VOW/

- U.S. ARMY WARRIOR TRANSITION COMMAND EMPLOYMENT INDEX:

HTTPS://WCT.ARMY.MIL/MODULES/EMPLOYERS/INDEX.HTML

Revised by Amendment 0001 https://www.dol.gov/vets/ https://www.fedshirevets.gov/ https://www.benefits.va.gov/vow/ https://wct.army.mil/modules/employers/index.html

- HIRING OUR HEROES: HTTPS://WWW.USCHAMBERFOUNDATION.ORG/HIRING-

OUR-HEROES

(END OF SPECIAL CONTRACT REQUIREMENT)

Revised by Amendment 0001 https://www.uschamberfoundation.org/hiring-our-heroes https://www.uschamberfoundation.org/hiring-our-heroes

W912EE-20-B-0008

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 80 00.00 09

SPECIAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

1.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

1.3 LIQUIDATED DAMAGES-CONSTRUCTION

1.4 CONTRACT DRAWINGS AND SPECIFICATIONS

1.5 CORRESPONDENCE AND ELECTRONIC COMMUNICATION

1.6 WORK TO BE PERFORMED BY CONTRACTOR'S OWN ORGANIZATION

1.7 PHYSICAL DATA

1.8 PAYMENT FOR MOBILIZATION AND DEMOBILIZATION

1.9 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE

1.10 OBSTRUCTION OF NAVIGABLE WATERWAYS

1.11 SECURITY REQUIREMENTS FOR UNCLASSIFIED CONTRACTS

1.12 I-WATCH

1.13 ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES

1.14 SECURITY CLEARANCE/ACCESS PRIVILEGES

1.15 PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM

1.16 FOREIGN NATIONALS WORKING ON GOVERNMENT CONTRACTS

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section Table of Contents --

DOCUMENT 00 80 00.00 09 Page 1 Revised By Amendment 0001

SECTION 00 80 00.00 09

SPECIAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EP-1110-1-8 (2009) Construction Equipment Ownership and Operating Expense Schedule

1.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 455 calendar days after the date the Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises. (FAR 52.211-10)

The NTP will be issued immediately after verification of bonds. Within seven (7) calendar days after issuance of the NTP, the Contractor shall initiate a meeting to discuss the submittal process with the Area or Resident Engineer or his authorized representative.

In the event that Optional Work Items (Items 0006 through 0012) are exercised under the terms of the contract, the time required for completion of the contract will be extended by a duration of 320 calendar days.

1.3 LIQUIDATED DAMAGES-CONSTRUCTION

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,175 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause. (FAR 52.211-12)

1.4 CONTRACT DRAWINGS AND SPECIFICATIONS

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall --

DOCUMENT 00 80 00.00 09 Page 2 Revised By Amendment 0001

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general --

(1) Large-scale drawings shall govern small scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and the contract drawings identified on the INDEX TO DRAWINGS shown on Drawing No.

G-002 entitled PROJECT LOCATION AND VICINITY MAPS, File No. YT-15-54.

(DFARS 252.236-7001)

1.5 CORRESPONDENCE AND ELECTRONIC COMMUNICATION

For ease and speed of communications, both the Government and Contractor shall exchange correspondence and all other documents duplicate in both hard paper copy and electronic format. Inclusion of an electronic copy is in addition to any other parts of the contract that may specify a minimum number of hard copies to be submitted, such as for shop drawing transmittals. Electronic submission can be accomplished by one of the following methods: email, file upload to the following website https://safe.amrdec.army.mil/SAFE, or through the Quality Control System (QCS) software interface with the Resident Management System (RMS).

Format for electronic submissions will be in portable document format (.pdf). File naming will be determined by the Contracting Officer and presented at the Preconstruction Conference. Documents include all general correspondence, administrative plans, all material submittals including shop drawings, progress schedules, submittal registers, requests for information (RFIs), Quality Control (QC) test results, pay requests, etc. Paper documents will govern, in the event of discrepancy with the electronic version. Generally, paper documents will also govern where effective receipt dates are required, such as contractor claims submitted under the Disputes clause of the contract and progress payment requests.

However in the case of administrative plans, shop drawings and other submittals transmitted for government review, both the electronic and hard copies are required to begin the review process, so the effective date of

DOCUMENT 00 80 00.00 09 Page 3 Revised By Amendment 0001 receipt will be the date when both the electronic and hard copies are received by the government.

1.6 WORK TO BE PERFORMED BY CONTRACTOR'S OWN ORGANIZATION

Within 10 days after award, the successful Bidder/Contractor must furnish the Contracting Officer a description of the items of work which will be performed with its own forces and the estimated cost of those items. (See Contract Clause NOTICE OF TOTAL HUBZONE SET-ASIDE.)

1.7 PHYSICAL DATA

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by surveys.

(b) Weather Conditions. Information with respect to temperatures and precipitation may be obtained from the National Weather Service.

(c) Transportation Facilities.

(1) Roads. Interstate 55, U.S. Highway No. 49, Mississippi State Highway No. 32, and local roads serve the general area.

(2) Railroads. The Contractor is responsible for determining the availability of railroad service.

(3) Water Routes. The Yazoo River serves points below the site of work. The Government does not guarantee dependable navigation on the Yazoo River. Periods of low water can limit or stop navigation. Periods of high water in combination with the elevations of the low steel of bridges on the Yazoo River may also limit or stop navigation. The Contractor's inability to navigate these waters or move his plant, materials or equipment shall not form the basis for a claim against the Government. The Government does not guarantee and in no way means to imply that the Contractor will be able navigate the Tallahatchie River or move his floating plant, materials or equipment to the site of work via the Yazoo and Tallahatchie Rivers.

(d) River Stages. Stage hydrographs for the Tallahatchie River at the Locopolis, Mississippi gage are shown on the contract drawings.

The Contractor is advised that in January 1981, the Interim Water Control Plan was implemented for the Yazoo Basin lakes. This plan enables greater flood prevention measures to be obtained in the Yazoo Basin. The Contractor is also advised that no modification to the normal operation of the Yazoo Basin lakes will be made to accommodate this work. A more complete history of river stages is available for inspection at the U.S. Army Engineer District, Vicksburg, Mississippi.

(e) Channel Traffic. Traffic on the Yazoo River consists of tugs, barge tows and small boats.

(f) Obstruction of Channel. The Government will not undertake to keep the channel free from vessels or other obstructions except to the

DOCUMENT 00 80 00.00 09 Page 4 Revised By Amendment 0001 extent of such regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act approved 8 August 1917. The Contractor will be required to conduct the work in such manner as to obstruct navigation as little as possible, and in case the Contractor's plant so obstructs the channel as to make difficult or endanger the passage of vessels, said plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford a practicable passage. Upon completion of the work, the Contractor shall promptly remove his plant, including buoys, piles, and other markers placed by him under the contract in navigable water or on shore.

(g) Low Steel of Bridges. The elevation of the low steel of each of the Yazoo River bridges downstream from the work site is shown below in tabular form. These bridges (except for the fixed bridges as noted below) are either turn or lift type. The Contractor is responsible for contacting the bridge owners as to the operability of the bridges.

LOCATION RIVER MILE BRIDGE LOW STEEL ELEVATION

IN FT., NGVD

Redwood 16.7 ICRR 103.6

Redwood 17.4 U.S. Hwy 61 152.5 (Fixed Bridge)

Satartia 53.3 MS Hwy 433 113.8

Yazoo City 75.5 U.S. Hwy 49W 158.4 (Fixed Bridge)

Yazoo City 83.0 ICRR 107.0

Belzoni 116.9 U.S. Hwy 12 159.2 (Fixed Bridge)

Silent Shade 132.0 U.S. Hwy 49 119.0

Phillipstown 149.7 Leflore County Rd. 134.5 (Fixed Bridge)

Sanders-Hooper 154.1 Leflore County Rd. 170.9 (Fixed Bridge)

Fort Loring 160.9 ICRR 133.6 (Operable)

Greenwood 164.9 U.S. Hwy 82 and 49E 134.9 (Fixed Bridge)

Greenwood 166.0 U.S. Hwy 49E 136.4 (Fixed Bridge) (Grand Ave.)

Greenwood 166.2 Poplar St. 136.0 (Fixed Bridge)

Greenwood 170.2 Ashwood Br. 139.0 (Fixed Bridge)

DOCUMENT 00 80 00.00 09 Page 5 Revised By Amendment 0001

Shellmound 188.5 Leflore County Rd. 139.6 (Fixed Bridge)

Money 192.9 Leflore County Rd. 138.26 East End (Fixed Bridge) 139.0 West End

Phillip Cutoff 202.6 MS Hwy 8 139.6 (Fixed Bridge)

Philipp 205.0 I.C.G. R.R. Bridge 163.0

Swan Lake 219.1 Tallahatchie Co. 170.0 (Fixed Bridge)

Locopolis 230.7 MS Hwy 32 (Fixed Bridge)

(h) Floods.

Floods. High water stages or events are not to be considered a "flood," and damages resulting therefrom are not compensable under Section 01 00 00.00 09 GENERAL CONTRACT REQUIREMENTS, paragraph DAMAGE TO WORK unless river or stream stages exceed channel capacity and overtop the natural or artificial banks. Channel excavation and all work incidental thereto and within the original and/or new top bank of the channel enlargement are not to be considered compensable resulting from any alleged damages associated with a "flood" under the paragraph herein or Section 01 00 00.00 09 GENERAL CONTRACT REQUIREMENTS, paragraph DAMAGE TO

WORK.

(e) Additional Data. Additional data consisting of additional cross sections, records of borings, and boring samples are available for inspection at:

U.S. Army Engineer District, Vicksburg 4155 Clay Street

Vicksburg, Mississippi 39183-3435

(FAR 52.236-4)

1.8 PAYMENT FOR MOBILIZATION AND DEMOBILIZATION

(a) The Government will pay all costs for the mobilization and demobilization of all of the Contractor's plant and equipment at the contract lump sum price for this item.

(1) Sixty percent of the lump sum price upon completion of the Contractor's mobilization at the work site.

(2) The remaining forty percent upon completion of demobilization.

(b) The Contracting Officer may require the Contractor to furnish cost data to justify this portion of the bid if the Contracting Officer believes that the percentages in subparagraphs (a)(1) and (2) of this clause do not bear a reasonable relation to the cost of the work in this contract.

(1) Failure to justify such price to the satisfaction of the

DOCUMENT 00 80 00.00 09 Page 6 Revised By Amendment 0001

Contracting Officer will result in payment, as determined by the Contracting Officer, of--

(i) Actual mobilization costs at completion of mobilization;

(ii) Actual demobilization costs at completion of demobilization;

and

(iii) The remainder of this item in the final payment under this contract.

(2) The Contracting Officer's determination of the actual costs in paragraph (b)(1) of this clause is not subject to appeal.

(DFARS 252.236-7004)

1.9 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE

(a) This special contract requirement does not apply to terminations. See 52.249-500, Basis for Settlement of Proposals and FAR Part 49.

(b) Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a Contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the Contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region III.

Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the Contracting Officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.

(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36, Rental Costs. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.

(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the SAT, the contracting officer shall request the Contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.

(USACE Acquisition Instruction ("UAI") 31.105-101)

DOCUMENT 00 80 00.00 09 Page 7 Revised By Amendment 0001

NOTE: EP-1110-1-8 , "Construction Equipment Ownership and Operating Expense Schedule" is available on the Internet at http://www.publications.usace.army.mil/USACEPublications/EngineerPamphlets.aspx, then search for EP 1110-1-8, then click on the link and then choose EP_1110-1-8_Vol-03.pdf or may be purchased from the Government Printing Office on CD-ROM by calling (202) 512-1800.

1.10 OBSTRUCTION OF NAVIGABLE WATERWAYS

(a) The Contractor shall-

(1) Promptly recover and remove any material, plant, machinery, or appliance which the Contractor loses, dumps, throws overboard, sinks, or misplaces, and which, in the opinion of the Contracting Officer, may be dangerous to or obstruct navigation;

(2) Give immediate notice, with description and locations of any such obstructions, to the Contracting Officer; and

(3) When required by the Contracting Officer, mark or buoy such obstructions until the same are removed.

(b) The Contracting Officer may--

(1) Remove the obstructions by contract or otherwise should the Contractor refuse, neglect, or delay compliance with paragraph (a) of this clause; and

(2) Deduct the cost of removal from any monies due or to become due to the Contractor; or

(3) Recover the cost of removal under the Contractor's bond.

(c) The Contractor's liability for the removal of a vessel wrecked or sunk without fault or negligence is limited to that provided in Sections 15, 19, and 20 of the River and Harbor Act of March 3, 1899 (33 U.S.C. 410 et. seq). (DFARS 52.236-7002)

1.11 SECURITY REQUIREMENTS FOR UNCLASSIFIED CONTRACTS

All Contractor employees (U.S. citizens and Non- U.S. citizens) working under this contract who require access to Automated Information Systems (AIS), (stand alone computers, network computers/systems, e-mail) shall, at a minimum, be designated into an ADP-III position (non-sensitive) in accordance with DoD 5220-22-R, Industrial Security Regulation. The investigative requirements for an ADP-III position are a favorable National Agency Check (NAC), SF-85P, Public Trust Position. The Contractor shall have each applicable employee complete a SF-85P and submit to the Security Officer, ATTN: CEMVK-PM, 4155 Clay Street, Vicksburg, MS 39183-3435 within three (3) working days after award of any contract or task order, and shall be submitted prior to the individual being permitted access to an AIS. Contractors that have a commercial or government entity (CAGE) Code and Facility Security Clearance through the Defense Security Service shall process the NACs and forward visit requests/results of NAC to the Security Officer, ATTN: CEMVK-PM, 4155 Clay Street, Vicksburg, MS 39183-3435. For those Contractors that do not have a CAGE Code or Facility Security Clearance, Security Officer, ATTN:

CEMVK-PM, 4155 Clay Street, Vicksburg, MS 39183-3435 Security Office will process the investigation in coordination with the Contractor and contract

DOCUMENT 00 80 00.00 09 Page 8 Revised By Amendment 0001 employees.

1.12 I-WATCH

The Contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.

1.13 ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES

All Contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The Contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in Contractor security matters or processes.

1.14 SECURITY CLEARANCE/ACCESS PRIVILEGES

All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.

1.15 PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM

The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.

1.16 FOREIGN NATIONALS WORKING ON GOVERNMENT CONTRACTS

In order for a foreign national to be permitted to work on a Government contract, the Contractor must submit a letter requesting such to the Foreign Disclosure Officer (FDO). The FDO will conduct a disclosure review and provide a recommendation to the Contracting Officer. If the request is approved, the foreign national must be escorted at all times

DOCUMENT 00 80 00.00 09 Page 9 Revised By Amendment 0001 while on a Government property or work site. Letters should be mailed to Foreign Disclosure Officer (Carol Bridges), ATTN: CEMVK-PM, 4155 Clay Street, Vicksburg, MS 39183

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section --

DOCUMENT 00 80 00.00 09 Page 10 Revised By Amendment 0001

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 00 00.00 09

GENERAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

1.2 PARTNERING

1.3 RIGHTS-OF-WAY

1.4 SURVEYS AND LAYOUT FOR CONSTRUCTION

1.5 LAYOUT AND MARKING OF RIGHTS-OF-WAY

1.6 PRECONSTRUCTION CONFERENCE

1.7 SUBMITTAL OF SUBCONTRACTING PLAN

1.8 NOTIFICATION OF AREA ENGINEER BEFORE BEGINNING WORK

1.9 ORDER OF WORK

1.10 SUSPENSION OF WORK OR REMOVAL OF EQUIPMENT

1.11 PROGRESS CHART

1.12 DESIGNATED BILLING OFFICE

1.13 PAYMENT INVOICES

1.14 TEMPORARY PROJECT FENCING

1.15 AS-BUILT DRAWINGS

1.16 PROJECT SIGN

1.17 MINIMUM REQUIRED INSURANCE

1.18 WORK IN QUARANTINED AREA

1.19 CERTIFICATES OF COMPLIANCE

1.20 PROCESS FOR OBTAINING CURRENT REQUIREMENTS OF THE U.S. ARMY CORPS

OF ENGINEERS SAFETY AND HEALTH REQUIREMENTS MANUAL (EM 385-1-1)

1.21 SAFETY SIGN

1.22 ACCIDENT PREVENTION PLAN

1.23 DAILY INSPECTIONS

1.24 ACCIDENT INVESTIGATIONS AND REPORTING

1.25 ACCOMMODATIONS FOR GOVERNMENT REPRESENTATIVES

1.26 MACHINERY AND MECHANIZED EQUIPMENT

1.27 VEHICLE WEIGHT LIMITATIONS

1.28 PUBLIC AND PRIVATE UTILITIES

1.29 DAMAGE TO WORK

1.30 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

1.31 CONTROL OF ACCESS TO CONSTRUCTION AREAS

1.32 MAINTENANCE OF TRAFFIC

1.33 HARBOR MAINTENANCE FEE

1.34 MEANS OF ESCAPE FOR PERSONNEL QUARTERED OR WORKING ON FLOATING

PLANT

1.35 VIDEO AND PHOTOGRAPHIC DOCUMENTATION

1.36 EMERGENCY ALARMS AND SIGNALS

1.37 SIGNAL LIGHTS

1.38 INSPECTION

1.39 FINAL EXAMINATION AND ACCEPTANCE

1.40 ACCEPTANCE OF COMPLETED WORK

1.41 COOPERATION WITH OTHER CONTRACTORS

SECTION 01 00 00.00 09 Page 1 Revised By Amendment 0001

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section Table of Contents --

SECTION 01 00 00.00 09 Page 2 Revised By Amendment 0001

SECTION 01 00 00.00 09

GENERAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

19 CFR 24.24 Harbor Maintenance Fee

33 CFR 156 Oil and Hazardous Material Transfer Operations

1.2 PARTNERING

The Government encourages formation of informal project partnerships on all projects. A project partnership strives to utilize a cooperative working relationship to jointly establish and effectively reach mutual project execution goals. The partnering process will in no way relax or stiffen the requirements of the contract, but will enhance the likelihood of success through improved working relationships and joint risk management. The possibility of an informal partnership may be discussed at the Pre-construction Conference for this project.

1.3 RIGHTS-OF-WAY

a. The rights-of-way for Contractor performance under this contract, within the limits indicated on the drawings, will be provided by the Government without cost to the Contractor. It is the Contractor's responsibility to carefully review and determine the scope of the rights-of-way. Any questions should be clarified with the Government prior to use. If these rights-of-way are used by the Contractor, he shall, at his own expense, do all work necessary to make such rights-of-way suitable for safe travel to and from the worksite. Upon completion of the Contractor's work, any such rights-of-way furnished by the Government shall be left in a condition satisfactory to the Contracting Officer.

b. When so directed by the Contracting Officer, the Contractor shall, without expense to the Government, promptly vacate and clean up any part of the Government grounds or rights-of-way that have been allotted to or have been in use by the Contractor.

c. The Contractor shall not obstruct any existing roads or any other means of existing ingress or egress on lands controlled by the United

SECTION 01 00 00.00 09 Page 3 Revised By Amendment 0001

States except with written permission of the Contracting Officer and shall maintain such roads and other means of ingress or egress in as good condition as exists at the time of commencement of work performance under this contract.

d. The Contractor shall procure, without expense to the Government, all additional lands, access roads, rights-of-way, and any other property rights necessary for his use in the performance of the work or as required by his method of operation. The Contractor shall provide the Contracting Officer with an authenticated copy of the conveyance under which the Contractor acquired such property rights, prepared and executed in accordance with the laws of the State in which the land is located. The Contractor shall also obtain from the property owners and present to the Contracting Officer a release of all claims against the Government which may result from the Contractor's use or possession of such real estate or property rights. The written conveyance and release shall be provided to the Contracting Officer prior to the Contractor's use of Contactor obtained real estate or property rights. If temporary rights-of-way are obtained by the Contractor the period of time for those rights shall coincide with Section 00 80 00.00 09 SPECIAL CONTRACT REQUIREMENTS, paragraph COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK, plus a reasonable time for any extension granted for the completion of the work. Any agreements or permits with levee boards, counties, parishes, municipalities, or other political subdivisions for moving material and equipment will be the responsibility of the Contractor and shall be obtained at no expense to the Government. Any delays to the Contractor resulting from delays in procuring access roads, rights-of-way, permits, or other real estate and property rights necessary for moving material and equipment for his work under this contract will not be a basis for any claim for increase in the cost of this contract. The Contractor shall make his own investigations to determine the conditions, restrictions and difficulties which may be encountered in acquiring such real estate, rights-of-way, or other property rights and in the transportation of material and equipment. The Contractor is responsible for identifying and requesting any required revisions to the stormwater permit, installation and maintenance of required BMPs, and necessary reports as required by the state. The contractor shall inform the government of any additional property rights planned for use under this contract prior to assuming any work associated with or on the additional property. The Government shall coordinate review of the additional property rights with state, local, and tribal entities to ensure cultural clearance prior to the Contractor's use of the area. Prior to approval from the Contracting Officer or other authorized individual, additional land usage that requires extensive clearing or disturbance shall be avoided especially if existing right of ways are sufficient to accomplish the required work. Use of property that violates any terms or requirements of existing project environmental or cultural clearances will not be allowed. The Contractor shall be solely liable for any and all damages and claims of any nature whatsoever arising from, related to, or growing out of the acquisition and use of this real estate, rights-of-way, property rights, etc.

e. Notwithstanding any language or drawings to the contrary in this contract, the United States will not provide access or rights-of-way over any public lands and will not be responsible for acquiring such.

f. The Contractor shall repair at no expense to the Government, any

SECTION 01 00 00.00 09 Page 4 Revised By Amendment 0001 and all damage to any existing roads or other means of existing ingress or egress when such damage is a result of his operations under this contract.

g. Right of Way shown on the contract drawings including that which is noted or intended for access purposes is not guaranteed by the Governmnent to be suitable for the contractor's operation and may require improvements by the contractor for access purposes and construction operations.

1.4 SURVEYS AND LAYOUT FOR CONSTRUCTION

All requirements outlined herein are subject to the acceptance of the contracting officer. The contractor shall be required to use competent personnel and suitable equipment for the layout work required and shall provide that all work be performed under the direct supervision of, or directly by, a registered professional surveyor that is duly licensed and entitled to practice surveying in the state of contract performance to perform the following:

a. Perform all calculations and other work as necessary to establish and/or verify all horizontal and vertical control data; and furnishing, placing and maintaining construction stakes, necessary for the proper prosecution of all features and items of work under this contract. All control monuments provided by the Government shall be field verified prior to commencement of construction activities. The contractor's surveyor shall be required to document any discrepancies discovered and any additional control that is required to facilitate construction activities. This information shall be submitted in writing to the Contracting Officer prior to initiating construction activities.

b. Layout and mark the right-of-way limits as described in paragraph

LAYOUT AND MARKING OF RIGHTS-OF-WAY.

c. Perform all necessary surveys for verification and backup for progress payments and certify all quantities for progress pay estimates as required by contract requirements and as determined by the Contracting Officer.

d. Perform all final Quality Control surveys required for final acceptance.

e. All partial and final surveys shall consist of cross sections conducted every 100 feet above and below the water surface. Cross sections conducted above the water surface shall consist of shots taken no more than 25 feet (horizontal distance) between points and at all catch points (slope intersections, ditches, and any other features deemed necessary, as determined by the contracting officer). Cross sections below the water surface shall be conducted using hydrographic survey equipment or other acceptable means as determined by the contracting officer. Cross Sectional data shall be mapped and electronically plotted at a horizontal and vertical scale of 1:20 with the channel centerline laid out and shown, as on the typical cross sections in the contract drawings. A sufficient horizontal and vertical scale, as determined by the Contracting Officer, shall be shown ascending from zero at the channel centerline in the horizontal direction (with positive values to the right of center reflecting the right descending riverbank and negative numbers to the left of center

SECTION 01 00 00.00 09 Page 5 Revised By Amendment 0001 representing the left descending riverbank) and ascending from just below the existing thalweg of the channel, elevation(s) in the vertical direction.

f. All survey, quantity and mapping submissions shall contain PLS certification stamp and signature.

g. No separate measurement or payment shall be made for work required under SURVEYS AND LAYOUT FOR CONSTRUCTION.

1.5 LAYOUT AND MARKING OF RIGHTS-OF-WAY

The Contractor shall layout and mark the rights-of-way limits as indicated on the drawings prior to beginning any other work, unless otherwise approved. The marking shall be placed at intervals approved by the Contracting Officer. The rights-of-way limits shall be marked by stakes, flagging or other approved means. The marking shall be highly visible from a distance of at least 100 feet, and shall be maintained for the duration of the contract. If the rights-of-way marking should fade significantly in color, become damaged or lost as a result of the Contractor's operation or as a result of vandalism, or in any other way cease to function as a highly visible marker of the rights-of-way limits, the Contractor shall layout and restore the marking to the original condition. After all work is complete and upon approval of the Contracting Officer, the Contractor shall remove all marking. No separate payment will be made for layout, marking and maintaining the rights-of-way limits or for removing the marking.

1.6 PRECONSTRUCTION CONFERENCE

a. A preconstruction conference will be arranged by the Area Engineer as soon after contract award as possible, and the conference will be conducted before work is allowed to commence. The Area Engineer will notify the Contractor of the time, date, and location for the meeting. At this conference, the Contractor will be oriented with respect to contract administration procedures, lines of authority, opportunity for formation of project partnerships including joint risk management, and construction matters. All known subcontractors performing at least 20 percent of the contract are required to attend this conference. Additional conferences may be established by the Area Engineer for any major subcontractors unknown at the time of the initial conference.

b. Submission by the Contractor of the items listed below will determine the date of the conference. The following items shall be submitted to the Area Engineer in hard copy and electronic (pdf) format for review at least seven (7) calendar days prior to the preconstruction conference:

(1) Accident Prevention Plan

(2) Quality Control Plan

(3) Environmental Protection Plan

(4) Six copies of the certified Large Construction Notice of Intent (LCNOI) for each site

(5) Work Schedule Diagram

SECTION 01 00 00.00 09 Page 6 Revised By Amendment 0001

c. The Contractor shall bring to this conference, in completed form, the following:

(1) Letter of superintendent appointment and authority

(2) List of subcontractors

d. The Contractor should bring to this conference, or at least be prepared to discuss, the following:

Submittal register

e. Minutes of this conference will be taken and prepared by the Area Engineer and sent to the Contractor for his concurrence and signature.

1.7 SUBMITTAL OF SUBCONTRACTING PLAN

a. This paragraph does not apply to small business concerns.

b. After bid opening, and within 7 days, the apparent low bidder, upon telephone notification by the Small and Disadvantaged Business Utilization Specialist, shall submit a Small and Disadvantaged Business Subcontracting Plan. The plan shall be submitted in accordance with the Contract Clauses SMALL BUSINESS SUBCONTRACTING PLAN - ALTERNATE I. The person responsible for administering the plan shall be named in paragraph AGENT FOR SUBMITTING SMALL BUSINESS SUBCONTRACTING PLAN of the Representations and Certifications.

1.8 NOTIFICATION OF AREA ENGINEER BEFORE BEGINNING WORK

At least 7 days before beginning work, and at least one day before resuming work after a period of 7 days or more when no work has been performed, the Contractor shall notify U.S. Army Corps of Engineers, Mr.

Jason Overstreet, Area Engineer, Greenwood Area Office, 100 Moore Street, Greenwood, Mississippi 38930-4512, telephone (662) 455-0247 .

1.9 ORDER OF WORK

The work shall be carried on in accordance with the Progress Chart (schedule) required by paragraph (a) of the Contract Clause SCHEDULES FOR CONSTRUCTION CONTRACTS. In preparing the Progress Chart (schedule), the Contractor shall adhere to the following order of work:

a. Prior to any other work, the existing Perimeter Ditch of Disposal Area 7D-V1-1 shall be cleaned out and regraded. See sheet C-105.

b. Channel excavation operations, including hydraulic dredge excavation, land based excavation and hauling, and combinations thereof, shall commence at the upper limit of the base contract channel work just downstream of Highway 32 Bridge and proceed continuously downstream to the lower limit of the channel work.

c. Upon execution of Optional Work Item 1, the Contractor shall not demobilize any of his dredging operation from the reach included in the base contract until channel excavation for that reach has been completed. However, he will be allowed to begin development of Disposal Area 7D-V2-1 provided that he has the capability to work in both locations concurrently with adequate personnel to ensure both

SECTION 01 00 00.00 09 Page 7 Revised By Amendment 0001 quality and safety are maintained.

d. Upon execution of Optional Work Item 1, channel excavation operations on the Optional Work Item reach shall commence at the upper limit of the channel excavation work just downstream of Sheley Road Bridge and proceed continuously downstream to the lower limit of the channel work.

e. All channel excavation associated with optional work item 1 that occurs on the left descending bank using land based excavation equipment shall be deposited in Disposal Area 7D-V2-2 subject to the limitations described in Section 31 23 17.00 09 DISPOSAL OF EXCAVATED MATERIAL, paragraph "Disposal Area 7D-V2-2 Initial Preparation".