Amendment_0001_Solicitation_W912EE20B0002.pdf

PDF 2 MB Posted

Attached to
Concordia Parish, Louisiana, MRL Item 329-R Seepage Remediation, F/C, MR&T WBMRL, Black Hawk, Louisiana
Solicitation number
W912EE20B0002
Issued by

About this file

This solicitation is for a firm-fixed-price construction contract to perform seepage remediation work at Black Hawk, Louisiana. The work includes installing relief wells, mobilization and demobilization, clearing and grubbing, turf maintenance, erosion control, and other features. The estimated value is between $5 million to $10 million. The period of performance is 180 calendar days from notice to proceed.

The solicitation was issued by the U.S. Army Corps of Engineers, Vicksburg District as invitation for bid W912EE20B0002. The NAICS code is 237990 and size standard is $39.5 million. The set-aside is 100% for small businesses. Bids were due by January 30, 2020 at the Corps' office in Vicksburg, Mississippi, though the notice indicates bids will not be opened until rights-of-way are obtained. The Corps intends to award without discussions to the lowest priced, responsible bidder meeting the criteria in the solicitation. The solicitation and plans are available electronically only on SAM.gov.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Reference Solicitation No. W912EE20B0002 for Concordia Parish, Louisiana, MRL Item 329-R Seepage Remediation, FC/MR&T WBMRL, Black Haw k, Louisiana, scheduled to open 30 January 2020 at 2:00 P.M. CDT. This solicitation is amended as follow s:

See Continuation Page for Summary of Changes.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 10

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 27-Jan-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912EE20B0002

X 9B. DATED (SEE ITEM 11)

27-Dec-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

27-Jan-2020

CODE

VICKSBURG CONTRACTING OFFICE

4155 CLAY ST

VICKSBURG MS 39183-3435

W912EE 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912EE20B0002

W912EE20B0002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

SUMMARY OF CHANGES

BID OPENING DATE: Bids for Solicitation W912EE20B0002 will not be opened by 1400 hours local time on 30 January 2020.

The bid opening date and time has been delayed indefinitely. A new bid opening date and time will be established by amendment at a future date.

Number 13.A. of the SF 1442 now states, “Sealed offers in original to perform the work required are due at the place specified in Item 8 by TBD (hour) local time TBD (date).”

RIGHT-OF-WAY: Right-of-Way is available.

SF 1442: The number of completion days has changed from 180 calendar days to 220 calendar days.

Number 11 of the SF 1442 now states, “The Contractor shall begin performance within 10 calendar days and complete it within 220 calendar days after receiving notice to proceed.”

SPECIFICATIONS: Section 00 80 00.00 09 is revised and replaced.

Specifications revised by this amendment have the notation "Revised by Amendment 0001" at the bottom of the page. Text added by this amendment is shown as underlined. Text deleted by this amendment is shown as overstruck.

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time 30-Jan-2020 02:00 PM has been deleted.

The contractor period of performance end date has increased by 40 days from 180 days to 220 days.

(End of Summary of Changes)

CONCORDIA PARISH, LOUISIANA,

MRL ITEM 329-R SEEPAGE REMEDIATION,

FC/MR&T WBMRL, BLACK HAWK, LOUISIANA

DESCRIPTION OF WORK: The work consists of furnishing all plant, labor, materials and equipment for the installation of relief wells in Concordia Parish, Louisiana. Principle features of the work include, but are not limited to mobilization and demobilization, clearing and grubbing, relief wells, existing turf maintenance, new turf establishment, storm water pollution prevention, and environmental protection features.

The estimated value of the proposed work is between $5,000,000.00 and $10,000,000.00.

FRETESHIA L. JOHNSON

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

(601)631-5219

SEE SPECIAL NOTICES TO BIDDERS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED ( RFP)

3. DATE ISSUED

19-Dec-2019

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by

GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance within 10 calendar days and complete it within 180 220 calendar days after receiving award, X notice to proceed. This performance period is mandatory, negotiable. ( See Section 00 80 00.00 09

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original to perform the work required are due at the place specified in Item 8 by 1400 (hour) local time 30 January 2020 IIf this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than ___60 ____ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

VICKSBURG DISTRICT CONTRACTING OFFICE

4155 CLAY STREET ROOM 120

VICKSBURG MS 39183-3435

W912EE

PAGE

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO.

W807PM93311050

6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

(601)631-7261 FAX: TEL: TEL: FAX:

1. SOLICITATION NO.

W912EE20B0002

X

X

(date).

W912EE20B0002

THIS SOLICITATION CONTAINS DEFINITIVE RESPONSIBILITY CRITERIA AS A PRECONDITION TO AWARD (SEE

THE DETERMINATION OF RESPONSIBILITY REQUIREMENTS PAGE BELOW).

Revised By Amendment 0001

TBD

TBD

W912EE20B0002

B4EDGDML

Cross-Out b4oc9flj Cross-Out b4oc9flj Cross-Out

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 80 00.00 09

SPECIAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

1.2 LIQUIDATED DAMAGES-CONSTRUCTION

1.3 EXCEPTION TO LIQUIDATED DAMAGES

1.4 CONTRACT DRAWINGS AND SPECIFICATIONS

1.5 CORRESPONDENCE AND ELECTRONIC COMMUNICATION

1.6 WORK TO BE PERFORMED BY CONTRACTOR'S OWN ORGANIZATION

1.7 PHYSICAL DATA

1.8 PAYMENT FOR MOBILIZATION AND DEMOBILIZATION

1.9 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE

1.10 SECURITY REQUIREMENTS FOR UNCLASSIFIED CONTRACTS

1.11 ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES

1.12 PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM

1.13 FOREIGN NATIONALS WORKING ON GOVERNMENT CONTRACTS

1.14 I-WATCH

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section Table of Contents --

DOCUMENT 00 80 00.00 09 Page 1 Revised By Amwndment 0001

W912EE20B0002

SECTION 00 80 00.00 09

SPECIAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 180220 calendar days after the date the Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises. (FAR 52.211-10)

The notice to proceed with construction will be issued after receipt and Government verification of the required performance and payment bonds. The contract also requires submission of various pre-work plans and Government approval of those plans as well as various preconstruction meetings prior to commencement of physical work at the site. Notice to proceed will not be delayed to await receipt of these plans. The contract performance time includes adequate time for submission and Government review of the required pre-work plans and all required preconstruction meetings to be conducted after notice to proceed.

1.2 LIQUIDATED DAMAGES-CONSTRUCTION

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $997 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed.

These liquidated damages are in addition to excess costs of repurchase under the Termination clause. (FAR 52.211-12)

1.3 EXCEPTION TO LIQUIDATED DAMAGES

Since the Contractor's obligations specified in Section 32 92 00.00 09 EXISTING TURF MAINTENANCE AND NEW TURF ESTABLISHMENT may extend beyond the completion time specified in paragraph COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK, these periods and the additional work, if required, will be exempt from liquidated damages provided all other work has been completed.

1.4 CONTRACT DRAWINGS AND SPECIFICATIONS

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall --

(1) Check all drawings furnished immediately upon receipt;

DOCUMENT 00 80 00.00 09 Page 2 Revised By Amwndment 0001

W912EE20B0002

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general --

(1) Large-scale drawings shall govern small scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and the contract drawings identified on the INDEX TO DRAWINGS.

(DFARS 252.236-7001)

1.5 CORRESPONDENCE AND ELECTRONIC COMMUNICATION

For ease and speed of communications, both the Government and Contractor shall exchange correspondence and all other documents duplicate in both hard paper copy and electronic format. Inclusion of an electronic copy is in addition to any other parts of the contract that may specify a minimum number of hard copies to be submitted, such as for shop drawing transmittals. Electronic submission can be accomplished by one of the following methods: email, file upload to the following website https://safe.amrdec.army.mil/SAFE, or through the Resident Management System - Contractor Mode (RMS-CM) software interface with the Resident Management System (RMS). Format for electronic submissions will be in portable document format (.pdf). Documents include all general correspondence, administrative plans, all material submittals including shop drawings, progress schedules, submittal registers, requests for information (RFIs), Quality Control (QC) test results, pay requests, etc.

Paper documents will govern, in the event of discrepancy with the electronic version. Generally, paper documents will also govern where effective receipt dates are required, such as contractor claims submitted under the Disputes clause of the contract and progress payment requests.

However in the case of administrative plans, shop drawings and other submittals transmitted for government review, both the electronic and hard copies are required to begin the review process, so the effective date of receipt will be the date when both the electronic and hard copies are received by the government.

DOCUMENT 00 80 00.00 09 Page 3 Revised By Amwndment 0001

W912EE20B0002

1.6 WORK TO BE PERFORMED BY CONTRACTOR'S OWN ORGANIZATION

Within 10 days after award, the successful Bidder/Contractor must furnish the Contracting Officer a description of the items of work which will be performed with its own forces and the estimated cost of those items.

1.7 PHYSICAL DATA

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by surveys and borings.

(b) Weather Conditions. Information with respect to temperatures and precipitation may be obtained from the National Weather Service.

(c) Transportation Facilities.

(1) Roads. U.S. Highway No. 15 and local roads serve the general area.

(2) Railroads. The Contractor is responsible for determining the availability of railroad service.

(d) Floods.

(1) (1) High water stages or events are not to be considered a "flood," and damages resulting therefrom are not compensable under Section 01 00 00.00 09 GENERAL CONTRACT REQUIREMENTS, paragraph DAMAGE TO WORK unless river or stream stages exceed channel capacity and overtop the natural or artificial banks. High water stages and/or high water events at stages below ordinary top bank of a river or stream are not floods, even if such water reaches the project. For example, water flowing through or over low points in the river or stream bank, such as drains, are not floods.

(e) Additional Data. Additional data consisting of additional cross sections, records of borings, and boring samples are available for inspection at:

U.S. Army Engineer District, Vicksburg 4155 Clay Street

Vicksburg, Mississippi 39183-3435

(FAR 52.236-4)

1.8 PAYMENT FOR MOBILIZATION AND DEMOBILIZATION

(a) The Government will pay all costs for the mobilization and demobilization of all of the Contractor's plant and equipment at the contract lump sum price for this item.

(1) Sixty percent of the lump sum price upon completion of the Contractor's mobilization at the work site.

DOCUMENT 00 80 00.00 09 Page 4 Revised By Amwndment 0001

W912EE20B0002

(2) The remaining forty percent upon completion of demobilization.

(b) The Contracting Officer may require the Contractor to furnish cost data to justify this portion of the bid if the Contracting Officer believes that the percentages in subparagraphs (a)(1) and (2) of this clause do not bear a reasonable relation to the cost of the work in this contract.

(1) Failure to justify such price to the satisfaction of the Contracting Officer will result in payment, as determined by the Contracting Officer, of--

(i) Actual mobilization costs at completion of mobilization;

(ii) Actual demobilization costs at completion of demobilization;

and

(iii) The remainder of this item in the final payment under this contract.

(2) The Contracting Officer's determination of the actual costs in paragraph (b)(1) of this clause is not subject to appeal.

(DFARS 252.236-7004)

1.9 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE

(a) This special contract requirement does not apply to terminations.

See 52.249-5000, Basis for Settlement of Proposals and FAR Part 49.

(b) Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a Contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the Contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region III. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the Contracting Officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.

(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36, Rental Costs. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.

(d) When actual equipment costs are proposed and the total amount of

DOCUMENT 00 80 00.00 09 Page 5 Revised By Amwndment 0001

W912EE20B0002

the pricing action exceeds the SAT, the contracting officer shall request the Contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.

(UAI 31.105-101)

NOTE: EP-1110-1-8, "Construction Equipment Ownership and Operating Expense Schedule" is available on the Internet at http://www.publications.usace.army.mil/USACEPublications/EngineerPamphlets.aspx, then search for EP 1110-1-8, then click on the link and then choose EP_1110-1-8_Vol-03.pdf or may be purchased from the Government Printing Office on CD-ROM by calling (202) 512-1800.

1.10 SECURITY REQUIREMENTS FOR UNCLASSIFIED CONTRACTS

All Contractor employees (U.S. citizens and Non- U.S. citizens) working under this contract who require access to Automated Information Systems (AIS), (stand alone computers, network computers/systems, e-mail) shall, at a minimum, be designated into an ADP-III position (non-sensitive) in accordance with DoD 5220-22-R, Industrial Security Regulation. The investigative requirements for an ADP-III position are a favorable National Agency Check (NAC), SF-85P, Public Trust Position. The Contractor shall have each applicable employee complete a SF-85P and submit to the Security Officer, ATTN: CEMVK-PM, 4155 Clay Street, Vicksburg, MS 39183-3435 within three (3) working days after award of any contract or task order, and shall be submitted prior to the individual being permitted access to an AIS.

Contractors that have a commercial or government entity (CAGE) Code and Facility Security Clearance through the Defense Security Service shall process the NACs and forward visit requests/results of NAC to the Security Officer, ATTN: CEMVK-PM, 4155 Clay Street, Vicksburg, MS 39183-3435. For those Contractors that do not have a CAGE Code or Facility Security Clearance, Security Officer, ATTN: CEMVK-PM, 4155 Clay Street, Vicksburg, MS 39183-3435 Security Office will process the investigation in coordination with the Contractor and contract employees.

1.11 ACCESS AND GENERAL PROTECTION/SECURITY POLICY AND PROCEDURES

All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks or background investigation and to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.

All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.

DOCUMENT 00 80 00.00 09 Page 6 Revised By Amwndment 0001

W912EE20B0002

1.12 PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM

The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award." *When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.

1.13 FOREIGN NATIONALS WORKING ON GOVERNMENT CONTRACTS

In order for a foreign national to be permitted to work on a Government contract, the Contractor must submit a letter requesting such to the Foreign Disclosure Officer (FDO). The FDO will conduct a disclosure review and provide a recommendation to the Contracting Officer. If the request is approved, the foreign national must be escorted at all times while on a Government property or work site. Letters should be mailed to Foreign Disclosure Officer (Carol Bridges), ATTN: CEMVK-PM, 4155 Clay Street, Vicksburg, MS 39183

1.14 I-WATCH

The Contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section --

DOCUMENT 00 80 00.00 09 Page 7 Revised By Amwndment 0001

W912EE20B0002