Complete project Scope of Work

View the file

Other files

File Type Posted
W912EE-17-T-0035_combined_synopsis_.pdf PDF
Bidding_Schedule.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

I. CONTRACT FOR WORK PERTAINING TO REPAIR OF EXISTING WATER

WELLS

1.1 PROJECT SCOPE OF WORK

1.1.1 GENERAL SCOPE OF WORK

There are 6 basic work items associated with this contract as follows:

a. Pump and motor repair or replacement.

b. Electrical repairs (includes installation and replacement of treated posts, panel box, disconnect switches, motor starters, wiring, wiring conduit, and lightning arrestors).

c. Repair or replacement of pond fill lines and butterfly valves.

d. Repair or replacement of drainage pipe.

e. Pump tests and reports.

f. Disposal of refuse and used equipment.

The Contractor shall provide all transportation, labor, equipment, and supplies to perform the basic work items listed above in accordance with the following conditions and in accordance with the State of Mississippi, Office of Land and Water Resources.

1.1.2 Location/Description

The work is located on property owned by the Corps of Engineers and known as Muscadine and Driftwood. The property is located in Washington County east of Avon, Mississippi. The total project area comprises approximately 1,500 acres and was acquired to mitigate construction losses associated with construction of the Upper Yazoo Projects. The area will be primarily operated in October through February of each year to attract waterfowl and other birds associated with moist habitat.

1.1.3 Work Period

Unless restricted by wet weather or other excruciating circumstances, the Contractor shall begin work within 5 days of notice to proceed. Work is permitted 7 days per week.

1.1.4 Detailed Work Description

Work Item

Description of Work

1 Driftwood - Well #12: Replace motor and pump. Wire to meter base. Set pump rotation and put back into service.

2 Muscadine - Well #10: Replace motor and pump. Replace lightening arrestor. Wire to meter base. Set pump rotation and put back into service.

3 Muscadine - Well #15: Replace motor and pump. Replace lightening arrestor. Wire to meter base. Set pump rotation and put back into service.

4 Muscadine - Well #16: Replace motor and pump. Replace lightening arrestor. Wire to meter base. Set pump rotation and put back into service.

5 Muscadine - Well #9: Replace motor and pump. Replace lightening arrestor. Wire to meter base. Set pump rotation and put back into service.

6 Muscadine - Well #9: Replace steel outfall with minimum 4-ft PVC outfall.

7 Muscadine - Well #6: Replace steel outfall with minimum 4-ft PVC outfall.

8 Muscadine – Well #12: Replace steel outfall with minimum 4-ft PVC outfall.

The objective of this contract is to standardize electrical equipment and piping at both locations and to make repairs in a timely manner; as noted in the above table. The contractor shall replace faulty, non-standard parts with parts specified in this contract. The alpha characters noted below represent the ones above in Section 1.1.1.

A. PUMP AND MOTOR REPAIR/REPLACEMENT

Submersible Electric Motor/Pump: Replacement parts shall be a Hitachi Dual Submersible Motor, heavy duty canned, dual voltage type of NEMA design, 3450 RPM. The outside diameter of the unit shall not exceed six inches and connected to a drop pipe that extends beyond the top of the well casing and capable of producing a minimum yield of 500 gallons per minute. The motor shall be capable of continuous operation under water at the specified conditions outlined above.

A suitable thrust bearing shall be incorporated in the lower end of the motor adequate to receive the entire hydraulic thrust load of the pump unit plus the weight of the rotating parts regardless of rotation. The motor shall be 15 HP, have a 1.15 service factor and suitable for use on 460/230 volt, three phase, 60 Hz electrical service. The motor/pump unit shall be positioned within 15’ to 20’ of well bottom.

The motor leads shall be of sufficient length so that they may be spliced above the bowl assembly and the leads shall be protected by a type 304 stainless steel cable guard held in place with stainless steel banding. As the motor leads exit the top of the cable guard it shall be properly protected to prevent damaging or cutting the lead by the cable guard material.

B. ELECTRICAL REPAIRS

Electrical Service Box: The service panel box shall be Square D Well Guard Class 8940 of NEMA Type 3R and will be connected to the electrical service through a visible blade, fused, disconnect switch suitable for irrigation purposes. The motor starter should be a NEMA size 2 (Square D 8502SDO2) with adjustable instantaneous overcurrent protection (Square D Motor Logic Class 9065 Type SS210). The box will have a lightning arresting device installed according to NEC Article 250 Section III and shall be grounded according to NEC Article 675.

The electrical service panel box shall be mounted on an insect and decay resistant (treated) post and have a weather head suited for line connection by the power association. Mounting and post dimensions shall comply with regulations established by Twin County Electric Power Association. Panel boxes shall not be mounted to utility poles owned by the power association.

Cable: Cable shall be sized to limit the voltage drop to no more than 5%. The cable shall have three separate conductors and a ground and shall be included in a single continuous jacketed assembly. The cable should be the length of the discharge pipe plus fifteen feet to extend from the surface plate to the electrical controller. The cable should be adequately secured to the discharge pipe by plastic ties, or other non metallic means, at 10 foot intervals.

C. REPAIR OR REPLACE POND FILL LINES AND BUTTERFLY VALVES

Pipe and Connectors: In no event shall underground pond fill piping be repaired using less than 8 inch Plastic Irrigation Pipe (PIP). A metal or PVC pond valve capable of controlling flow must be secured on the outflow of each fill line. All PVC pipe must be assembled utilizing PVC cleaner and PVC pipe glue. If the disconnection of underground piping is required during well repair or new well installation, the Contractor shall provide all labor, equipment, and supplies to reconnect the piping to the new or repaired well head.

D. REPAIR OR REPLACE POND DRAIN PIPES AND BUTTERFLY VALVES

Pipe and Connectors: In no event shall pond drain piping be replaced using less than 10” PIP.

Steel pipe being replaced shall be excavated and removed from the pond levee. The overall length of the PVC pipe shall be the same length as the steel pipe being removed (+/- 5 feet). The PVC pipe being replaced shall be placed in the approximate location as the pipe being removed.

Each drain pipe shall extend through the levee and approximately 10’ – 15’ on either side of the levee depending on length of pipe being removed. The exterior end of the pipe shall be fitted with a drain T and adjustable valve capable of controlling flow. The drain T shall also be fitted with a stand pipe cut to the length necessary to hold no more than 24” of water on the interior of each pond. The Contractor may be required to fit a slotted pipe on the interior end of the pipe to prevent large debris from clogging the drain pipe but allowing small trash to flow freely.

E. PUMP TESTS AND REPORTS: The Contractor shall make final electrical connections to control panels and if required, the Contractor shall contact the local power association and have service connected upon replacement or installation of new well/pump/motor.

The Contractor shall set pump rotation and test the production (in gallons per minute) of each well. Well draw down and the flow (GPM) will be recorded and provided to a Government representative in the form of a written report.

F. DISPOSAL OF USED PARTS: The Contractor shall be responsible for proper disposal of all excess electrical cable, switches, electrical boxes, pumps, motors, wire coverings, and plastic pipe. The Contractor shall relocate and stockpile all used metal parts (i.e. pipe) to the respective project headquarters facility (i.e. either Muscadine or Driftwood).

2.1 Quality Control/Quality Assurance.

2.1.1 Quality Control. The Contractor shall establish a quality control plan that addresses the contract performance requirements identified in paragraph 8. A copy of the Contractor's Quality Control Plan must be provided to the Contracting Officer for approval before Notice-to-Proceed will be issued. As changes occur, the plan will be updated and provided to the Contracting Officer. The plan shall include, but not be limited to the following:

2.1.1.1. A dated file of all inspections conducted by the Contractor and the action taken.

2.1.1.2. A detailed dated file documenting parts used to make repairs by well and/or pond number.

2.1.1.3. Identify recurring maintenance problems and propose a solution to prevent recurring problems in the infrastructure.

2.2.2. Quality Assurance. The Government will periodically evaluate the Contractor's performance by appointing a representative(s) to monitor performance. The Quality Assurance Representative will evaluate the contractor’s performance through intermittent on-site inspections. The government may inspect each task as completed or increase the number of quality control inspections if called for by repeated failures discovered during quality control inspections. Likewise, the government may decrease the number of inspections if performance dictates.

3. PERFORMANCE REQUIREMENTS.

3.1. Contractor shall begin work on repairs within 5 days of notice to proceed.

3.2. Repairs shall be made using specified standard equipment as described within the scope of work.

3.3. Contractor shall complete repairs within the time period specified in the delivery order.

3.4. Maintain a dated file documenting repairs by well or pond number within each project area.

3.5. The Contractor shall provide the Government with a detailed dated report of all parts used and repairs made by well and/or pond number. This report shall be submitted within 10 days upon completion of work issued in a delivery order.

3.6. Contractor shall be responsible for making repairs to levee tops in the case of “rutting”.

4. SUSTAINABLE ACQUISITION

4.1. Bio-based. The United States Department of Agriculture (USDA) designates certain biobased products for federal procurement and specifies minimum biobased content levels for those products. Any designated product that is being offered or supplied under this contract shall meet USDA BioPreferred’s minimum biobased content level. Visit the BioPreferred web site for the complete list of designated products and the associated minimum biobased content level requirements.

SECURITY REQUIREMENTS:

Access and General Protection/Security Policy and Procedures.

All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks or background investigation and to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.

I-Watch: The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training."

Will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas. All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.

Pre-screen candidates using E-Verify Program. The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award." *When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative.

This Form will be provided to the Contracting Officer and shall become part of the official contract file.

11 1214 13

2 3 7654

Ü

!. 2017 Well Repair driftwood_mitigation_area_boundary muscadine_mitigation_area_boundary

1:24,000 Date: 8/23/2017

2017 Muscadine Driftwood Well Repair

0 0.125 0.25 0.5 0.75 1 Miles

2.1 Quality Control/Quality Assurance.