Statement of Work
Transformer Supply, Vicksburg District:
Narrows Dam, U.S. Army Corps of Engineers (USACE)
1. Scope: The principal components of the work to be performed include design, manufacture, factory test, and deliver to Narrows Dam Power Plant in Arkansas; four
8,400/12,000 kVA, 69 kV/39.8 kV high-voltage winding, 13.2 kV low-voltage winding; cooling class OFAF/OFAF, Class I single-phase GSU power transformers and accessories, with an option to provide on-site long-term temporary storage. The work will also include offloading and movement of the transformers at the Narrows Dam Power plant, reassembly, oil-filling, perform field tests and furnishing of spare parts. All work will be performed to comply with site operations, environmental protection, and safety and health provisions.
2. Materials: The Bill of Materials is below.
Line Item
# Item Description Qty
Design, Manufacture and Test
8,400/12,000 kVA; 69 kV/39.84 kV high-voltage winding, 13.2 kV low-voltage winding; cooling class OFAF/OFAF; single-phase GSU power transformer and accessories.
Deliver Transformer and Accessories
FFP
Deliver 8,400/12,000 kVA single-phase power transformer and accessories from manufacturing facility complete to the Narrows Dam power plant
Off-load Transformer and Accessories
FFP
Off-load 8,400/12,000 kVA transformer and accessories at the Narrows Dam power plant transformer yard, perform inspections, perform cleaning, move transformers to its operating location, perform transformer reassembly, furnish transformer oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer and Commissioning
Agent. 4
4 Furnish Spare Parts 1
3. Delivery: The Government requires delivery to be made to the Narrows Dam Power
Plant in Arkansas.
4. Period of Performance: The period of performance shall be from date of award and be delivered NLT 31 May 2017.