BID ABSTRACT

For Bids Under Solicitation, W912EE-15-B-0002 Flood Control, Mississippi River and Tributaries

Mississippi River, Stone Bank Paving Mile 616-326 AHP

Kesser International, Inc. Little Rock, AR

LINE

ITEM

NO. DESCRIPTION EST QTY UM

UNIT

PRICE AMOUNT

0001 Mobilization and Demobilization 1 LS $385,000.00 $385,000.00 0002 Stone Bank Paving, Stone 125lb max, Upper Bank (Mile 616-494)

0002AA First 13,000 Tons 4,900 TN $44.00 $215,600.00 0002AB Over 13,000 Tons 4,900 TN $42.00 $205,800.00

0003 Stone Bank Paving, Stone 125lb max, Upper Bank (Mile 494-326) 0003AA First 10,000 Tons 6,550 TN $44.00 $288,200.00 0003AB Over 10,000 Tons 6,550 TN $42.00 $275,100.00

0004 Upstream Towing 100 MI $100.00 $10,000.00 0005 Downstream Towing 100 MI $50.00 $5,000.00

Total $1,384,700.00

K & K Industries, Inc. Newberry, Michigan

LINE

ITEM

NO. DESCRIPTION EST QTY UM

UNIT

PRICE AMOUNT

0001 Mobilization and Demobilization 1 LS $111,400.31 $111,400.31 0002 Stone Bank Paving, Stone 125lb max, Upper Bank (Mile 616-494)

0002AA First 13,000 Tons 4,900 TN $46.78 $229,222.00 0002AB Over 13,000 Tons 4,900 TN $46.78 $229,222.00

0003 Stone Bank Paving, Stone 125lb max, Upper Bank (Mile 494-326) 0003AA First 10,000 Tons 6,550 TN $49.28 $322,784.00 0003AB Over 10,000 Tons 6,550 TN $49.28 $322,784.00

0004 Upstream Towing 100 MI $221.66 $22,166.00 0005 Downstream Towing 100 MI $125.04 $12,504.00

Total $1,250,082.31

Government Estimate

LINE

ITEM

NO. DESCRIPTION EST QTY UM

UNIT

PRICE AMOUNT

0001 Mobilization and Demobilization 1 LS $203,300.00 $203,300.00 0002 Stone Bank Paving, Stone 125lb max, Upper Bank (Mile 616-494)

0002AA First 13,000 Tons 4,900 TN $36.80 $180,320.00 0002AB Over 13,000 Tons 4,900 TN $36.80 $180,320.00

0003 Stone Bank Paving, Stone 125lb max, Upper Bank (Mile 494-326) 0003AA First 10,000 Tons 6,550 TN $38.50 $252,175.00 0003AB Over 10,000 Tons 6,550 TN $38.50 $252,175.00

0004 Upstream Towing 100 MI $140.00 $14,000.00 0005 Downstream Towing 100 MI $90.00 $9,000.00

Total $1,091,290.00

I certify that I have opened, read and recorded on this abstract all offers received in response to the solicitation

Sheet1

2015-06-04T14:47:49-0500
BROWN.SCOTT.L.1295322973

File details come from the government source that posted it. Updated .