B01_corrected_bid_abstract.pdf

PDF 103 KB Posted

Attached to
FC/ MR&T, Yazoo Basin, Mississippi Project Office, Concrete Paving of Berm Ditches, Grenada Lake Dam
Solicitation number
W912EE-15-B-0010
Issued by

View the file

Other files

File Type Posted
B01_bid_abstract.pdf PDF
Amendment_0002.pdf PDF
amendment_01.pdf PDF
15b0010.pdf PDF
385-1-1.PDF PDF
specifications.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID ABSTRACT

For Bids Under Solicitation, W912EE-15-B-0010

FC/MR&T, Yazoo Basin, Mississippi Project Office Concrete Paving of Berm Ditches, Grenada Lake Dam

Grenada County, Grenada Mississippi

Fuel Tank Maintenance Co., LLC., Cookeville, TN

LINE

ITEM

NO. DESCRIPTION EST QTY UM UNIT PRICE AMOUNT

0001 Construction of 11,000 feet of lower ditch 1 JB $918,830.00 $918,830.00 Total Base Contract $918,830.00 $918,830.00 Option A

0002 Construction of next 400 feet upper ditch 1 JB $32,000.00 $32,000.00 Option B

0003 Construction of next 400 feet upper ditch 1 JB $32,000.00 $32,000.00 Option C

0004 Construction of next 400 feet upper ditch 1 JB $32,000.00 $32,000.00 Option D

0005 Construction of next 400 feet upper ditch 1 JB $32,000.00 $32,000.00 Total Base and Options $1,046,830.00

Carter's Contracting Services, Inc. Andalusia, AL

LINE

ITEM

NO. DESCRIPTION EST QTY UM UNIT PRICE AMOUNT

0001 Construction of 11,000 feet of lower ditch 1 JB $871,793.00 $871,793.00 Total Base Contract $871,793.00 $871,793.00 Option A

0002 Construction of next 400 feet upper ditch 1 JB $31,774.00 $31,774.00 Option B

0003 Construction of next 400 feet upper ditch 1 JB $31,774.00 $31,774.00 Option C

0004 Construction of next 400 feet upper ditch 1 JB $31,774.00 $31,774.00 Option D

0005 Construction of next 400 feet upper ditch 1 JB $31,774.00 $31,774.00 Total Base and Options $998,889.00

Century Construction and Realty, Inc., Tupelo, MS

LINE

ITEM

NO. DESCRIPTION EST QTY UM UNIT PRICE AMOUNT

0001 Construction of 11,000 feet of lower ditch 1 JB $875,000.00 $875,000.00 Total Base Contract $875,000.00 $875,000.00 Option A

0002 Construction of next 400 feet upper ditch 1 JB $45,700.00 $45,700.00 Option B

0003 Construction of next 400 feet upper ditch 1 JB $45,700.00 $45,700.00 Option C

0004 Construction of next 400 feet upper ditch 1 JB $45,700.00 $45,700.00 Option D

0005 Construction of next 400 feet upper ditch 1 JB $45,700.00 $45,700.00 Total Base and Options $1,057,800.00

Colom Construction Co., Inc., Ripley, MS

LINE

ITEM

NO. DESCRIPTION EST QTY UM UNIT PRICE AMOUNT

0001 Construction of 11,000 feet of lower ditch 1 JB $841,563.00 $841,563.00 Total Base Contract $841,563.00 $841,563.00 Option A

0002 Construction of next 400 feet upper ditch 1 JB $31,610.00 $31,610.00 Option B

0003 Construction of next 400 feet upper ditch 1 JB $31,610.00 $31,610.00 Option C

0004 Construction of next 400 feet upper ditch 1 JB $31,610.00 $31,610.00 Option D

0005 Construction of next 400 feet upper ditch 1 JB $31,610.00 $31,610.00 Total Base and Options $968,003.00

Towns Construction Co., Inc., Grenada, MS

ITEM

NO. DESCRIPTION EST QTY UM UNIT PRICE AMOUNT

0001 Construction of 11,000 feet of lower ditch 1 JB $983,290.88 $983,290.88 Total Base Contract $983,290.88 $983,290.88 Option A

0002 Construction of next 400 feet upper ditch 1 JB $33,025.57 $33,025.57 Option B

0003 Construction of next 400 feet upper ditch 1 JB $32,821.88 $32,821.88 Option C

0004 Construction of next 400 feet upper ditch 1 JB $38,744.86 $38,744.86 Option D

0005 Construction of next 400 feet upper ditch 1 JB $38,648.18 $38,648.18 Total Base and Options $1,126,531.37

Dirtworks, Inc. of Vicksburg, Vicksburg, MS

ITEM

NO. DESCRIPTION EST QTY UM UNIT PRICE AMOUNT

0001 Construction of 11,000 feet of lower ditch 1 JB $523,428.00 $523,428.00 Total Base Contract $523,428.00 $523,428.00 Option A

0002 Construction of next 400 feet upper ditch 1 JB $14,000.00 $14,000.00 Option B

0003 Construction of next 400 feet upper ditch 1 JB $14,000.00 $14,000.00 Option C

0004 Construction of next 400 feet upper ditch 1 JB $14,000.00 $14,000.00 Option D

0005 Construction of next 400 feet upper ditch 1 JB $14,000.00 $14,000.00 Total Base and Options $579,428.00

Expert Maintenance & Construction Svcs. LLC, Prairville, LA

LINE

ITEM

NO. DESCRIPTION EST QTY UM UNIT PRICE AMOUNT

0001 Construction of 11,000 feet of lower ditch 1 JB $788,265.63 $788,265.63 Total Base Contract $788,265.63 $788,265.63 Option A

0002 Construction of next 400 feet upper ditch 1 JB $28,664.00 $28,664.00 Option B

0003 Construction of next 400 feet upper ditch 1 JB $28,664.00 $28,664.00 Option C

0004 Construction of next 400 feet upper ditch 1 JB $28,664.00 $28,664.00 Option D

0005 Construction of next 400 feet upper ditch 1 JB $28,664.00 $28,664.00 Total Base and Options $902,921.63

Government Estimate

LINE

ITEM

NO. DESCRIPTION EST QTY UM UNIT PRICE AMOUNT

0001 Construction of 11,000 feet of lower ditch 1 JB $784,700.00 $784,700.00 Total Base Contract $784,700.00 $784,700.00 Option A

0002 Construction of next 400 feet upper ditch 1 JB $26,800.00 $26,800.00 Option B

0003 Construction of next 400 feet upper ditch 1 JB $26,800.00 $26,800.00 Option C

0004 Construction of next 400 feet upper ditch 1 JB $26,800.00 $26,800.00 Option D

0005 Construction of next 400 feet upper ditch 1 JB $26,800.00 $26,800.00 Total Base and Options $891,900.00

I certify that I have opened, read and recorded on this abstract all offers received in response to the solicitation

Sheet1

2015-09-16T09:02:04-0500
CANNADA.DUSTIN.1394393777

File details come from the government source that posted it. Updated .