W912DW27QA0060003.pdf

PDF 3 MB Posted

Attached to
Mud Mountain Dam Sewage Lagoon Repair
Solicitation number
W912DW27QA006
Issued by

About this file

This is Amendment 0003 to Solicitation W912DW27QA006, issued by the U.S. Army Corps of Engineers, Seattle District, effective November 25, 2026. The amendment answers additional questions from offerors regarding a sewage lagoon liner repair project at Mud Mountain Dam in Enumclaw, Washington.

The primary scope of work involves cleaning the bottom portion of a sewage lagoon, inspecting and repairing the geomembrane liner, replacing two broken PVC inlet pipes, clearing a clogged outlet pipe, and replacing the chlorinator. The contractor must complete all work within 45 calendar days of Notice to Proceed. Key technical requirements include two areas of mandatory experience: cleaning and sanitizing of sewage lagoons, and repair or installation of a geosynthetic liner. The Lead Seamer must possess an industry-standard certification such as IAGI Certified Welding Technician or equivalent documented experience. Award will be made to the lowest-priced offeror receiving acceptable ratings on both Technical and Past Performance evaluation factors. Submittals required before mobilization include a detailed work plan, Activity Hazard Analysis, Accident Prevention Plan, and product data sheets for materials. The contract uses a firm-fixed-price structure with payment upon completion of all work and testing. The government provides water for testing and will handle aerator movement and electrical operations. A one-year warranty against defects in material and workmanship is required, with warranty claims to be addressed within 14 days of receipt and remedied within 30 calendar days.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Instructions, Conditions, & Notices to Offerors or Quoters

Miscellaneous text in this section has been added to:

Response to Questions (2):

Q Cleaning and sanitizing experience: - Section M requires project experience in "Cleaning and sanitizing of sewage lagoons." Will a completed project involving demolition of existing pond components, removal of accumulated material, and sanitizing of a stormwater retention pond satisfy this requirement? Or must the project specifically involve a sanitary sewage lagoon?

: A According to the criterion, only "cleaning and sanitizing of sewage lagoons" will earn an acceptable rating.

Geosynthetic liner experienceQ: - Section M requires project experience in "Repair of a geosynthetic liner." Will a completed project involving installation of a new geosynthetic liner (approximately 70,000 square feet of geomembrane) in an existing pond retrofit, including pipe boots through the liner at inlet and outlet penetrations, satisfy this requirement?

A: Yes, installation of a new geosynthetic liner is acceptable. See updated 52.212-5.

Subcontractor experiencQ: e - May a quoter use the project experience of a proposed subcontractor who will perform that portion of the work (for example, a liner repair subcontractor) to meet one of the two required experience areas?

: See response A regarding use of subcontractor experience in Amendment 0001, also captured in 52.212-5.

: Lead seamerQ - May the Lead Seamer required by SOW Section 3.2 be an employee of a subcontractor, provided the seamer's certification or documented experience is submitted with the quote?

W912DW27QA0060003

See response A: regarding use of subcontractor experience in Amendment 0001, also captured in 52.212-5.

:Q Final water hold test (SOW 6.6). Amendment 0001 removed the sentence stating that additional repairs are not covered if the final test is unsuccessful. If the 6.6 test fails because of a leak in liner above the cleaned zone, will locating and repairing that leak be handled as a change to the contract, or is it to be included in the quoted price?

: A If the 6.6 test fails because of a leak in liner above the cleaned zone (the portion of the liner which remains under gravel and is not exposed or inspected under this scope), locating and repairing that leak will be handled as a change to the contract requiring a formal contract modification pursuant to clause 52.212-4 and is not to be included in the quoted price.

:Q Incoming flow. Will the Government stop or divert sewage flow into the lagoon while crews are working in the lagoon bottom? If controlling that flow is the contractor's responsibility, what is the approximate daily flow?

A: All the sources of sewage flow into the lagoon have been secured (facilities in the park and workshops flow into the lagoon and are not in use, facilities in the main admin building do not flow into the lagoon). Contractor is responsible for managing rainwater that may accumulate in the lagoon.

Q: Water supply for tests 6.5 and 6.6 (SOW 3.8). Where is the water connection, what is its size, and what flow rate is available? Test 6.6 takes roughly 75,000 gallons to the outlet elevation.

A: The government will use its own water truck to fill the lagoon with water for these tests (water will be drawn from the river).

Q: Test 6.5 water. Where may the test 6.5 water be discharged before the gravel is returned (SOW 5.3(f))? Alternatively, may the gravel be placed with the test water in the lagoon?

: A The gravel in the lower section of the lagoon will need to be spread evenly in a safe manner, which will be difficult if water remains in the lagoon. The work plan submittal must include a plan for replacing the gravel. Water may be pumped from the bottom of the lagoon into the chlorinator vault (see reference a), which flows to the drain field.

Q: Sludge. Is there an estimate of the sludge depth or volume in the lower section of the lagoon?

QuotersA: will need to estimate sludge volume themselves using visual inspection from site visit and photos provided with SOW. Reference a shows that the inlet pipe is one (1) foot above bottom of lagoon.

Q: Inlet pipes (SOW 5.2(a)). What are the nominal diameter and approximate length of the two broken PVC inlet pipes? What size is the inlet pipe boot?

A: Contactor is required to replace PVC pipes like for like in diameter and length based on their own inspection. Additional requirements for the new PVC are stated in SOW 5.2(a).

Q: Chlorinator (SOW 5.2(c)). Is a tablet-feed chlorinator of equal capacity acceptable in place of the Sanuril Model 100?

A: Yes. Contractor is responsible for ensuring suitable size and fit of new chlorinator and all required details for installation.

Q: Wage determination WA20260125. Which classifications apply to a geomembrane seamer, a vacuum truck operator, and an excavator under 15 metric tons? If none applies, should a conformance request (SF 1444) be submitted after award?

The contractor A: is responsible for determining which classifications apply and following procedures to ensure compliance with laws concerning Davis Bacon wage rates.

Q: Safety staffing. Under EM 385-1-1, does this work require a full-time Site Safety and Health Officer, or may the designated Competent Person fill that role?

The government anticipates that a Level 3 SSHO (Competent Person, CP or Qualified Person, A:

QP) will be acceptable, HOWEVER the quoter must fully consider all potential risks and plan to implement controls to allow for no higher than medium risk in order to use a Level 3 SSHO (Competent Person, CP or Qualified Person, QP) rather than a full-time, Level 1, SSHO.

The contractor is required to develop an Activity Hazard Analysis (AHA) as a submittal post award and must show that every job step has a residual RAC of "Medium Risk" or lower for a CP/QP to

1.

2.

be allowed. Approval of the AHA will signify approval to use a CP/QP rather than a level 1 SSHO.

The Accident Prevention Plan must identify by name the CP/QP who will be responsible for all hazards, including biological & pathogen exposure, H2S exposure, and fall protection/slope access.

Q: Aerator (SOW 5.1(a)). What is the weight of the floating aerator? Will Government personnel de-energize it, or is lockout and disconnection by the contractor's electrician?

See update to SOW, the government will A: accomplish all movement of the aerator and any required electrical operations.

Evaluation Factors for Award

The following clauses were modified:

52.212-2 Evaluation-Commercial Products and Commercial Services. (Deviation 2026-O0038) Feb 2026 hereby reads as follows:

Evaluation-Commercial Products and Commercial Services (Feb 2026) (Deviation 2026-O0038)

(a) Evaluation factors. The Government will award a contract resulting from this solicitation to the responsible Offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors will be used to evaluate offers:

1. Technical

a. Quoter's shall submit information on at least one (1), but no more than three (3) projects completed within the last 10 years collectively demonstrating the quoter's recent technical experience related to the scope of the requirement outlined in the Statement of Work (SOW). If projects do not collectively address the below minimum requirements, the quoter's proposal will be rated as unacceptable. To be rated acceptable, the project submissions must demonstrate experience in the following two (2) areas of the scope:

Cleaning and sanitizing of sewage lagoons Repair of a geosynthetic lineror installation

For each project, provide:

Project title and location Description of work performed Dollar value Date completed Contracting agency or owner Point of contact (name, phone, and email) Any information related to performance of the contract provided by the customer

*Experience must be by the proposed "team" consisting of the prime and subcontractor. If *subcontractor experience is used the prime MUST use the proposed subcontractor.

b. Lead Seamer Certification: The Quoter shall submit evidence of the Lead Seamer's certifications or qualifications as required by Section 3.2 of the SOW.

The Government will evaluate the quoter's technical experience submitted. Quoters will be evaluated as either Acceptable or Unacceptable for this factor.

Acceptable: The Quoter submitted 1 to 3 projects demonstrating recent experience in both required scope areas (lagoon cleaning and liner repair) and provided valid Lead Seamer certifications/evidence conforming to SOW Section 3.2.

Unacceptable: The Quoter failed to submit the required project information, the submitted projects do not clearly demonstrate experience in both scope areas, or the Quoter failed to provide valid Lead Seamer certification/evidence.

2. Past Performance

The Quoter should provide documentation of successful performance on the relevant projects submitted under the Technical factor (such as CPARS, reference letters, or past evaluations).

Note: The Government reserves the right to review CPARS and any other publicly available information to evaluate this factor.

The Government will evaluate the Quoter's record of past and current performance to ascertain the probability of successfully performing the required efforts of the scope of work.

Acceptable: The Government has a reasonable expectation that the Quoter will successfully perform the SOW based on their performance record, OR the Quoter has no record of past performance (Neutral).

Unacceptable: The Government does not have a reasonable expectation of successful performance based on a documented record of poor performance.

Note: Quoters with no historical past performance data will receive a "Neutral" rating, which will be evaluated as "Acceptable" for this factor.

3. Price

The Quoter shall submit a firm-fixed-price quote using the provided Price Schedule. The Quoter must fill out all Contract Line-Item Numbers (CLINs) and state the total evaluated price for the entire requirement.

Price will be evaluated for fairness and reasonableness. Award will be made to the lowest priced quote that receives an Acceptable rating on both the Technical and Past Performance factors.

(End of provision)

Construction Specification

Scope of Work

Sewage Lagoon Liner Repair

1.0 BACKGROUND: The sewage lagoon liner servicing Mud Mountain Dam does not hold liquid and is believed to leak near its lowest elevation, at the boot around the inlet pipe or lower. Testing shows that the inlet piping itself is not leaking and the outlet from chlorine contact chamber to drainfield is performing as intended. In addition, the outlet pipe leading to the chlorinator is clogged and two PVC inlet pipes leading to the bottom of the lagoon are broken.

2.0 SCOPE OF WORK: The primary work included in this scope includes cleaning the bottom portion of the lagoon, inspection for leaks, repairing any leaks found, performing comprehensive testing to determine whether all leaks have been repaired, and returning lagoon to operational state.

Additional work includes replacing two broken PVC inlet pipe and fittings, clearing the clogged outlet pipe and replacing the chlorinator. All work must be complete within 45 calendar days of

Notice to Proceed (NTP).

3.0 GENERAL

3.1 Standards and Regulations: Perform to the standards in the contract and comply with all Local, State, and Federal Regulations during the services performed. Ascertain the extent to which these regulations affect the operations resulting from this contract. Comply with all applicable regulations. Applicable regulations include, but are not limited to the following:

a. Engineering Manual (EM) 385-1-1 (USACE – Safety and Health Requirements Manual), dated

March 2024;

b. Occupational Safety and Health Standards (29 CFR 1910);

c. ASTM D4437 (2018) Standard Practice for Nondestructive Testing (NDT) for Determining the

Integrity of Seams Used in Joining Flexible Polymeric Sheet Geomembranes

d. ASTM D6392 (2012; R 2018) Standard Test Method for Determining the Integrity of

Nonreinforced Geomembrane Seams Produced Using Thermo-Fusion Methods

e. ASTM D5641 (2016) Standard Practice for Geomembrane Seam Evaluation by Vacuum

Chamber

f. ASTM D5820 (1995; R 2018) Standard Practice for Pressurized Air Channel Evaluation of

Dual Seamed Geomembranes

3.1.1 Activity Hazard Analysis (AHA): Prepare an AHA in accordance with Paragraph 1-6 of EM 385-

1-1. ENG Form 6206, Sep 2024, or corporate equivalent form presenting the same information may be used. This must be submitted and approved by the Quality Assurance Representative (QAR) before mobilization to site (Submittal b).

3.1.2 Accident Prevention Plan (APP): Use a Competent Person to prepare the site-specific Accident

Prevention Plan (APP) in accordance with paragraph 2-7. b of EM-385-1-1 and using ENG Form

6293. This must be submitted and approved by the QAR before mobilization to site (Submittal c).

Include:

a. Biological & Pathogen Exposure Control Plan (EM 385-1-1 3-7a)

Lock-Out Tag-Out plan (if the aerator will need to be electrically disconnected)

b. Hot work permit in accordance with NFPA 51B or OSHA-compliant corporate equivalent (to include seaming)

c. H2S exposure control plan (controlling for H2S that may have accumulated at the bottom of the lagoon and in the chlorinator chamber)

d. Slip, Trip and Fall Prevention Plan

3.2 Certifications: The Lead Seamer must possess an industry-standard certification for the installation and repair of HDPE liners, such as the IAGI Certified Welding Technician (CWT) certification or a Manufacturer’s Installer Certification from an approved HDPE geomembrane manufacturer. In lieu of formal certification, a minimum of three (3) years of documented experience in the installation and repair of HDPE liners, verified by a submitted project log or reference letters, shall be acceptable.

3.3 Measurement and Payment: Payment will be made in accordance with FAR 52.232-5 Payments under Fixed-Price Construction Contracts. on a job basis after the accomplishment of all specified work, including all testing witnessed by the government QAR and documented by contractor.

3.4 Location: The sewage lagoon is located at 30525 SE Mud Mountain Rd, Enumclaw, WA. See figure 1 for details.

3.5 Access and Staging Area: Access the work location through the contractor gate to the right of the park gate when approaching. The sewage lagoon sits within a 100’x120’ fenced area, which is accessed by a double swing gate which allows for a 20 ft opening. If removal of fencing is required, removal and reinstallation will be done at contractor’s expense. An additional 50’x120’ area between this fence and the access road may also be used for staging. See figure 1 for details.

3.6 Waste management: Remove and dispose of all waste and sewage properly offsite in accordance with local regulations. Submittal (a), Work Plan, must include plan for disposal of waste.

3.7 Work Hours and Work Limits: Plan and accomplish all work in a way to minimize any interferences and inconveniences to the government, the public, and other contractors. Blockages of roadways are not allowed. Conduct business between the hours of 6:30am and 4pm Monday through Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings.

Work may take place outside of these hours subject to agreement with operations staff on a case-by-case basis.

3.8 Facilities: Provide portable toilets for the contractor’s own use only. A reasonable amount of potable water and electrical power will be made available to the contractor for performing work in the area. Carefully conserve water and electricity furnished. Install and maintain any necessary temporary connections and distribution lines remove these prior to final acceptance of construction.

3.9 Environmental Conditions: Work will take place outdoors and is subject to local weather at the site.

3.10 Operation Security Requirements

General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The

Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated point of contact. Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The

Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative.

The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random

Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition

(HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures – this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or

HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.

3.10.1 Physical security and access control requirements: All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost

Marshal/Directorate of Emergency Services/Security Office using the National Crime

Information Center-Interstate Identification Index (commonly referred to as “NCIC-III”) and

Terrorist Screening Database (commonly referred to as “TSDB”). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures. Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the

RA.

3.10.2 Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say

Something): All contract personnel shall receive initial and annual refresher training from the

RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.

3.10.3 Escorting in classified and/or sensitive areas: In accordance with applicable regulations, all contract personnel who do not possess the appropriate security clearance or access privileges will be escorted in areas where they may be exposed to classified information or operations, sensitive information or activities, or restricted areas.

3.10.4 Pre-screen candidates using E-Verify Program: Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR

Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with

FAR 22.102-1(i). An initial list of verified/ eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility

Verification, and submit it to the Contracting Officer to become part of the official contract file.

3.11 Submittals:

3.11.1 Submittals requiring QAR approval before mobilization to site: Submit the documents under this heading to the QAR no later than five business days after notice to proceed. They will be reviewed and returned within five business days of receipt with either approval or documentation of deficiencies. Address any deficiencies noted and resubmit for approval. All work must be complete within 45 calendar days of NTP regardless of deficiencies in submittals.

a. Detailed work plan and schedule (identification of definable features of work), including:

i. Detailed work plan identifying all definable features of work

ii. Sequence and estimated schedule of work to be performed including proposed start date.

iii. Quality Control (QC) procedures and testing to be used by the contractor

iv. Testing which will be witnessed by the QAR for Quality Assurance, including all tests listed in section 6 of this scope of work, at minimum. Include format in which test results will be documented.

b. Activity Hazard Analysis (AHA);

c. Accident Prevention Plan;

d. Make and model of vacuum truck to be used;

e. HDPE liner boot product data sheet;

f. HDPE patch material product data sheet;

g. HDPE seam rod/pellet product data sheet;

h. Typical HDPE patch seam detail drawing;

i. Typical HDPE boot seam detail drawing;

j. Product data sheet for replacement PVC pipe and fittings, including banded couplings

k. Product data sheet for paint to be applied to exposed PVC pipe

l. Product data for replacement chlorinator

3.11.2 Submittals required before close-out of contract:

m. Patch material manufacturers quality assurance manual

n. As-built drawings showing details of all work accomplished

o. Test results in format approved from Submittal (a)

p. Manufacturer’s warranty information

4.0 MATERIALS: The current liner is identified as GSE HD Textured Geomembrane (Single Sided), 40 mil. The contractor must use equivalent material as verified by product data sheet submittal (texture is not required if the upper side of the current liner is untextured). Seaming rods and pellets must have essentially identical properties to the geomembrane sheet.

5.0 EXECUTION: This section contains a basic outline of required tasks. Show all identifiable features of your work in Submittal (a) – Work Plan.

5.1 Cleaning:

Remove aerator to a safe location prior to cleaning. Disconnect electrical and anchor connections as needed.

a. Remove material from the lower section of the liner up to 1 foot vertically above the bottom edge of the inlet pipe, or 2 feet above the bottom of the lagoon, to make it sanitary to work and allow for inspection for leaks. Clean the entire surface and all seams of the inlet pipe boot and on both sides of the wooden baffle. The liner is currently covered by a 4”-6” deep gravel blanket, and approximately 15 cubic yards of gravel will need to be removed. Use a vacuum truck to avoid causing damage to the liner and gently clean liner to reveal surface. Do not use any cleaning material or tool that could cause damage to the liner.

b. Conduct inspection as described in 6.1.

c. Either disposed of soiled gravel in accordance with local regulations or clean and stockpile gravel for reuse.

a. If gravel is disposed of, procure and transport new gravel to replace it.

b. If gravel is cleaned and stockpiled, it must be cleaned to a sanitary condition for safety during spreading and levelling. Stockpile in a designated staging area on a continuous, seamless 10-mil polyethylene underlayment; completely enclose with a sediment berm

(sandbags or wattles) and cover daily with a anchored 6-mil plastic cover to prevent rainwater infiltration and wind erosion. Prior to returning the gravel to the lagoon, sanitize the material to eliminate waterborne pathogens by thoroughly washing/wetting the gravel with a sodium hypochlorite or calcium hypochlorite solution achieving a minimum concentration of 500 parts per million (ppm) free chlorine (1/3 cup liquid bleach per gallon). Allow the gravel to remain in contact with the sanitizing solution for a minimum of two (2) hours within a temporary, lined containment wash-bay, then rinse with fresh water and allow to dry before spreading and leveling in the lagoon. Capture and store all water from the sanitization process. This water may be pumped into the lagoon after the satisfactory completion of the final controlled water hold test (6.6).

5.2 Repair of Accessories: (Tasks in this item may be completed simultaneously with repair of liner but must be complete before liner is filled with water.)

a. Remove white PVC piping downstream of the breaks at two inlet pipes. Install new schedule 80

PVC of the same nominal pipe size. Utilize 30-degree or 22.5-degree PVC elbows to match 2:1 gravel slope and install a Banded Flexible Coupling (such as a Fernco Strong Back RC Series or

Mission Banded Coupling) upstream of new elbow to reduce bending stress on pipe. Install all piping, including elbow, to rest on gravel blanket. Apply two coats of paint to all PVC piping that is exposed above the gravel blanket down to 1 foot below the low pool level during normal operation (the lower edge of the outlet pipe) in accordance with PVC manufacturers’ paint recommendation for UV protection (water-based acrylic latex paint).

b. Clear clog between outlet pipe and chlorinator.

c. Replace chlorinator with new (Sanuril model 100 or equivalent) and provide one 45-pound pail of compatible chlorination tablets.

5.3 Repair of Lagoon Liner:

a. Test 6.2 must be satisfactory before executing these tasks. If test is not satisfactory, remediate deficiencies and repeat test.

b. Repair tears, holes, blisters and other defects with patches. Provide patches that have rounded corners, meet requirements of section 4.0, and extend a minimum of 6 inches beyond the edge of defects. The seamer with qualifications submitted and approved must be present for all seaming.

c. If a defect is found in the boot around the inlet pipe or support pipes for baffle, replace the boot, banding and tape and weld new seams around the edges. The seamer with qualifications submitted and approved must be present for all seaming.

d. Perform Test 6.3 and 6.4. Tests must be satisfactory before proceeding to next step. If tests are not satisfactory, remediate deficiencies and repeat test.

e. Install sufficient temporary ballast to keep liner in place and perform test 6.5. If test is not satisfactory, remediate deficiencies and repeat test.

f. Return gravel to lagoon and spread evenly for 4”-6” cover. If new gravel is provided rather than re-use of existing gravel, it must match the size and smoothness of the removed gravel (crushed gravel is not acceptable).

g. Perform test 6.6.

h. Reinstall aerator.

6.0 INSPECTIONS AND TESTS: The government QAR will provide inspection of all work in accordance with FAR 52.212-4(b)– Terms and Conditions – Commercial Products and Commercial

Services. This section describes the minimum testing standards. Provide details of how this testing will be carried out in submittal (a) – Work Plan. Notify Point of Contact two business days in advance of conducting tests. Government observation does not relieve contractor of responsibility for quality or constitute acceptance of work. Final acceptance will not occur until after all work and required closeout documents are received.

6.1 Visually inspect for leaks after 5.1 of this scope is accomplished.

6.2 Prior to seaming, collect and test trial seam samples in accordance with ASTM D6392. Test must be satisfactory prior to start of lagoon repair.

6.3 Perform a vacuum box test on patches in accordance with ASTM D5641. Perform visual inspection. Test must be satisfactory prior to controlled water hold test.

6.4 If the inlet pipe boot or baffle support pipe boot is replaced, perform non-destructive Air

Lance Testing in accordance with ASTM D4437, Paragraph 7.2. The test nozzle must deliver a minimum of 50 PSI held within 2 inches of the weld edge. Mark any flutters, bubbles, or inflation as a leak, repair, and re-test.

6.5 Perform a controlled water-hold test of the repaired liner system at the elevation of 1 foot above the bottom edge of the inlet pipe for a minimum duration of 24 hours. Measure initial and final water elevations from a fixed datum. Net unexplained water level loss, after adjustment for precipitation, temperature and authorized water additions/removals, shall not exceed 1/8 inch over the test period. If the allowable loss is exceeded, investigate, repair deficiencies, and repeat the test at no additional cost to the Government. Water will be provided by the government.

6.6 Perform a controlled water-hold test of the repaired liner system at the elevation of the outlet pipe for a minimum duration of 24 hours. Measure and record initial and final water elevations from a fixed datum. Do not demobilize until this test is complete. Test will be considered successful if net unexplained water level loss, after adjustment for precipitation, temperature and authorized water additions/removals, is less than 1/4 inch. Additional repairs if this test is unsuccessful are not covered under this contract. Water will be provided by the government.

7.0 WARRANTY: Provide a one-year warranty against any defects in material or workmanship and pass on all manufacturers’ extended warranties. Respond to any claim for warranty work within 14 days of receipt and accomplish work to remedy warranty items within 30 calendar days of receipt of claim.

8.0 POINT OF CONTACT: The point of contact and QAR information will be included with the award.

9.0 REFERENCE DRAWINGS: Drawings provided for reference only. Drawings may not reflect actual site conditions or show all equipment installed and the government does not guarantee the accuracy of the reference drawings and information provided within this document. Verify all existing conditions, relevant dimensions and access points before pricing and commencement of work. Site visit for bidders will be provided.

a. As-Built Drawings – Sewage Treatment Facility, Plan Profile and Sections, Mud

Mountain Dam, E-3-8-278, 1974FEB19

b. As-Built Drawings – Sewage Lagoon @ Mud Mountain Dam Liner Replacement, November 30, 2018 (includes current liner product data sheets)

10.0 FIGURES

Figure 1: Location and Access

Figure 2: lagoon photo

Figure 3: lagoon photo

Figure 4: lagoon photo

Figure 5: lagoon photo

Figure 6: lagoon photo

Figure 7: lagoon photo

IDCode: J
Page: 1
Pages: 7
AmendNo: 0003
EffDate: 25 NOV 2026
ReqNo:
ProjNo:
IssCode: W912DW
AdmCode:
IssuedBy: W071 ENDIST SEATTLE

KO CONTRACTING DIVISION, 4735 EAST MARGINAL WAY SOUTH

SEATTLE, WA 98134-2329

UNITED STATES

WHITNY HART, EMAIL: WHITNY.HART@USACE.ARMY.MIL TELEPHONE: (206) 638-6270

AdminBy:

SCD: PAS:

ContractorNameAdd:
SolNo: W912DW27QA006
SolChg: 1
SolDate: 09 NOV 2026
AwardChg: Off
AwardNo:
Code:
FacCode:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: The purpose of amendment 0003 is to answer additional questions.
ContNameTitle:
CoNameTitle: SCOTT W. BRITT
ContDate:
CODate: 25 NOV 2026