W912DW25Q0030 0001.pdf

PDF 256 KB Posted

Attached to
Albeni Falls Dam Main Unit Turbine Blade Seals Replacement
Solicitation number
W912DW25Q0030
Issued by

About this file

This document is an Amendment (0001) to a federal solicitation for Albeni Falls Powerhouse Main Unit Turbine Blade Seals. The amendment modifies the product description in sections 3.1 and 3.2, requiring the contractor to furnish eight (8) sets of molded Kaplan turbine blade seals. Specific requirements include James Walker "Solosele KB Hydro OSJ" or equivalent seals with precise dimensional specifications, such as an outer diameter of 44.250 inches and inner diameter of 42.750 inches. The seals must be designed for Kaplan turbines, ensure leak-free sealing, and be compatible with existing housing dimensions.

The solicitation includes detailed technical specifications for seal assemblies, requiring match-marked sets with uniform free stack height, documentation of quality assurance, and installation instructions. Delivery terms mandate free-on-board (FOB) delivery to the U.S. Army Corps of Engineers Albeni Falls Dam Warehouse in Oldtown, Idaho within 14 weeks of contract award. Shipments are restricted to Monday-Thursday between 7:00 a.m. and 4:00 p.m. PST, excluding federal holidays. The manufacturer must provide a minimum one-year warranty covering parts, labor, and workmanship, and individually vacuum pack each seal assembly for long-term storage.

View the file

Other files

File Type Posted
39000.pdf PDF
39001.pdf PDF
38996.pdf PDF
W912DW25Q0030.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The pupuse of this amendment is to add information to the product description in section 3.1 and 3.2.

No other changes

1. CONTRACT ID CODE PAGE OF PAGES

1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 11-Jul-2025

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DW25Q0030

X 9B. DATED (SEE ITEM 11)

03-Jul-2025

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

11-Jul-2025

CODE

USA ENGINEER DISTRICT, SEATTLE

ATTN: CENWS-CT

4735 EAST MARGINAL WAY SOUTH, BLDG. 1202

SEATTLE WA 98134-2388

W912DW 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DW25Q0030

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

The following have been modified:

PRODUCT DESCRIPTION

TECHNICAL

SPECIFICATIONS ALBENI

FALLS POWERHOUSE

MAIN UNIT TURBINE BLADE SEALS

1.0 INTENT

The following specif ications pertain to the purchase of four (4) sets of seals for Albeni Falls Powerhouse Main Unit Kaplan turbine blades. The turbine runner is a 4-bladed vertical axis Kaplan.

2.0 SCOPE

The successful bidder shall be required to furnish and deliver the Kaplan blade seals and all accessories to Albeni Falls Dam by the date shown in the “Shipment and Delivery section.

Contractor shall also provide submittals as stated in these specif ications.

3.0 BLADE SEALS FOR MAIN UNITS

The contractor shall furnish eight (8) sets of molded Kaplan turbine blade seals. The dif ferent seals and their requirements are detailed below:

3.1 - Four (4) seals shall be James Walker or Equal nitrile back-to-back shallex (chevron style) seals to suit housing dimensions shown in the attached reference drawings. The seals shall be specially designed for Kaplan turbines to assure a long-term leak- free sealing action.

The seals sets are to include two header rings, two v-rings, and one center gland ring. The blade seals shall be press cured in endless form & split for in-place installation. For each set, the two header rings are to be square cut, the two v-rings are to be cut with one scarf joint, and the center gland ring also cut with a scarf joint.

The nominal packing size will have an OD of 44.250 and an ID of 42.750 (0.75-inch wide).

The housing ID is 42.750 +/- 0.005 inch (BLH 38993, Piece 6) final dimension after interference fit with trunnion. The housing OD is 44.250 + 0.002/-0.000 diameter bore (BLH 39000, Piece 1). The total packing ring stack height is 2.25-inch nominally. The piece that applies the axial compression includes an additional height of 7/16-inch, per drawing BLH- 39000. It is expected to be included in the assembly and reinstalled af ter the seals are replaced. This is not required if the seal design does not need compression.

The seals shall be designed to fit within the existing packing box dimensions as shown on the attached reference drawings. The seals shall be an engineer approved, manufactured product which has been sold for at least ten years.

Provide seal assemblies that have been match‐marked by the manufacturer to provide uniform f ree stack height within +/‐ 1/32” and appropriate stagger of the splits. The seal assemblies are to be verif ied by the manufacturer that they are within the tolerance and suitable for the dimensions of the housing. The manufacturer is to have a mock‐up of the housing for final fit‐up and matchmarking. At a minimum, this mock-up for the housing will be two plates set at the packing housing width. Prior to delivery, match mark the set and provide quality assurance documentation in the shipment showing the f inal measurements.

The blade seals will function against the blade packing sleeve (ID) and the retaining ring (OD). The trunnion (ID blade seal surface) will rotate from 19-34 degrees (15 degrees total) during operation, while the hub (OD blade seal surface) will be stationary. The OD of the blade seal housing is Cast Steel Fed Spec QQ-S-681b Class 2 Med (BLH 39000, Piece 1).

The ID of the blade seal housing is ASTM A296- 49T or stainless-steel Type 410 Annealed (BLH 38993, Piece 6).

3.2 - The seals shall be James Walker model “Solosele KB Hydro OSJ” or Equal to suit measured housing dimensions. The seals shall be designed to fit within the existing packing box dimensions as shown on drawings BLH 38996, BLH 39000, and BLH-39002. The f inal dimensions will be provided at contract award and may increase a maximum of 0.040-inch, to be conf irmed between James Walker engineering or Equivalent manufacturer engineering and the US Corps of Engineers’ Hydroelectric Design Center.

The nominal packing size will have an OD of 44.250 and an ID of 42.750 (0.75-inch wide). The housing ID is 42.750 +/- 0.005 inch (BLH 38993, Piece 6) final dimension after interference fit with trunnion. The housing OD is 44.250 + 0.002/-0.000 diameter bore (BLH 39000, Piece 1). The total packing ring stack height is 2.25-inch nominally. The piece that applies the axial compression includes an additional height of 7/16-inch, per drawing BLH-39000. It is expected to be included in the assembly and reinstalled af ter the seals are replaced. This is not required if the seal design does not need compression.

The blade seals will function against the blade packing sleeve (ID) and the retaining ring (OD). The trunnion (ID blade seal surface) will rotate from 19-34 degrees (15-degrees total) during operation, while the hub (OD blade seal surface) will be stationary. The OD of the blade seal housing is Cast Steel Fed Spec QQ-S-681b Class 2 Med (BLH 39000, Piece 1). The ID of the blade seal housing is ASTM A296-49T or stainless-steel Type 410 Annealed (BLH 38993, Piece 6)

If the contractor wishes to provide an “approved equal” product, the contractor shall be responsible for submitting all product data sheets and other documentation necessary to prove that the products meets all of the specifications. The design shall incorporate a radially compressed, f loating seal set specially designed for Kaplan turbines to assure a long-term leak-f ree sealing action. The turbine blade seals shall be designed to completely seal out water and seal in turbine oil, requiring no compression in the axial direction of the blade.

The seals shall be an engineer approved equal of standard, commercially available manufactured product which has been sold for at least ten years. The seals shall include a split to allow for f ield installation and provisions for on-site joining during install

4.0 SUBMITTED DOCUMENTATION

Submit the following for approval, prior to the shipment of the seals. Manufacturer’s drawings and installation procedures shall be provided for the seals requested.

4.1 Blade Seal Assembly Drawings

Submit for approval prior to manufacturing of new seals. The Government will be taking housing measurements and will confirm with manufacturing the suitability of use. Include the required surface f inish of the contact surfaces of the housing on the drawing.

The drawings shall include material, dimension, specifications, vendor name and phone number, and a drawing number that can be referenced for replacement blade packing on future orders. The drawings shall be provided as PDF digital format so it can be added to the existing drawing database.

If available, the CADD version of the drawing shall also be provided.

4.2 Blade Seal Installation Instructions

Submit for approval instructions for installing the blade seals into the housing. The instructions are required to reflect installation in place (without removal of the blades) and include details for the specific assembly shown in the attached drawing of the seal assembly (shown in BLH-39002).

4.3 Blade Seal Quality Documentation

Prior to shipment from the manufacturer, submit for approval the quality documentation and photos showing the seals were measured to match tolerances and acceptance criteria shown in the blade seal drawing.

5.0 WARRANTY

All items shall be covered by the manufacture’s standard warranty on all parts, labor, and workmanship f rom factory defects. Warranty period shall be a minimum of one year.

6.0 PACKAGING

All seal assemblies shall be individually vacuum packed to facilitate long term storage. All seal assemblies and all accessories shall be packaged into a single box or wood crate for storage. This container shall be mounted on a pallet so that it can be handled with a forklift or pallet jack. Include a copy of the final quality documentation and drawing inside the crate. The box or crate shall be clearly labeled on one side and on top with the following description:

Contract Number Turbine Blade Seals for Main Units Contractor’s Company Name Contractor’s Seal Model Name / Part Number Contractor’s Point of Contact Name Contractor’s Point of Contact Phone Number

7.0 SHIPMENT AND DELIVERY

All items shall be delivered free-on-board (FOB) to the project within 14 weeks of contract award. The contractor shall be responsible for packing and shipping the components in a manner that will ensure undamaged and complete arrival to the powerhouse. No shipments are allowed other than normal business hours of Monday-Thursday 7:00 a.m. to 4:00 p.m. PST, excluding federal holidays.

All shipments shall be delivered to:

U.S. Army Corps of Engineers Albeni Falls Dam Warehouse Receiving 2376 E. Highway 2 Oldtown, ID 83822

(End of Summary of Changes)

TECHNICAL SPECIFICATIONS ALBENI FALLS POWERHOUSE
1.0 INTENT
2.0 SCOPE
3.0 BLADE SEALS FOR MAIN UNITS
4.0 SUBMITTED DOCUMENTATION
5.0 WARRANTY
6.0 PACKAGING
7.0 SHIPMENT AND DELIVERY