This document contains questions from the government seeking non-proprietary answers from industry regarding a two-phase design-build project for fish passage improvements at Albeni Falls Dam. The government requests responses by January 9, 2024 to questions about the suitability of economic price adjustments for cement, concrete, and steel commodities; the amount of time needed between project phases to develop technical proposals; and the potential influence of an availability of funds clause on submitting an offer. The related federal contract opportunity is a request for information regarding the design-build project being conducted by the Army Corps of Engineers Engineering District Seattle.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GOVERNMENT QUESTIONS TO INDUSTRY:
Responses are due in writing to charles.d.idle@usace.army.mil and gregory.a.cook@usace.army.mil by 2:00 PM PST on January 9, 2024.
This announcement is not a contract solicitation, request for proposal, promise to issue any future contract, forum to discuss upcoming work, nor commitment to offer work of any kind on the part of the Government.
The Government is seeking nonproprietary answers to the questions (below). Please ensure you inform the Government of any proprietary information included in your response. The Prime Contractor's answers to the questionnaire will only be made available to the Government. Note that the Government may use the provided answers to develop the final RFP.
EMAIL SUBJECT: AFD FPF RFI: Answers to Government Questions – Company Name
1. Provisions, Clauses, Funding, etc.
a. The Government is considering Economic Price Adjustment (EPA) for the following commodities:
· Cement and Concrete: PCU32733273 (Bureau of Labor Statistics)
· Metals and Metal Products: WPU101704 (Hot Rolled Steel Bars, Plates, and Structural Shapes -Bureau of Labor Statistics)
How important is EPA to the Offeror and are these the correct commodities to consider?
b. In your estimation, how much time (in weeks) would you require between Phase 1 and Phase 2, of this 2 Phase Design Build project, to develop your technical proposal?
c. This action may be subject to the availability of funds. Would the inclusion of FAR Clause 52.232-18: Availability of Funds influence your decision to submit an offer? If so, please explain.
FAR Clause 52.232-18 Availability of Funds: Funds are not presently available for this contract. The Government’s obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer.