Q and A.pdf
PDF 69 KB Posted
- Attached to
- Finger Weir Materials, Mud Mountain Dam, Enumclaw, WA Federal contract opportunity
- Solicitation number
- W912DW24Q0027
About this file
This document is a Question and Answer (Q&A) related to Solicitation W912DW24Q0027 for the purchase of materials and tools for a Finger Weir assembly at Mud Mountain Dam in Enumclaw, WA. The Q&A addresses a question about the spacing between 5/8" diameter staggered holes in two line items for 316 stainless steel 1/4" perforated plates. The response indicates there is no special criteria for the hole spacing other than they must be evenly spaced. The solicitation covers a variety of stainless steel materials and tools required for the Finger Weir assembly project, including plates, tubes, bars, welding wire, grinding disks, and handheld tools. The contracting agency is the U.S. Army Corps of Engineers Seattle District.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912DW24Q0027 MMD FPF FINGER WEIR MATERIALS.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912DW24Q0027
MMD FPF Finger Weir Assembly
Q&A
Q: The below two line items men�on staggered spacing, but no distance of the spacing has been noted.
Can you please advise on the distance of the spacing between the 5/8” holes?
(2) 316 Stainless Steel 1/4" Perforated Plate, 81 5/8” Length, 16” width, 5/8” Diameter staggered holes.
(10) 316 Stainless Steel 1/4" Perforated Plate, 96” Length, 50” Wide, 5/8” Diameter Staggered holes.
A: There is no special criteria for the distance of spacing other than they are evenly spaced.
END Q&A