This solicitation is for a construction project to perform maintenance dredging of the Keystone Harbor Federal Navigation Channel in Coupeville, Washington. The Corps of Engineers, Seattle District, will dredge approximately 50,000 cubic yards of sediment to a depth of 25 feet with an additional 2 feet of allowable overdepth. In-water work must occur between 2100 to 0500 hours to accommodate ferry traffic. Dredged material will be placed on the shoreline on the east side of the harbor using a clamshell dredge and barge for transport. Interested offerors should be familiar with tide, current and weather conditions in the work area. The resulting contract will be a firm-fixed-price construction contract between $1 million to $5 million. The small business NAICS code is 237990 and size standard is $30 million in average annual receipts. This procurement is reserved solely for small businesses. The solicitation and any updates can be found on SAM.gov and interested vendors can add themselves to the interested vendors list.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912DW20B0003- Keystone Dredging_ABSTRACT (Final).pdf | ||
| W912DW20B0003- FY20 Keystone Dredging (Final).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The due date for the receipt of bids is not extended and it is 8 September 2020 at 10:00 AM Pacific Time.
The purpose of this amendment is to accomplish the follow ing:
1.Replace the Attachment 01 57 20.00 10-B- Water Quality Monitoring Plan in its entirety.
2. Add FAR clause 52.204-26 in full text.
All other terms and conditions remain the same. See the follow ing changes in red:
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 01-Sep-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DW20B0003
X 9B. DATED (SEE ITEM 11)
05-Aug-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
01-Sep-2020
CODE
USA ENGINEER DISTRICT, SEATTLE
ATTN: CENWS-CT
4735 EAST MARGINAL WAY SOUTH, BLDG. 1202
SEATTLE WA 98134-2388
W912DW 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DW20B0003
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 45 00 - REPRESENTATIONS AND CERTIFICATIONS
The following have been added by full text:
52.204-26 COVERED TELECOMMUNICATIONS EQUIPMENT OR SERVICES--REPRESENTATION (DEC
2019)
(a) Definitions. As used in this provision, “covered telecommunications equipment or services” has the meaning provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
(b) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for “covered telecommunications equipment or services”.
(c) Representation. The Offeror represents that it [ ___ ] does, [ ___ ] does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument.
(End of provision)
(End of Summary of Changes)
Attachment 01 57 20.00 10-B
R0001
Water Quality Monitoring Plan – Mechanical and Hydraulic Dredging Keystone Harbor Maintenance Dredging and Disposal
19 March 2020
1. Introduction The Keystone Harbor Federal Navigation Maintenance Dredging and Disposal project requires the following water quality monitoring parameters pursuant to Water Quality Certification (WQC) #18080/Public Notice of Application CENWS-PMP-20-01 Keystone Harbor, Whidbey Island, WA for State of Washington 401 Water Quality Certification and Coastal Zone Management Act Consistency (date) and WAC 173-201A-210.
2. Mechanical Dredging:
Keystone Harbor will be dredged at night to avoid to conflicts with the Washington State Ferry service. During the dredging activities, at night, scow(s)/barge(s) will be off-loaded to a temporary staging area/stock pile or trucks. Placement of material on trucks or stockpiled upland will also occur at night during dredging. Material will be moved and graded to the placement site during daylight hours. The material is coarse grained (sand/gravel) and will contain little water when it’s placed on land so impacts to water quality are not expected.
Turbidity applicable criteria:
o Turbidity should not exceed 5 NTU over background or 10% over background if background is greater than 50 NTU, or a visible plume at the point of compliance.
Constituents monitored:
o Turbidity monitoring during the channel dredging is not possible since dredging will occur at night to avoid interference with the Washington State Ferry service.
o Turbidity monitoring at the placement site is not necessary. Since the material will be placed on land or in trucks, will have little to no water in it, and is course grained material, impacts to water quality in the nearby water bodies are not expected.
3. Hydraulic Dredging:
Keystone Harbor will be dredged at night to avoid to conflicts with the Washington State Ferry service. Placement of material via pipeline will also occur at night during dredging. The material is coarse grained (sand/gravel) so impacts to water quality are not expected.
Turbidity applicable criteria:
o Turbidity should not exceed 5 NTU over background or 10% over background if background is greater than 50 NTU, or a visible plume at the point of compliance.
Constituents monitored:
o Turbidity monitoring during the channel dredging is not possible since dredging will occur at night to avoid interference with the Washington State Ferry service.
o Visual monitoring at the placement site will occur only if light conditions allow. This would likely occur at dawn during summer months after a night of dredging, but prior to ferry service commencement. The contractor will observe if there is a turbidity plume from shore and at the Point of Compliance, which is 150 feet down current from the placement.
Frequency of Monitoring:
The contractor shall monitor for turbidity visually daily after placement activities at dawn, if it occurs prior to the ferry service commencement.
The contractor shall continue to monitor and record (written) daily visual turbidity monitoring at the disposal site during every disposal event every day at dawn (only if there is daylight prior to the ferry service commencement). At any point, including observations outside normal monitoring, if visual monitoring indicates a turbidity plume, the exceedance protocol listed below shall be followed.
Sampling Approach:
The contractor shall visually observe turbidity at dawn (if prior to ferry service commencement) and record the findings according to the frequency.
The contractor shall visually observe turbidity within the placement area and record the findings of every disposal action at dawn, if it occurs prior to ferry service commencement.
Monitoring Locations:
The area of mixing point of compliance for turbidity is 150 feet down-current from the point of placement, and thus will move as disposal progresses.
Exceedances and Exceedance Protocol If a visual turbidity plume is present at or beyond 150 feet from the dredging activity and/or within the disposal area for a disposal action, that sample is recorded as an EXCEEDANCE.
o The Contractor shall immediately verify that dredging and disposal BMPs are already implemented. If not, immediately implement appropriate BMPs.
o The Contractor shall notify the Corps by telephone as soon as is practicable, but within 30 minutes after there has been a visual exceedance.
o The Corps will notify Washington Department of Ecology (WA Ecology) of the situation as soon as is practicable, but within 24 hrs of the visual exceedance.
o The Corps will work with the Contractor to evaluate and identify conditions or actions that may be contributing to increased turbidity.
During the notification and evaluation period, the Contractor will monitor and record the turbidity plume every 30 minutes until it is no longer visible.
If the visual turbidity is caused by the dredging and/or disposal actions, those actions will be immediately addressed and corrected.
If compliance cannot be achieved, the Contracting Officer may issue a stop work order until corrections are completed and/or plume has dissipated.
Once compliance has again been achieved, the Contracting Officer will order the Contractor to resume dredging.
The Corps will provide monitoring data to WA Ecology and notify WA Ecology that dredging has resumed.
4. Reporting:
The Corps will report exceedances, including potential causes and BMPs to prevent reoccurrence, and/or dredging shut downs to WA Ecology by telephone and email as soon as is practicable, but within 24 hrs.
The contractor shall document any dredging shut downs with an Incident Report, which will be transmitted to the Corp by email and through the QCS/RMS system within 24 hours of the exceedance.
The Incident Report shall document all exceedances and will include the date, time, location, activity, turbidity data collected, name of person collecting the data, names of persons notified of the exceedance, photographs if taken, and summary of how the exceedance was resolved following the above protocol.
The Incident Report shall be sent to WA Ecology within five (5) days of the exceedance, per the 401 Certification.
Per the 401 WQC, weekly turbidity (visual or measured) reporting will be sent to WA Ecology.
Within 60 days of termination of the dredging and disposal activities, the Corps will submit a summary report of the turbidity results to WA Ecology.
5. Responsibility and Communication Plan:
The Corps will oversee turbidity monitoring conducted by the contractor.
The Corps will be responsible for coordinating with WA Ecology and submitting the Turbidity
Monitoring Reports and data provided by the contractor.
The Corps will notify WA Ecology within 24 hours if an exceedance occurs.
The Corps will coordinate with the dredging contractor.
The contractor shall provide Turbidity Monitoring Report and data to the Corps, as directed.
The contractor shall notify the Corps within 30 minutes of a confirmed exceedance and follow required notifications per the exceedance protocols.
The contractor POC will be provided in the Contractor Water Quality Monitoring Plan.
The Corps Points of Contact for turbidity monitoring will be Michael Suh, Project Manager (206-
764-6671), and Chemine Jackels, Environmental Coordinator (206-764-3646).
The WA Ecology Point of Contact is Laura Inouye, (360-407-6165).
Official reporting of any incidents are to be sent to both the WA Ecology Point of Contact AND to the fednotification@ecy.wa.gov inbox.
mailto:fednotification@ecy.wa.gov
| 01 57 20.00 10-B R0001.pdf |
| 2. Mechanical Dredging: |
| 3. Hydraulic Dredging: |
| 4. Reporting: |
| 5. Responsibility and Communication Plan: |