W912DW19R0008 AMENDMENT NO. 0001

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912DW19R0008

86518

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Request for Proposal (RFP) W912DW19R0008, Aircraft Engine Test and Evaluation Facility, JBLM, WA Amendment No. 0001

Please see continuation page for the Amendment details.

1. CONTRACT ID CODE PAGE OF PAGES

1 24

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 07-May-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DW19R0008

X 9B. DATED (SEE ITEM 11)

24-Apr-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

07-May-2019

CODE

USA ENGINEER DISTRICT, SEATTLE

ATTN: CENWS-CT

4735 EAST MARGINAL WAY SOUTH, BLDG. 1202

SEATTLE WA 98134-2388

W912DW 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

dd

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT NO. 0001

1. The purpose of this Amendment No. 0001 is to incorporate the following revised documents:

a. Section 00 21 16, Instructions to Offerors

b. Section 00 22 16, Evaluation Factors for Award

c. Section 00 72 00, General Conditions

d. Section 00 73 00-A, Index of Drawings

e. Section 23 09 23, Appendix A

f. Drawing Sheet T-007

2. The proposal due date and time remains unchanged as a result of this Amendment No. 0001.

3. The attached revised sections are to be replaced in their entirety. Specifications changes are generally identified, for convenience, either by strikeout for deletions, and double underlining of text for additions or a single dark line in the margin. All portions of the revised sections shall apply whether or not changes have been indicated.

4. NOTICE TO OFFERORS: Offerors must acknowledge receipt of all amendments including this amendment by number and date on SF1442.

5. All other terms and conditions remain unchanged.

Encl:

Section 00 21 16 (Revised) Section 00 22 16 (Revised) Section 00 72 00 (Revised) Section 00 73 00-A (Revised) Section 23 09 23 Appendix A Drawing Sheet T-007 (Revised)

SECTION 00 21 16 - INSTRUCTIONS TO PROPOSERS

The following have been modified:

INSTRUCTIONS TO OFFERORS

REVISED – AMENDMENT NO. 0001

1. PROPOSAL SUBMISSION INSTRUCTIONS

Due to heightened security at Government installations, those offerors who have their proposals hand-delivered shall contact Procurement Technician, Sonia Frees at 206-764-3516 or Contract Specialist, Shawna West at 206-764-6575 prior to delivering to the address shown below. At the time specified below, it will be announced that receipt of proposals is closed.

Time-consuming sign-in and escort procedures and may impact the timely delivery of offers. See FAR 52.215-1 for rules concerning late proposals.

See Box 13 of the Standard Form 1442 for the time and date proposal(s) are due or as identified in subsequent amendments

EMAIL: Emailed Proposal will NOT be accepted.

FAX: Faxed Proposal will NOT be accepted.

FED-EX/UPS: Shawna West, Contract Specialist, Building 1202 U.S. Army Corps of Engineers, Seattle District

CENWS-CTA

4735 E. Marginal Way S., Bldg # 1202

Seattle, WA 98134-2385 Note: Commercial Carriers will not deliver to PO Boxes

MAIL: Shawna West, Contract Specialist, Building 1202 U.S. Army Corps of Engineers, Seattle District

CENWS-CTA

PO Box 3755 Seattle, WA 98124-3755

HAND DELIVERY: Shawna West, Contract Specialist, Building 1202 U.S. Army Corps of Engineers, Seattle District

CENWS-CTA

4735 E. Marginal Way S., Bldg # 1202

Seattle, WA 98134-2385

The method of Hand Deliver has changed and takes longer than the previous method of arriving at the Federal Center South building lobby to deliver your proposal. Please allow sufficient time to allow for heightened security at Government installations and to get to our new location in Building #1202. Allow time to park, pass through a metal detector, sign in, and receive a building pass at the Federal Center South Building. From there, you will be directed to the new USACE Oxbow Building (#1202) which sits behind the Federal Center South Building. Allow additional time.

Report to the Security Desk in the lobby of the USACE Oxbow Building and call Sonia Frees, Procurement Technician at 206-764-3516, or Shawna West, Contract Specialist at 206-764-6575. A Contracting representative will come down and accept your Proposal.

Note: If delivery is by any means other than Hand Delivery, please check prior to the due date and time to ensure that your proposal arrives on time. The Packaging that contains the proposals shall be marked:

“Proposals for Solicitation Number: W912DW19R0008, DO NOT OPEN”

Offerors shall submit one (1) original and three (3) copies printed for Volume I and one (1) original printed for Volume II. Volume II shall be completely separated from Volume I and appropriately marked. Offerors shall also submit one (1) CD in read-only format with Volume I and Volume II copied on it, using two (2) .pdf files using the naming convention as follows:

#1: W912DW19R0008_COMPANYNAME_VOLUME_I_FACTORS_1-2

#2: W912DW19R0008_COMPANYNAME_VOLUME_II_REQD_DOCS

2. PROPOSAL CHARACTERISTICS

2.1 Volume I, Factors 1-2 (File #1):

2.1.1 Contents of this Volume/File shall be arranged in the following sequence:

Table of Contents Factor 1: Relevant Experience Factor 2: Past Performance

2.1.2 Page limitations for Factor 1 and Factor 2 are shown in Table 1, below. Tables of Content, Dividers, and blank pages are not included in the page limitations below, and should not be numbered. Do not submit cover sheets or cover letters for any Evaluation Factor. They will not be reviewed or evaluated.

Evaluation Factor Title Page Limitation

1 Relevant Experience 32 pages per project, single-sided, excluding Section 00 22 16 Attachments 2 and/or 3, as applicable 2 Past Performance 6 pages per project, single-sided

2.1.3 Pages for each factor should be separately and sequentially numbered (i.e., the first page submitted for evaluation for each factor should be “1”). All text shall be at least 10 pt. pitch and easily read. All text shall be typed and single-spaced. Each page shall be 8-1/2 by 11 inches. This includes pages containing diagrams, charts, and tables. Margins shall be no less than one inch (right, left, top, and bottom).

2.1.4 Pages that exceed the page limitations for any factor will not be reviewed and the information contained on those pages will not be considered for evaluation. Page limitations are per factor, i.e., an Offeror may not reduce the page count for one factor in order to submit additional pages for another factor.

2.2 Volume II, Required Documents (File #2):

2.2.1 Submit the following components in the sequence listed below:

Cover Letter Table of Contents Corporate Certificate/Authority to Bind Partnership/Joint Venture (Section 00 10 00) Completed SF 1442 and Price Schedule (Section 00 10 00) Completed SF 30 or acknowledgment of amendment(s) on SF 1442 (if applicable) Bid Guarantee Pre-Award Information (Section 00 45 00) Certification Pursuant to FAR 52.209-13 (Section 00 45 00) Joint Venture Agreement (if applicable)

2.2.2 Cover Letter Requirements:

2.2.2.1 The cover letter shall contain:

Solicitation number Name, title, address, email, and telephone number of the Offeror.

Offeror’s tax identification number (TIN) Names, titles, emails, and telephone numbers of persons authorized to negotiate on the

Offeror’s behalf with the Government in connection with this RFP.

Name, title and signature of the person authorized to sign the proposal.

A statement specifying agreement with all terms, conditions and provisions included in the RFP.

There is no page limit for Required Documents (File#2).

3. JOINT VENTURE TEAM ARRANGEMENTS (INCLUDING MENTOR-PROTÉGÉS)

3.1.1 No contract may be awarded to a Joint Venture/Mentor-Protégé that is not registered in the System for Award Management (SAM) database. The Joint Venture/Mentor-Protégé must have its own registered Data Universal Numbering System (DUNS) number. Any Joint Venture/Mentor-Protégé agreement that is required to be approved by the Small Business Administration (SBA) shall be approved in accordance to the applicable Code of Federal Regulations (CFR). If the applicable requirements are not met prior to the due date for proposals, the proposal will be rendered unawardable.

3.1.1.1 In the cover letter of your proposal, provide the complete names, addresses, and phone number of the companies comprising the Joint Venture/Mentor-Protégé.

3.1.1.2 A copy of the Joint Venture/Mentor-Protégé agreement.

3.1.1.3 Signature requirements: SF 1442, SOLICITATION, OFFER, AND AWARD (pages 00 10 00-1 and 00 10 00-2), Block 20 requires that the name and title of a person authorized to sign the offer for the Joint Venture/Mentor-Protégé be provided. In the case of a Joint Venture/Mentor- Protégé, subject Standard Form shall be signed by the principal representative of the Joint Venture/ Mentor-Protégé (or the alternate principal representative, if the principal representative is unavailable).

3.1.1.4 In addition to the requirements stated above, and to assure a single point of contact for resolution of contractual matters and payments, the Offeror shall submit a certificate signed by each participant in the Joint Venture containing the following statement:

“The parties hereto expressly understand and agree as follows:

1. (Name, title, and company) is the principal representative of the Joint Venture. As such, all communications regarding the administration of the contract and the performance of the work thereunder may be directed to him or her. In the absence of (same name, title, and company), (enter name, title, and company of alternate) is the alternate principal representative of the Joint Venture/Mentor-Protégé. These individuals have authority to sign on behalf of the Joint Venture/Mentor-Protégé.

2. Direction, approvals, required notices, and all other communications from the Government to the Joint Venture/Mentor-Protégé, including transmittal of payments by the Government, shall be directed to (enter name, title, and company of principal), principal representative of the Joint Venture/Mentor-Protégé.”

NOTE: Provide telephone numbers and email addresses for the points of contact listed in the above statement.

4. RETURN ADDRESS REQUIREMENTS

Offeror(s) must ensure that ALL mail sent to the Seattle District, U.S. Army Corps of Engineers, either pre-contract or post-contract award, has a return mailing address on the outside of the envelope, package, box, etc. ANY MAIL addressed to the U.S. Army Corps of Engineers, including but not limited to; bids, modifications to bids, proposals, revised proposals, bonds, correspondence, etc., will be REJECTED by the US Army Corps of Engineers mail room facility located in Building 1202, at 4735 East Marginal Way South, Seattle, WA 98134 if it does not contain a return mailing address. THERE WILL BE NO EXCEPTIONS.

5. COPIES OF SOLICITATION DOCUMENTS AND AMENDMENTS

Copies of the solicitation and amendments are available by INTERNET ACCESS ONLY. All solicitation documents will be posted to the Federal Business Opportunities website at http://www.fbo.gov under solicitation number W912DW19R0008.

It shall be the contractor’s responsibility to check the websites for any amendments. The Offeror shall submit in the proposal all requested information specified in this solicitation. There will be no public opening of the proposals received as a result of this solicitation.

A list of interested vendors (potential offerors and subcontractors) is available on the Federal Business Opportunities web site listed above (registration required).

Additional information regarding this solicitation and potential Offerors and/or subcontractors is available at http://www.nws.usace.army.mil/BusinessWithUs/Contracting.aspx.

6. BIDDER INQUIRY

Prospective Offerors shall submit contracting and technical inquiries and questions concerning this solicitation document via Bidder Inquiry in ProjNet at www.projnet.org/projnet.

To submit and review bid inquiry items, Offerors will need to be a current registered user or self-register into system. To self-register go to web page, click BID tab select Bidder Inquiry, select agency USACE, enter Key for this solicitation listed below, and your e-mail address, click login. Fill in all required information and click create user. Verify that information on next screen is correct and then click continue.

From this page you may view all bidder inquiries or add inquiry.

Offerors will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.

The Solicitation Number is: W912DW19R0008.

The Bidder Inquiry Key is: TG47H4-E6KFT5

The Bidder Inquiry System will be unavailable for new inquires seven (7) calendar days prior to proposal submission in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.

Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

7. PROPOSAL EXPENSES AND PRE-AWARD COSTS

This Request for Proposals (RFP) does not commit the Government to pay, as a direct charge, any costs incurred in the preparation and submission of a proposal.

8. ACCURACY IN PROPOSALS

Proposals must set forth full, accurate, and complete information as required by this RFP (including attachments).

The penalty for making false statements is prescribed in 18 U.S.C. 1001.

9. PLAN HOLDER’S LIST

For Viewing a List of Interested Vendors (i.e. Plan Holder’s List) and Receiving Notifications or email of changes regarding a solicitation, Federal Business Opportunities has these features available. For this solicitation, go to https://www.fbo.gov/ and register as a vendor or enter user name and password to login. If you wish for General Contractors, Subcontractors, Suppliers, Plan Rooms or Print Shops to have the ability to contact you, click on the "Add me to Interested Vendors" for the solicitation.

10. SUBJECT TO THE AVAILABILITY OF FUNDS

FAR Clause 52.232-18 Availability of Funds (APR 1984): Funds are not presently available for this contract. The Government’s obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer.

11. STATUTORY COST LIMITATION

This requirement is designated as an Unspecified Minor Military Construction (UMMC) project. UMMC projects are subject to a statutory limitation of $6,000,000.00. An offer in excess of this amount may not be awarded.

12. ACCESS REQUIREMENTS AND DIRECTIONS

JBLM is a controlled access installation. In order to gain access to attend the pre-proposal conference and site-visit, a temporary one (1) day vehicle pass is required to drive on JBLM. The pass may be obtained from the Visitor Center at the JBLM Main Gate. Due to heightened security, the following procedures describe how to gain access for yourself and any subcontractors attending (if they or you do not have current access to the military installation):

All attendees must have valid picture identification*. All attendees driving privately-owned vehicles (POVs) must have a valid driver’s license, proof of vehicle insurance and vehicle registration. For rental vehicle access, you must have a rental agreement.

* REAL ID Act: On 1 May 2016, JBLM began enforcing the provisions of the REAL ID Act, passed by Congress in 2005. Under the provisions of this Act, a standard driver’s license or ID card issued by any of the following states is not accepted for unescorted access on JBLM: Minnesota, Missouri and Washington. Persons requesting unescorted access on JBLM and who present a standard license or ID from one of those states will be required to present additional documentation to verify their identity prior to being allowed access on JBLM. The list of acceptable documents to present, along with a standard driver’s license or ID Card issued by one of those states, include: DoD CAC, DoD Uniformed Services Identification and Privileges Cards, U.S. Passport or U.S. Passport Card, VA Issued Health Card, U.S. Coast Guard Merchant Mariner Card, Transportation Worker ID Card (TWIC) issued by DHS, U.S. Government issued, authenticated Federal PIV credentials. US Military or Draft Record containing name and DOB, etc. A full list acceptable identification verification documents accepted can be found at http://www.lewismcchord.army.mil/ under ‘Access to JBLM’/’Visitors center’/”Visitor Information”. A state Enhanced Driver’s License (EDL) from Washington State and Minnesota are acceptable for access. Please visit the

Department of Homeland Security (DHS) website at https://www.dhs.gov/real-id-frequently-asked-questions for more information regarding REAL ID and frequently asked questions.

DIRECTIONS to Visitor Center / Liberty Gate (Main Gate): From I-5, take Exit 120 (JBLM - Lewis Main) and proceed to the Visitor Center. The Visitor Center is on the far right just before the Main Gate.

13. PRE-PROPOSAL CONFERENCE AND SITE VISIT

A one-time, pre-proposal conference and site visit will be conducted on 2 May 2019 at 9:00 am local time.

Directions to the pre-proposal conference and site visit are included as a separate attachment to the solicitation posting. Offerors and any subcontractors desiring to attend should arrive no later than 9:00 am local time for the pre-proposal conference and site visit.

OFFERORS ARE URGED AND EXPECTED to inspect the site where construction is to be performed and to satisfy themselves as to all general and local conditions which may affect the cost of performance of the Contract, to the extent such information is reasonably obtainable.

SECTION 00 22 16 - SUPPLEMENTARY INSTRUCTIONS TO PROPOSERS

EVALUATION FACTORS FOR AWARD

REVISED – AMENDMENT NO. 0001

1.0 BASIS OF AWARD

Award of this Contract will be made to the technically acceptable responsible Offeror submitting the lowest priced offer – Lowest Priced Technically Acceptable Offer (LPTA). This acquisition will result in the award of a firm-fixed price, construction contract.

The technical evaluation of each proposal will be solely on the basis of Technical Evaluation Factors found in this section.

The Government will evaluate each proposal on a technically acceptable/unacceptable basis only with respect to the technical evaluation factors (criteria) described herein. Award will be to the Offeror who presents the technically acceptable proposal with the overall total lowest price. It is the intent of the Government to award off initial offers without discussions.

2.0 PROPOSAL EVALUATION

2.1 Technical Evaluation:

Acceptability will be based on all factors receiving an acceptable rating. The proposal will be evaluated according to the CRITERIA for Non-Price Evaluation Factors of this section.

Proposals will receive either an ACCEPTABLE or an UNACCEPTABLE rating for each of the evaluation factors. Find the description of these ratings in Table 1.

TABLE 1: TECHNICAL ACCEPTABLE/UNACCEPTABLE RATINGS

Rating: Description:

Acceptable Proposal clearly meets the minimum requirements of the solicitation.

Unacceptable Proposal does not clearly meet the minimum requirements of the solicitation.

2.2 Price Evaluation:

In accordance with FAR provision 52.217-5, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Additionally, the prices for the base and option line items will be evaluated for fairness and reasonableness through the use of a price analysis. The prices for the base and option items will also be checked for unbalancing of line items.

The low offeror shall be determined as follows—

1) Those offerors whose non-priced proposals were determined to be technically acceptable and their offered prices determined fair and reasonable will be eligible for award consideration.

2) The Government will award to the technically acceptable lowest priced offeror and lowest price is determined by totaling the base items and option items.

3.0 EVALUATION PROCESS:

The evaluation process consists of three parts:

1) Proposal Compliance Review. This is an initial review to ensure that all required forms and certifications are complete and that a complete proposal is received. An initial review of each of the proposals will be conducted to check for apparent errors, omissions and areas that require clarification. The purpose of this preliminary review session is to eliminate minor irregularities or apparent clerical mistakes. This preliminary evaluation will ensure that each proposal contains the Price Volume II and the correct number of copies.

2) Relevant Experience and Past Performance. Relevant Experience and Past Performance will be evaluated according to the CRITERIA for Non-Price Evaluation Factors found in this section.

3) Price Evaluation. The Government will evaluate price for fairness and reasonableness through the use of price analysis. Price will also be verified for unbalancing of line items.

3.1 Definitions:

a) Clarification is a limited exchange with an Offeror for the sole purpose of eliminating minor irregularities, informalities, or apparent clerical mistakes in the proposal or to address adverse past performance not previously addressed with the Offeror. Clarifications do not give an Offeror the opportunity to revise or modify its proposal and are used, as necessary, when not opening discussions.

b) Communications are a limited exchange with an Offeror used to assist in determinations of the competitive range. Communications are limited to enhancing Government understanding of proposals and addressing adverse past performance information not previously addressed if said information is the determining factor preventing an Offeror from being included in the competitive range. Such communications shall not be used to cure proposal deficiencies or material omissions, or otherwise revise the proposal.

c) Discussions offer the opportunity to resolve deficiencies or weaknesses in the proposals, based on the requirement and the evaluations factors set forth in the solicitation. If the Contracting Officer determines it is necessary to open discussions, they must discuss with all Offerors in the competitive range. Offerors have the opportunity to revise their proposals at the conclusion of discussions.

d) Year: A “year” is 365 consecutive days.

3.2 Bid Guarantee:

The Offeror is required to submit a bid guarantee along with its proposal. The bid guarantee shall be included in Volume II of the proposal. Any proposal received without a bid guarantee will be rejected and is ineligible for review by the Government. The amount of the Bid Guarantee shall be twenty (20) percent of the Offeror’s proposed price or $3,000,000.00, whichever is less.

3.3 Submission Format:

See Section 00 21 16 for Proposal Submission Instructions and Proposal Characteristics.

4.0 EVALUATION CRITERIA

4.1 Criteria for Non-Price Evaluation Factors:

Proposals shall concisely, accurately, and completely provide the information required for each of the following non-price evaluation factors. NOTE: Absence of complete information will be deemed as if no support information was provided for that factor. Proposals that do not meet the minimum requirements of all of the non-price evaluation factors shall be determined to be UNACCEPTABLE and are not eligible for award consideration. NO assumptions may be made by the Government. Your proposal must CLEARLY demonstrate the requisite technical experience and qualifications to receive an ACCEPTABLE rating for each of the following criteria:

TABLE 2: EVALUATION

FACTORS: LOCATION: DESCRIPTION:

FACTOR A VOLUME 1, TAB A

RELEVANT EXPERIENCE

FACTOR B VOLUME 1, TAB B PAST PERFORMANCE

5.0 FACTOR A– Relevant Experience:

5.1 Definitions for Factor A (Definitions for the purposes of this factor):

Airfield means a designated area within or contiguous to a controlled perimeter of facilities specifically configured for aircraft operations; to include maintenance, ground movement, and takeoff/landing operations.

Complexity means construction with many varied elements of work or sequencing of the work required for a project of this nature.

Function means construction of an aircraft engine test facility, aircraft or vehicle maintenance facility, and or airfield facility with imbedded systems such as deluge fire sprinkler system, apparatus bays and/or a high temperature exhaust duct.

Magnitude/Cost means projects equal to or greater than Contract amount of $3,000,000.

Relevant means the present or past performance effort involved with construction or renovation projects similar in function, scope, magnitude, and complexity within the past ten (10) years.

Scope means containing many of the elements of work and of physical size of a vertical construction building building, with the minimum of 3,000 square feet.

Similar means not identical but showing a resemblance in qualities or characteristics of the proposed project.

Team means the Prime Contractor/Offeror (including any Affiliates as defined in Paragraph 5.2, below) and/or its major/key subcontractors, taken as a whole.

5.2 Submission Requirements for Factor A:

For this Factor, the Offeror shall submit examples of construction projects which illustrate the relevant experience on projects of similar function, scope, magnitude, and complexity as defined in paragraph 5.1. The Offeror may submit construction projects performed by parent companies, affiliates, separate divisions, or other entities associated with the Offeror (hereinafter collectively referred to as Affiliate(s)). If the Affiliate(s) have the relevant experience, and the Offeror can show that this association will continue through the execution of this contract, then that experience may be deemed relevant, and will be considered for this Factor.

Restated, only those projects for which the Offeror or its Affiliate(s) (as long as it is demonstrated that said Affiliate(s) will affect the performance of the Offeror) were the prime contractor shall be submitted. If the experience of an Affiliate is submitted for evaluation, it shall be accompanied by a letter of commitment signed by the Affiliate and the Offeror binding affiliate resources to the performance of the project. This letter must be signed by a person authorized to bind the Affiliate to dedicate its resources—its workforce, management, facilities, or other resources— to the performance of the work under this solicitation.

The Offeror shall document the teaming arrangement with the Affiliate by utilizing the Letter of Commitment for Affiliate, Parent Company, Separate Division, or Other Entity (Attachment 2) found at the end of this Section 00 22 16, or of similar document.

Offeror shall submit at least one (1) project example, but not more than four (4) project examples which demonstrate Offeror’s (or that of an Affiliate specifically for the execution of this contract) relevant experience with a construction value of at least $3,000,000. The submitted project(s) for paragraph 5.2.1 and 5.2.2 shall have been performed by the Offeror acting as the Prime Contractor (or Affiliate). The submitted project(s) for paragraph 5.2.3 may have been performed by the Offeror acting as a Key Subcontractor or a Key Subcontractor on your team for this project. If submitting a project performed by a Key Subcontractor, Attachment 3, Letter of Commitment for Key Subcontractor, shall also be provided. Each submitted project shall be 100% completed and accepted by the client within ten (10) years from the date of issuance of this solicitation. If the Offeror submits more than four (4) project examples, only the first four will be evaluated, starting with the most recent and working backwards in time. The submitted project(s) shall also have elements matching the following:

5.2.1 At least one (1) project shall be new construction of a pre-engineered building where the Offeror performed as the Prime Contractor (or Affiliate).

5.2.2 At least one (1) project shall be new construction or renovation of an aircraft facility within or contiguous to a Federal Government airfield where the Offeror performed as the Prime Contractor (or Affiliate).

5.2.3 At least one (1) project shall be new construction of a facility with a deluge fire sprinkler system or a high temperature exhaust duct where the Offeror performed as the Prime Contractor (or Affiliate) or Key Subcontractor, or a Key Subcontractor on your team for this project.

Note: Project experience for Factor A must be submitted using Attachment 1.

The total of at least one (1) and not more than four (4) submitted projects combined, must meet the three elements of the especially relevant construction experience areas listed above, although all three elements do not necessarily need to be present in any one project, or all projects. However, each project submitted must demonstrate at least one of the three elements indicated above and in the matrix below.

Using a Relevant Experience Matrix similar to that shown below, clearly identify to which experience area(s) each project example pertains (i.e. Project 1 demonstrates new construction or renovation of an aircraft facility within or contiguous to a Federal Government airfield):

Relevant Experience Matrix for Factor A:

Submitted Projects:

New construction of a pre-engineered building, shall be as Prime Contractor (or Affiliate)

Para. 5.2.1

New construction or renovation of an aircraft facility within or contiguous to a Federal Government airfield, shall be as Prime Contractor (or Affiliate)

Para. 5.2.2

New construction of a facility with a deluge fire sprinkler system or a high temperature exhaust duct, shall be as Prime Contractor (or Affiliate) or Key Subcontractor

Para. 5.2.3

1 X

2 X X

3 X

5.3 Evaluation Method for Factor A:

Factor A will be evaluated to determine whether it meets the requirements of this factor. If any of the required information is not provided in the Offeror’s proposal, the Offeror will be evaluated as “Unacceptable.” The Government reserves the right to verify the experience record of cited projects or other recent projects by reviewing the Past Performance Information Retrieval system (PPIRS) which includes the CCASS/ACASS ratings, other DOD or Government appraisal systems. The Government may check any or all cited references to verify supplied information.

TABLE 3: FACTOR A - RELEVANT EXPERIENCE OF OFFEROR/PRIME

Acceptable The proposal clearly demonstrates how at least one of the project examples submitted meets the requirements of paragraph 5.2.

Unacceptable The proposal does not clearly demonstrate how at least one of the project examples submitted meets the requirements of paragraph 5.2.

6.0 FACTOR B – Past Performance

6.1 Submission Requirements for Factor B:

The project examples submitted for Paragraph 5.2 will be used for evaluation of Past Performance. DO NOT provide Past Performance references for projects other than those project examples provided for Factor A.

If a completed interim and/or final Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted with the proposal. Offeror shall not submit a Past Performance Questionnaire (PPQ) when a completed CPARS evaluation is available. If both are submitted, only the CPARS will be evaluated.

Completed PPQs should be submitted with your proposal ONLY if a CPARS evaluation is not available. If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the Offeror should complete and submit with the proposal the first page of the PPQ (Attachment 4), which will provide contract and client information for the respective project(s). Offeror should follow-up with clients/references to ensure timely submittal of questionnaires.

If the client requests, PPQs may be submitted directly to the Government's point of contact, Shawna West, via email at shawna.west@usace.army.mil prior to the proposal closing date. The Offeror shall instruct the clients to refer to the solicitation number in the subject line. The PPQs are Source Selection materials. All successfully submitted PPQs will receive an e-mail confirmation upon receipt. If the Offeror does not receive the confirmation, it is their responsibility to follow up to ensure the Government has received the information.

Offeror shall not incorporate by reference into their proposal PPQs or CPARS previously submitted for other solicitations. However, this does not preclude the Government from utilizing previously submitted past performance information in the past performance evaluation.

Offeror may provide explanation on problems encountered on past projects and the corrective actions taken by the Offeror.

6.2 Evaluation Method for Factor B: The method of rating for Factor B shall be as follows:

The Government will evaluate past performance based on a demonstrated record of performance. Past performance information is an indicator of an Offeror’s ability to perform the contract successfully. The Government will evaluate the successful completion of all project examples submitted in the proposal for Factor A. The Government reserves the right to check any or all cited references to verify supplied information and to assess owner satisfaction.

The Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS), including Contractor Performance Assessment Reporting System

(CPARS).

While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.

TABLE 4: FACTOR B – PAST PERFORMANCE EVALUATION RATING

Acceptable

Based on the offeror’s performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror’s performance record is unknown.

Unacceptable

Based on the offeror’s performance record, the Government does not have a reasonable expectation that the offeror will be able to successfully perform the required effort.

NOTE: In the case of an Offeror without a record of past performance or for whom information on past performance is not available, the Offeror’s past performance may not be evaluated as favorable or unfavorable.

[Ref: FAR 15.305(a)(2)(iv)]. Therefore, the Offeror shall be determined to have unknown past performance. In the context of acceptability/unacceptability, “unknown” shall be considered “acceptable.”

SECTION 00 22 16 - ATTACHMENT 1

OFFEROR or KEY SUBCONTRACTOR EXPERIENCE FORM

USE ONE FORM PER PROJECT

COMPLETE THE APPLICABLE ITEMS FOR FACTOR A

Note: A separate Word version of this document will be accessible on fedbizopps at fbo.gov

Provide the following information to show examples of projects your company constructed within the last ten (10) years indicating experience with recent and relevant projects.

1. Type of Construction Represented: ______________________________________________________

2. Name of Offeror: ____________________________________________________________________

3. Project Title: _______________________________________________________________________

4. Contract/Project Number: _____________________________________________________________

5. Project Owner and Location: ___________________________________________________________

6. Total Contract Value: $ _____________________________

7. If Offeror performed as Subcontractor, the $-value of Subcontract: $ ___________________________

8. Construction Phase Start Date (Month/Day/Year): __________________________________________

9. Original Construction Phase Completion Date (Month/Day/Year): _____________________________

10. Actual Construction Phase Completion Date (Month/Day/Year): _____________________________ (Actual date if project has been completed)

11. Name of Owner/Client POC: __________________________________________________________

12. Telephone Number of Owner/Client POC: _______________________________________________

13. Email Address of Owner/Client POC: ___________________________________________________

14. General Scope of Construction Project: __________________________________________________

COMPLETE ONLY FOR FACTOR A – RELEVANT EXPERIENCE OF OFFEROR/PRIME:

15. Describe/demonstrate how the project is relevant to the solicitation in the following areas, as stated in the Factor A Definitions:

(a) Complexity: ____________________________________________________________________

(b) Function: ____________________________________________________________________

(c) Magnitude/Cost:_________________________________________________________________

(d) Similar:________________________________________________________________________

16. If applicable, explain how the project is relevant to the solicitation in the following areas, as defined in Factor A:

(a) New construction of a pre-engineered building:________________________________________

(b) New construction or renovation of an aircraft facility within or contiguous to a Federal Government airfield:

(c) New construction of a facility with a deluge fire sprinkler system or a high temperature exhaust duct:__________________________________________________________________________

17. Describe your role and responsibility during construction of the project (indicate whether your firm performed as a prime or subcontractor and what percentage of work you self-performed and/or type of work you subcontracted out, if applicable):

20. Summarize your performance evaluation by Customer/Client, if known:

21. Were you issued a Cure Notice, Show Cause Letter, Terminated for Default and/or Assessed Liquidated Damages? (If “Yes” provide an explanation):

ATTACHMENT 2

LETTER OF COMMITMENT OF AFFILIATE, PARENT COMPANY,

SEPARATE DIVISION, OR OTHER ENTITY

(USE COMPANY’S LETTERHEAD)

TO: Contracting Officer:

SUBJECT: Letter of Commitment for Proposed Contract for:

Dear Sir or Madam:

I hereby indicate my commitment that, in the event of an award of a contract to (Fill in name of Proposer), (insert name of affiliate, parent company, separate division, or other entity) will fulfill the duties of (state role on project).

Sincerely, (Signed by Authorized Official) Date:

ATTACHMENT 3

LETTER OF COMMITMENT OF KEY SUB-CONTRACTOR

(USE SUB-CONTRACTOR’S COMPANY LETTERHEAD)

TO: Contracting Officer:

SUBJECT: Letter of Commitment for Proposed Contract for:

Dear Sir or Madam:

I hereby indicate my commitment that, in the event of an award of a contract to (Fill in name of Offeror), (insert name of subcontractor) will fulfill the duties of (state role on project).

Sincerely, (Signed by Authorized Official)

Date:

NOTE: NAVFAC/USACE REQUESTS THAT THE CLIENT COMPLETES THIS QUESTIONNAIRE AND

SUBMITS DIRECTLY BACK TO THE OFFEROR. THE OFFEROR WILL SUBMIT THE COMPLETED

QUESTIONNAIRE TO USACE WITH THEIR PROPOSAL, AND MAY DUPLICATE THIS

QUESTIONNAIRE FOR FUTURE SUBMISSION ON USACE SOLICITATIONS. CLIENTS ARE

HIGHLY ENCOURAGED TO SUBMIT QUESTIONNAIRES DIRECTLY TO THE OFFEROR.

HOWEVER, QUESTIONNAIRES MAY BE SUBMITTED DIRECTLY TO USACE. [PLEASE CONTACT

THE OFFEROR FOR USACE POC INFORMATION. THE GOVERNMENT RESERVES THE RIGHT TO

VERIFY ANY AND ALL INFORMATION ON THIS FORM.

2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other Percent of project work performed:

If subcontractor, who was the prime (Name/Phone #):

3. Contract Information:

Contract Number:

Delivery/Task Order Number (if applicable):

Contract Type: Firm Fixed Price Cost Reimbursement Other (Please specify):

Contract Title:

Contract Location:

Award Date (mm/dd/yyyy):

Contract Completion Date (mm/dd/yyyy):

Actual Completion Date (mm/dd/yyyy):

Explain Differences:

Original Contract Price (Award Amount):

Final Contract Price (to include all modifications, if applicable):

Explain Differences:

4. Project Description:

Complexity of Work High Med Routine How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.):

CLIENT INFORMATION (Client to complete Blocks 5-8)

5. Client Information:

Name:

Title:

Phone Number:

Email Address:

6. Describe the client’s role in the project:

7. Date Questionnaire was completed (mm/dd/yy):

8. Client’s Signature:

ATTACHMENT 4: CUSTOMER SATISFACTION SURVEY

NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0)

CONTRACT INFORMATION (Contractor to complete Blocks 1-4)

1. Contractor Information:

Firm Name: CAGE Code:

Address: DUNs Number:

Phone Number:

Email Address:

Point of Contact: Contact’s Phone Number:

ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT EVALUATION

(E) Exceptional:

Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.

An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.

(VG) Very Good:

Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.

(S) Satisfactory:

Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract. There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.

(M) Marginal:

Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.

A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.

(U) Unsatisfactory:

Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.

An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.

(N) Not Applicable:

No information or did not apply to your contract.

Rating will be neither positive nor negative.

ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT EVALUATION

TO BE COMPLETED BY CLIENT

PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST REFLECTS

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.

1. QUALITY:

a) Quality of technical data/report preparation efforts E VG S M U N

b) Ability to meet quality standards specified for technical performance

E VG S M U N

c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance

E VG S M U N

d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)

E VG S M U N

2. SCHEDULE/TIMELINESS PERFORMANCE:

a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)

E VG S M U N

b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract

E VG S M U N

3. CUSTOMER SATISFACTION:

a) To what extent were the end users satisfied with the project? E VG S M U N

b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes; responsiveness to administrative reports, businesslike and communication)

E VG S M U N

c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer?

E VG S M U N

d) Overall customer satisfaction E VG S M U N

4. MANAGEMENT/ PERSONNEL/LABOR

a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force?

E VG S M U N

b) Ability to hire, apply, and retain a qualified workforce to this effort

E VG S M U N

c) Government Property Control E VG S M U N

d) Knowledge/expertise demonstrated by contractor personnel E VG S M U N

e) Utilization of Small Business concerns E VG S M U N

f) Ability to simultaneously manage multiple projects with multiple disciplines

E VG S M U N

g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes

E VG S M U N

h) Effectiveness of overall management (including ability to effectively lead, manage and control the program)

E VG S M U N

5. COST/FINANCIAL MANAGEMENT

a) Ability to meet the terms and conditions within the contractually agreed price(s)?

E VG S M U N

b) Contractor proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client

E VG S M U N

c) If this is/was a Government cost type contract, please rate the Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns)

E VG S M U N

Please provide responses to the questions above (if applicable) and/or additional remarks. Furthermore, please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk. (Please attach additional pages if necessary)

End of Evaluation…