W912DW19B0002-R0002.pdf
PDF 990 KB Posted
- Solicitation number
- W912DW19B0002
About this file
Amendment R0002 for solicitation W912DW19B0002
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Signed_Abstract_of_Offers.pdf | ||
| W912DW19B0002-R0001.pdf | ||
| W912DW19B0002_AFD_Water_Mist.pdf | ||
| Request_for_Visitation_Authority.docx | DOCX document | |
| W912DW19B0002_Albeni_Falls_Drawings-_RTA.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
W912DW19B0002, AFD Oil Room Water Mist Fire Protection System, Oldtow n, ID
(see continuation page)
1. CONTRACT ID CODE PAGE OF PAGES
1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 03-May-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DW19B0002
X 9B. DATED (SEE ITEM 11)
29-Mar-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
03-May-2019
CODE
USA ENGINEER DISTRICT, SEATTLE
ATTN: CENWS-CT
4735 EAST MARGINAL WAY SOUTH, BLDG. 1202
SEATTLE WA 98134-2388
W912DW 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DW19B0002
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
R0002
1. This amendment two (0002) provides for the following:
a. Inclusion of Small Business Subcontracting Plan requirements in Section 00 21 00 Instructions to Bidders.
b. Revision to Spec Section 01 82 00.
c. Addition of Spec Section 08 11 13.
2. The proposal submittal time and date of May 7, 2019 at 1:00:00 p.m. LOCAL TIME remains the same.
3. The attached revised sections are to be replaced in their entirety. Specifications changes are generally identified, for convenience, either by strikeout for deletions, and double underlining of text for additions or a single dark line in the margin. All portions of the revised sections shall apply whether or not changes have been indicated.
4. NOTICE TO OFFERORS: Offerors must acknowledge receipt of this amendment by number and date on offer.
Encl:
00 21 00 Instructions to Bidders (revised) 01 82 00 (revised) 08 11 13 (new)
SECTION 00 21 00 - INSTRUCTIONS
The following have been modified:
INSTRUCTIONS TO BIDDERS
! ! ! INSTRUCTIONS TO B I D D E R S ! ! !
1. TELEPHONES: There are no public telephones at the Seattle District Corps of Engineers.
2. BUSINESS HOURS: For the Seattle District Corps of Engineers are from 7:30 A.M. to 4:00 P.M., Monday through Friday.
3. ATTENTION: If hand delivering your bid, please allow sufficient time to allow for heightened security at Government installations and to get to Building #1202. Allow time to park, pass through a metal detector, sign in, and receive a building pass at the Federal Center South Building. From there, you will be directed to the USACE Oxbow Building (#1202) which sits behind the Federal Center South Building. Allow additional time.
Report to the Security Desk in the lobby of the USACE Oxbow Building (#1202) and you will be directed to the bid opening room. This room will be available 30 minutes prior to the bid opening.
If you do not wish to be present when bids are opened and would like to drop off your bid, contact the following persons upon reporting to the Security Desk: Sonia Frees, Procurement Technician, at 206-764-3516, or the Contracting Specialist Monique Paano, at 206-764-6084. A Contracting representative will come down and accept your bid.
A bid is not received by the Government until it is in the physical possession of a representative of the Contracting office. Security guards and other non-contracting personnel are NOT authorized to accept bids on behalf of the Government.
Bids are due by the date and time listed in block 13 of the SF1442.
Note: If delivery is by any means other than Hand Delivery, please check prior to the due date and time to ensure that your bid has arrived on time.
4. BIDDING DOCUMENTS: Register for solicitations at the Internet site: http://www.fedbizopps.gov/
5. FOR INQUIRIES AND ADMINISTRATIVE MATTERS:
Contact: Monique Paano, Contract Specialist, Monique.a.paano@usace.army.mil, or 206-764-6084.
Mail: Seattle District, U.S. Army Corps of Engineers, P.O. Box 3755, CENWS-CTC Seattle, WA 98124-3755
Street: Seattle District, U.S. Army Corps of Engineers, 4735 E. Marginal Way S., Bldg 1202, Seattle, WA 98134-
6. TECHNICAL QUESTIONS:
All inquiries regarding this solicitation are to be submitted via ProjNet-Bidsm. Telephone and email inquiries will not be accepted. ProjNet-Bidsm is a web-based program that allows bidders to post questions regarding the solicitation and to view all questions by other bidders and answers by USACE. ProjNet-Bidsm can be accessed through ProjNetsm at https://www.projnet.org To access the ProjNet-Bidsm website the first time:
1) Click the Bid tab
2) Click Bidder Inquiry. (The Agency is USACE.)
3.a) Enter the following information for access:
1. The Bidder Inquiry Key: DNEM9E-4339H6
2. Valid business contact information (e.g. Company name, contact person, business address, phone number and email address). (required on first project only)
3. Establish Secret Question and Answer which will be used as a password (required on first project only) 3.b) For subsequent access use your email address, the Bid Inquiry Key and response to the Secret Question to access the ProjNet-Bidsm Module.
4) Submit technical questions. When an answer is posted to a question, the question and answer is then available for all other bidders to review.
5) For questions about the ProjNet-Bidsm, please contact the Call Center help desk toll free at 1-800-428-HELP (4357), which operates from 8AM to 5PM (Central US time zone).
ProjNet-Bid will be closed for questions 3 business days prior to the solicitation due date. All bidders will be held to have reviewed the questions and responses in ProjNet-Bidsm prior to bid submission. Nothing in the solicitation is changed unless an amendment is sent out.
7. RETURN THE FOLLOWING WITH YOUR BID:
SF1442 Solicitation, Offer, and Award
Section 00 45 00 Representations and Certifications to include the Pre-Award information
20% Bid Bond (SF24) -- Bid Bonds must be accompanied by a Power of Attorney containing an original signature from the surety. Powers of Attorney dated prior to the date of the bond will only be accepted if accompanied by certification from a current officer of the surety attesting to its authenticity and continuing validity. Electronic, mechanically applied and printed signatures, seals and dates on the power of attorney shall be considered original signatures, seals and dates, without regard to the order in which they were affixed.
Current SF24 forms are available at the following website:
http://www.gsa.gov/portal/forms/type/TOP.
8. SYSTEM FOR AWARD MANAGEMENT (SAM)
In accordance with FAR 4.1102, bidders, including those that are a Joint Venture, are required to be registered in SAM at the time they submit their bid. If the bidder is not registered in the SAM database at the time it submits its bid, the Contracting Officer will proceed to award to the next otherwise successful registered bidder. Bidders may obtain information on registration and annual confirmation requirements via the internet at http://www.sam.gov. Bidder’s SAM registration must, to clarfiy be current at the time of award.
9. BASIS OF AWARD
The Government anticipates awarding a Single Award Firm Fixed Price (FFP) Contract as a result of this IFB in accordance with FAR Part 14.408-1(a)(3). The contracting officer will make a contract award to that responsive and responsible bidder whose bid conforms to the requirements of this IFB and is found to be the most advantageous to the Government, considering only price and the price related factors included in the solicitation.
10. IMPORTANT NOTE FOR OTHER THAN U.S. SMALL BUSINESSES ONLY:
Small Business Subcontracting Plan is Required: In accordance with FAR 19.702(a)(2), the offeror selected for award shall submit a subcontracting plan to be eligible for award. The subcontracting plan does not need to be submitted with your offer, but is required to be completed prior to award. If the selected offeror fails to submit a plan, the offeror will be ineligible for award. For information on the evaluation of subcontracting plans, see Army Federal Acquisition Regulation Supplement (AFARS) Appendix DD.
(End of Summary of Changes)
AFD Oil Storage Room Water Mist Fire Protection System 18024 Pend Oreille River, ID W912DW19B0002
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 82 00
DEMONSTRATION AND TRAINING
PART 1 GENERAL
1.1 DESCRIPTION OF WORK
1.2 SUBMITTALS
1.3 INSTRUCTOR QUALIFICATIONS
1.4 ATTENDANCE
1.5 SCHEDULING
PART 2 PRODUCTS
2.1 TRAINING MATERIALS
PART 3 EXECUTION
3.1 GENERAL
3.2 COURSE CONTENT
3.2.1 Training Class on System Operation (WM-1A)
3.2.2 Training Classes for Maintenance Personnel (WM-2, WM-3)
3.3 VIDEO RECORDING
3.3.1 General
3.3.2 Audio-Video Recordings
-- End of Section Table of Contents --
SECTION 01 82 00 Page 1
RTA R0002
SECTION 01 82 00
DEMONSTRATION AND TRAINING
PART 1 GENERAL
1.1 DESCRIPTION OF WORK
This section covers furnishing all labor, equipment, and materials for providing demonstration and training for the water mistfire protection system at the Albeni Falls Powerhouse.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only.
Submittals having an "HDC" designation are to be submitted to the Hydroelectric Design Center.Submittals related to system configuration, hydraulic calculation, and equipment selection, including manufacturer's catalog data, working drawings, connection drawings, control diagrams and certificates shall be submitted concurrently as a complete package. The package will be reviewed by the U.S. Army Engineer District Fire Protection Engineer. The following shall be submitted in accordance with
SECTION 01 33 00, SUBMITTAL PROCEDURES:
SD-07 Certificates
Instructor Qualifications, Water Mist System; G
Submit at least thirty (30) days prior to start of first training session.
Resume of the Technician and Associated Video Production Company;
G
The Contractor shall submit the resume of the technician and associated video production company within thirty (30) days prior to the start of the training.
SD-11 Closeout Submittals
Training Course Plan, Water Mist System; G
Submit at least thirty (30) days prior to start of first training session.
Training Schedule; G
Submit at least thirty (30) days prior to start of first training session. At least one training session for the water mist system operation and safety shall be given prior to the first water mist discharge test.
SECTION 01 82 00 Page 2
Training Course Agenda, Water Mist System; G
Submit at least 2 weeks prior to start of first training session.
Training Materials, Water Mist System; G
Submit prior to start of first training session.
DVD Training Sections; G
Two (2) copies of the DVD material shall be submitted to the Contrcting Officer within 10 days after completion of the DVD training sections.
1.3 INSTRUCTOR QUALIFICATIONS
All training instructors shall be experienced in providing training for fire extinguishing systems, shall have expert knowledge of all aspects concerning the operation and maintenance of the water mist system being furnished, and shall be authorized and certified by the equipment manufacturers. At least thirty (30) days prior to the training, instructor qualifications, water mist systems shall be submitted.
1.4 ATTENDANCE
Attendance at each training session will not exceed 15 Government personnel.
1.5 SCHEDULING
One complete set of training sessions shall be conducted at the Project Offices at a mutually agreeable time selected by the Contracting Officer.
A maximum of two "Operations & Safety" sessions may be scheduled during evening hours to accommodate working schedules of Operators. "Electrical Maintenance" and "Mechanical Maintenance" sessions will be scheduled during regular working hours of electrical and mechanical maintenance personnel, Monday through Thursday, 7:30 a.m. to 4:00 p.m. Training sessions shall not be scheduled on any Government holidays. All sessions will be scheduled shortly after installation of the water mist system, and completion of Contractor testing of the system, but will be no later than three months after completion of the system tests. The Contracting Officer will give the Contractor at least one-month notice in advance concerning the preferred training dates at each project. The Contractor shall coordinate with the Government Representative regarding use of Government audio-visual equipment.
PART 2 PRODUCTS
2.1 TRAINING MATERIALS
The Contractor shall provide detailed and comprehensive training manuals covering all course subjects for use by each trainee, plus three additional copies. Prior to the first training session three (3) hardcopies and one electronic copy of all training manuals shall be submitted. The electronic copy shall be provided on CD in pdf format. In addition, the Contractor shall provide two complete sets of any training aids used during the training, including any special devices or test equipment used to simulate equipment problems. Training materials shall
SECTION 01 82 00 Page 3 become the property of the Government upon completion of the training.
PART 3 EXECUTION
3.1 GENERAL
The Contractor shall furnish all labor and materials necessary to conduct comprehensive on-site training for all aspects of the new equipment installed under this contract. A minimum of 6 sessions shall be provided as detailed in Paragraph "COURSE CONTENT AND SESSIONS". At least thirty
(30) days prior to the first session a training course plan, water mist systemand training schedule shall be submitted for approval. It shall include a plan with recommendations for conducting all required training courses. No training may begin until the government approves the training plan. At least fourteen (14) days prior to the first session, the Contractor shall submit; training course agenda, water mist system and all required copies of the training materials, water mist system to the Government Representative.
3.2 COURSE CONTENT
The Contractor shall conduct two (2) complete training courses for plant personnel on the operation and maintenance of the water mist system. Each course consists of three (3) classes, for a total of six training classes.
The two (2) courses shall be conducted and accomplished within 30 calendar days, and each course shall be conducted and accomplished within five (5) consecutive working days.
Training courses for the water mist fire protection system shall be as follows:
Class WM-1: Water Mist System Operation & Safety (4-hour Class)
Class WM-2: Water Mist System Electrical Maintenance(8-hour Class)
Class WM-3: Water Mist System Mechanical Maintenance (8-hour Class)
3.2.1 Training Class on System Operation (WM-1A)
Each 4-hour training class consists of two (2), 2-hour sessions on system operation. The first two hour session of each classshall be conducted as a classroom/lecture type training and the following two hour session of the class shall be a hands-on type training with the actual installed equipment. Topics of the training classes on system operation shall include, but not be limited to, system summary, principles of operation, complete operation procedures, emergency response procedures with normal operation and in the event of equipment malfunction, and safety requirements of the fire extinguishing system. Training classes shall include demonstrations of operations procedures and should utilize, as appropriate, special devices or test equipment designed to simulate common events and operational problems.
3.2.2 Training Classes for Maintenance Personnel
(WM-2, WM-3)
a.Class WM-2: Water Mist System Electrical Maintenance shall be
SECTION 01 82 00 Page 4
RTA R0002
g3endnp9 Highlight g3endnp9 Highlight provided for electrical maintenance personnel and Class WM-3: Water Mist System Mechanical Maintenance shall be provided for mechanical maintenance personnel. Each class shall include approximately four hour session of classroom/lecture type training and another four hour session of hands-on training with the actual installed equipment.
Topics of the training classes for maintenance personnel shall include detailed description of the system and all aspects of maintenance, adjustment, troubleshooting, problem diagnosis and repair procedures, as appropriate for electrical and mechanical classes. Training classes shall include demonstrations of how to diagnose various types of equipment failure and should utilize, as appropriate, special devices or test equipment designed to simulate common problems.
b. Class WM-3 for Water Mist Mechanical Maintenance shall also include detailed description of the mechanical portions of the fire protection system system and all aspects of operation procedures, maintenance, adjustment, troubleshooting, problem diagnosis and repair procedures.
3.3 VIDEO RECORDING
3.3.1 General
The Contractor shall videotape a minimum of one session of each of the training courses for future Government use. Training videos shall become property of the Government upon completion of the training.
3.3.2 Audio-Video Recordings
The Contractor shall provide equipment, materials, and trained personnel to visually and audibly record (DVD) on site operations and maintenance (O&M) training sessions for this contract. The video technician shall be employed by a video production company that has been in business for a minimum of 2 years or an independent video technician with a minimum of 2 years commercial experience. The Contractor shall submit the resume of the technician and associated video production company. The Contractor shall submit for approval an agenda or an outline breakdown of the proposed presentation. DVD shall be produced in the DVD industrial standard format. Audio shall be adjusted, filtered or otherwise controlled to ensure that the trainer can be understood at all times.
Each system or piece of equipment shall be covered in a single tape or set of DVDs which shall be correlated with the O&M manuals provided. DVD and their individual storage cases shall be identified with a typewritten label showing the project, equipment or system, and contract number; this same information shall be provided as an introduction on each DVD. When two or more DVDs are provided, they shall be submitted as a set in an appropriate storage container. Two copies of the DVD material shall be submitted to the Contracting Officer within 10 days after completion of DVD training sections.
-- End of Section --
SECTION 01 82 00 Page 5
RTA R0002
g3endnp9 Highlight
SECTION TABLE OF CONTENTS
DIVISION 08 - OPENINGS
SECTION 08 11 13
STEEL DOORS AND FRAMES
02/10
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 DELIVERY, STORAGE, AND HANDLING
PART 2 PRODUCTS
2.1 FIRE DOORS
2.1.1 Labels
2.1.2 Astragal on Fire Doors
2.2 GASKET
2.3 HARDWARE PREPARATION
2.4 FINISHES
2.4.1 Electrolytic Zinc-Coated Anchors and Accessories
2.4.2 Factory-Applied Enamel Finish
2.5 FABRICATION AND WORKMANSHIP
PART 3 EXECUTION
3.1 INSTALLATION
3.1.1 Doors
3.1.2 Fire Doors
3.2 PROTECTION
3.3 CLEANING
-- End of Section Table of Contents --
SECTION 08 11 13 Page 1
SECTION 08 11 13
STEEL DOORS AND FRAMES
02/10
PART 1 GENERAL
Description: This specification covers requirements for the replacement of two non-rated egress doors shown on the contract drawing F-101 with doors of 1-1/2 hour fire rating as defined by the NFPA 80 specification and this UFGS. The doors do not have the same dimensions. The contractor is responsible for field measuring existing door frames and providing doors with final fits in accordance with NFPA 80 . Existing framing and frame hardware locations are to be re-used. Contractor shall provide new door hardware similar in appearance to existing door hardware. Labels indicating compliance to NFPA 80 and hour ratings are to be applied at the factory. The old non-rated egress doors become property of the contractor and must be removed from the work site after project completion.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM A879/A879M (2012) Standard Specification for Steel Sheet, zinc Coated by the Electrolytic Process for Applications Requiring Designation of the Coating Mass on Each Surface
ASTM E283 (2004; R 2012) Determining the Rate of Air Leakage Through Exterior Windows, Curtain Walls, and Doors Under Specified Pressure Differences Across the Specimen
BUILDERS HARDWARE MANUFACTURERS ASSOCIATION (BHMA)
ANSI/BHMA A156.115 (2016) Hardware Preparation in Steel Doors and Steel Frames
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 252 (2017) Standard Methods of Fire Tests of Door Assemblies
NFPA 80 (2016; TIA 16-1) Standard for Fire Doors and Other Opening Protectives
STEEL DOOR INSTITUTE (SDI/DOOR)
SDI/DOOR A250.3 (2007; R 2011) Test Procedure and Acceptance Criteria for Factory Applied Finish Painted Steel Surfaces for Steel Doors and Frames
SECTION 08 11 13 Page 2
SDI/DOOR A250.6 (2003; R2009) Recommended Practice for Hardware Reinforcing on Standard Steel Doors and Frames
SDI/DOOR A250.8 (2003; R2008) Recommended Specifications for Standard Steel Doors and Frames
UNDERWRITERS LABORATORIES (UL)
UL 10C (2016) UL Standard for Safety Positive Pressure Fire Tests of Door Assemblies
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Fire Doors; G
Accessories
Weatherstripping
Submit manufacturer's descriptive literature for doors, frames, and accessories. Include data and details on door construction, panel (internal) reinforcement, insulation, fire hour rating, and door edge construction.
] 1.3 DELIVERY, STORAGE, AND HANDLING
Deliver doors and accessories undamaged and with protective wrappings or packaging. Store doors under cover in clean, dry, ventilated, and accessible locations, with 1/4 inch airspace between doors. Remove damp or wet packaging immediately and wipe affected surfaces dry. Replace damaged materials with new.
PART 2 PRODUCTS
2.1 FIRE DOORS
The two new fire doors shown on contract drawing F-101 shall be of 1-1/2 hour fire rating as specified by NFPA 80 . The existing door framing for both doors shall be reused as well as existing hardware locations. New door hardware shall be included and can be installed at the factory or on site. Contractor is responsible for final fitting and ensuring smooth closure and opening door operation after installation. Affix label as required by NFPA 80 . Measurement of existing frame dimensions is the responsibility of the contractor and required to guarantee proper fitment
SECTION 08 11 13 Page 3 of new fire rated doors. The requirements of NFPA 80 takes precedence over details indicated or specified.
2.1.1 Labels
Provide fire doors and frames bearing the label of Underwriters Laboratories (UL), Factory Mutual Engineering and Research (FM) attesting to the rating required. Testing must be in accordance with NFPA 252 or UL 10C . Provide labels that are metal with raised letters, bearing the name or file number of the door and frame manufacturer. Labels must be permanently affixed at the factory to frames and to the hinge edge of the door. Do not paint door and labels.
2.1.2 Astragal on Fire Doors
On pairs of labeled fire doors, conform to NFPA 80 and UL requirements.
2.2 GASKET
Provide Black synthetic rubber gasket with tabs for factory fitting into factory slotted frames. Insert gasket in groove after frame is finish painted. Provide door gasket where air leakage of weatherstripped doors does not exceed 1.25 cubic feet per minute of air per square foot of door area when tested in accordance with ASTM E283. Door gaps must comply with
NFPA 80
2.3 HARDWARE PREPARATION
Provide minimum hardware reinforcing gages as specified in SDI/DOOR A250.6 .
If required drill and tap doors and frames to receive finish hardware.
Prepare doors and frames for hardware in accordance with the applicable requirements of SDI/DOOR A250.8 and SDI/DOOR A250.6 . For additional requirements refer to ANSI/BHMA A156.115 . Drill and tap for surface-applied hardware at the project site.
2.4 FINISHES
2.4.1 Electrolytic Zinc-Coated Anchors and Accessories
Provide electrolytically deposited zinc-coated steel in accordance with ASTM A879/A879M , Commercial Quality, Coating Class A. Phosphate treat and factory prime zinc-coated surfaces as specified in SDI/DOOR A250.8 .
2.4.2 Factory-Applied Enamel Finish
Provide coatings that meet test procedures and acceptance criteria in accordance with SDI/DOOR A250.3 . After factory priming, apply two coats of low-gloss enamel to exposed surfaces. Separately bake or oven dry each coat. Drying time and temperature requirements must be in accordance with the coating manufacturer's recommendations. Provide red finish coat color to match approved color sample.
] 2.5 FABRICATION AND WORKMANSHIP
Provide finished doors and frames that are strong and rigid, neat in appearance, and free from defects, waves, scratches, cuts, dents, ridges, holes, warp, and buckle. Provide molded members that are clean cut, SECTION 08 11 13 Page 4 straight, and true, with joints coped or mitered, well formed, and in true alignment. Dress exposed welded and soldered joints smooth. Design door frame sections for use with the wall construction indicated. Corner joints must be well formed and in true alignment. Conceal fastenings where practicable.
PART 3 EXECUTION
3.1 INSTALLATION
3.1.1 Doors
Hang doors in accordance with clearances specified in NFPA 80 . After erection clean and adjust hardware.
3.1.2 Fire Doors
Install fire doors and frames, including hardware, in accordance with
NFPA 80 .
3.2 PROTECTION
Protect doors and frames from damage. Repair damaged doors and frames prior to completion and acceptance of the project or replace with new, as directed. Wire brush rusted frames until rust is removed. Clean thoroughly. Apply an all-over coat of rust-inhibitive paint of the same type used for shop coat.
3.3 CLEANING
Upon completion, clean exposed surfaces of doors and frames thoroughly.
Remove mastic smears and other unsightly marks.
-- End of Section --
SECTION 08 11 13 Page 5
| SF30 |
| 00 21 00 Instructions to Bidders |
| 01 82 00 |
| 08 11 13 |