AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Answ er Vendor Questions See Contiunuation.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 20-Mar-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DW18Q0029

X 9B. DATED (SEE ITEM 11)

06-Mar-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

19-Mar-2018

CODE

USA ENGINEER DISTRICT, SEATTLE

ATTN: CENWS-CT

4735 EAST MARGINAL WAY SOUTH, BLDG. 1202

SEATTLE WA 98134-2388

W912DW 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DW18Q0029

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

QUESTION ANSWERS

Range Area Noxious Weeds Control for Joint Base Lewis-McChord, Yakima Training Center, Washington Response to Bidder Questions for Solicitation W912DW18Q0029

A. QUESTION: Please clarify what constitutes "one job" for pricing Item 0003 (Task 3) Control of Musk and Scotch Thistle. Is "one job" the 100 acre increment described in 5.3.1.1 and you expect to be billed this price each time the control measures for a 100 acre section is complete OR is "one job" the entire 995 acres and the price for all control measures on all acreage for the entire life of this contract?

ANSWER: Task 3 - Control of Musk and Scotch Thistle: The one "job" includes both the thistle populations, musk & Scotch, across multiple sites that when totaled equate to approximately 995 acres; 480 & 515 acres respectively. To ensure and provide effective treatment, the Contractor will need to plan to survey, and treat as appropriate, the 995 acres. However, it’s key to understand, due to variability in the populations, that they need to expect to survey 995 acres (both species combined), actual treatment acres will be less. The price you provide on the price schedule should reflect the cost to control 995 acres under this task. There is language in the PWS that describes the variability in range populations.

The invoicing for the contract is detailed in section 1.7 of the PWS.

B. QUESTION: How many total acres for the mil class 2 roads? Is it 96 miles at 1.94 acres per mile totaling

186.3 acres plus an additional 20.6 miles (40 acres)? Is it a total of 226.3 miles?

ANSWER: Miles of Mil Class 2 Roads = approximately 40 acres required for treatment.

Explanation: Per section 5.1 of the PWS, there are 96 miles total at YTC – this is solely background information. Only 20.6 miles of the Mil Class Roads will be designated for treatment.

The width of treatment is 1.94 acres per linear mile (8 ft. on either side of the road must be treated). This results to approximately 40 acres required for treatment (20.6 miles x 1.94 acre/mile = 40 acres)

C. QUESTION: How does the payment process work? Would the first invoice be sent as soon as the initial sterilizing treatment is complete?

ANSWER: Per section 1.7 of the PWS, there will be 2 invoices for all services performed in the PWS. The first invoice will be paid when the contractor has completed the initial treatments. You can invoice up to 75% of the awarded amount for each task on the first invoice. The second invoice will be paid out once all work is complete and meet the requirements of the contract.

D. QUESTION: Who was the previous contractor to fulfill this requirement?

ANSWER: The prior contractor was Alliance Property Services of 15206 Union Ave SW, Lakewood, WA 98498.

W912DW18Q0029

E. QUESTION: If our employees have public/private applicators WSDA licenses and their commercial operator’s license is currently being processed by the WSDA should we include some sort of proof that we have submitted the fee and application to the WSDA and that its currently pending?

ANSWER: Yes.

(End of Summary of Changes)