SCOPE OF WORK

Yakima

HMA Paving and Removal

1. LOCATION AND DESCRIPTION:

Project is located in the city of Yakima, See attached photos for location.

BASE ITEM 0001

Estimated area of 14,000 SF to be prepped and paved @ 2.5 inches thick. 1,400 lineal feet by 10 feet wide.

Estimated quantity of new 5/8’’ top course needed is 0 tons if grindings are used. Estimated area of 14,000 SF of asphalt to be removed and disposed of. Removal and disposal may be done by excavation or grinding the existing asphalt in place. The grindings may be used as part of the base prep for the new asphalt. The average thickness of existing asphalt is 2.5 inches.

BASE ITEM 0002

Estimated area of 8,000 SF to be prepped and paved @ 2.5 inches thick. 800 lineal feet by 10 feet wide.

Estimated quantity of new 5/8” top course needed is 0 tons if grindings are used. Estimated area of 8,000 SF of asphalt to be removed and disposed of. Removal and disposal may be done by excavation or grinding the existing asphalt in place. The grindings may be used as part of the base prep for the new asphalt. The average thickness of existing asphalt is 2.5 inches. Additionally on this site there is a second 10 foot wide path that includes an additional 500 SF of asphalt to be replaced.

BASE ITEM 0003

Estimated area of 3,500 SF to be prepped and paved @ 2.5 inches thick. 250 lineal feet by 12 feet wide with 2 approach ramps. Estimated quantity of new 5/8” top course needed is 0 tons if grindings are used.

Estimated area of 3,500 SF of asphalt to be removed and disposed of. Removal and disposal may be done by excavation or grinding the existing asphalt in place. The grindings may be used as part of the base prep for the new asphalt. The average thickness of existing asphalt is 2.5 inches. Additionally on this site there is a second 10 foot wide path that includes an additional 500 SF of asphalt to be replaced.

2. WORK TO BE DONE:

Equipments and materials will be used for removal of existing asphalt, preparation and paving as specified here-in. Existing asphalt will be saw cut, removed, and disposed of offsite. Removal and disposal may be done by excavation or grinding the existing asphalt in place. The grindings may be used as part of the base prep for the new asphalt. Existing sub grade shall be graded and compacted as needed. 5/8” or grindings shall be added to the base course where needed to match grade. 2.5 inches of hot mix asphalt production and placement will conform to the 2014 WSDOT Standard Specifications, M41-10 section 5.04. A tack coat of asphalt will be applied to all paved surfaces on which any course of HMA is to be placed or abutted.

The grade of PG asphalt binder to be used is HMA CL. 1/2 IN PG 64-28. All work will conform to the scope of work and the following additional requirements;

a. Saw cut and clean existing pavement edges to allow appropriate bonding.

b. Grade and compact top-course prior to paving.

c. Add tack coat per specifications before overlaying to ensure adequate bonding of the overlay to the existing pavement surface.

d. Place hot mix asphalt per specification in one 2.5-inch thick minimum layer

e. Transition taper should maintain thickness of the overlay top lift

f. Add tack coat to the transverse joint to seal existing and new pavement at transition

g. A spill prevention control and countermeasures plan is required.

* All provided quantities are estimated.

3. Testing and Submittals Submittals for all materials being permanently incorporated into the project must be submitted to and approved by the Quality Assurance Representative (QAR) before being installed. Submittals and test results can be emailed to travis.j.hightower@usace.army.mil and anthony.w.doersam@usace.army.mil.

4. EQUIPMENT NEEDED

Any and all equipment needed for existing asphalt removal and disposal, preparation, paving, and spill prevention control, will be furnished by the contractor.

5. PERIOD OF PERFORMANCE

It is anticipated that the work shall commence on or about July 5, 2017 and end on or about August 15th 2017.

6. SECURITY

Pre-screen candidates using E-Verify Program. Proposed language: "The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award." *When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.

7. INSPECTION AN SUPERVISION:

All work shall be conducted under the direction of the Emergency Management Branch, Seattle District, Corps of Engineers.

8. SAFETY REQUIREMENTS

Operation of equipment shall be conducted in accordance with the requirements of EM 385-1-1, “Safety and Health Requirements Manual”. All Personnel are required to have PPE in accordance with EM 385-1-1. All dump trucks are required to have back up alarms and tailgates. All dozers shall have ROPS and backup alarms. EM 385-1-1 can be found at http://www.usace.army.mil/CESO/Pages/EM385-1-1.aspx

9. Plan Enhancement Site Visit A plan enhancement site visit will be held if necessary.

10. MEASUREMENT AND PAYMENT:

mailto:travis.j.hightower@usace.army.mil mailto:anthony.w.doersam@usace.army.mil http://www.usace.army.mil/CESO/Pages/EM385-1-1.aspx

Payment will be made after the inspection and acceptance of the work by an authorized member of USACE Emergency Management.

11. MAIL INVOICES TO:

Emergency Management will prepare the invoice for the contractor, DO NOT mail copies to the Corps of Engineers nor to Millington TN. If the contractor prepares their own invoice, then mail original to: