ABSTRACT OF OFFERS - CONSTRUCTION
1. Solicitation No. W912DW-16-B-0009
2. Date Issued: 12 August 2016
3. Date Opened: 12 September 2016
4. Issuing Office:
Department of the Army Corps of Engineers, Seattle District P.O. Box 3755 Seattle, WA 98124-2255
5. Project Title:
Unrestricted
6. Number of Amendments Issued: 2
1st Apparent low = ROGNLIN'S, Inc.
% Difference From GE: -43%
2nd Apparent low = Razz Construction, Inc.
% Difference From GE: -37%
3rd Apparent low = Quigg Bros, Inc.
% Difference From GE: -30%
SIGNATURE: Bid Opening Officer: MONIQUE PAANO
FY16 Westhaven Marina Breakwater Repair, Westport, WA
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
8. GOVERNMENT ESTIMATE
(Check A, B or C and Complete D, E F) A. Hired Labor B. Reasonable Contract (w/out profit) XX C. Reasonable Contract (w/ profit)
7A. ITEM 7B. DESCRIPTION OF OFFERED ITEM 7C. EST 7D. UNIT 7E. UNIT 7F. AMOUNT
NUMBER QTY PRICE
BASE ITEMS
0001 Mobilization and Demobilization 1 Job 464,500.00$ 464,500.00$
Remove, dispose, and replace bottom 7 rows of planking and hardware of Breakwater C (Sta 0+00 to 16+00) 11,200 LF 56.00$ 627,200.00$
Restore toe berm to +4.0 ft MLLW with Class III armor stone on marina side of Breakwater C (Sta 0+00 to 16+00) 1,800 TON 121.00$ 217,800.00$
1,309,500.00$
OPTIONAL ITEMS
Remove, dispose, and replace bottom 7 rows of planking and hardware of Breakwater A (Sta. 6+70 to 9+70) 2,100 LF 60.00$ 126,000.00$
0005 Breakwater A Toe Berm Repair -$
0005AA
Restore toe berm to +4.0-ft MLLW with Class V armor stone on Breakwater A (Sta 6+70 to 9+70) 500 TON 122.00$ 61,000.00$
0005AA
Restore toe berm to +4.0-ft MLLW with Class V armor stone on Breakwater A (Sta 6+70 to 9+70) 500 TON 122.00$ 61,000.00$
0006 Breakwater C Toe Berm Repair -$
0006AA
Restore toe berm to +4.0-ft MLLW with Class III armor stone on Breakwater C on marina side (Sta. 0+00 to 16+00) 800 TON 122.00$ 97,600.00$
0006AB
Restore toe berm to +4.0-ft MLLW with Class III armor stone on Breakwater C on marina side (Sta. 0+00 to 16+00) 1,600 TON 122.00$ 195,200.00$
0007 Breakwater B Toe Berm Repair -$
0007AA
Restore toe berm to +7.5-ft MLLW with Class V armor stone on Breakwater B (Sta.
1+50 to 7+00) 500 TON 122.00$ 61,000.00$
0007AB
Restore toe berm to +7.5-ft MLLW with Class V armor stone on Breakwater B (Sta.
1+50 to 7+00) 500 TON 122.00$ 61,000.00$
0008 Replace additional planking -$
0008AA
Remove, dispose, and replace miscellaneous missing planking and hardware on Breakwater A (Sta 6+70 to 9+70, Harbor Side), B (Sta. 1+50 to 7+00, Harbor Side), C (Sta. 0+00 to 16+00, Marina Side), not otherwise specified 150 LF 60.00$ 9,000.00$
0008AB
Remove, dispose, and replace miscellaneous missing planking and hardware on Breakwater A (Sta 6+70 to 9+70, Harbor Side), B (Sta. 1+50 to 7+00, Harbor Side), C (Sta. 0+00 to 16+00, Marina Side), not otherwise specified 450 LF 61.00$ 27,450.00$
699,250.00$ 2,008,750.00$
TOTAL BASE ITEMS
TOTAL OPTIONAL ITEMS
TOTAL BASE & OPTIONAL
9. OFFERS
NO. 1 NO. 2 NO. 3
Razz Construction Rognlins, Inc. Quigg Brothers Bellingham, WA Aberdeen, WA Aberdeen, WA
B. Bid Security Type/Amt : 20% Bid Bond B. Bid Security Type/Amt : 20% Bid Bond B. Bid Security Type/Amt : 20% Bid Bond Business Size: Business Size: Business Size:
C. Amendments Acknowledged: 2 C. Amendments Acknowledged: 2 C. Amendments Acknowledged: 2
D. ITEM 7C. EST E. UNIT F. AMOUNT D. ITEM 7C. EST E. UNIT F. AMOUNT D. ITEM 7C. EST E. UNIT F. AMOUNT
NO. QTY PRICE NO. QTY PRICE NO. QTY PRICE
BASE
ITEMS BASE ITEMS BASE ITEMS
0001 1 198,000.00$ 198,000.00$ 0001 1 99,500.00$ 99,500.00$ 0001 1 210,000.00$ 210,000.00$ 0002 11200 21.00$ 235,200.00$ 0002 11200 36.00$ 403,200.00$ 0002 11200 44.00$ 492,800.00$ 0003 1800 200.00$ 360,000.00$ 0003 1800 90.00$ 162,000.00$ 0003 1800 85.00$ 153,000.00$
TOTAL BASE ITEMS 793,200.00$ TOTAL BASE ITEMS 664,700.00$ TOTAL BASE ITEMS 855,800.00$
OPTIONAL ITEMS OPTIONAL ITEMS OPTIONAL ITEMS
0004 2100 21.00$ 44,100.00$ 0004 2100 36.00$ 75,600.00$ 0004 2100 57.00$ 119,700.00$ 0005 -$ 0005 -$ 0005 -$
0005AA 500 95.00$ 47,500.00$ 0005AA 500 87.00$ 43,500.00$ 0005AA 500 100.00$ 50,000.00$ 0005AB 500 95.00$ 47,500.00$ 0005AB 500 87.00$ 43,500.00$ 0005AB 500 100.00$ 50,000.00$
0006 -$ 0006 -$ 0006 -$ 0006AA 800 95.00$ 76,000.00$ 0006AA 800 87.00$ 69,600.00$ 0006AA 800 85.00$ 68,000.00$ 0006AB 1600 95.00$ 152,000.00$ 0006AB 1600 87.00$ 139,200.00$ 0006AB 1600 85.00$ 136,000.00$
0007 -$ 0007 -$ 0007 -$ 0007AA 500 95.00$ 47,500.00$ 0007AA 500 87.00$ 43,500.00$ 0007AA 500 100.00$ 50,000.00$ 0007AB 500 95.00$ 47,500.00$ 0007AB 500 87.00$ 43,500.00$ 0007AB 500 100.00$ 50,000.00$
0008 -$ 0008 -$ 0008 -$ 0008AA 150 22.00$ 3,300.00$ 0008AA 150 38.00$ 5,700.00$ 0008AA 150 50.00$ 7,500.00$ 0008AB 450 22.00$ 9,900.00$ 0008AB 450 38.00$ 17,100.00$ 0008AB 450 50.00$ 22,500.00$
TOTAL OPTIONAL ITEMS 475,300.00$ TOTAL OPTIONAL ITEMS 481,200.00$ TOTAL OPTIONAL ITEMS 559,700.00$ TOTAL BASE & OPTIONAL 1,268,500.00$ TOTAL BASE & OPTIONAL 1,145,900.00$ TOTAL BASE & OPTIONAL 1,415,500.00$
Standard Form 1419 (2001)
COE SEATTLE DISTRICT (VERSION 3/01)
| 2016-09-13T12:31:37-0700 | |