This document outlines requirements for a tank inspection and SPCC plan preparation project. The contractor shall conduct formal external inspections of above ground storage tanks using STI SP001 checklists, including ultrasonic thickness testing unless tanks are double-walled. The contractor shall also visit the site, document details for an updated SPCC plan in accordance with 40 CFR 122, and have a licensed professional engineer develop and certify the updated plan. One hard copy of the SPCC plan shall be provided to the US Army Corps of Engineers. The contractor must inspect tanks within one month of notice to proceed and provide the certified SPCC plan within two months post inspection. Offerors must have a minimum of 10 years experience with above ground storage tanks and certified technicians with STI SP001 and ASNT Level II qualifications.
This federal contract opportunity is solicitation number W912DS24Q0001 for tank inspection services at the Caven Point Marine Terminal issued by the Department of the Army Corps of Engineers Engineering District New York.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Tank-Photos.pdf | ||
| Amendment1_Q-and-A.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of work
SPCC Preparation and Tank Inspection
The Contractor shall perform the following tasks:
Tank Inspection
The Contractor shall conduct a formal external inspection (FEI) using the Steel Tank Institute(STI) SP001 checklist. Inspector shall be STI SP001 and American Society for Nondestructive Testing (ASNT) Level II certified. The contractor shall determine the suitability for continued service without entry into the AST interior. The Inspection will include ultrasonic thickness testing (UTT) unless the AST is double-walled or ConVault style. A determination of original shell thickness and corrosion rate will establish a remaining service life. If the tanks are determined to be other than category 1 tanks, contractor shall make arrangements to perform an internal inspection at a later date.
Conduct Site Visit
The Contractor shall visit the facility to observe and document details required for the SPCC plan. Any significant deficiencies shall be discussed with the on-site government representative.
SPCC Plan
The Contractor shall prepare an SPCC plan following regulations set forth in 40 CFR 122 Section 311(j)(1)(C) of the Clean Water Act as amended by the Oil Pollution Act of 1990. Any drawings provided by the government shall be updated from the site visit with the new SPCC Plan. Due to the amount of Oil stored on site, an updated SPCC must be certified by a PE. The contractor shall have a PE develop and approve the new SPCC Plan. The Contractor shall provide one PE stamped hard copy of the SPCC Plan to US Army Corps of Engineers.
Period of Performance:
The Contractor shall inspect the tanks within one (1) month of a notice to proceed and provide a PE certified updated SPCC Plan within 2 months post inspection.
Information for Offerors:
In order for a bid to be acceptable, the Offeror shall comply with the following minimum requirements:
A. The Offeror shall have a minimum of 10 years of experience in manufacture, repair and inspection of Above Ground Storage Tanks.
B. The Offeror shall have certified technicians and field inspectors with STI SP001 and ASNT Level II certificates.
Offerors shall provide documentation with the offer to demonstrate that they comply with the minimum requirements above.