This document is a section from the Specifications for a Maintenance Dredging project of the New York Harbor, Sandy Hook Channel, New Jersey Federal Navigation Project.
The key details are: The work consists of providing materials, plant, labor, equipment and services to perform maintenance dredging of approximately 76,370 CY from the Sandy Hook Channel, with placement of the dredged material at the Sea Bright Offshore Borrow Area (SBOBA). The contract has a basic work item and two option items for additional dredging. The Contractor must achieve a minimum average production rate of 8,000 CY per day for dredging, transportation, and placement. The work is anticipated to be performed from September 2024 to January 2025, with dredging starting in October 2024. The contractor must comply with environmental restrictions and coordinate with the National Park Service. The total estimated cost of the entire work is between $1,000,000 and $5,000,000.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Maintenance Dredging of NY Harbor, Sandy Hook Channel, NJ FNP SHC24
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
01/20
PART 1 GENERAL
1.1 FAR 52.211-10, COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
1.2 WORK COVERED BY THE CONTRACT DOCUMENTS
1.2.1 Project Description
1.3 PERFORMANCE OF WORK BY THE CONTRACTOR
1.4 DFARS 236.204, DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECTS
1.5 DATUM AND BENCH MARKS
1.6 MISPLACED MATERIAL
1.7 AUTHORIZED CONSTRUCTION AREA AND TRESPASSING
1.8 EXISTING WORK
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
01/20
PART 1 GENERAL
1.1 FAR 52.211-10, COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
a. The Contractor shall be required to (i) commence work under this contract within five (5) calendar days after the date the Contractor receives the Notice to Proceed, (ii) prosecute the work diligently, and
(iii) complete the basic work ready for use, not later than 60 cal endar days , after the date the Contractor receives the notice to proceed. Should any option(s) be exercised, an addi t i onal one ( 1) cal endar day f or each 8, 000 cubi c yar ds t o be r emoved under t he opt i on( s) will be allowed. The time stated for completion shall include final cleanup of the premises.
(FAR 52.212-3)
b. All work shall be in accordance with the drawings and specifications or instructions attached hereto and made a part thereof, or to be furnished hereafter by the Contracting Officer or Contracting Officer Representative (COR) and subject, in every detail, to his supervision, direction, and instructions.
1.2 WORK COVERED BY THE CONTRACT DOCUMENTS
1.2.1 Project Description
The work to be performed under this project consists of providing all materials, plant, labor, equipment and services (except those furnished by the Government) to perform maintenance dredging of New York Harbor, Sandy Hook Channel , with placement of the material at the Sea Bright Offshore Borrow Area (SBOBA). Dredged material shall only be placed within the approximately 93-acre placement area in SBOBA with coordinates as identified on the contract plans. The contractor will be solely responsible for coordination and compliance with the transportation, offloading, and placement site(s) requirements. See Section 35 20 23.10 18 entitled "SBOBA DREDGED MATERIAL TRANSPORT AND PLACEMENT MONITORING" for more information.
The maintenance for this project consists of dredging approximately 76,370 CY of basic work material based on the before dredge survey performed in September 2023. For more details, see "ESTIMATED QUANTITIES" in Section 00 30 00 "ADMINISTRATIVE REQUIREMENTS" of these Specifications. The dredge material has been determined to be composed of sand and gravel.
A summary of the Dredging Areas is shown in the table below:
DREDGING AREAS TOTAL ESTIMATED
QUANTITY (CY)
BASIC WORK: (-35' MLLW + 2' OD) 76,370
SECTION 01 11 00 Page 2
OPTION 1: (-35' MLLW + 2' OD) 24,215
OPTION 2: (-35' MLLW + 2' OD) 58,055
Contract time for completion is based on a minimum average production rate of 8, 000 cubi c yar ds ( CY) per day for dredging, transportation, processing and placement at the SBOBA. Should the total quantity of material exceed the estimated quantities within the Solicitation Contract Form, additional time will be allowed at the rate of one (1) calendar day for each 8,000 cubic yards in excess of the established limit. The time stated for completion shall include final clean up.
The contractor must bid on all items of the bid schedule. The following CLINs require dredging of the New York Harbor, Sandy Hook Channel, New Jersey, Federal Navigation Project, with subsequent transportation, processing and placement of the dredged material at the SBOBA:
CLIN 0002 (BASIC WORK) - requires dredging to the plane of -35 feet MLLW plus 2 foot allowable overdepth.
CLIN 0005 (OPTION 1) - requires dredging to the plane of -35 feet MLLW plus 2 foot allowable overdepth.
CLIN 0006 (OPTION 2) - requires dredging to the plane of -35 feet MLLW plus 2 foot allowable overdepth.
Exercise of the options are at the discretion of the Government and may be exercised at the time of award. If exercised, the options listed above shall be exercised in the order that is listed. Option 2 shall not be executed without the execution of Option 1. The minimum average production rate for the options remains the same at 8,000 CY per day for dredging, transportation, and placement at SBOBA.
Based on the before dredge survey performed in September 2023, the maximum quantity available to be dredged is 76,370 CY from the contract areas in the basic work contract area, and 82,270 CY from the option areas of the New York Harbor, Sandy Hook Channel, New Jersey, Federal Navigation Project. For a detailed breakdown of quantity available to be dredged, see paragraph 1.9 "ESTIMATED QUANTITIES" in Section 01 30 00 of the Specifications.
Scow monitoring is required for this project. The contractor is required to comply with Section 35 20 29 entitled "SBOBA DREDGED MATERIAL TRANSPORT AND PLACEMENT MONITORING", of these specifications.
Sampling and testing was conducted by the Government in 2017, and the grain size test results are included in the specifications in Section 00 90 01 as Attachment J . The complete sampling and testing results can be found as attachments to this solicitation on SAM.gov.
The New Jersey Department of Environmental Protection (NJDEP) State Water Quality Certificate (WQC) for the maintenance dredging of New York Harbor, Sandy Hook Channel, New Jersey, Federal Navigation Project is attached in Section 01 90 02 of this solicitation. The contractor must comply with all conditions of the NJDEP WQC.
SECTION 01 11 00 Page 3
U.S. Fish and Wildlife Service (USFWS) issued a Programmatic Biological Opinion on October 2017 entitled "Biological Option on The Effects of Recurrent Maintenance Dredging of The Sandy Hook Channel, Monmouth County, New Jersey on Four Federally Listed Species" (PBO).
1. The issued PBO contains dredge window restrictions for the Sandy Hook Federal Navigation Channel. No dredging of beach or any subtidal area within 300 feet of the MLLW lines shall be performed from 1 March 31 August of each year to protect Piping Plovers.
2. No installation or removal of security fencing, pipeling, or any other temporary structures on the beach shall be performed from 1 March to 31 August of each year to protect Piping Plovers.
3. Should dredging occur between 1 September and 30 November , the Corps will arrange for a survey of all beach within the impact area for the presence of seabeach amaranth plants no more than 14 days before the start of each dredging action. The Corps will mark any plants occurring inside the impact area, but outside of the sand removal area, with string-and-post fencing and appropriate signage.
Project personnel and vehicles shall not disturb deabeach amaranth plants within the fencing .
4. Due to the recent observance of the Northeastern Beach Tiger Beetles, a pre-dredge northeastern beach tiger beetles survey must be conducted between mid-September and mid-October during fair weather.
If any adult or larvae northeastern beach tiger beetles are discovered during the survey, the beetles must be translocated to a USACE, USFWS, and NPS-approved location outside of the dredging footprint. A post-translocation species survey shall be conducted after translocation to ensure no endangered species remain in the dredging foorprint.
As per CLIN 0004 (NORTHEASTERN BEACH TIGER BEETLES SURVEY AND TRANSLOCATION EFFORTS), the contractor shall coordinate with USFWS, NPS and USACE to provide a qualified and approved northeastern beach tiger beetle expert to conduct the pre-dredge species survey, translocation efforts, and a post-translocation species survey. Translocation efforts shall not proceed without the agreement of the USFWS, USACE, and NPS. Dredging shall not commence until USFWS has concurred with the completion of the northeastern beach tiger beetles conservation measure .
Security: The contractor shall provide unarmed Site Control Services, including a 4x4 vehicle to secure the beach access points at Parking Lots M and J located in Sandy Hook, for 24 hours per days, 7 days per week.
Site Control Service personnel cannot be the SSHO and cannoy have other duties. Ensuring that the beach remains closed off to the publicin the location of the dredging work will be their sole responsibility and they will conform with the requirements of the National Park Service. The Site Control Service Personnel personnel shall maintain adequate communication with National Park Service Officers and Dispatch as necessary. The Contractor and the Site Control Service Personnel shall review the requirements set forth in the National Park Service (NPS) Special Use Permit (SUP) and ensure all conditions of the SUP shall be followed. The NPS SUP for the previous maintenance dredging cycle of Sandy Hook Channel can be found in Section 00 90 02. An NPS SUP for this dredging cycle will be provided to the contractor prior to construction.
SECTION 01 11 00 Page 4
The contractor shall erect a fence around the work area that is along the shoreline in order to keep the public from accessing the work area in coordination with the NPS request. See 00 90 02 for NPS SUP requirements.
Three (3) large signs shall be placed at the fence line at each end of the fence closure and additional signs shall be posted at the beach access points at Parking Lots M and J in Sandy Hook National Recreational Area.
These signs shall be 3' x 3' and include wording indicating; Beach Closed, Dredging Project, and Beach Collapse Hazard. The signs shall contain a warning drawing identifying the hazards of the sandy beach collapse into deep water adjacent to dredging operations. Other signs shall be posted along the fence line in accordance with Section 01 50 00 Temporary Construction Facilities and Controls - Paragraph 2.1.4. All signage must be approved by NPS prior to installation.
Site Control Services, signs and fencing shall remain active on site until scarping and overall disturbance of the beach at the dredging area has stabilized and general safety of the area at the dredging location is held to be acceptable. Prior to the expiration of the NPS SUP or at the direction of the USACE and NPS, all signs, fencing, and appurtenances shall be removed from the Project Area.
Due to the inability for a hopper dredge to safely complete the work during a previous dredging cycle, it is recommended that a hopper dredge not be used to complete the anticipated work.
The work is anticipated to be performed within the approximate time period of September 2024 - January 2025. Dredging shall begin in October 2024 and cannot commence until USFWS has concurred with the northeastern beach tiger beetles conservation measure.
1.3 PERFORMANCE OF WORK BY THE CONTRACTOR
The Contractor shall perform on the site, and with its own organization and equipment, work equivalent to at least forty (40) percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performance of the work, the Contractor requests a reduction and the Contracting Officer and/or his Representative determines that the reduction would be to the advantage of the Government. (FAR 52.236-01)
1.4 DFARS 236.204, DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECTS
The entire work (CLINs 0001 through 0006) is estimated to cost approximately $1,000,000.00 to $5,000,000.00.
1.5 DATUM AND BENCH MARKS
Soundings and Elevations shown in the contract drawings are in US Survey Feet and refer to Mean Lower Low Water (MLLW) [epoch 1983-2001]. The Plane of MEAN LOWER LOW WATER (MLLW) is 2.7-2.9 FEET BELOW NAVD88 AS DETERMINED USING VDATUM (VER. 4.3). The following Benchmark information should be referenced for defining local datum and required project depth.
New York Harbor, Sandy Hook Channel, NJ
NSRS Benchmark:
Benchmark: SIMPSON 2
SECTION 01 11 00 Page 5
PID: KV0709
Elevation: 6.92' (NAVD 1988)
Local Control Data:
Benchmark: SIMPSON 2 RM 3
PID: KV0707
Elevation: 6.85' (NAVD 1988)
All control should be verified prior to utilization.
The contractor may contact the New York District Survey Branch at (201) 333-0284 for assistance in bench mark discrepancies or clarification in benchmark and / or tide gage location.
1.6 MISPLACED MATERIAL
Should the Contractor during the progress of the work, lose, dump, throw overboard, sink, or misplace any material, plant, machinery, or appliance, which in the opinion of the Contracting Officer and/or his Representative may be dangerous to or obstruct navigation, the Contractor shall recover and remove the same with the utmost dispatch. The Contractor shall give immediate notice, with description and location of such obstructions, to the Contracting Officer and/or his Representative or inspector, and when required shall mark or buoy such obstruction until the same are removed.
Should he refuse, neglect, or delay compliance with the above requirements, such obstructions may be removed by the Contracting Officer and/or his Representative, and the cost of such removal may be deducted from any money due or to become due to the Contractor, or may be recovered under his bond. The liability of the Contractor for the removal of a vessel wrecked or sunk without fault or negligence shall be limited to that provided in Sections 15, 19, and 20 of the Rivers and Harbors Act of March 3, 1899 (33 USC. 410 et seq.) (DOD FARS SUPPL. 52.236-7006).
1.7 AUTHORIZED CONSTRUCTION AREA AND TRESPASSING
Do not inflict damage upon land and properties outside the authorized construction area by unwarranted entry upon, passage through, damage to, or disposal of, material on such land or property. The Contractor may make a separate agreement with any other party, regarding the use of, or right to, land or facilities outside the contract area. If such an agreement is made, it must be in writing and a copy shall be provided to the Contracting Officer. The Contractor must hold and save the Government, its officers, and agents free from liability arising from trespassing or damage occasioned by his operations.
1.8 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that
SECTION 01 11 00 Page 6 which existed before new work started.
c. The responsibility for damage to the permanent work must be as set forth in the article of the contract clause entitled "PERMITS AND RESPONSIBILITIES". Except as herein provided, damage to all work, utilities, materials, structures, equipment, and plant, including temporary construction and utilities, pavements, vehicles, vessels, and other property along the routes used by the Contractor's plant, vessels, equipment, pipelines and/or vehicles must be repaired to the satisfaction of the Contracting Officer, at the Contractor's expense, regardless of the cause of such damage.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 7
| 01 11 00 - SUMMARY OF WORK |
| 01 11 00 - SUMMARY OF WORK |
| PART 1 GENERAL |
| 1.1 FAR 52.211-10, COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK |
| 1.2 WORK COVERED BY THE CONTRACT DOCUMENTS |
| 1.2.1 Project Description |
| 1.3 PERFORMANCE OF WORK BY THE CONTRACTOR |
| 1.4 DFARS 236.204, DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECTS |
| 1.5 DATUM AND BENCH MARKS |
| 1.6 MISPLACED MATERIAL |
| 1.7 AUTHORIZED CONSTRUCTION AREA AND TRESPASSING |
| 1.8 EXISTING WORK |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |