This document is a solicitation for a construction contract to renovate portions of Building 20 located at Watervliet Arsenal in Watervliet, New York. The U.S. Army Corps of Engineers, New York District intends to award a firm-fixed price contract to survey and repair or replace damaged concrete roof planks, remove and replace the existing roof membrane and associated components, and install new insulated metal roof panels and a roof lightning protection system. Additional work includes replacing existing roof fans and moving HVAC air handling units to the roof in the manufacturing floor area. The period of performance is 365 calendar days from notice to proceed. The solicitation will be posted on the beta SAM website on or about August 11, 2021 with proposals due approximately 30 days later. This acquisition will be a small business set-aside with an estimated cost between $5 million and $10 million.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912DS21B0016
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1. Provide updated Wage Rates.
2. Provide responses to bidder inquires for informational purposes only.
3. Provide the Hazardous Material Report.
4. Provide pre-bid site survey photos.
Bidder must acknow ledge receipt of this amendment by the date specified in the bid (or as amended) by one of the follow ing methods: in the space provided on SF1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND
WITHDRAWAL OF BIDS (FAR 15.208).
1. CONTRACT ID CODE PAGE OF PAGES
J 1 30
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 03-Sep-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS21B0016
X 9B. DATED (SEE ITEM 11)
12-Aug-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
03-Sep-2021
CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 16-300
NEW YORK NY 10278-0090
W912DS 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
The following have been modified:
TOTALS AND NOTES
TOTALS
TOTAL BASE CLIN 0001 $_______________
TOTAL OPTION CLINs 0002-0004 $_________________
TOTAL BASE Plus OPTION CLINs 0001-0004 $ __________________________
NOTES
(1) Total Offer shall include all costs associated with each item number including all bonding, overhead and profit.
(2) Offeror must submit a price for every CLIN. Failure to do so may result in Offer being unacceptable.
(3) Optional Items may be exercised at any time within 90 calendar days after contract award. The Contracting
Officer may exercise the Optional Items by written notice to the Contractor, postmarked within the period specified above. The Government may exercise any, all or none of the listed Optional Items in any order.
(4) Proposed Contract Duration is 365 Days.
(5) Offer Acceptance Period: Offers are to be valid for 90 calendar days for offer acceptance from the Offer
Acceptance.
BIDDER INQUIRIES:
Submission of inquiries will open on 12 August 2021. Please submit technical inquiries and questions relating to this solicitation via Bidder Inquiry in ProjNet at https://www.projnet.org. Submission of inquires will close 30 August 2021 11:59 AM EDT. The Government reserves the right to decline addressing questions received after this date. If an Offeror believes that the requirements in this solicitation contains an error, omission, or are otherwise unsound;
immediately notify the Contract Specialist in writing with supporting rationale. The Government reserves the right to award this contract based on the initial bid, as received, without discussions. To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment or question will receive an acknowledgement via e-mail, followed by an answer after it has been processed by our technical team. All timely questions and approved answers will be made available through ProjNet. Approved answers to all timely questions will also be posted on beta.sam.gov in the form of a report generated from ProjNet as soon as the comment/question entering period is over and answers are all finalized.
Bidder Inquiry Key: 45KPK5-7N9M8H Specific Instructions for Initial ProjNet Bid Inquiry Access:
1. From the ProjNet home page, click on Quick Add on the upper right side of the screen.
2. Identify the Agency as USACE.
3. Key. Enter the Bidder Inquiry Key listed above.
4. E-mail. Enter the e-mail address you would like to use for communication.
5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.
6. Enter your First Name, Last Name, Company, City, State, Phone, E-mail, Secret Question, Secret Answer, and Time Zone. Remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.
7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
Specific Instructions for Future ProjNet Bid Inquiry Access:
Steps 1 through 3: same as above.
4. E-mail. Enter the e-mail address you used to register previously in ProjNet.
5. Click Continue. A page will then open asking for the answer to your Secret Question.
6. Enter your Secret Answer and click Login. Once this is completed, you are logged into the system.
SECTION 00 70 00 - CONDITIONS OF THE CONTRACT
The following have been added by full text:
AMENDMENT 0002
QUESTIONS AND GOVERNMENT REPLY
(Questions that may be of general interest to all Offerors and/or the Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s). Questions and answers are issued to the offerors “For Information Only” and do not revise the solicitation, plans or specifications.)
Question 1:
Inquiry ID 9378168: Sheet S004 note 1.B indicates contractor shall retain third party QA agency approved by government. Does WVA/USACE have a list of government approved agencies?
Government Response:
There is no list of pre-qualified agencies.
The successful bidder shall submit the third-party QA agency special inspector qualifications per SECTION 01 45 35 SPECIAL INSPECTIONS for government approval.
Question 2:
Inquiry ID 9387442: Sheet S-001 section 7.A.6 refers to detail C-8 sheet S-502 for supplemental steel needed at crack repairs.
Is this referring to detail C-7, or is there a missing detail?
Government Response:
There is no section 7.A.6 on S-001. The Government believes this comment is in reference to note 7.A.3.a.(3). Confirmed that this note is referring to detail C-7 on sheet S-502.
Question 3:
The Bid Form, note (3) states:
"Optional Items (Additives) may be exercised at any time within 180 calendar days after contract award" Will consideration be given for material escalation if there is a delay in exercising an option?
The period to exercise options will be reduced to within 90 calendar days after contract award.
Question 4:
Inquiry ID 9378158: General Architectural notes indicate HAZMAT has been identified in the building and is contractor responsibility and refers to Hazardous materials report. Please provide a copy of the hazardous materials report referenced
Government Response:
There are trace amounts of ACM identified on the roof that do not fall under the requirements stipulated by the state of NY. Contractor required to provide compliance with all federal and state requirements.
The Hazardous Material Report will be included as a solicitation amendment.
Question 5:
Inquiry ID 9393724: Sheet ED101 states to disconnect and remove existing AHUSs 480V feeds back to the source panel. These panels are not identified on the drawing. Please provide approximate location of the source panel for each AHU being removed.
Government Response:
The existing AHUs are served from the local overhead existing bus duct with bus duct mounted disconnect switches. Respondents should figure twenty linear feet of conductor and conduit for demolition and forty linear feet for connection to the newly proposed units on the roof.
Question 6:
Inquiry ID 9393730: Please provide the approximate size of the feeder conduits and conductors for the AHU's being removed.
Feeders conductors are 3#12+1#12G in 1/2" conduit.
Question 7:
Inquiry ID 9393750: Hi: The drawings refer to a Hazardous material report. However, there is no such report available on sam.gov for this solicitation. Please provide this information at the earliest.
Government Response:
There are trace amounts of ACM identified on the roof that do not fall under the requirements stipulated by the state of NY. Contractor required to provide compliance with all federal and state requirements.
The Hazardous Material Report will be included as a solicitation amendment.
Question 8:
Inquiry ID 9393752: Who has the existing DDC controls for the building?
Government Response:
Johnson Controls, Metasys.
The successful bidder will be required to coordinate with the COE COR to contact the WVA DDC POC for this facility.
WAGE RATES (AMENDMENT 0002)
"General Decision Number: NY20210002 08/13/2021 Superseded General Decision Number: NY20200002 State: New York JN 8/13/2021
Construction Types: Building, Heavy and Highway Counties: Albany, Columbia, Fulton, Greene, Montgomery, Rensselaer, Saratoga, Schenectady, Schoharie and Washington Counties in New York.
BUILDING CONSTRUCTION PROJECTS (For all counties except COLUMBIA, FULTON, GREENE & MONTGOMERY) (does not include single family homes and apartments up to a including 4 stories), HEAVY
AND HIGHWAY CONSTRUCTION PROJECTS
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.95 for calendar year 2021 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.95 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2021. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/01/2021 1 03/12/2021 2 04/02/2021 3 04/16/2021 4 05/21/2021 5 06/25/2021 6 07/02/2021 7 08/06/2021 8 08/13/2021
ASBE0040-002 05/01/2020
Rates Fringes
Asbestos/Insulator Worker SCOPE OF WORK: includes application of all insulating materials, protective, coverings, coating and finishing to all types of mechanical systems.....................$ 36.36 22.76
HAZARDOUS MATERIAL HANDLER
Duties limited to preparation wetting;
stripping; removal;
scrapping; vacuuming;
bagging; and disposing of all insulation materials, whether they contain asbestos or not from mechancial systems..........$ 36.36 22.76
BOIL0197-002 01/01/2017
Rates Fringes
BOILERMAKER......................$ 34.54 24.78
BRNY0002-019 07/01/2018
Rates Fringes
BRICKLAYER
BRICKLAYERS, STONE MASONS,
CEMENT MASONS, PLASTERERS,
POINTERS, CAULKERS &
CLEANERS....................$ 36.19 20.48
HEAVY & HIGHWAY
CONSTRUCTION
CEMENT MASONS..............$ 37.23 19.51
MARBLE, TILE & TERRAZZO
FINISHERS...................$ 27.16 16.85
MARBLE, TILE & TERRAZZO
WORKERS.....................$ 34.66 19.58
CARP0279-006 07/01/2019
Rates Fringes
Carpenters:
HEAVY AND HIGHWAY
CONSTRUCTION (COLUMBIA AND
GREENE COUNTIES)
Carpenters, Millwrights, Pile Drivers...............$ 38.09 29.08
CARP0291-005 07/01/2021
Rates Fringes
Carpenters:
SARATOGA COUNTY
BUILDING....................$ 32.73 23.05
WASHINGTON COUNTY
BUILDING....................$ 28.65 22.20
PAID HOLIDAYS: Labor Day, provided the employee has been on the payroll the calender week or any of the holiday week preceding the holiday and works the day after the holiday.
CARP0291-008 07/01/2021
ALBANY, FULTON, MONTGOMERY, RENSSELAER, SCHENECTADY AND
SCHOHARIE COUNTIES
Carpenters:
BUILDING CONSTRUCTION
(Excluding Montgomery County) Carpenters & Soft Floor Layers.....................$ 32.73 23.05 Piledriver.................$ 31.68 20.60
HEAVY & HIGHWAY
CONSTRUCTION
Carpenters.................$ 34.52 23.55
CARP0291-010 07/01/2021
Rates Fringes
Carpenters:
CARPENTERS..................$ 34.52 23.55
DIVER TENDERS...............$ 34.02 21.10
DIVERS (Dry Day)............$ 35.52 23.55
DIVERS......................$ 59.52 23.55
PILEDRIVERS.................$ 33.02 21.10
ELEC0236-001 06/01/2020
ALBANY; COLUMBIA; FULTON; GREENE (that portion North of a line following the south limits of the city of Catskill);
MONTGOMERY; RENSSELAER, SARATOGA; SCHENECTADY; SCHOHARIE;
WASHINGTON
ELECTRICIAN......................$ 41.20 28.11
ELEC0363-004 04/01/2021
GREENE COUNTY (Portion of)
Rates Fringes
ELECTRICIAN......................$ 43.00 3%+33.67+a
FOOTNOTE:
a. Paid Holidays: New Year's Day, President's Day, Memorial Day, Fourth of July, Labor Day, Presidential Election Day, Veteran's Day, Thanksgiving Day, Day after Thanksgiving, Christmas Day
ELEC1249-003 05/04/2020
Rates Fringes
ELECTRICIAN (LINE
CONSTRUCTION: LIGHTING AND
TRAFFIC SIGNAL Including any and all Fiber Optic Cable necessary for Traffic Signal Systems, Traffic Monitoring systems and Road Weather information systems) Flagman.....................$ 27.72 6.75%+33.90 Groundman (Truck Driver)....$ 36.96 6.75%+33.90 Groundman Truck Driver (tractor trailer unit)......$ 39.27 6.75%+33.90 Lineman & Technician........$ 46.20 6.75%+33.90 Mechanic....................$ 36.96 6.75%+33.90
FOOTNOTE:
a. New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, plus President's Day, Good Friday, Decoration Day, Election Day for the President of the United States and Election Day for the Governor of the State of New York, provided the employee works the day before or the day after the holiday.
ELEC1249-004 05/03/2021
Rates Fringes
ELECTRICIAN (Line Construction) Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :
Flagman....................$ 32.82 7%+34.40 Groundman digging machine operator...................$ 49.23 7%+34.40 Groundman truck driver (tractor trailer unit).....$ 46.50 7%+34.40 Groundman Truck driver.....$ 43.76 7%+34.40 Lineman and Technician.....$ 54.70 7%+35.40 Mechanic...................$ 43.76 7%+34.40 Substation:
Cable Splicer..............$ 60.17 7%+35.40 Flagman....................$ 32.82 7%+34.40 Ground man truck driver....$ 43.76 7%+34.40 Groundman digging machine operator...................$ 49.23 7%+34.40
Groundman truck driver (tractor trailer unit).....$ 46.50 7%+34.40 Lineman & Technician.......$ 54.70 7%+35.40 Mechanic...................$ 43.76 7%+34.40 Switching structures;
railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation Cable Splicer..............$ 61.62 7%+35.40 Flagman....................$ 33.61 7%+34.40 Groundman Digging Machine Operator...................$ 50.42 7%+34.40 Groundman Truck Driver (tractor-trailer unit).....$ 47.62 7%+34.40 Groundman Truck Driver.....$ 44.82 7%+34.40 Lineman & Technician.......$ 56.02 7%+35.40 Mechanic...................$ 44.82 7%+34.40
FOOTNOTE:
a. PAID HOLIDAYS: New Year's Day, Presidents' Day, Memorial Day, Good Friday, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, and Election Day for the President of the United States and Election Day for the Governor of New York State, provided the employee works two days before or two days after the holiday.
ELEC1249-007 05/03/2021
COLUMBIA COUNTY
Rates Fringes
ELECTRICIAN (LIGHTING AND
TRAFFIC SIGNAL INCLUDING ANY
AND ALL FIBER OPTIC CABLE
NECESSARY FOR THE TRAFFIC
SIGNAL SYSTEMS, TRAFFIC
MONITORING SYSTEMS AND ROAD
WEATHER INFORMATION SYSTEMS)
Flagman.....................$ 28.29 7%+34.40 Groundman Digging Machine Operator....................$ 42.44 7%+34.40 Groundman Truck Driver (Tractor-trailer unit)......$ 40.08 7%+34.40 Groundman Truck Driver......$ 37.72 7%+34.40 Lineman and Technician......$ 47.15 7%+34.40 Mechanic....................$ 37.72 7%+34.40
PAID HOLIDAYS:
a. Memorial Day, New Year's Day, President's Day, Good Friday, Decoration Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, and Election Day for the President of the United States and Election Day for the Governor of New York State, provided the employee works two days before or two days after the holiday.
ELEC1249-008 01/03/2021
Rates Fringes
ELECTRICIAN (Line Construction)
TELEPHONE, CATV
FIBEROPTICS CABLE AND
EQUIPMENT
Cable splicer..............$ 34.78 3%+5.14 Groundman..................$ 17.50 3%+5.14 Installer Repairman- Teledata Lineman/Technician- Equipment Operator.........$ 33.01 3%+5.14 Tree Trimmer................$ 27.36 3%+9.98
a. New Year's Day, President's Day, Good Friday, Decoration Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day, Day after Thanksgiving, Christmas Day.
ELEV0035-001 01/01/2020
ALBANY; COLUMBIA (Towns of Claverack, Hillsdale, Ghent, Stockport, Austerlitz, Canaan, New Lebanon, Chatham, Kinderhook, Styvesant and Greenport); FULTON; GREENE (Towns of Durham, Greenville, New Baltimore, Coxcsackie and Athens);
MONTGOMERY, RENSSELAER, SARATOGA, SCHENECTADY, SCHOHARIE AND
WASHINGTON COUNTIES
Elevator Constructor.............$ 47.51 34.765+a+b
FOOTNOTE:
a.Vacation: 6%/under 5 years based on regular hourly rate for all hours worked. 8%/over 5 years based on regular hourly rate for all hours worked.
b. PAID HOLIDAYS: New Year's Day; Memorial Day; Independence Day; Labor Day; Veterans' Day; Thanksgiving Day; the Friday after Thanksgiving Day; and Christmas Day.
ELEV0138-004 01/01/2020
COLUMBIA COUNTY (THE TOWNS OF ANCRAM, CLERMONT, COPAKE,
GALLATIN, GERMANTOWN, LIVINGSTON, AND TAGHKANIC); GREEN COUNTY
(THE TOWNS OF HUNTER AND CATSKILL)
ELEVATOR MECHANIC................$ 60.49 34.765+a+b
FOOTNOTE:
a.Vacation: 6%/under 5 years based on regular hourly rate for all hours worked. 8%/over 5 years based on regular hourly rate for all hours worked.
b. PAID HOLIDAYS: New Year's Day; Memorial Day; Independence Day; Labor Day; Veterans' Day; Thanksgiving Day; the Friday after Thanksgiving Day; and Christmas Day.
ENGI0106-001 07/01/2018
HEAVY & HIGHWAY
Rates Fringes
Power equipment operators:
GROUP 1.....................$ 43.47 26.05+a GROUP 2.....................$ 42.56 26.05+a GROUP 3.....................$ 39.99 26.05+a GROUP 4.....................$ 47.47 26.05+a GROUP 5.....................$ 46.47 26.05+a GROUP 6.....................$ 45.47 26.05+a GROUP 7.....................$ 45.08 26.05+a
POWER EQUIPMENT OPERATOR CLASSIFICATIONS (HEAVY & HIGHWAY):
GROUP 1: Asphalt Curb Machine, Self Propelled, Slipform, Automated Concrete Spreader (CMI Type), Automatic Fine Grader, Backhoe (Except Tractor Mounted, Rubber Tired), Backhoe Excavator Full Swing (CAT 212 or similar type), Back Filling Machine, Belt Placer (CMI Type), Blacktop Plant (Automated), Boom truck , Cableway, Caisson Auger, Central Mix Concrete Plant (Automated), Concrete Curb Machine, Self Propelled, Slipform, Concrete Pump, Crane, Cherry Picker, Derricks (steel erection), Dragline, Overhead Crane (Gantry or Straddle type), Pile Driver, Truck Crane, Directional Drilling Machine, Dredge, Dual Drum Paver, Excavator (All Purpose Hydraulically Operated) (Gradall or Similar), Front End Loader ( 4 cu. yd. and Over), Head Tower (Sauerman or Equal), Hoist (Two or Three Drum), Holland Loader, Maintenance Engineer, Mine Hoist, Mucking Machine or Mole Pavement Breaker(SP) Wertgen; PB-4 and similar type, Power Grader, Profiler (over 105 H.P.)
Quad 9, Quarry Master (or equivalent), Scraper, Fireman, Form Tamper, Grout Pump, Gunite Machine, Hammers (Hydraulic self-propelled), Hydra-Spiker, ride-on, Hydraulic Pump (jacking system), Hydro-Blaster (Water), Mulching Machine, Oiler, Parapet Concrete or Pavement, Shovel, Side Boom, Slip Form Paver, Tractor Drawn, BeltType Loader, Truck or Trailer Mounted Log , Chipper (Self Feeder), Tug Operator (Manned Rented Equipment Excluded), Tunnel Shovel
GROUP 2: Asphalt Paver, Backhoe (Tractor Mounted, Rubber Tired), Bituminous Recycler Machine, Bituminous Spreader and Mixer, Blacktop Plant (NonAutomated), Blast or Rotary Drill (Truck or Tractor Mounted), Boring Machine, Cage Hoist, Central Mix Plant (NonAutomated) and All Concrete Batching Plants, Cherry Picker (5 tons capacity and under), Concrete Paver (Over 16S), Crawler Drill, Self-contained, Crusher, Diesel Power Unit, Drill Rigs, Tractor Mounted, Front End Loader (Under 4 cu. yd.), Greaseman/Lubrication Engineer, HiPressure Boiler (15 lbs. and over), Hoist (One Drum), Hydro-Axe, Kolman Plant Loader and Similar Type Loaders, L.C.M. Work Boat Operator, Locomotive Mixer (for stabilized base selfpropelled), Monorail Machine, Plant Engineer, Profiler (105 H.P. and under), Grinder, Post Hole Digger and Post Driver, Power Broom (towed), Power Heaterman, Power Sweeper, Revinius Widener, Roller (Grade and Fill), Scarifier, ride-on, Shell Winder, Skid steer loader (Bobcat or similar), Span-Saw, ride-on, Steam Cleaner, Pug Mill, Pump Crete Ready Mix Concrete Plant Refrigeration Equipment (for soil stabilization)Road Widener, Roller (all above subgrade), Sea Mule, Self-contained Ride-on Rock Drill, Excluding Air-Track Type Drill, Skidder, Tractor with Dozer and/or Pusher, Trencher.
Tugger Hoist, Vermeer saw (ride on, any size or type), Winch, Winch Cat
GROUP 3: A Frame Winch Hoist on Truck , Articulated Heavy Hauler, Aggregate Plant, Asphalt or Concrete Grooving, Machine (ride on), Ballast Regulator, Ride-on Boiler (used in conjunction with production), Bituminous Heater, self-propelled, Boat (powered), Cement and Bin Operator, Compressors, Dust Collectors, Fork Lift, Generators, Pumps, Welding Machines, Light Plants, Heaters (hands-off equipment), Concrete Pavement Spreader and Finisher, Concrete Paver or Mixer (16S and under), Concrete Saw (self-propelled), Conveyor, Deck Hand, Directional Drill Machine Locator, Drill, (Core), Drill, (Well,) Farm Tractor with accessories, Fine Grade Machine, Tamper, ride-on, Tie Extractor, ride-on, Tie Handler, ride-on, Tie Inserter, ride-on, Tie Spacer, ride-on, Tire Repair, Track Liner, ride-on, Tractor, Tractor (with towed accessories), Vibratory Compactor, Vibro Tamp, Well Point
GROUP 4: Tower Cranes
GROUP 5: Cranes 50 tons and over
GROUP 6: Cranes 49 tons and below
GROUP 7: Master Mechanic
FOOTNOTE:
a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day
ENGI0106-012 07/01/2018
BUILDING
EXCLUDING MONTGOMERY COUNTY
Rates Fringes
POWER EQUIPMENT OPERATOR
GROUP A(1)..................$ 43.79 25.70+a GROUP A.....................$ 43.30 25.70+a 1..........................$ 45.04 25.70+a 2..........................$ 46.04 25.70+a GROUP B.....................$ 42.28 25.70+a GROUP C.....................$ 39.38 25.70+a
Hazardous work - Anytime Operating Engineers are involved with level C or above, $2.50 per hour over regular rate.
FOOTNOTE:
a. Paid Holidays: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day.
POWER EQUIPMENT OPERATOR CLASSIFICATIONS (BUILDING):
GROUP A(1): Crane, hydraulic cranes, tower crane, locomotive crane, piledriver, cableway, derricks, whirlies, dragline, boom truck (over 5 tons)
GROUP A(1): Crane Premiums:
1 over 150'- $1.00 2 over 200'- $2.00
GROUP A: Shovel, All Excavators (including rubber tire full swing), gradalls, power road grader, all CMI equipment, front-end rubber tire loader, tractor-mounted drill (quarry master), mucking machine, concrete central mix plant, concrete pump, Belcrete system, automated asphalt concrete plant and tractor road paver, boom truck (5 tons and under), maintenance engineer, self contained crawler, drill-hydraulic rock drill.
GROUP B: Backhoe, (rubber-tired backhoe/loader combination), bulldozer, pushcat, tractor, traxcavator, scraper, LeTourneau grader, form fine grader, road roller, blacktop roller, blacktop spreader, power brooms, sweepers, trenching machine, Barber Green loader, side booms, hydrohammer, concrete spreader, concrete finishing machine, one drum hoist, power hoisting (single drum), hoist - two drum or more, three drum engine, power hoisting (two drum and over), two drum and swinging engine, three drum swinging engine, hod hoist, A-L frame winches, cord and well drillers (one drum), post hole digger, model CHB Vibro-Tamp or similar machine, batch bin and plant operator, dinkey locomotive, skid steer loader, track excavator 5/8 cu. yd. or smaller
GROUP C: Fork lift, high lift, lull, oiler, fireman and heavy- duty greaser, boilers, and steam generators, pump, vibrator, motor mixer, air compressor, dust collector, welding machine, well point, mechanical heater, generators, temporary light plants, concrete pumps, electric submersible pump 4"" and over, murphy type diesel generator, conveyor, elevators, concrete mixer and belcrete power pack (belcrete system), seeding, and mulching machines, pumps
IRON0012-011 07/01/2019
ALBANY; COLUMBIA; FULTON (Albin, Bleecker, Broad, Johnstown, Mayfield, Northampton and Perth); GREENE, MONTGOMERY (Amsterdam, Charleston, Florida, Glen, Mohawk and Root);
RENSSELAER, SARATOGA; SCHENECTADY; SCHOHARIE; and WASHINGTON
COUNTIES:
Ironworkers:
Sheeter, Bucker-up..........$ 31.80 28.59 Sheeter.....................$ 31.80 28.59 Structural, Ornamental, Rodman, Machinery Mover, Rigger, Fence Erector, Reinforcing, Stone Derrickmen..................$ 31.55 28.59
IRON0440-007 01/01/2019
FULTON (Twps. of Caroga, Ephratah, Oppenheim, Stratford);
MONTGOMERY (Twps of Canajoharie, Minden, Palatine, St.
Johnsville):
IRONWORKER
Structural, Ornamental, Rodman, Machinery Mover, Rigger, Fence Erector, Reinforcement, and Stone Derrickman..................$ 28.25 25.94
LABO0017-001 07/01/2019
COLUMBIA COUNTY (Twps of Greenport, Claverack, Clermont, Germantown, Livingston, Hillsdale, Taghkanic, Gallatin, Copake, Ancram, Philmont and the City of Hudson)
LABORER
COLUMBIA COUNTY (Townships of Greenport, Claverack, Clermont, Germantown, Livingston, Hillsdale, Taghkanic, Gallatin, Copake, Ancram, Philmont, and the City of Hudson) (Asbestos, lead, toxic and hazardous waste abatement and any other environmental related work) HEAVY & HIGHWAY GROUP 1:...................$ 38.90 27.15+a GROUP 2:...................$ 43.15 27.15+a GREENE COUNTY (Township of Catskill) HEAVY & HIGHWAY:
GROUP 1:...................$ 34.15 27.15+a GROUP 2:...................$ 38.90 27.15+a GROUP 3:...................$ 43.15 27.15+a GROUP 4:...................$ 48.00 27.15+a
TUNNEL, SHAFT & CAISSON
WORK
GROUP 1....................$ 48.05 29.50+a
For HEAVY & HIGHWAY CLASSIFICATIONS in COLUMBIA COUNTY (Townships of Greenport, Claverack, Clermont, Germantown, Livingston, Hillsdale, Taghkanic, Gallatin, Copake, Ancram, Philmont and the City of Hudson)
HEAVY & HIGHWAY CLASSIFICATIONS
GROUP 1: Asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous material abatement when protective equipment and clothing are not required
GROUP 2: Asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous material abatement when protective clothing and equipment is required
For HEAVY & HIGHWAY CLASSIFICATIONS in GREENE COUNTY (Township of Catskill)
FOOTNOTE:
a. PAID HOLIDAYS: New Years Day, President's Day, Memorial Day, Independence Day, Lincoln's Birthday, Labor Day, Election Day, Veterans Day, Thanksgiving Day, Christmas Day, provided the employee is an employee of the company prior to the scheduled holiday and reports to work the first day following the holiday unless prevented from doing so for legitimate reasons.
GROUP 1: Flagperson, gateperson
GROUP 2: General laborers, chuck tender, handling and distributing drinking water, distributing all tools and supplies of laborers, nipper, powder carrier, magazine tender, warehouse laborers, concrete man, vibrator man, mason tender, mortar man, spraying, brushing and covering of concrete for curing and preservative purposes, traffic striper, scaffold builder, concrete curb and sidewalk form setter; permanent traffic striping and reflective devices, placing and maintenance of all flares, cones, lights, signs, barricades, traffic patterns, and all temporary reflective type materials for traffic control, custodial work, traffic directors, temporary heat or light tenders, tool room, dewatering pump men, pitman, dumpmen, snow removal and firewatch, asphalt man, joint setter, signal person, pipelayer, pipe lining and relining, wellpoints, conduit and duct layer, wire puller, rip rap and dry stone layer, steel rod carrier, core drill, rock splitter, Hilti gun air or electric, jackhammer, bush hammer, pavement breaker, chipping hammer, wagon drill, air track, jib rig, joy drill, gunite and sand blasting, coal passer and other machine operators, power tool operator, sprayer and nozzle man on mulching and seeding machine, all guard rail and fence, all seeding and sod laying, all landscape work, grade checker, all bridge work, walk behind self-propelled power saw, grinder, groover or similar type machine, walk behind tamper and roller of all types, salvage, stripping, wrecking and dismantling laborer (including barman, cutting torch and burner man), sheeting and shoring coming under laborers jurisdiction, bit grinder, operator of form pin puller and drivers, sandblasting, joint and jet sealer, filling and wiring baskets for gabion walls, permanent sign man, median barrier, sta-wall or similar type product, chain saw operator, railroad track laborer, waterproofer, pre-stressed and pre-cast concrete brick, block and stone pavers, power tools used to perform work usually done by laborers, power buggy and pumpcrete operator, fireproof, plaster and caustic pump, asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous materials abatement when protective clothing and equipment is not required, power brush cutter, retention liners, artificial turf, retaining walls, walk behind surface planer, welding related to laborers work, remote controlled equipment normally operated by laborers, all technician work including but not limited to stitching, seaming, heat welding, fireproof sprayer, mortar mixer, concrete finisher, form setter for concrete curbs and flatwork.
Gunite nozzle man, stone cutters, granite stone layer, manhole, catch basin or inlet installing, laser men.
Ground man on milling machine
GROUP 3 Ingersoll Rand heavy duty crawler-master HCMZ, any drill using a 4"" or larger bit, asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous material abatement when protective clothing and equipment is required, all working foremen including grade, pipe concrete, clearing, blacktop, drill, paving and blaster etc., Hydraulic drill or similar, forklift for masonry only, Blaster and asphalt screedman
GROUP 4: Asbestos, toxic, lead or hazardous material abatement foreman
For TUNNEL, SHAFT & CAISSON WORK CLASSIFICATIONS
a. PAID HOLIDAYS: New Years Day, President's Day, Memorial Day, Independence Day, Labor Day, Election Day, Veterans Day, Thanksgiving Day, Christmas Day
GROUP 1: Laborer, Pit and Dumpman, Chuck Tender, Brakeman and Powderman;
Miner and all machine men, Safety Miner, all shaft work, caisson work, drilling, blow pipe, all air tools, tugger, scaling, nipper gunniting from pot to nozzle, bit grinder, signal man (top and bottom), shield driven tunnel, mixed face and soft ground liner plate tunnel in free air
LABO0035-001 07/01/2017
FULTON (TWPS OF CAROGA, EPHRATA, OPPENHEIM, AND STRAFORD);
MONTGOMERY (TWPS OF CANAJOHARIE, MINDEN AND PALATINE, ROOT AND
ST. JOHNSVILLE)
Laborers Building Construction Asbestos Removal............$ 24.00 20.64+a Blasters, Form Setters, MotorBuggy Operator (Rider Type)......................$ 23.00 20.64+a Hazardous Waste Removal Hazardous waste removal includes wetting, stripping, removal, scrapping, vaccuuming, bagging and disposing of all insulation materials, whether they contain asbestos or not, from mechanical systems.........$ 24.00 20.64+a
HEAVY & HIGHWAY:
GROUP 1:...................$ 28.05 23.74+a GROUP 2:...................$ 28.25 23.74+a GROUP 3:...................$ 28.45 23.74+a GROUP 4:...................$ 28.65 23.74+a Laborers....................$ 22.50 20.64+a Pipelayers, Motor Mixers, Motor Buggy Operator (Walk Behind) Power Lift (Walk Behind)...............$ 22.65 20.64+a Wagon Drill Operator........$ 22.90 20.64+a
FOOTNOTE:
a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day.
GROUP 1: Common Laborers, Flagman, Outboard and Hand boats
GROUP 2: Bull Float, Chain Saw, Concrete aggregate bin, Concrete Bootman, Gin Buggy, Hand or Machine Vibrator, Jackhammer, Mason Tender, Mortar Mixer, Pavement Breaker, Handlers of all steel mesh, Small generators for laborer's tools, Installation of bridge drainage, Pipelayers, Vibrator type rollers, Tamper, Drill doctor, Tail or Screw Operator on asphalt paver, Water pump operator (1 1/2"" and single diaphragm), Nozzle (asphalt, gunnite, seeding and sand blasting), Laborers on chain link fence erection, Rock splitter and power unit, Pusher type concrete saw and all other gas, electric, oil, and air tool operators, Wrecking laborers
GROUP 3: All rock or drilling machine operators (except quarry master and similar type), Acetylene torch operators, and Asphalt paver, Powderman
GROUP 4: Blasterers, Form setters, Stone or Granite Curb setters
LABO0157-001 07/01/2017
FULTON (Twps. of Bleeker, Mayfield, Northhampton, Johnstown, Broadalbin and Perth); MONTGOMERY (Twps. of Mohawk, Glen, Charleston, Amsterdam, and Florida); SARATOGA (Twps. of Day, Hadley, Edinburg, Corinth, Moreau, South Glens Falls, Providence, Greenfield, Wilton, Northcumberland, Galway, Milton, Saratoga Springs, Charlton, Ballston, Malta and Clifton Park); SCHENECTADY and SCHOHARIE COUNTIES.
LABORER
BUILDING:
GROUP 1....................$ 28.74 20.14+a GROUP 2....................$ 30.09 20.14+a
HEAVY & HIGHWAY:
GROUP 1:...................$ 30.55 21.29+a GROUP 2:...................$ 30.75 21.29+a GROUP 3:...................$ 30.95 21.29+a GROUP 4:...................$ 31.15 21.29+a GROUP 5:...................$ 32.55 21.29+a
LABORER CLASSIFICATIONS
Group 1: Common Laborers
Group 2: Asbestos and Toxic Materials
Commercial projects valued at $800,000 or less and/or industrial projects valued at $100,000 or less, excluding demolition work (the complete razing of structures) 75% of the basic wage scale with full benefits will apply
FOOTNOTE:
a. PAID HOLIDAYS: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day
LABORER CLASSIFICATIONS
GROUP 1: Common laborers, flagman, outboard & hand boats
GROUP 2: Bull float, chain saw, concrete aggregate bin, concrete bootman, gin buggy, hand or machine vibrator, jackhammer, mason tender, mortar mixer, pavement breaker, handlers of all steel mesh, small generators for laborers' tools, installation of bridge drainage, pipelayers, vibrator type rollers, tamper, drill doctor, tail or screw operator on asphalt paver, water pump operator (1 1/2"") and single diaphragm), nozzle (asphalt, gunnite, seeding, and sand blasting), laborers on chain fence erection, rock splitter and power unit, pusher type concrete saw and all other gas, electric, oil, and air tool operators, wrecking laborers
GROUP 3: All rock drilling machine operators (except quarry master and similar type), acetylene torch operator, and asphalt paver, powderman
GROUP 4: Blasterers, form setters, stone or granite curb setters
GROUP 5: Hazardous waste removal
LABO0190-001 07/01/2019
ALBANY; GREEN; RENSSELAER COUNTY, WASHINGTON COUNTY, SARATOGA
COUNTY (Townships of Stillwater, Halfmoon, Saratoga)
Laborers:
BUILDING:
GROUP 1....................$ 28.51 23.17
GROUP 2....................$ 29.86 23.17
LABORERS CLASSIFICATIONS
GROUP 1: Common Laborers
GROUP 2: Hazardous waste removal Commercial projects valued at $800,000 or less and/or industrial projects valued at $100,000 or less excluding demolition work, (complete razing of structures) will receive 75% of basic wage scale with full fringes will apply
LABO0190-002 07/01/2018
ALBANY; RENSSELAER; COLUMBIA (Twps. of Stuyvesant, Stockport, Kinderhook, New Lebanon, Cannan, Ghent, Chatham, Austerlitz).
GREENE (except Catskill Township). WASHINGTON COUNTY. SARATAGO COUNTY (Townships of Stillwater, Halfmoon Saratoga)
HEAVY & HIGHWAY:
GROUP 1:...................$ 30.94 22.70
GROUP 2:...................$ 31.14 22.70
GROUP 3:...................$ 31.34 22.70
GROUP 4:...................$ 31.54 22.70
GROUP 5:...................$ 32.94 22.70
PAID HOLIDAYS: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day.
LABORERS CLASSIFICATIONS
GROUP 1: Common laborers, flagmen, outboard and hand boats
GROUP 2: Bull float, chain saw, concrete aggregated bin, concrete bootman, gin buggy, hand or machine vibrator, jackhammer, mason tender, mortar mixer, pavement breaker, handlers of all steel mesh, small generators for laborers' tools, installation of bridge drainage, pipelayers, vibrator type rollers, tampers, drill doctor, Tail or screw operator on asphalt paver, Water pump operator (1 1/2"" and single diaphragm), Nozzle (asphalt, gunnite, seeding, and sand blasting) Laborers on chain link fence erection, rock splitter and power unit, pusher type concrete saw and all other gas, electric, oil, air tool operators, and wrecking laborers
GROUP 3: All rock air drilling machine operators (except quarry master and similar type), acetylene torch operators, and asphalt paver, powderman
GROUP 4: Blasterers, form setters, stone or granite curb setters
GROUP 5: Hazardous waste removal
LABO0235-006 05/01/2018
COLUMBIA (Twps. of Greenport, Claverack, Hillsdale, Livingston, Germantown, Taghkanic, Copake, Clermont, Gallatin, Ancram):
HEAVY & HIGHWAY
GROUP 1....................$ 24.40 29.75+a GROUP 2....................$ 28.16 29.75+a GROUP 3....................$ 29.16 29.75+a
LABORERS CLASSIFICATIONS (HEAVY & HIGHWAY)
GROUP 1: Flagperson; Placing and maintenance of all flares, cones, lights, signs, barricades; traffic control custodial work; traffic directors; temporary heat or light tenders;
tool rooms
GROUP 2: General Laborers, Dumpman, Pitman, Concrete man;
Signal man; Pipelayers; Rip rap; Dry stone layer; Jack hammer; Powderman; Highscalers power buggy operator; Steel rod carrier; Vibratory operator; other machine operator;
wrecking; Vibrator operator-compactor; Gunite and sandblasting; Water pump 2"" or under; Nipper; Chucker;
Asphalt Workers
GROUP 3: Asphalt raker; Asphalt Screedman; Drillers (all);
Laser Beam Operator; Form Setter/Aligners; Blasters
FOOTNOTE:
a. PAID HOLIDAYS: New Years Day, Presidents Day, Good Friday, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Day, November Election Day, Thanksgiving Day, and Christmas Day
PAIN0009-013 07/01/2020
Rates Fringes
GLAZIER..........................$ 32.65 28.32
PAIN0155-002 05/01/2018
COLUMBIA AND GREENE COUNTIES
Rates Fringes
Painters:
Drywall Finisher............$ 32.99 22.76 Lead Abatement Work.........$ 32.99 22.76 Painter/Paperhanger.........$ 32.99 22.76 Spray Rate..................$ 33.99 22.76
PAIN0201-001 05/01/2019
Rates Fringes
Painters:
Lead Abatement Workers, Structural Steel Zone 1.....................$ 30.09 16.65 Zone 2.....................$ 30.09 16.65 Painters, Drywall Finishers, Spray Zone 1.....................$ 29.09 16.65 Zone 2.....................$ 29.09 16.65
Zone #1 Entire counties of ALBANY, FULTON, MONTGOMERY, RENNSELAER, SCHOHARIE, SCHENECTADY AND SARATOGA
ZONE #2 All of WASHINGTON County
PAIN0806-002 10/01/2020
ALBANY, COLUMBIA, FULTON, GREENE, MONTGOMERY, RENNSELAER,
SCHOHARIE, SCHENECTADY, SARATOGA AND WASHINGTON
Painters:
Structural Steel and Bridge.$ 51.50 49.63
PLUM0007-001 05/01/2021
ALBANY; COLUMBIA; FULTON; GREENE; MONTGOMERY; RENSSELAER;
SCHENECTADY; SARATOGA (Towns of Charlton, Clifton Park, Galway, Halfmoon, Milton, Stillwater and Waterford)
PLUMBER/PIPEFITTER...............$ 46.34 26.44
PLUM0112-019 05/01/2020
Townships of Canajoharie and Minden
Rates Fringes
PLUMBER (Including Steamfitting) Northern Zone...............$ 37.85 28.45
* PLUM0773-002 05/01/2020
SARATOGA (Remainder of County); WASHINGTON COUNTY:
Rates Fringes
PLUMBER/PIPEFITTER...............$ 38.30 31.38
ROOF0203-003 06/01/2019
SCHOHARIE COUNTY:
Rates Fringes
ROOFER...........................$ 26.30 16.16
ROOF0241-001 07/01/2018
Rates Fringes
ROOFER...........................$ 30.05 19.27
SFNY0669-001 04/01/2021
SPRINKLER FITTER.................$ 38.96 25.37
SHEE0083-001 06/01/2019
Rates Fringes
Sheet metal worker...............$ 33.73 33.04+a
FOOTNOTE:
a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day. If any of these holidays fall on a Saturday or Sunday, either the preceding Friday or following Monday will be observed as the holiday.
TEAM0294-003 07/01/2021
Rates Fringes
Truck drivers:
HEAVY & HIGHWAY
GROUP 1....................$ 32.65 27.52+a GROUP 2....................$ 32.71 27.52+a GROUP 3....................$ 32.80 27.52+a GROUP 4....................$ 32.93 27.52+a GROUP 5....................$ 33.09 27.52+a
TRUCK DRIVERS CLASSIFICATIONS (HEAVY & HIGHWAY)
GROUP 1: Pick-ups, panel trucks, flatboy material trucks (straight jobs), single axle dump trucks, dumpsters, receivers, greasers, truck tireman
GROUP 2: Tandems, batch trucks, mechanics
GROUP 3: Semi-trailers, low-boy trucks, asphalt distributor trucks, agitator, mixer trucks and dumpcrete type vehicles, truck mechanic, fuel truck
GROUP 4: Specialized earth moving equipment - euclid type or similar off-highway equipment, where not self-loaded, straddle (ross) carrier, self-contained concrete unit
GROUP 5: Off-highway tandem back dump, twin engine equipment and double hitched equipment where not self-loaded
FOOTNOTE:
a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, provided the employee works the day before and the day after the holiday.
TEAM0294-004 07/01/2019
BUILDING CONSTRUCTION
EXCLUDING MONTGOMERY COUNTY
Rates Fringes
Truck drivers:
GROUP 1.....................$ 27.67 24.28+a GROUP 2.....................$ 27.97 24.28+a
FOOTNOTES:
a. One week vacation after 1 year; 2 weeks vacation after 5 years.
TRUCK DRIVERS BUILDING CLASSIFICATIONS
GROUP 1: Straight, winch, transit mix on job site, road oilers, dump, panel, pick-up, water and fuel trucks on site (including nozzle)
GROUP 2: Euclid or similar equipment, lowboy or lowboy trailers
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .