PROJECT: Watervliet Arsenal, New York Job Order Contract (JOC)

DESCRIIPTION: The general scope of w ork of this contract is to provide all w ork, materials, supplies, parts (to include system components), transportation, plant, supervision, labor, and equipment, except w hen specif ied as Government-furnished, needed to repair, or construct real property facilities at Watervliet Arsenal, Watervliet, NY.

VALUE: The estimated value is capped at $3,000,000 for the base year and $3,000,000 for each of 4 option years. The minimum guarantee is $20,000. Individual job orders w ill be firm fixed price and w ill range from a minimum of $2,000 to a maximum of $500,000.

ACQUISITION: The acquisition is a 100% SDVOSB set-aside, and the NAICS code 236220..

CONTRACT SPECIALIST: Matthew Lubiak, 917-790-8089, matthew .lubiak@usace.army.mil

SUBMISSION OF PROPOSALS: Proposals must be submit no later than the date and time stated in Block 13.a.

Matthew Lubiak USACE Contracting 16-300 c/o PSC Mail Center 26 Federal Plaza, New York, NY 10278

Offerors are advised to allow ample time to pass through security checks in order to have their proposals delivered before 2:00 p.m.

MATTHEW E LUBIAK 917-790-8089

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

24-Jan-2020

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______ calendar days and complete it w ithin ________ calendar days af ter receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________Each Job Order

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________4 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________25 Feb 2020 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 1843

NEW YORK NY 10278-0090

W912DS

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

212 -264-3013FAX:TEL: (917)790-8173 TEL: FAX:

W912DS20R0007 133

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W912DS20R0007

Section 00 10 00 - Solicitation

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

BASE YEAR

FFP

NET AMT

0001AA

BASE - Normal working hours

FFP

All work at Watervliet Arsenal performed during normal working hours. ENTER

COEFFICIENT

FOB: Destination

0001AB

BASE YEAR - Normal working hours(Secure)

FFP

All work at Watervliet Arsenal performed at secure locations durning normial working hours. ENTER COEFFICIENT

0001AC

BASE Other than normal hours

FFP

All work at Watervliet Arsenal performed during other than normal working hours.

ENTER COEFFICIENT

0001AD

BASE Other than normal hours (Secure)

FFP

All work at Watervliet Arsenal performed at secure locations durning other than normial working hours. ENTER COEFFICIENT

0001AE

BASE Non Pre-Priced Tasks

FFP

All work for Non Pre-Priced tasks. ENTER COEFFICIENT

OPTION OPTION YEAR 1

0002AA

OPTION OPTION 1 Normal working hours

FFP

All work at Watervliet Arsenal performed during normal working hours.

[Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.]

0002AB

OPTION OPTION 1 - Normal working hours(Secure)

FFP

All work at Watervliet Arsenal performed at secure locations durning normial

0002AC

OPTION OPTION 1 Other than normal hours

FFP

All work at Watervliet Arsenal performed during other than normal working hours.

[Coefficients for the option periods are subject to economic price adjustment from

0002AD

OPTION OPTION 1 Other than normal hours(Secure)

FFP

All work at Watervliet Arsenal performed at secure locations durning other than

0002AE

OPTION OPTION 1 Non Pre-Priced Tasks

FFP

OPTION OPTION YEAR 2

0003AA

OPTION OPTION 2 Normal working hours

FFP

All work at Watervliet Arsenal performed during normal working hours.

[Coefficients for the option periods are subject to economic price adjustment from

0003AB

OPTION OPTION 2 Normal working hours(Secure)

FFP

All work at Watervliet Arsenal performed at secure locations durning normial working hours.. ENTER COEFFICIENT

0003AC

OPTION OPTION 2 Other than normal hours

FFP

All work at Watervliet Arsenal performed during other than normal working hours.

[Coefficients for the option periods are subject to economic price adjustment from

0003AD

OPTION OPTION 2 Other than normal hours(Secure)

FFP

All work at Watervliet Arsenal performed at secure locations durning other than

0003AE

OPTION OPTION 2 Non Pre-Priced Tasks

FFP

OPTION OPTION YEAR 3

0004AA

OPTION OPTION 3 Normal working hours

FFP

All work at Watervliet Arsenal performed during normal working hours.

[Coefficients for the option periods are subject to economic price adjustment from

0004AB

OPTION OPTION 3 Normal working hours(Secure)

FFP

All work at Watervliet Arsenal performed at secure locations durning normial

0004AC

OPTION OPTION 3 Other than normal hours

FFP

All work at Watervliet Arsenal performed during other than normal working hours.

[Coefficients for the option periods are subject to economic price adjustment from

0004AD

OPTION OPTION 3 Other than normal hours(Secure)

FFP

All work at Watervliet Arsenal performed at secure locations durning other than

0004AE

OPTION OPTION 3 Non Pre-Priced Tasks

FFP

OPTION OPTION YEAR 4

0005AA

OPTION OPTION 4 Normal working hours

FFP

All work at Watervliet Arsenal performed during normal working hours.

[Coefficients for the option periods are subject to economic price adjustment from

0005AB

OPTION OPTION 4 Normal working hours(Secure)

FFP

All work at Watervliet Arsenal performed at secure locations durning normial working hours.. ENTER COEFFICIENT

0005AC

OPTION OPTION 4 Other than normal hours

FFP

All work at Watervliet Arsenal performed during other than normal working hours.

[Coefficients for the option periods are subject to economic price adjustment from

0005AD

OPTION OPTION 4 Other than normal hours(Secure)

FFP

All work at Watervliet Arsenal performed at secure locations durning other than

0005AE

OPTION OPTION 4 Non Pre-Priced Tasks

FFP

Section 00 21 16 - Instructions to Proposers

CLAUSES INCORPORATED BY REFERENCE

52.204-6 Unique Entity Identifier OCT 2016 52.204-7 System for Award Management OCT 2018 52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2017 52.225-10 Notice of Buy American Requirement--Construction

Materials

MAY 2014

CLAUSES INCORPORATED BY FULL TEXT

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm Fixed Price Indefinite Delivery Indefinite Quantity Job Order Contract contract resulting from this solicitation.

(End of provision)

52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK (MAY

2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements,of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

5.9% 6.9%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Watervliet Arsenal, Albany County, NY.

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) The amount of the bid guarantee shall be $600,000 (20% of the contract annual maximum of $3,000,000).

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from

Chief, Contracting Division U.S. Army Corps of Engineers New York District 26 Federal Plaza, Room 16-300 New York, NY 10278

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)

(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.

(b) The use in this solicitation of any Defense Federal Acquisition Regulation Supplement (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

Section 00 22 00 - Supplementary Instructions

INSTRUCTIONS TO OFFERORS

SECTION IV

FACTORS FOR EVALUATION, BASIS OF AWARD, EVALUATION CRITERIA, RATING SYSTEM AND

DEFINITIONS (SECTION 00 22 11)

1.0 OVERVIEW

This is a “Best Value Trade-Off” solicitation, in accordance with FAR 15.101-1, for the Job Order Contract (JOC) for Maintenance and Repairs at Watervliet Arsenal, NY. The Government will evaluate the proposals in accordance with the criteria described herein, and award a single firm fixed price contract to the responsible Offeror, whose proposal conforms with all the terms and conditions of the solicitation and whose proposal is determined to represent the overall best value to the Government. The Government will not award a contract to an Offeror whose proposal contains a deficiency, as defined in paragraph 5.3 per FAR 15.001.

The Government will evaluate the strengths, weaknesses and any deficiencies in the proposals. Price will be evaluated on fairness, reasonableness, and affordability, but will not be scored.

2.0 GENERAL INSTRUCTIONS

Submit proposal on the most favorable terms from a price and technical standpoint. Two (2) separate volumes shall be submitted as indicated below.

Source Selection Evaluation Factors

Factor Location Description Summary

Factor 1 Vol. 1 Management and Subcontracting Plan proposed management and on-site staff

Factor 2 Vol. 1 Past Relevant Experience Example projects

Factor 3 Vol. 1 Past Performance Past Performance Questionnaires

Factor 4 Vol. 2 Price (Coefficients) Standard Form 1442 and Proposal Data Sheet, Contract Line Item Schedule, with proposed Coefficients

Relative Importance of Factors for Overall Tradeoff

All technical factors (1, 2, and 3) are of equal importance to each other, and when combined, are approximately equal in importance to price (Factor 4).

3.0 EVALUATION FACTORS

Volume I – Technical Proposal

3.1 Factor 1: Management Plan (Tab A). The offeror shall submit a list of proposed management and on-site staff, their backgrounds, and respective positions with regard to this contract. The plan shall demonstrate the offeror’s ability to manage multiple task orders and address their ability to coordinate multiple subcontractors on single or multiple projects; their response time to Government needs; their purchasing system; a plan to administer payroll and labor relation functions; and provide a Quality Control Plan. Such areas of consideration should be:

1.1.2 Explain plan for interaction between the Government and Contractor staff.

Provide an organizational chart to clearly delineate the lines of authority and leadership of key personnel and project managers. Outline the proposed corporate and on-site staff, their resumes, responsibilities and authorities with regard to this contract and how they will interface with each other.

1.1.3 Outline the minimum and maximum on-site staffing levels and describe how and when staffing levels will be adjusted. Discuss the proximity to the installation and how this may affect response time. Address responsibilities, capabilities, and levels of authority in order to assure project accomplishment in a timely and responsive manner. Explain management controls in this process and discuss staffing levels available to cope and negotiate delivery orders simultaneously and effectively. Discuss how staff will provide sketches, plans, shop drawings and as-built drawings, and a plan for ensuring accuracy of sizing calculations (dimensions, electrical capacity, load limits, HVAC sizing, etc). Outline how staff will control cost and be responsible for requisition, purchase, delivery, and inspection of materials.

1.1.4 Develop a proposed Quality Control Plan. Describe what measures and controls will be taken to insure that requirements will be met. Outline the quality control staffing to include experience, training and education requirements and what disciplines of construction are areas of expertise. Outline the quality control staff qualifications, responsibilities and authority, and quality control reporting procedure. Outline what measures will be taken to correct construction deficiencies. Outline a proposed safety plan, explaining how Occupational Safety Health Administration (OSHA) and the requirements of EM-385-1-1 will be met.

1.1.5 Provide rationale for selection and utilization of subcontractors. Explain the subcontracting support capability; criteria for subcontractor selection; plan for coordinating, scheduling, and ensuring timeliness of work execution; and completion of multiple projects with multiple subcontractors. Discuss how the subcontracted effort will be integrated into the total contract effort. What means of communication will there be between contractor and subcontractor? How will multiple projects affect plans? Delineate controls management will have on timeliness and quality of subcontracted effort. Discuss utilization of local business, in the vicinity of the installation, as either a prime or subcontractor.

1.2 Factor 2: Past Relevant Experience (Tab B). The Offeror shall demonstrate not less than five (5) examples of projects not less than 75% complete or physically completed within the last five (5) years and shall be similar in scope, magnitude and complexity.

Physical completion is defined as the date the facility was turned over to, or occupied by the owner. Projects similar in scope, magnitude and complexity are defined as: Scope is defined as maintenance and repair projects on any of the following types: infrastructure projects (i.e., water lines, sanitary lines, storm water systems, fire protection systems, electrical systems and HVAC systems, industrial facilities, administrative facilities, and residential/family housing. Magnitude is defined as the maintenance and repair of projects between $50,000 to $500,000 in a single facility or a multi-building complex.

Complexity is defined as the use of a multi-disciplined team in construction of the facilities of the type as described under scope. Include actual and scheduled start, completion and duration dates and a list of references. References should include company name, point of contact, and phone number. Be specific regarding experience, especially that relating to facilities maintenance and repair projects and minor new construction. Identify scopes of work in previous projects to include types and levels of skills, trade, and equipment.

1.3 Factor 3: Past Performance (Tab C). Client/Agency surveys. The Offeror shall demonstrate at a minimum satisfactory performance and evaluation information, including timely completion of punch list and warranty work, for the projects submitted.

The Past Performance Questionnaire included in the solicitation is provided for the offeror or its team members to submit to the client for each project the offeror includes in its proposal for Factor 1. Ensure correct phone numbers and email addresses are provided for the client point of contact. Completed Past Performance Questionnaires (PPQ) should be submitted with your proposal. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before the proposal closing date, the offeror should complete and submit with the proposal the first page of the PPQ (FORM A2), which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Matthew Lubiak via email at matthew.lubiak@usace.army.mil prior to proposal closing date. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.

Also include performance recognition documents received within the last five (5) years such as award fee determinations, customer letters of commendation, and any other forms of performance recognition.

In addition to the above the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved though the Contractor Performance Assessment Reporting System (CPARS), using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the offeror.

While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.

In addition, the Offeror is required to provide information terminations and past projects (within the past five (5) years) in which they have been issued a CURE NOTICE and provide accompanying information as to the details for such action(s) with an explanation of why they were issued a cure notice.

1.4 Rating for Factor 1: Management and Subcontracting Plan, and for Factor 2: Past Relevant Experience.

Color Rating

Adjectival Rating

Description

Blue Outstanding Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is low.

Purple Good Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate.

Green Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.

Yellow Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.

Red Unacceptable Proposal does not meet requirements of the solicitation, and thus, contains one or more deficiencies, and/or risk of unsuccessful performance is unacceptable. Proposal is unawardable.

1.5 Rating for Factor 3: Past Performance

PAST PERFORMANCE RISK RATINGS

Past Performance Relevancy Ratings Rating Definition Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.

Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.

Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.

Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.

Performance Confidence Assessments Rating Description Substantial Confidence Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.

Satisfactory Confidence Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.

Limited Confidence Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.

No Confidence Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.

Unknown Confidence (Neutral) No recent/relevant performance record is available or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.

If the Government does not obtain past performance information for the projects identified by the Offeror and cannot establish a past performance record for the Offeror through other sources, past performance will be rated neither favorably nor unfavorably. The performance confidence assessment will be considered "Unknown Confidence", which is a neutral rating assessment.

The government will not award to an Offeror that receives rating below Satisfactory Confidence for this factor.

1.6 Volume II – Price Proposal

Location

Description

Vol. 2

Tab A Price (Standard Form 1442 and Proposal Data Sheet, Contract Line Item Schedule, and Supplemental Pricing Information)

Tab B Bid Guarantee

Tab C Required Pre-Award Information

NOTE: The Government will evaluate all factors. Price will be evaluated for fairness and reasonableness and affordability through the use of a price analysis. The price evaluators will also check for appearance of unbalancing of bids.

1.7 Price Evaluation Method.

General. All evaluation factors other than price are of equal importance to each other, and when combined, are approximately equal in important to price. The Government will use a Best Value – Trade Offs source selection process, in accordance with FAR 15.101-2, for this acquisition. As reflected in the Price Proposal Schedule, the Offeror must provide coefficients for the Base Year that will be applied to the construction to be performed under this Contract at Watervliet Arsenal during regular working hours and outside regular working hours.

All Unit Prices listed in the Construction Task Catalog are priced at a net value of 1.0000. The Adjustment Factors shall be an increase or decrease to all the Unit Prices listed in the Construction Task Catalog. For example, 1.1000 would be a 10% increase to the Unit Prices and

0.9500 would be a 5% decrease to the Unit Prices. Offerors who submit separate Adjustment Factors for separate Unit Prices will be considered non-responsive and their proposal will be rejected.

The failure of the Offeror to provide coefficients or prices in all locations where a coefficient or price is required in the Price Proposal Schedule may be cause for the proposal to be deemed non-responsive, and may result in the proposal being rejected.

Evaluation Contractor’s Coefficients (Contractor’s Coefficients), the Offeror must propose coefficients for the work at Watervliet Arsenal that are listed the Price Proposal Schedule for all Base Year Contract Line Items (CLINs) The proposed coefficients will be examined to determine that the coefficients are all fair and reasonable, and do not appear to be unbalanced. If coefficients are determined to be unbalanced, or otherwise appear not to be fair and reasonable, it may result in a determination that the proposal is materially deficient, and cause the proposal to be rejected. (Note: Option Year coefficients calculated in accordance with Contract Clause 5152.237-9000 ADJUSTMENTS TO

CONTRACTOR’S COEFFICIENT FOR OPTION YEARS (JOB ORDER CONTRACTS))

4.0 VOLUME 2, TAB B – BID GUARANTEE

Submission Requirements: Submit the bid bond in accordance with the instruction in Section 00

21 00, and Provision 52.228-1.

Evaluation Criteria: This item is not rated. The Government will review the Bid Bond for legal sufficiency. The Bond must be legally sufficient.

5.0 SOURCE SELECTION EVALUATION BOARD (SSEB)

5.1. The SSEB will be established to conduct the evaluation of proposals received in response to this solicitation. The evaluation will be based on the content of the proposal and any subsequent discussions required, as well as information obtained from other sources, e.g. past performance information. The SSEB will not consider any information incorporated by reference, except as expressly allowed by this solicitation.

5.2 EVALUATION

5.2.1 The SSEB will evaluate the proposals and assign a consensus rating for each evaluation factor, except that performance risk ratings are assigned to past performance (see below).

5.2.2. The Government intends to award without discussions. Offerors are cautioned to put forth their best efforts, and to furnish all information clearly to allow the Government to evaluate proposals.

Offerors should not assume that they will have an opportunity to clarify or correct anything in their proposal after submitting it.

5.2.3. A "Competitive Range" is a subjective determination of the most highly rated proposals in the event that the Government decides that discussions with Offerors are required or are considered to be in the Government's best interests. In such an event, the Contracting Officer will establish a competitive range of all the most highly rated proposals.

5.2.4. If discussions are held, the Government may engage in a broad give and take with those Offerors in the competitive range, in accordance with FAR 15.306 (d). The Government will provide the Offeror an advance agenda for the discussions. During discussions, the Government may ask the Offeror to further explain its proposal and to answer questions about it.

5.2.5. Upon conclusion of discussions, those Offerors still considered the most highly rated, will be afforded an opportunity to submit their proposal revisions for final evaluation and selection.

5.3 DEFINITIONS

5.3.1 Deficiency: A material failure of a proposal to meet a Government requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level. (FAR 15.001)

5.3.2. Weakness: A flaw in the proposal that increases the risk of unsuccessful contract performance.

5.3.3. Significant Weakness: A flaw in the proposal that appreciably increases the risk of unsuccessful contract performance.

5.3.4. Strength: Any aspect of a proposal that, when judged against a stated evaluation criterion, enhances the merit of the proposal or increases the probability of successful performance of the contract.

5.3.5. Significant Strength: A significant strength appreciably enhances the merit of a proposal or appreciably enhances the probability of successful contract performance.

5.3.6. Deviation: Proposal implies or specifically offers a deviation below the specified criteria. The

Offeror may or may not have called the deviation to the Government's attention. A deviation is a deficiency. The proposal must conform to the solicitation requirements for award.

5.3.7. Uncertainty: Any aspect of a non-cost/price factor proposal for which the intent of the offer is unclear (e.g. more than one way to interpret the offer or inconsistencies in the proposal indicating that there may have been an error, omission, or mistake).

5.4 EVALUATION RATING SYSTEM

5.4.1 General: The Government will review the proposals and rate the quality of each evaluation factor.

The SSEB will rate each proposal against the specified evaluation criteria in the Solicitation requirements. They will not compare proposals at this time. After all proposals are rated, the Government will compare the ratings and relative advantages and disadvantages of proposals against each other.

5.4.2. Review Write-up: The Government will support each rating with a narrative, separately listing all strengths or advantages, weaknesses or disadvantages, deficiencies, and required clarifications.

5.4.3. Rating System: After listing proposal strengths, weaknesses and deficiencies, the SSEB will assign an adjective rating of "Outstanding", "Good", "Acceptable", "Marginal", or "Unacceptable" to each factor except the Past Performance Factor, which reflect the Government's confidence in each Offeror's ability, as demonstrated in its proposal, to perform the requirements stated in the

RFP. The adjectival ratings shall be assigned, using the following criteria, which incorporate a proposal risk assessment:

5.4.3.1. Outstanding: Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is low.

5.4.3.2. Good: Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate.

5.4.3.3. Acceptable: Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.

5.4.3.4. Marginal: Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.

5.4.3.5. Unacceptable: Proposal does not meet requirements of the solicitation, and thus, and contains one or more deficiencies, and/or risk of unsuccessful performance in unacceptable. Proposal is unawardable.

5.5 PAST PERFORMANCE CONFIDENCE ASSESSMENT RATING SYSTEM

5.5.1 Past Performance Risk Ratings assess the risks associated with an Offeror's likelihood of success in performing the requirements stated in the RFP based on the Offeror's demonstrated performance on recent, relevant contracts.

5.5.2. Performance Confidence Assessment (Overall) Rating System:

5.5.2.1. Neutral Confidence: No recent/relevant performance record is available or the Offeror's performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.

5.5.2.2. Substantial Confidence: Based on the Offeror’s recent/relevant performance record, the

Government has a high expectation that the Offeror will successfully perform the required effort.

5.5.2.3. Satisfactory Confidence: Based on the Offeror's recent/relevant performance record. The

Government has a reasonable expectation that the Offeror will successfully perform the required effort.

5.5.2.4. Limited Confidence: Based on the Offeror's recent/relevant performance record, the

Government has a low expectation that the Offeror will successfully perform the required effort.

5.5.2.5. No Confidence: Based on the Offeror's recent/relevant performance record, the Government has no expectation that the Offeror will be able to successfully perform the required effort.

6.0 BASIS OF AWARD

The Contracting Officer will award a firm fixed-price contract to the responsible Offeror whose proposal the Source Selection Authority has determined conforms to the solicitation, is fair and reasonable, and offers the best overall value to the Government, considering all non-price factors described herein, and price. Price will be evaluated and it is considered approximately equal in importance to all other evaluation factors when combined. After the Government individually evaluates and rates each proposal, the Source Selection Authority will compare proposals to determine which proposal represents the best value. The Government reserves the right to accept other than the lowest price offer, other than the highest rated offer, or to reject all offers. The Government will not award a contract to an Offeror whose proposal contains a deficiency, as defined in FAR 15.001. No award will be made to an Offeror receiving either:

a. A rating below SATISFACTORY CONFIDENCE in Factor 3.

b. A rating of UNACCEPTABLE in Factors 1 or 2.

SECTION 00 22 11

ATTACHMENTS

ATTACHMENT 1 - RELEVANT PROJECT INFORMATION SHEET

(Information shall be provided in below format)

1. Project name and location (city, country)

2a. Name of Firm that performed this work (this should be the Offeror or one of the Offeror’s committed subcontractors)

2b. Offeror’s involvement in this project (write in “Prime”, “Subcontractor”, or “Joint-Venture Partner”) (if submitting subcontractor’s experience tell us what the subcontractor’s involvement was on the project)

3a. Project Owner’s name (Government Agency, commercial firm or other organization)

3b. Project Owner's complete address

4. Contract number of project

5. Date contract was signed

6. Date work was begun 7. Date work was completed or is scheduled for completion

8. Initial contract price (amount for which the Offeror was responsible)

USD $

9. Current Contract amount (or amount Offeror has invoiced to date)

USD $

10a. Technical point of contact of the Project Owner (name, title, e-mail address, phone number and fax number)

10b. Contracting point of contact of the Project Owner (name, title, e-mail address, phone and fax numbers)

11. Description of Construction work (describe scope of project and scope of work actually performed by the Offeror (or proposed Subcontractor). Include the type of construction, criteria used, and any other information to demonstrate relevance of the project. For additional explanation, please attach a continuation sheet.

12. Current status of the project (fill in % complete)

The work is ________ % complete.

(If not 100%, indicate current status, on-schedule, behind, terminated for convenience, etc.)

13. Point of contact for Past Performance information (if different from Project Owner) (name, title, e-mail address, phone and fax numbers)

14. Explain any Problem(s) Encountered and Solution(s) to Resolve them. If the initial completion date or initial contract amount changed during performance of the work, or there were any safety issues, the Offeror should provide an explanation here. If no problems were encountered and the contract was completed within the original schedule and budget, state so here. For additional explanation, please attach a continuation sheet.

ATTACHMENT 2 – KEY PERSONNEL RESUME FORM

Name___________________________________________________________________

Management Title:_________________________________________________________

Role on this Project: _______________________________________________________

Number of Years: With this firm ____________________With other firms______________

Number of Years in this position or role: ________________________________________

Specialization: ____________________________________________________________

Professional Registration or Certification (Type and State of Registration):

Experience and Qualifications Relevant to this Project:

ATTACHMENT 3 – PAST PERFORMANCE QUESTIONNAIRE (PPQ)

NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0) CONTRACT INFORMATION (Contractor to complete Blocks 1-4)

1. Contractor Information Firm Name: CAGE Code:

Address: DUNs Number:

Phone Number:

Email Address:

Point of Contact: Contact Phone Number:

2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other (Explain) Percent of project work performed:

If subcontractor, who was the prime (Name/Phone #):

3. Contract Information Contract Number:

Delivery/Task Order Number (if applicable):

Contract Type: Firm Fixed Price Cost Reimbursement Other (Please specify):

Contract Title:

Contract Location:

Award Date (mm/dd/yy):

Contract Completion Date (mm/dd/yy):

Actual Completion Date (mm/dd/yy):

Explain Differences:

Original Contract Price (Award Amount):

Final Contract Price (to include all modifications, if applicable):

Explain Differences:

4. Project Description:

Complexity of Work High Med Routine How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)

CLIENT INFORMATION (Client to complete Blocks 5-8)

5. Client Information Name:

Title:

Phone Number:

Email Address:

6. Describe the client’s role in the project:

7. Date Questionnaire was completed (mm/dd/yy):

8. Client’s Signature:

NOTE: NAVFAC/USACE REQUESTS THAT THE CLIENT COMPLETES THIS QUESTIONNAIRE AND SUBMITS DIRECTLY BACK TO THE OFFEROR. THE OFFEROR WILL SUBMIT THE COMPLETED QUESTIONNAIRE TO USACE WITH THEIR PROPOSAL, AND MAY DUPLICATE THIS QUESTIONNAIRE FOR FUTURE SUBMISSION ON USACE SOLICITATIONS.

CLIENTS ARE HIGHLY ENCOURAGED TO SUBMIT QUESTIONNAIRES DIRECTLY TO THE OFFEROR. HOWEVER, QUESTIONNAIRES MAY BE SUBMITTED DIRECTLY TO USACE. PLEASE CONTACT THE OFFEROR FOR USACE POC INFORMATION. THE GOVERNMENT RESERVES THE RIGHT TO VERIFY ANY AND ALL INFORMATION ON THIS FORM.

ATTACHMENT 3 – PAST PERFORMANCE QUESTIONNAIRE (PPQ) (cont.)

ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE

RATING DEFINITION NOTE

(E) Exceptional Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.

An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.

(VG) Very Good Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.

(S) Satisfactory Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract. There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.

(M) Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.

A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.

(U) Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.

An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.

(N) Not Applicable

No information or did not apply to your contract

Rating will be neither positive nor negative.

TO BE COMPLETED BY CLIENT

PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST REFLECTS

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.

1. QUALITY:

a) Quality of technical data/report preparation efforts E VG S M U N

b) Ability to meet quality standards specified for technical performance E VG S M U N

c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance

E VG S M U N

d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)

E VG S M U N

2. SCHEDULE/TIMELINESS OF PERFORMANCE:

a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)

E VG S M U N

b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract

E VG S M U N

3. CUSTOMER SATISFACTION:

a) To what extent were the end users satisfied with the project? E VG S M U N

b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes;

responsiveness to administrative reports, businesslike and communication)

E VG S M U N

c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer?

E VG S M U N

d) Overall customer satisfaction E VG S M U N

4. MANAGEMENT/ PERSONNEL/LABOR

a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force?

E VG S M U N

b) Ability to hire, apply, and retain a qualified workforce to this effort E VG S M U N

c) Government Property Control E VG S M U N

d) Knowledge/expertise demonstrated by contractor personnel E VG S M U N

e) Utilization of Small Business concerns E VG S M U N

f) Ability to simultaneously manage multiple projects with multiple disciplines E VG S M U N

g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes

E VG S M U N

h) Effectiveness of overall management (including ability to effectively lead, manage and control the program)

E VG S M U N

5. COST/FINANCIAL MANAGEMENT

a) Ability to meet the terms and conditions within the contractually agreed price(s)?

E VG S M U N

b) Contractor proposed innovative alternative methods/processes that reduced cost,…