AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1. Correct the Price Proposal Schedule to clarify that proposed coefficients are to by entered on Base Year CLINs only (0001AA - 0001AE).
Offerors are not to enter prices for Option Year CLINs.
2. Provide answ ers, for informational purposes only, to questions from prospective offerors.
3. Provide updated Wage Determination.
The proposal due date remains unchanged. Proposals are due by March 4, 2020 at 2:00PM ET.
NOTE: Offeror must acknow ledge receipt of this amendment by the date specified in the proposal (or as amended) by one of the follow ing methods: in the space provided on SF1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS (FAR 15.208)
1. CONTRACT ID CODE PAGE OF PAGES
1 37
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 25-Feb-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS20R0007
X 9B. DATED (SEE ITEM 11)
24-Jan-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
24-Feb-2020
CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 16-300
NEW YORK NY 10278-0090
W912DS 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DS20R0007
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0001
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
BASE YEAR
FFP
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001AA
BASE - Normal working hours
FFP
All work at Watervliet Arsenal performed during normal working hours. ENTER
COEFFICIENT
FOB: Destination
NET AMT
Enter coefficients on SubCLINS 0001AA - 0001AE
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001AB
BASE YEAR - Normal working hours(Secure)
FFP
All work at Watervliet Arsenal performed at secure locations durning normial working hours. ENTER COEFFICIENT FOB: Destination
NET AMT
0001AC
BASE Other than normal hours
FFP
All work at Watervliet Arsenal performed during other than normal working hours.
ENTER COEFFICIENT
0001AD
BASE Other than normal hours (Secure)
FFP
All work at Watervliet Arsenal performed at secure locations durning other than normial working hours. ENTER COEFFICIENT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001AE
BASE Non Pre-Priced Tasks
FFP
All work for Non Pre-Priced tasks. ENTER COEFFICIENT FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
OPTION OPTION YEAR 1
FFP
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0002AA
OPTION OPTION 1 Normal working hours
FFP
All work at Watervliet Arsenal performed during normal working hours.
[Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.] FOB: Destination
NET AMT
Do not enter coefficient here
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0002AB
OPTION OPTION 1 - Normal working hours(Secure)
FFP
All work at Watervliet Arsenal performed at secure locations durning normial working hours. [Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.] FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0002AC
OPTION OPTION 1 Other than normal hours
FFP
All work at Watervliet Arsenal performed during other than normal working hours.
[Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.] FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0002AD
OPTION OPTION 1 Other than normal hours(Secure)
FFP
All work at Watervliet Arsenal performed at secure locations durning other than normial working hours. [Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.] FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0002AE
OPTION OPTION 1 Non Pre-Priced Tasks
FFP
All work for Non Pre-Priced tasks. [Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.] FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
OPTION OPTION YEAR 2
FFP
NET AMT
Do not enter coefficient here
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0003AA
OPTION OPTION 2 Normal working hours
FFP
All work at Watervliet Arsenal performed during normal working hours.
[Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.] FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0003AB
OPTION OPTION 2 Normal working hours(Secure)
FFP
All work at Watervliet Arsenal performed at secure locations durning normial working hours. [Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.] FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0003AC
OPTION OPTION 2 Other than normal hours
FFP
All work at Watervliet Arsenal performed during other than normal working hours.
[Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.] FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0003AD
OPTION OPTION 2 Other than normal hours(Secure)
FFP
All work at Watervliet Arsenal performed at secure locations during other than normal working hours. [Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.] FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0003AE
OPTION OPTION 2 Non Pre-Priced Tasks
FFP
All work for Non Pre-Priced tasks. [Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.] FOB: Destination
NET AMT
Do not enter coefficient here
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
OPTION OPTION YEAR 3
FFP
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0004AA
OPTION OPTION 3 Normal working hours
FFP
All work at Watervliet Arsenal performed during normal working hours.
[Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.] FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0004AB
OPTION OPTION 3 Normal working hours(Secure)
FFP
All work at Watervliet Arsenal performed at secure locations during normal working hours. [Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.] FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0004AC
OPTION OPTION 3 Other than normal hours
FFP
All work at Watervliet Arsenal performed during other than normal working hours.
[Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.] FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0004AD
OPTION OPTION 3 Other than normal hours(Secure)
FFP
All work at Watervliet Arsenal performed at secure locations during other than normal working hours. [Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.] FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0004AE
OPTION OPTION 3 Non Pre-Priced Tasks
FFP
All work for Non Pre-Priced tasks. [Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.] FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
OPTION OPTION YEAR 4
FFP
NET AMT
Do not enter coefficient here
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0005AA
OPTION OPTION 4 Normal working hours
FFP
All work at Watervliet Arsenal performed during normal working hours.
[Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.] FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0005AB
OPTION OPTION 4 Normal working hours(Secure)
FFP
All work at Watervliet Arsenal performed at secure locations during normal working hours. [Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.] FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0005AC
OPTION OPTION 4 Other than normal hours
FFP
All work at Watervliet Arsenal performed during other than normal working hours.
[Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.] FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0005AD
OPTION OPTION 4 Other than normal hours(Secure)
FFP
All work at Watervliet Arsenal performed at secure locations during other than normal working hours. [Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.] FOB: Destination
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0005AE
OPTION OPTION 4 Non Pre-Priced Tasks
FFP
All work for Non Pre-Priced tasks. [Coefficients for the option periods are subject to economic price adjustment from the base year. Do not enter coefficient here.] FOB: Destination
NET AMT
Do not enter coefficient here
Q&A for Solicitation / Request for Proposal
(W912DS20R0007)
19-Feb-2020
The following Government responses to questions from interested vendors are provided for informational purposes only.
Q1. The RFP indicates a bid bond for $600k or 20% of the annual limit of $3M is required. Our surety is asking whether a $3M P&P Bond will be required at award of each base and option period and reduced to actual value at the end of each period. Our understanding is that the bid bond is to ensure that responses are from bondable contractors and that the P&P bonds will only be required on a job order basis. Please clarify.
A1. P&P bonds for the annual limit amount of $3M will be required in accordance with AFARS 5117.9004-2(g), which states:
(g) JOC solicitations and contracts must clearly notify offerors of initial and continuing bonding requirements. The term bonding used in this paragraph includes any relevant alternative payment protection as discussed in FAR 28.102-1. Bonding must be sufficient to cover the stated estimated annual maximum contract value. No JOC contract shall cite the total estimated maximum value of the contract (including option periods) as the estimated annual maximum value, although there may be language in the contract allowing ordering beyond that maximum but less than the estimated value of the total contract with option periods. The estimated annual maximum value will be a reasonable figure based on historical experience and known workload for the coming year. This approach should avoid the prior difficulties associated with adjusting bonding coverage every time a new task order is awarded. Because contractors can now plan their liability for premiums, and because they get unliquidated/unneeded premiums reimbursed by the bonding agent, payment incrementally through the use of the coefficient becomes both logical and reasonable. Contractors must be clearly notified, in the solicitation and contract, of their responsibility for ensuring sufficient bond coverage during the course of the contract. All costs associated with bonding (specifically including bond premiums) shall be included in the coefficient. If the estimated annual maximum value is exceeded, FAR 28.102-2(a) and (b) apply. Since the bond premium is repaid through the coefficient and the coefficient is paid as an indirect cost under progress payment or other normal payment provisions there will be no separate repayment(s) for bond premiums.
Q2. Please clarify the Non Pre-priced (NPP) Contract Line Item (CLIN).
A2. The NPP Line Item is the Contractor’s markup on any items not in the Construction Task Catalog (CTC). It is to establish a markup rate in the contract to reduce negotiation needed on each individual Job Order. The price proposed for the NPP CLIN will be in the same format as the coefficients. For example, if your proposed markup on NPP items is 10%, then enter 1.10 for the NPP CLIN.
"General Decision Number: NY20200002 02/07/2020
Superseded General Decision Number: NY20190002
State: New York
Construction Types: Building, Heavy and Highway
Counties: Albany, Columbia, Fulton, Greene, Montgomery, Rensselaer, Saratoga, Schenectady, Schoharie and Washington Counties in New York.
BUILDING CONSTRUCTION PROJECTS (For all counties except COLUMBIA, FULTON & GREENE) (does not include single family homes and apartments up to a including 4 stories), HEAVY AND
HIGHWAY CONSTRUCTION PROJECTS
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.80 for calendar year 2020 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.80 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2020. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/03/2020 1 02/07/2020
ASBE0040-002 05/01/2019
Rates Fringes
Asbestos/Insulator Worker SCOPE OF WORK: includes application of all insulating materials, protective, coverings, coating and finishing to all types of mechanical systems.....................$ 36.04 21.92
HAZARDOUS MATERIAL HANDLER
Duties limited to preparation wetting;
stripping; removal;
scrapping; vacuuming;
bagging; and disposing of all insulation materials, whether they contain asbestos or not from mechancial systems..........$ 36.04 21.92
BOIL0197-002 01/01/2017
Rates Fringes
BOILERMAKER......................$ 34.54 24.78
BRNY0002-019 07/01/2018
Rates Fringes
BRICKLAYER
BRICKLAYERS, STONE MASONS,
CEMENT MASONS, PLASTERERS,
POINTERS, CAULKERS &
CLEANERS....................$ 36.19 20.48
HEAVY & HIGHWAY
CONSTRUCTION
CEMENT MASONS..............$ 37.23 19.51
MARBLE, TILE & TERRAZZO
FINISHERS...................$ 27.16 16.85
MARBLE, TILE & TERRAZZO
WORKERS.....................$ 34.66 19.58
CARP0279-006 07/01/2019
Rates Fringes
Carpenters:
HEAVY AND HIGHWAY
CONSTRUCTION (COLUMBIA AND
GREENE COUNTIES)
Carpenters, Millwrights, Pile Drivers...............$ 38.09 29.08
CARP0291-005 07/01/2019
Rates Fringes
Carpenters:
SARATOGA COUNTY
BUILDING....................$ 31.52 21.70
WASHINGTON COUNTY
BUILDING....................$ 28.10 21.20
PAID HOLIDAYS: Labor Day, provided the employee has been on the payroll the calender week or any of the holiday week preceding the holiday and works the day after the holiday.
CARP0291-008 07/01/2019
ALBANY, FULTON, MONTGOMERY, RENSSELAER, SCHENECTADY AND
SCHOHARIE COUNTIES
Rates Fringes
Carpenters:
BUILDING CONSTRUCTION
Carpenters & Soft Floor Layers.....................$ 31.68 20.60 Piledriver.................$ 31.68 20.60
HEAVY & HIGHWAY
CONSTRUCTION
Carpenters.................$ 33.02 21.10
CARP0291-010 07/01/2019
Rates Fringes
Carpenters:
CARPENTERS..................$ 33.02 21.10
DIVER TENDERS...............$ 34.02 21.10
DIVERS (Dry Day)............$ 34.02 21.10
DIVERS......................$ 58.02 21.10
PILEDRIVERS.................$ 33.02 21.10
ELEC0236-001 06/01/2019
ALBANY; COLUMBIA; FULTON; GREENE (that portion North of a line following the south limits of the city of Catskill);
MONTGOMERY; RENSSELAER, SARATOGA; SCHENECTADY; SCHOHARIE;
WASHINGTON
ELECTRICIAN......................$ 39.35 28.00
ELEC0363-004 04/01/2019
GREENE COUNTY (Portion of)
Rates Fringes
ELECTRICIAN......................$ 41.00 3%+30.95+a
FOOTNOTE:
a. Paid Holidays: New Year's Day, President's Day, Memorial Day, Fourth of July, Labor Day, Presidential Election Day, Veteran's Day, Thanksgiving Day, Day after Thanksgiving, Christmas Day
ELEC1249-003 05/06/2019
Rates Fringes
ELECTRICIAN (LINE
CONSTRUCTION: LIGHTING AND
TRAFFIC SIGNAL Including any and all Fiber Optic Cable necessary for Traffic Signal
Systems, Traffic Monitoring systems and Road Weather information systems) Flagman.....................$ 27.00 6.75%+24.15 Groundman (Truck Driver)....$ 36.00 6.75%+24.15 Groundman Truck Driver (tractor trailer unit)......$ 36.00 6.75%+24.15 Lineman & Technician........$ 45.00 6.75%+24.15 Mechanic....................$ 36.00 6.75%+24.15
FOOTNOTE:
a. New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, plus President's Day, Good Friday, Decoration Day, Election Day for the President of the United States and Election Day for the Governor of the State of New York, provided the employee works the day before or the day after the holiday.
ELEC1249-004 05/06/2019
Rates Fringes
ELECTRICIAN (Line Construction) Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :
Flagman....................$ 31.23 6.75%+24.15 Groundman digging machine operator...................$ 46.85 6.75%+24.15 Groundman truck driver (tractor trailer unit).....$ 41.64 6.75%+24.15 Groundman Truck driver.....$ 41.64 6.75%+24.15 Lineman and Technician.....$ 52.05 6.75%+24.15 Mechanic...................$ 41.64 6.75%+24.15 Substation:
Cable Splicer..............$ 57.26 6.75%+24.15 Flagman....................$ 31.23 6.75%+24.15 Ground man truck driver....$ 41.64 6.75%+24.15 Groundman digging machine operator...................$ 46.85 6.75%+24.15 Groundman truck driver (tractor trailer unit).....$ 41.64 6.75%+24.15 Lineman & Technician.......$ 52.05 6.75%+24.15 Mechanic...................$ 41.64 6.75%+24.15 Switching structures;
railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation Cable Splicer..............$ 58.71 6.75%+24.15 Flagman....................$ 32.02 6.75%+24.15 Groundman Digging Machine Operator...................$ 48.03 6.75%+24.15 Groundman Truck Driver (tractor-trailer unit).....$ 42.70 6.75%+24.15 Groundman Truck Driver.....$ 42.70 6.75%+24.15 Lineman & Technician.......$ 53.37 6.75%+24.15 Mechanic...................$ 42.70 6.75%+24.15
FOOTNOTE:
a. PAID HOLIDAYS: New Year's Day, Presidents' Day, Memorial Day, Good Friday, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, and Election Day for the President of the United States and Election Day for the Governor of New York State, provided the employee works two days before or two days after the holiday.
ELEC1249-007 05/06/2019
COLUMBIA COUNTY
Rates Fringes
ELECTRICIAN (LIGHTING AND
TRAFFIC SIGNAL INCLUDING ANY
AND ALL FIBER OPTIC CABLE
NECESSARY FOR THE TRAFFIC
SIGNAL SYSTEMS, TRAFFIC
MONITORING SYSTEMS AND ROAD
WEATHER INFORMATION SYSTEMS)
Flagman.....................$ 27.77 6.75%+24.15 Groundman Digging Machine Operator....................$ 41.65 6.75%+24.15 Groundman Truck Driver (Tractor-trailer unit)......$ 37.02 6.75%+24.15 Groundman Truck Driver......$ 37.02 6.75%+24.15 Lineman and Technician......$ 46.28 6.75%+24.15 Mechanic....................$ 37.02 6.75%+24.15
PAID HOLIDAYS:
a. Memorial Day, New Year's Day, President's Day, Good Friday, Decoration Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, and Election Day for the
President of the United States and Election Day for the Governor of New York State, provided the employee works two days before or two days after the holiday.
ELEC1249-008 01/01/2019
Rates Fringes
ELECTRICIAN (Line Construction)
TELEPHONE, CATV
FIBEROPTICS CABLE AND
EQUIPMENT
Cable splicer..............$ 32.78 3%+4.93 Groundman..................$ 16.49 3%+4.93 Installer Repairman- Teledata Lineman/Technician- Equipment Operator.........$ 31.12 3%+4.93 Tree Trimmer................$ 25.79 3%+9.98+a
a. New Year's Day, President's Day, Good Friday, Decoration Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day, Day after Thanksgiving, Christmas Day.
* ELEV0035-001 01/01/2020
ALBANY; COLUMBIA (Towns of Claverack, Hillsdale, Ghent, Stockport, Austerlitz, Canaan, New Lebanon, Chatham, Kinderhook, Styvesant and Greenport); FULTON; GREENE (Towns of Durham, Greenville, New Baltimore, Coxcsackie and Athens);
MONTGOMERY, RENSSELAER, SARATOGA, SCHENECTADY, SCHOHARIE AND
WASHINGTON COUNTIES
Elevator Constructor.............$ 47.51 34.765+a+b
FOOTNOTE:
a.Vacation: 6%/under 5 years based on regular hourly rate for all hours worked. 8%/over 5 years based on regular hourly rate for all hours worked.
b. PAID HOLIDAYS: New Year's Day; Memorial Day; Independence Day; Labor Day; Veterans' Day; Thanksgiving Day; the Friday after Thanksgiving Day; and Christmas Day.
* ELEV0138-004 01/01/2020
COLUMBIA COUNTY (THE TOWNS OF ANCRAM, CLERMONT, COPAKE,
GALLATIN, GERMANTOWN, LIVINGSTON, AND TAGHKANIC); GREEN COUNTY
(THE TOWNS OF HUNTER AND CATSKILL)
ELEVATOR MECHANIC................$ 60.49 34.765+a+b
FOOTNOTE:
a.Vacation: 6%/under 5 years based on regular hourly rate for all hours worked. 8%/over 5 years based on regular hourly rate for all hours worked.
b. PAID HOLIDAYS: New Year's Day; Memorial Day; Independence Day; Labor Day; Veterans' Day; Thanksgiving Day; the Friday after Thanksgiving Day; and Christmas Day.
ENGI0106-001 07/01/2018
HEAVY & HIGHWAY
Rates Fringes
Power equipment operators:
GROUP 1.....................$ 43.47 26.05+a GROUP 2.....................$ 42.56 26.05+a GROUP 3.....................$ 39.99 26.05+a GROUP 4.....................$ 47.47 26.05+a GROUP 5.....................$ 46.47 26.05+a GROUP 6.....................$ 45.47 26.05+a GROUP 7.....................$ 45.08 26.05+a
POWER EQUIPMENT OPERATOR CLASSIFICATIONS (HEAVY & HIGHWAY):
GROUP 1: Asphalt Curb Machine, Self Propelled, Slipform, Automated Concrete Spreader (CMI Type), Automatic Fine Grader, Backhoe (Except Tractor Mounted, Rubber Tired), Backhoe Excavator Full Swing (CAT 212 or similar type), Back Filling Machine, Belt Placer (CMI Type), Blacktop Plant (Automated), Boom truck , Cableway, Caisson Auger, Central Mix Concrete Plant (Automated), Concrete Curb Machine, Self Propelled, Slipform, Concrete Pump, Crane, Cherry Picker, Derricks (steel erection), Dragline, Overhead Crane (Gantry or Straddle type), Pile Driver, Truck Crane, Directional Drilling Machine, Dredge, Dual Drum Paver, Excavator (All Purpose Hydraulically Operated) (Gradall or Similar), Front End Loader ( 4 cu. yd. and Over), Head Tower (Sauerman or Equal), Hoist (Two or Three Drum), Holland Loader, Maintenance Engineer, Mine Hoist, Mucking Machine or Mole Pavement Breaker(SP) Wertgen; PB-4 and similar type, Power Grader, Profiler (over 105 H.P.)
Quad 9, Quarry Master (or equivalent), Scraper, Fireman, Form Tamper, Grout Pump, Gunite Machine, Hammers (Hydraulic self-propelled), Hydra-Spiker, ride-on, Hydraulic Pump (jacking system), Hydro-Blaster (Water), Mulching Machine, Oiler, Parapet Concrete or Pavement, Shovel, Side Boom, Slip Form Paver, Tractor Drawn, BeltType Loader, Truck or Trailer Mounted Log , Chipper (Self Feeder), Tug Operator (Manned Rented Equipment Excluded), Tunnel Shovel
GROUP 2: Asphalt Paver, Backhoe (Tractor Mounted, Rubber Tired), Bituminous Recycler Machine, Bituminous Spreader and Mixer, Blacktop Plant (NonAutomated), Blast or Rotary Drill (Truck or Tractor Mounted), Boring Machine, Cage Hoist, Central Mix Plant (NonAutomated) and All Concrete Batching Plants, Cherry Picker (5 tons capacity and under), Concrete Paver (Over 16S), Crawler Drill, Self-contained, Crusher, Diesel Power Unit, Drill Rigs, Tractor Mounted, Front End Loader (Under 4 cu. yd.), Greaseman/Lubrication Engineer, HiPressure Boiler (15 lbs. and over), Hoist (One Drum), Hydro-Axe, Kolman Plant Loader and Similar Type
Loaders, L.C.M. Work Boat Operator, Locomotive Mixer (for stabilized base selfpropelled), Monorail Machine, Plant Engineer, Profiler (105 H.P. and under), Grinder, Post Hole Digger and Post Driver, Power Broom (towed), Power Heaterman, Power Sweeper, Revinius Widener, Roller (Grade and Fill), Scarifier, ride-on, Shell Winder, Skid steer loader (Bobcat or similar), Span-Saw, ride-on, Steam Cleaner, Pug Mill, Pump Crete Ready Mix Concrete Plant Refrigeration Equipment (for soil stabilization)Road Widener, Roller (all above subgrade), Sea Mule, Self-contained Ride-on Rock Drill, Excluding Air-Track Type Drill, Skidder, Tractor with Dozer and/or Pusher, Trencher.
Tugger Hoist, Vermeer saw (ride on, any size or type), Winch, Winch Cat
GROUP 3: A Frame Winch Hoist on Truck , Articulated Heavy Hauler, Aggregate Plant, Asphalt or Concrete Grooving, Machine (ride on), Ballast Regulator, Ride-on Boiler (used in conjunction with production), Bituminous Heater, self-propelled, Boat (powered), Cement and Bin Operator, Compressors, Dust Collectors, Fork Lift, Generators, Pumps, Welding Machines, Light Plants, Heaters (hands-off equipment), Concrete Pavement Spreader and Finisher, Concrete Paver or Mixer (16S and under), Concrete Saw (self-propelled), Conveyor, Deck Hand, Directional Drill Machine Locator, Drill, (Core), Drill, (Well,) Farm Tractor with accessories, Fine Grade Machine, Tamper, ride-on, Tie Extractor, ride-on, Tie Handler, ride-on, Tie Inserter, ride-on, Tie Spacer, ride-on, Tire Repair, Track Liner, ride-on, Tractor, Tractor (with towed accessories), Vibratory Compactor, Vibro Tamp, Well Point
GROUP 4: Tower Cranes
GROUP 5: Cranes 50 tons and over
GROUP 6: Cranes 49 tons and below
GROUP 7: Master Mechanic
FOOTNOTE:
a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day
ENGI0106-002 07/01/2018
BUILDING
Rates Fringes
Power equipment operators:
GROUP A(1)..................$ 43.79 25.70+a GROUP A.....................$ 43.30 25.70+a 1..........................$ 45.04 25.70+a 2..........................$ 46.04 25.70+a GROUP B.....................$ 42.28 25.70+a GROUP C.....................$ 39.38 25.70+a
Hazardous work - Anytime Operating Engineers are involved with level C or above, $2.50 per hour over regular rate.
a. Paid Holidays: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day.
POWER EQUIPMENT OPERATOR CLASSIFICATIONS (BUILDING):
GROUP A(1): Crane, hydraulic cranes, tower crane, locomotive crane, piledriver, cableway, derricks, whirlies, dragline, boom truck (over 5 tons)
GROUP A(1): Crane Premiums:
1 over 150'- $1.00 2 over 200'- $2.00
GROUP A: Shovel, All Excavators (including rubber tire full swing), gradalls, power road grader, all CMI equipment, front-end rubber tire loader, tractor-mounted drill (quarry master), mucking machine, concrete central mix plant, concrete pump, Belcrete system, automated asphalt concrete plant and tractor road paver, boom truck (5 tons and under), maintenance engineer, self contained crawler, drill-hydraulic rock drill.
GROUP B: Backhoe, (rubber-tired backhoe/loader combination), bulldozer, pushcat, tractor, traxcavator, scraper, LeTourneau grader, form fine grader, road roller, blacktop roller, blacktop spreader, power brooms, sweepers, trenching machine, Barber Green loader, side booms, hydrohammer, concrete spreader, concrete finishing machine, one drum hoist, power hoisting (single drum), hoist - two drum or more, three drum engine, power hoisting (two drum and over), two drum and swinging engine, three drum swinging engine, hod hoist, A-L frame winches, cord and well drillers (one drum), post hole digger, model CHB Vibro-Tamp or similar machine, batch bin and plant operator, dinkey locomotive, skid steer loader, track excavator 5/8 cu. yd. or smaller
GROUP C: Fork lift, high lift, lull, oiler, fireman and heavy- duty greaser, boilers, and steam generators, pump, vibrator, motor mixer, air compressor, dust collector, welding machine, well point, mechanical heater, generators, temporary light plants, concrete pumps, electric submersible pump 4"" and over, murphy type diesel generator, conveyor, elevators, concrete mixer and belcrete power pack (belcrete system), seeding, and mulching machines, pumps
IRON0012-011 07/01/2019
ALBANY; COLUMBIA; FULTON (Albin, Bleecker, Broad, Johnstown, Mayfield, Northampton and Perth); GREENE, MONTGOMERY (Amsterdam, Charleston, Florida, Glen, Mohawk and Root);
RENSSELAER, SARATOGA; SCHENECTADY; SCHOHARIE; and WASHINGTON
COUNTIES:
Ironworkers:
Sheeter, Bucker-up..........$ 31.80 28.59 Sheeter.....................$ 31.80 28.59 Structural, Ornamental, Rodman, Machinery Mover, Rigger, Fence Erector, Reinforcing, Stone Derrickmen..................$ 31.55 28.59
IRON0440-007 01/01/2019
FULTON (Twps. of Caroga, Ephratah, Oppenheim, Stratford);
MONTGOMERY (Twps of Canajoharie, Minden, Palatine, St.
Johnsville):
IRONWORKER
Structural, Ornamental, Rodman, Machinery Mover, Rigger, Fence Erector, Reinforcement, and Stone Derrickman..................$ 28.25 25.94
LABO0017-001 07/01/2019
COLUMBIA COUNTY (Twps of Greenport, Claverack, Clermont, Germantown, Livingston, Hillsdale, Taghkanic, Gallatin, Copake, Ancram, Philmont and the City of Hudson)
LABORER
COLUMBIA COUNTY (Townships of Greenport, Claverack, Clermont, Germantown, Livingston, Hillsdale, Taghkanic, Gallatin, Copake, Ancram, Philmont, and the City of Hudson) (Asbestos, lead, toxic and hazardous waste abatement and any other environmental related work) HEAVY & HIGHWAY GROUP 1:...................$ 38.90 27.15+a GROUP 2:...................$ 43.15 27.15+a GREENE COUNTY (Township of Catskill) HEAVY & HIGHWAY:
GROUP 1:...................$ 34.15 27.15+a GROUP 2:...................$ 38.90 27.15+a GROUP 3:...................$ 43.15 27.15+a GROUP 4:...................$ 48.00 27.15+a
TUNNEL, SHAFT & CAISSON
WORK
GROUP 1....................$ 48.05 29.50+a
For HEAVY & HIGHWAY CLASSIFICATIONS in COLUMBIA COUNTY (Townships of Greenport, Claverack, Clermont, Germantown, Livingston, Hillsdale, Taghkanic, Gallatin, Copake, Ancram, Philmont and the City of Hudson)
HEAVY & HIGHWAY CLASSIFICATIONS
GROUP 1: Asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous material abatement when protective equipment and clothing are not required
GROUP 2: Asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous material abatement when protective clothing and equipment is required
For HEAVY & HIGHWAY CLASSIFICATIONS in GREENE COUNTY (Township of Catskill)
FOOTNOTE:
a. PAID HOLIDAYS: New Years Day, President's Day, Memorial Day, Independence Day, Lincoln's Birthday, Labor Day, Election Day, Veterans Day, Thanksgiving Day, Christmas Day, provided the employee is an employee of the company prior to the scheduled holiday and reports to work the first day following the holiday unless prevented from doing so for legitimate reasons.
GROUP 1: Flagperson, gateperson
GROUP 2: General laborers, chuck tender, handling and distributing drinking water, distributing all tools and supplies of laborers, nipper, powder carrier, magazine tender, warehouse laborers, concrete man, vibrator man, mason tender, mortar man, spraying, brushing and covering of concrete for curing and preservative purposes, traffic striper, scaffold builder, concrete curb and sidewalk form setter; permanent traffic striping and reflective devices, placing and maintenance of all flares, cones, lights, signs, barricades, traffic patterns, and all temporary reflective type materials for traffic control, custodial work, traffic directors, temporary heat or light tenders, tool room, dewatering pump men, pitman, dumpmen, snow removal and firewatch, asphalt man, joint setter, signal person, pipelayer, pipe lining and relining, wellpoints, conduit and duct layer, wire puller, rip rap and dry stone layer, steel rod carrier, core drill, rock splitter, Hilti gun air or electric, jackhammer, bush hammer, pavement breaker, chipping hammer, wagon drill, air track, jib rig, joy drill, gunite and sand blasting, coal passer and other machine operators, power tool operator, sprayer and nozzle man on mulching and seeding machine, all guard rail and fence, all seeding and sod laying, all landscape work, grade checker, all bridge work, walk behind self-propelled power saw, grinder, groover or similar type machine, walk behind tamper and roller of all types, salvage, stripping, wrecking and dismantling laborer (including barman, cutting torch and burner man), sheeting and shoring coming under laborers jurisdiction, bit grinder, operator of form pin puller and drivers, sandblasting, joint and jet sealer, filling and wiring baskets for gabion walls, permanent sign man, median barrier, sta-wall or similar type product, chain saw operator, railroad track laborer, waterproofer, pre-stressed and pre-cast concrete brick, block and stone pavers, power tools used to perform work usually done by laborers, power buggy and pumpcrete operator, fireproof, plaster and caustic pump, asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous materials abatement when protective clothing and equipment is not required, power brush cutter, retention liners, artificial turf, retaining walls, walk behind surface planer, welding related to laborers work, remote controlled equipment normally operated by laborers, all technician work including but not limited to stitching, seaming, heat welding, fireproof sprayer, mortar mixer, concrete finisher, form setter for concrete curbs and flatwork.
Gunite nozzle man, stone cutters, granite stone layer, manhole, catch basin or inlet installing, laser men.
Ground man on milling machine
GROUP 3 Ingersoll Rand heavy duty crawler-master HCMZ, any drill using a 4"" or larger bit, asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous material abatement when protective clothing and equipment is required, all working foremen including grade, pipe concrete, clearing, blacktop, drill, paving and blaster etc., Hydraulic drill or similar, forklift for masonry only, Blaster and asphalt screedman
GROUP 4: Asbestos, toxic, lead or hazardous material abatement foreman
For TUNNEL, SHAFT & CAISSON WORK CLASSIFICATIONS
a. PAID HOLIDAYS: New Years Day, President's Day, Memorial Day, Independence Day, Labor Day, Election Day, Veterans Day, Thanksgiving Day, Christmas Day
GROUP 1: Laborer, Pit and Dumpman, Chuck Tender, Brakeman and Powderman;
Miner and all machine men, Safety Miner, all shaft work, caisson work, drilling, blow pipe, all air tools, tugger, scaling, nipper gunniting from pot to nozzle, bit grinder, signal man (top and bottom), shield driven tunnel, mixed face and soft ground liner plate tunnel in free air
LABO0035-001 07/01/2017
FULTON (TWPS OF CAROGA, EPHRATA, OPPENHEIM, AND STRAFORD);
MONTGOMERY (TWPS OF CANAJOHARIE, MINDEN AND PALATINE, ROOT AND
ST. JOHNSVILLE)
Laborers Building Construction Asbestos Removal............$ 24.00 20.64+a Blasters, Form Setters, MotorBuggy Operator (Rider Type)......................$ 23.00 20.64+a Hazardous Waste Removal Hazardous waste removal includes wetting, stripping, removal, scrapping, vaccuuming, bagging and disposing of all insulation materials, whether they contain asbestos or not, from mechanical systems.........$ 24.00 20.64+a
HEAVY & HIGHWAY:
GROUP 1:...................$ 28.05 23.74+a GROUP 2:...................$ 28.25 23.74+a GROUP 3:...................$ 28.45 23.74+a GROUP 4:...................$ 28.65 23.74+a Laborers....................$ 22.50 20.64+a Pipelayers, Motor Mixers, Motor Buggy Operator (Walk Behind) Power Lift (Walk Behind)...............$ 22.65 20.64+a Wagon Drill Operator........$ 22.90 20.64+a
FOOTNOTE:
a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day.
GROUP 1: Common Laborers, Flagman, Outboard and Hand boats
GROUP 2: Bull Float, Chain Saw, Concrete aggregate bin, Concrete Bootman, Gin Buggy, Hand or Machine Vibrator, Jackhammer, Mason Tender, Mortar Mixer, Pavement Breaker, Handlers of all steel mesh, Small generators for laborer's tools, Installation of bridge drainage, Pipelayers, Vibrator type rollers, Tamper, Drill doctor, Tail or Screw Operator on asphalt paver, Water pump operator (1 1/2"" and single diaphragm), Nozzle (asphalt, gunnite, seeding and sand blasting), Laborers on chain link fence erection, Rock splitter and power unit, Pusher type concrete saw and all other gas, electric, oil, and air tool operators, Wrecking laborers
GROUP 3: All rock or drilling machine operators (except quarry master and similar type), Acetylene torch operators, and Asphalt paver, Powderman
GROUP 4: Blasterers, Form setters, Stone or Granite Curb setters
LABO0157-001 07/01/2017
FULTON (Twps. of Bleeker, Mayfield, Northhampton, Johnstown, Broadalbin and Perth); MONTGOMERY (Twps. of Mohawk, Glen, Charleston, Amsterdam, and Florida); SARATOGA (Twps. of Day, Hadley, Edinburg, Corinth, Moreau, South Glens Falls, Providence, Greenfield, Wilton, Northcumberland, Galway, Milton, Saratoga Springs, Charlton, Ballston, Malta and Clifton Park); SCHENECTADY and SCHOHARIE COUNTIES.
LABORER
BUILDING:
GROUP 1....................$ 28.74 20.14+a
GROUP 2....................$ 30.09 20.14+a
HEAVY & HIGHWAY:
GROUP 1:...................$ 30.55 21.29+a GROUP 2:...................$ 30.75 21.29+a GROUP 3:...................$ 30.95 21.29+a GROUP 4:...................$ 31.15 21.29+a GROUP 5:...................$ 32.55 21.29+a
LABORER CLASSIFICATIONS
Group 1: Common Laborers
Group 2: Asbestos and Toxic Materials
Commercial projects valued at $800,000 or less and/or industrial projects valued at $100,000 or less, excluding demolition work (the complete razing of structures) 75% of the basic wage scale with full benefits will apply
FOOTNOTE:
a. PAID HOLIDAYS: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day
LABORER CLASSIFICATIONS
GROUP 1: Common laborers, flagman, outboard & hand boats
GROUP 2: Bull float, chain saw, concrete aggregate bin, concrete bootman, gin buggy, hand or machine vibrator, jackhammer, mason tender, mortar mixer, pavement breaker, handlers of all steel mesh, small generators for laborers' tools, installation of bridge drainage, pipelayers, vibrator type rollers, tamper, drill doctor, tail or screw operator on asphalt paver, water pump operator (1 1/2"") and single diaphragm), nozzle (asphalt, gunnite, seeding, and sand blasting), laborers on chain fence erection, rock splitter and power unit, pusher type concrete saw and all other gas, electric, oil, and air tool operators, wrecking laborers
GROUP 3: All rock drilling machine operators (except quarry master and similar type), acetylene torch operator, and asphalt paver, powderman
GROUP 4: Blasterers, form setters, stone or granite curb setters
GROUP 5: Hazardous waste removal
LABO0190-001 07/01/2019
ALBANY; GREEN; RENSSELAER COUNTY, WASHINGTON COUNTY, SARATOGA
COUNTY (Townships of Stillwater, Halfmoon, Saratoga)
Laborers:
BUILDING:
GROUP 1....................$ 28.51 23.17
GROUP 2....................$ 29.86 23.17
LABORERS CLASSIFICATIONS
GROUP 1: Common Laborers
GROUP 2: Hazardous waste removal Commercial projects valued at $800,000 or less and/or industrial projects valued at $100,000 or less excluding demolition work, (complete razing of structures) will receive 75% of basic wage scale with full fringes will apply
LABO0190-002 07/01/2018
ALBANY; RENSSELAER; COLUMBIA (Twps. of Stuyvesant, Stockport, Kinderhook, New Lebanon, Cannan, Ghent, Chatham, Austerlitz).
GREENE (except Catskill Township). WASHINGTON COUNTY. SARATAGO COUNTY (Townships of Stillwater, Halfmoon Saratoga)
HEAVY & HIGHWAY:
GROUP 1:...................$ 30.94 22.70
GROUP 2:...................$ 31.14 22.70
GROUP 3:...................$ 31.34 22.70
GROUP 4:...................$ 31.54 22.70
GROUP 5:...................$ 32.94 22.70
FOOTNOTE:
PAID HOLIDAYS: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day.
LABORERS CLASSIFICATIONS
GROUP 1: Common laborers, flagmen, outboard and hand boats
GROUP 2: Bull float, chain saw, concrete aggregated bin, concrete bootman, gin buggy, hand or machine vibrator, jackhammer, mason tender, mortar mixer, pavement breaker, handlers of all steel mesh, small generators for laborers' tools, installation of bridge drainage, pipelayers, vibrator type rollers, tampers, drill doctor, Tail or screw operator on asphalt paver, Water pump operator (1 1/2"" and single diaphragm), Nozzle (asphalt, gunnite, seeding, and sand blasting) Laborers on chain link fence erection, rock splitter and power unit, pusher type concrete saw and all other gas, electric, oil, air tool operators, and wrecking laborers
GROUP 3: All rock air drilling machine operators (except quarry master and similar type), acetylene torch operators, and asphalt paver, powderman
GROUP 4: Blasterers, form setters, stone or granite curb setters
GROUP 5: Hazardous waste removal
LABO0235-006 05/01/2018
COLUMBIA (Twps. of Greenport, Claverack, Hillsdale, Livingston, Germantown, Taghkanic, Copake, Clermont, Gallatin, Ancram):
HEAVY & HIGHWAY
GROUP 1....................$ 24.40 29.75+a GROUP 2....................$ 28.16 29.75+a GROUP 3....................$ 29.16 29.75+a
LABORERS CLASSIFICATIONS (HEAVY & HIGHWAY)
GROUP 1: Flagperson; Placing and maintenance of all flares, cones, lights, signs, barricades; traffic control custodial work; traffic directors; temporary heat or light tenders;
tool rooms
GROUP 2: General Laborers, Dumpman, Pitman, Concrete man;
Signal man; Pipelayers; Rip rap; Dry stone layer; Jack hammer; Powderman; Highscalers power buggy operator; Steel rod carrier; Vibratory operator; other machine operator;
wrecking; Vibrator operator-compactor; Gunite and sandblasting; Water pump 2"" or under; Nipper; Chucker;
Asphalt Workers
GROUP 3: Asphalt raker; Asphalt Screedman; Drillers (all);
Laser Beam Operator; Form Setter/Aligners; Blasters
FOOTNOTE:
a. PAID HOLIDAYS: New Years Day, Presidents Day, Good Friday, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Day, November Election Day, Thanksgiving Day, and Christmas Day
PAIN0009-013 05/01/2019
Rates Fringes
GLAZIER..........................$ 29.15 22.03
PAIN0155-002 05/01/2018
COLUMBIA AND GREENE COUNTIES
Rates Fringes
Painters:
Drywall Finisher............$ 32.99 22.76 Lead Abatement Work.........$ 32.99 22.76 Painter/Paperhanger.........$ 32.99 22.76 Spray Rate..................$ 33.99 22.76
PAIN0201-001 05/01/2019
Painters:
Lead Abatement Workers, Structural Steel Zone 1.....................$ 30.09 16.65 Zone 2.....................$ 30.09 16.65 Painters, Drywall Finishers, Spray Zone 1.....................$ 29.09 16.65 Zone 2.....................$ 29.09 16.65
Zone #1 Entire counties of ALBANY, FULTON, MONTGOMERY, RENNSELAER, SCHOHARIE, SCHENECTADY AND SARATOGA
ZONE #2 All of WASHINGTON County
PAIN0806-002 10/01/2018
ALBANY, COLUMBIA, FULTON, GREENE, MONTGOMERY, RENNSELAER,
SCHOHARIE, SCHENECTADY, SARATOGA AND WASHINGTON
Painters:
Structural Steel and Bridge.$ 49.50 41.88
PLUM0007-001 05/01/2018
ALBANY; COLUMBIA; FULTON; GREENE; MONTGOMERY; RENSSELAER;
SCHENECTADY; SARATOGA (Towns of Charlton, Clifton Park, Galway, Halfmoon, Milton, Stillwater and Waterford)
PLUMBER/PIPEFITTER...............$ 41.59 25.94
PLUM0112-019 05/01/2018
Townships of Canajoharie and Minden
Rates Fringes
PLUMBER (Including Steamfitting) Northern Zone...............$ 35.50 27.55
PLUM0773-002 05/01/2019
SARATOGA (Remainder of County); WASHINGTON COUNTY:
Rates Fringes
PLUMBER/PIPEFITTER...............$ 37.50 30.98
ROOF0203-003 06/01/2019
SCHOHARIE COUNTY:
ROOFER...........................$ 26.30 16.16
ROOF0241-001 07/01/2018
Rates Fringes
ROOFER...........................$ 30.05 19.27
SFNY0669-001 04/01/2019
Rates Fringes
SPRINKLER FITTER.................$ 36.70 24.94
SHEE0083-001 06/01/2019
Rates Fringes
Sheet metal worker...............$ 33.73 33.04+a
FOOTNOTE:
a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day. If any of these holidays fall on a Saturday or Sunday, either the preceding Friday or following Monday will be observed as the holiday.
TEAM0294-002 07/01/2019
BUILDING CONSTRUCTION
Rates Fringes
Truck drivers:
GROUP 1.....................$ 27.67 24.28+a GROUP 2.....................$ 27.97 24.28+a
FOOTNOTES:
a. One week vacation after 1 year; 2 weeks vacation after 5 years.
TRUCK DRIVERS BUILDING CLASSIFICATIONS
GROUP 1: Straight, winch, transit mix on job site, road oilers, dump, panel, pick-up, water and fuel trucks on site (including nozzle)
GROUP 2: Euclid or similar equipment, lowboy or lowboy trailers
TEAM0294-003 07/01/2019
Rates Fringes
Truck drivers:
HEAVY & HIGHWAY
GROUP 1....................$ 30.34 25.88+a GROUP 2....................$ 30.40 25.88+a GROUP 3....................$ 30.49 25.88+a
GROUP 4....................$ 30.60 25.88+a GROUP 5....................$ 30.76 25.88+a
TRUCK DRIVERS CLASSIFICATIONS (HEAVY & HIGHWAY)
GROUP 1: Pick-ups, panel trucks, flatboy material trucks (straight jobs), single axle dump trucks, dumpsters, receivers, greasers, truck tireman
GROUP 2: Tandems, batch trucks, mechanics
GROUP 3: Semi-trailers, low-boy trucks, asphalt distributor trucks, agitator, mixer trucks and dumpcrete type vehicles, truck mechanic, fuel truck
GROUP 4: Specialized earth moving equipment - euclid type or similar off-highway equipment, where not self-loaded, straddle (ross) carrier, self-contained concrete unit
GROUP 5: Off-highway tandem back dump, twin engine equipment and double hitched equipment where not self-loaded
FOOTNOTE:
a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, provided the employee works the day before and the day after the holiday.
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .