DRAFT_CEAC_100 Specs_Volume 4 of 4_Edited_20200511.pdf

PDF 5 MB Posted

Attached to
Cyber Engineering and Academic Center, United States Military Academy, West Point, NY
Solicitation number
W912DS19R0019
Issued by

About this file

This pre-solicitation notice describes a firm fixed-price construction contract to be awarded through a Request for Proposal process. The project scope involves construction of a new 136,000 square foot Cyber and Engineering Academic Center building on the campus of the United States Military Academy at West Point, along with an underground parking structure for 450 vehicles and associated site work. The period of performance is approximately 1461 calendar days. Plans and specifications will be posted on beta.SAM.gov on or about June 8, 2020, with proposals due approximately 45 days later. The procurement method will be Best Value Trade-Off and proposals are to be submitted to the U.S. Army Corps of Engineers in New York. The estimated value of construction is between $100-250 million. Interested offerors must register with the System for Award Management to access solicitation documents on beta.SAM.gov.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Army Corps of Engineers New York District

Section 26 00 00.00 20 Basic Electrical Materials and Methods through

Section 41 22 13.14 Bridge Cranes, Overhead Electric, Top Running

Contract #: W912-DS-17-D0007 Task Order #: W912DS-18-F-0016

SPECIFICATIONS

Cyber & Engineering Academic Center United States Military Academy West Point, NY

May 11, 2020

100% Submission

Volume 4 of 4 jyost Rectangle

Cyber & Engineering Center and Parking Structure August 14, 2019 West Point Military Academy, West Point, NY 100% Submission

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 75 95 ROOF SYSTEM 20-YEAR DIAGNOSTICS / PERFORMANCE WARRANTY

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 14 00 WORK RESTRICTIONS

01 22 00.00 10 PRICE AND PAYMENT PROCEDURES

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 PROJECT SCHEDULE

01 32 33 PHOTOGRAPHIC DOCUMENTATION

01 33 00 SUBMITTAL PROCEDURES

01 33 29 SUSTAINABILITY REPORTING

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 35 91 HISTORIC TREATMENT PROCEDURES

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 QUALITY CONTROL

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 45 20.00 18 TESTING FOR MECHANICAL AND ELECTRICAL SYSTEMS

01 45 35 SPECIAL INSPECTIONS

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 58 00 PROJECT IDENTIFICATION

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

01 78 00 CLOSEOUT SUBMITTALS (WEST POINT)

01 78 23 OPERATION AND MAINTENANCE DATA

01 78 24.00 10 FACILITY DATA REQUIREMENTS

01 91 00.15 TOTAL BUILDING COMMISSIONING

01 91 00.20 CRANE COMMISSIONING

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION

02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS

02 82 13.00 10 ASBESTOS ABATEMENT

02 82 16.00 20 ENGINEERING CONTROL OF ASBESTOS CONTAINING MATERIALS

02 82 33.13 20 REMOVAL/CONTROL AND DISPOSAL OF PAINT WITH LEAD

02 83 13.00 20 LEAD IN CONSTRUCTION

DIVISION 03 - CONCRETE

03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING

03 15 00.00 10 CONCRETE ACCESSORIES

03 20 00.00 10 CONCRETE REINFORCING

03 23 00 STRESSED TENDON REINFORCING

03 30 00.00 10 CAST-IN-PLACE CONCRETE

03 35 00.00 10 CONCRETE FINISHING

03 39 00.00 10 CONCRETE CURING

03 42 13.00 10 PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE

PROJECT TABLE OF CONTENTS Page 1

CONSTRUCTION

03 45 00 PRECAST ARCHITECTURAL CONCRETE

DI VI SI ON 04 - MASONRY

04 20 00 UNIT MASONRY

DI VI SI ON 05 - METALS

05 05 23.13 10 ULTRASONIC INSPECTION OF WELDMENTS

05 12 00 STRUCTURAL STEEL

05 21 00 STEEL JOIST FRAMING

05 30 00 STEEL DECKS

05 40 00 COLD-FORMED METAL FRAMING

05 43 00 METAL STRUT FRAMING AND ALUMINUM T-SLOT FRAMING

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 51 00 METAL STAIRS

05 51 33 METAL LADDERS

05 52 00 METAL RAILINGS

05 72 00 DECORATIVE METAL SPECIALTIES

05 72 11 ARCHITECTURAL ORNAMENTAL GLASS RAILINGS

DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES

06 10 00 ROUGH CARPENTRY

06 20 00 FINISH CARPENTRY

06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS

06 61 16 SOLID SURFACING FABRICATIONS

DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON

07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS

07 13 53 ELASTOMERIC SHEET WATERPROOFING

07 21 13 BOARD AND BLOCK INSULATION

07 21 16 MINERAL FIBER BLANKET INSULATION

07 21 23 ACOUSTICAL SPRAY CELLULOSE

07 22 00 ROOF AND DECK INSULATION

07 27 10.00 10 BUILDING AIR BARRIER SYSTEM

07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS

07 42 63 FABRICATED WALL PANEL ASSEMBLIES

07 52 00 MODIFIED BITUMINOUS MEMBRANE ROOFING

07 60 00 FLASHING AND SHEET METAL

07 81 00 SPRAY-APPLIED FIREPROOFING

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DI VI SI ON 08 - OPENI NGS

08 11 13 STEEL DOORS AND FRAMES

08 11 16 ALUMINUM DOORS AND FRAMES

08 13 76 BI-FOLDING METAL DOORS

08 14 00 WOOD DOORS

08 31 00 ACCESS DOORS AND PANELS

08 33 13 COILING COUNTER DOORS

08 33 23 OVERHEAD COILING DOORS

08 34 73 SOUND CONTROL DOOR ASSEMBLIES

08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

08 44 00 CURTAIN WALL AND GLAZED ASSEMBLIES

08 51 13 ACOUSTICAL ALUMINUM WINDOWS

PROJECT TABLE OF CONTENTS Page 2

08 51 23 STEEL WINDOWS

08 60 45 SKYLIGHTS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

08 91 00 METAL WALL LOUVERS

DI VI SI ON 09 - FI NI SHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 GYPSUM BOARD

09 30 10 CERAMIC, QUARRY, AND GLASS TILING

09 51 00 ACOUSTICAL CEILINGS

09 62 38 STATIC-CONTROL FLOORING

09 65 00 RESILIENT FLOORING

09 66 23 RESINOUS MATRIX TERRAZZO FLOORING

09 67 23.14 CHEMICAL RESISTANT RESINOUS FLOORING

09 68 00 CARPETING

09 69 13 RIGID GRID ACCESS FLOORING

09 84 20 ACOUSTICAL WALL PANELS

09 90 00 PAINTS AND COATINGS

09 96 00 HIGH-PERFORMANCE COATINGS

DI VI SI ON 10 - SPECI ALTI ES

10 11 00 VISUAL DISPLAY UNITS

10 14 00.10 EXTERIOR SIGNAGE

10 14 00.20 INTERIOR SIGNAGE

10 21 13 TOILET COMPARTMENTS

10 22 39 FOLDING PANEL PARTITIONS (VERTICALLY RETRACTABLE

ACOUSTICAL WALLS)

10 22 43 SLIDING PARTITIONS

10 26 00 WALL AND DOOR PROTECTION

10 28 13 TOILET ACCESSORIES

10 44 16 FIRE EXTINGUISHERS

10 52 00 AUTOMATIC FIRE PROTECTIVE SMOKE CURTAINS

DI VI SI ON 11 - EQUI PMENT

11 11 37 ELECTRIC VEHICLE SUPPLY EQUIPMENT

11 12 00 PARKING CONTROL EQUIPMENT

11 13 19.13 LOADING DOCK LEVELERS

11 53 00 LABORATORY EQUIPMENT AND FUMEHOODS

DI VI SI ON 12 - FURNI SHI NGS

12 22 00 CURTAINS AND DRAPES

12 24 13 ROLLER WINDOW SHADES

12 31 00 MANUFACTURED METAL CASEWORK

12 36 00 COUNTERTOPS

12 48 13 ENTRANCE FLOOR MATS AND FRAMES

12 93 00 SITE FURNISHINGS

DI VI SI ON 13 - SPECI AL CONSTRUCTI ON

13 21 48 ACOUSTIC ISOLATION CONSTRUCTION

DI VI SI ON 14 - CONVEYI NG EQUI PMENT

14 21 23 ELECTRIC TRACTION PASSENGER ELEVATORS

PROJECT TABLE OF CONTENTS Page 3

14 24 13 HYDRAULIC FREIGHT ELEVATORS

14 24 23 HYDRAULIC PASSENGER ELEVATORS

DI VI SI ON 21 - FI RE SUPPRESSI ON

21 12 00 STANDPIPE SYSTEMS

21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

21 13 17.00 10 DRY PIPE SPRINKLER SYSTEM, FIRE PROTECTION

21 13 18.00 10 PREACTION AND DELUGE SPRINKLER SYSTEMS, FIRE PROTECTION

21 22 00.00 40 CLEAN AGENT FIRE EXTINGUISHING SYSTEMS

21 30 00 FIRE PUMPS

DI VI SI ON 22 - PLUMBI NG

22 05 48.00 20 MECHANICAL SOUND, VIBRATION, AND SEISMIC CONTROL

22 07 19.00 40 PLUMBING PIPING INSULATION

22 14 29.00 40 SUMP PUMPS

22 15 09.00 40 GENERAL SERVICE COMPRESSED-AIR SYSTEMS CLEANING PROCEDURES

22 31 00 WATER SOFTENERS, CATION-EXCHANGE (SODIUM CYCLE)

DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND

EQUIPMENT

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

23 09 23.01 LONWORKS DIRECT DIGITAL CONTROL FOR HVAC AND OTHER

BUILDING CONTROL SYSTEMS

23 11 25 FACILITY GAS PIPING

23 21 23 HYDRONIC PUMPS

23 25 00 CHEMICAL TREATMENT OF WATER FOR MECHANICAL SYSTEMS

23 52 00 HEATING BOILERS

23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE

23 64 26 CHILLED AND CONDENSER WATER PIPING SYSTEMS

23 65 00 COOLING TOWERS

23 81 00.00 20 UNITARY AIR CONDITIONING EQUIPMENT

23 81 23.00 20 COMPUTER ROOM AIR CONDITIONING UNITS

23 83 16 RADIANT-HEATING HYDRONIC PIPING

DI VI SI ON 25 - I NTEGRATED AUTOMATI ON

25 05 11 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS

25 10 10 UTILITY MONITORING AND CONTROL SYSTEM (UMCS) FRONT END

AND INTEGRATION

DI VI SI ON 26 - ELECTRI CAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 08 00 APPARATUS INSPECTION AND TESTING

26 09 13 POWER MONITORING SYSTEM

26 09 43 DIGITAL-NETWORK LIGHTING CONTROLS

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 24 13 SWITCHBOARDS

26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION

26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS

26 32 15.00 10 DIESEL-GENERATOR SET STATIONARY 100-2500 KW, WITH

PROJECT TABLE OF CONTENTS Page 4

AUXILIARIES

26 32 33.00 10 UNINTERRUPTIBLE POWER SUPPLY (UPS) SYSTEM ABOVE 15 KVA

CAPACITY

26 36 00.00 10 AUTOMATIC TRANSFER SWITCHES

26 41 00 LIGHTNING PROTECTION SYSTEM

26 51 00 INTERIOR LIGHTING

26 56 00 EXTERIOR LIGHTING

DI VI SI ON 27 - COMMUNI CATI ONS

27 05 14.00 10 DISTRIBUTED ANTENNA SYSTEM (DAS)

27 05 28.36 40 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

27 51 16 PUBLIC ADDRESS SYSTEMS

DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM

DI VI SI ON 31 - EARTHWORK

31 00 00 EARTHWORK

31 05 19 GEOTEXTILE

31 09 13 MONITORING DURING CONSTRUCTION

31 11 00 CLEARING AND GRUBBING

31 21 13 RADON MITIGATION

31 31 16.13 CHEMICAL TERMITE CONTROL

31 31 16.19 TERMITE CONTROL BARRIERS

31 32 11 SOIL SURFACE EROSION CONTROL

31 62 20.50 MICROPILES

31 68 13 SOIL AND ROCK ANCHORS

DI VI SI ON 32 - EXTERI OR I MPROVEMENTS

32 05 33 LANDSCAPE ESTABLISHMENT

32 11 23 AGGREGATE BASE COURSES

32 11 23.23 BASE COURSE DRAINAGE LAYERS

32 12 13 BITUMINOUS TACK AND PRIME COATS

32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS

32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS

32 16 15 CONCRETE BLOCK PAVEMENTS

32 17 23 PAVEMENT MARKINGS

32 31 13 CHAIN LINK FENCES AND GATES

32 32 23 SEGMENTAL CONCRETE BLOCK RETAINING WALL

32 92 19 SEEDING

32 92 23 SODDING

32 93 00 EXTERIOR PLANTS

DI VI SI ON 33 - UTI LI TI ES

33 01 30.16 TV INSPECTION OF SEWER PIPELINES

33 01 30.72 RELINING SEWERS

33 05 23 TRENCHLESS UTILITY INSTALLATION

33 30 00 SANITARY SEWERAGE

33 40 00 STORM DRAINAGE UTILITIES

33 51 15 NATURAL-GAS / LIQUID PETROLEUM GAS DISTRIBUTION

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

PROJECT TABLE OF CONTENTS Page 5

DI VI SI ON 34 - TRANSPORTATI ON

34 71 13.16 BARRIER CABLE SYSTEM

DI VI SI ON 41 - MATERI AL PROCESSI NG AND HANDLI NG EQUI PMENT

41 22 13.14 BRIDGE CRANES, OVERHEAD ELECTRIC, TOP RUNNING

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 6

SECTION 26 00 00.00 20

BASIC ELECTRICAL MATERIALS AND METHODS

07/06

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D709 (2017) Standard Specification for Laminated Thermosetting Materials

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

IEEE 100 (2000; Archived) The Authoritative Dictionary of IEEE Standards Terms

IEEE C2 (2017; Errata 1-2 2017; INT 1 2017) National Electrical Safety Code

IEEE C57.12.28 (2014) Standard for Pad-Mounted Equipment

- Enclosure Integrity

IEEE C57.12.29 (2014) Standard for Pad-Mounted Equipment

- Enclosure Integrity for Coastal Environments

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

NEMA 250 (2014) Enclosures for Electrical Equipment (1000 Volts Maximum)

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2;

TIA 17-3; TIA 17-4; TIA 17-5; TIA 17-6;

TIA 17-7; TIA 17-8; TIA 17-9; TIA 17-10;

TIA 17-11; TIA 17-12; TIA 17-13; TIA

17-14) National Electrical Code

U.S. DEPARTMENT OF DEFENSE (DOD)

UFC 3-501-01 Electrical Engineering

UFC 3-520-01 Interior Electrical Systems

UFC 3-530-01 Interior and Exterior Lighting Systems

UFC 3-550-01 Exterior Power Distribution

UFC 3-560-01 Operations and Maintenance: Electrical Safety

SECTION 26 00 00.00 20 Page 1

UFC 3-575-01 Lightning and Static Electricity Protection Systems

UFC 3-580-01 Telecommunications Interior Infrastructure Planning and Design

1.2 ADDITIONAL REFERENCES

The latest edition of the publications listed below shall be considered part of this specification. The US Army Corps of Engineers New York District Engineering Planning Standards Unified Facilities Criteria:

UFC 3-501-01 Electrical Engineering; UFC 3-520-01 Interior Electrical Systems; UFC 3-530-01 Interior and Exterior Lighting Systems;

UFC 3-550-01 Exterior Power Distribution; UFC 3-560-01 Operation and Maintenance: Electrical Safety; UFC 3-575-01 Lightning and Static Electricity Protection Systems; UFC 3-580-01 Telecommunications Interior Infrastructure Planning and Design.

1.3 RELATED REQUIREMENTS

This section applies to certain sections of Division 11, EQUIPMENT, and Division 14, CONVEYING EQUIPMENT, Divisions 22 and 23, PLUMBING and HEATING VENTILATING AND AIR CONDITIONING. This section applies to all sections of Division 26 and 33, ELECTRICAL and UTILITIES, of this project specification unless specified otherwise in the individual sections. This section has been incorporated into, and thus, does not apply to, and is not referenced in the following sections.

Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM Section 26 24 13 SWITCHBOARDS Section 26 51 00 INTERIOR LIGHTING Section 26 56 00 EXTERIOR LIGHTING Section 33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

1.4 DEFINITIONS

a. Unless otherwise specified or indicated, electrical and electronics terms used in these specifications, and on the drawings, shall be as defined in IEEE 100 .

b. The technical sections referred to herein are those specification sections that describe products, installation procedures, and equipment operations and that refer to this section for detailed description of submittal types.

c. The technical paragraphs referred to herein are those paragraphs in PART 2 - PRODUCTS and PART 3 - EXECUTION of the technical sections that describe products, systems, installation procedures, equipment, and test methods.

1.5 ELECTRICAL CHARACTERISTICS

Electrical characteristics for this project shall be 13.8 kV primary, three phase, three wire, 60 Hz, and 480/277 volts secondary, three phase, four wire. Final connections to the power distribution system at the existing manhole shall be made by the Contractor as directed by the Contracting Officer .

SECTION 26 00 00.00 20 Page 2

1.6 ADDITIONAL SUBMITTALS INFORMATION

Submittals required in other sections that refer to this section must conform to the following additional requirements as applicable.

1.6.1 Shop Drawings (SD-02)

Include wiring diagrams and installation details of equipment indicating proposed location, layout and arrangement, control panels, accessories, piping, ductwork, and other items that must be shown to ensure a coordinated installation. Wiring diagrams shall identify circuit terminals and indicate the internal wiring for each item of equipment and the interconnection between each item of equipment. Drawings shall indicate adequate clearance for operation, maintenance, and replacement of operating equipment devices.

1.6.2 Product Data (SD-03)

Submittal shall include performance and characteristic curves.

1.7 QUALITY ASSURANCE

1.7.1 Regulatory Requirements

In each of the publications referred to herein, consider the advisory provisions to be mandatory, as though the word, "shall" had been substituted for "should" wherever it appears. Interpret references in these publications to the "authority having jurisdiction," or words of similar meaning, to mean the Contracting Officer. Equipment, materials, installation, and workmanship shall be in accordance with the mandatory and advisory provisions of NFPA 70 unless more stringent requirements are specified or indicated.

1.7.2 Standard Products

Provide materials and equipment that are products of manufacturers regularly engaged in the production of such products which are of equal material, design and workmanship. Products shall have been in satisfactory commercial or industrial use for 2 years prior to bid opening. The 2-year period shall include applications of equipment and materials under similar circumstances and of similar size. The product shall have been on sale on the commercial market through advertisements, manufacturers' catalogs, or brochures during the 2-year period. Where two or more items of the same class of equipment are required, these items shall be products of a single manufacturer; however, the component parts of the item need not be the products of the same manufacturer unless stated in the technical section.

1.7.2.1 Alternative Qualifications

Products having less than a 2-year field service record will be acceptable if a certified record of satisfactory field operation for not less than 6000 hours, exclusive of the manufacturers' factory or laboratory tests, is furnished.

1.7.2.2 Material and Equipment Manufacturing Date

Products manufactured more than 3 years prior to date of delivery to site shall not be used, unless specified otherwise.

SECTION 26 00 00.00 20 Page 3

1.8 WARRANTY

The equipment items shall be supported by service organizations which are reasonably convenient to the equipment installation in order to render satisfactory service to the equipment on a regular and emergency basis during the warranty period of the contract.

1.9 POSTED OPERATING INSTRUCTIONS

Provide for each system and principal item of equipment as specified in the technical sections for use by operation and maintenance personnel.

The operating instructions shall include the following:

a. Wiring diagrams, control diagrams, and control sequence for each principal system and item of equipment.

b. Start up, proper adjustment, operating, lubrication, and shutdown procedures.

c. Safety precautions.

d. The procedure in the event of equipment failure.

e. Other items of instruction as recommended by the manufacturer of each system or item of equipment.

Print or engrave operating instructions and frame under glass or in approved laminated plastic. Post instructions where directed. For operating instructions exposed to the weather, provide weather-resistant materials or weatherproof enclosures. Operating instructions shall not fade when exposed to sunlight and shall be secured to prevent easy removal or peeling.

1.10 MANUFACTURER'S NAMEPLATE

Each item of equipment shall have a nameplate bearing the manufacturer's name, address, model number, and serial number securely affixed in a conspicuous place; the nameplate of the distributing agent will not be acceptable.

1.11 FIELD FABRICATED NAMEPLATES

ASTM D709. Provide laminated plastic nameplates for each equipment enclosure, relay, switch, and device; as specified in the technical sections or as indicated on the drawings. Each nameplate inscription shall identify the function and, when applicable, the position.

Nameplates shall be melamine plastic, 0.125 inch thick, white with black center core for normal only power equipment and red with white center core for emergency power equipment. Surface shall be matte finish. Corners shall be square. Accurately align lettering and engrave into the core.

Minimum size of nameplates shall be one by 2.5 inches. Lettering shall be a minimum of 0.25 inch high normal block style.

1.12 WARNING SIGNS

Provide warning signs for the enclosures of electrical equipment including substations, pad-mounted transformers, pad-mounted switches, generators, and switchgear having a nominal rating exceeding 600 volts.

SECTION 26 00 00.00 20 Page 4

a. When the enclosure integrity of such equipment is specified to be in accordance with IEEE C57.12.28 or IEEE C57.12.29 , such as for pad-mounted transformers, provide self-adhesive warning signs on the outside of the high voltage compartment door(s). Sign shall be a decal and shall have nominal dimensions of 7 by 10 inches with the legend "DANGER HIGH VOLTAGE" printed in two lines of nominal 2 inch high letters. The word "DANGER" shall be in white letters on a red background and the words "HIGH VOLTAGE" shall be in black letters on a white background. Decal shall be Panduit No. PPSO710D72 or approved equal.

1.13 ELECTRICAL REQUIREMENTS

Electrical installations shall conform to IEEE C2 , NFPA 70 , and requirements specified herein.

1.14 INSTRUCTION TO GOVERNMENT PERSONNEL

Where specified in the technical sections, furnish the services of competent instructors to give full instruction to designated Government personnel in the adjustment, operation, and maintenance of the specified systems and equipment, including pertinent safety requirements as required. Instructors shall be thoroughly familiar with all parts of the installation and shall be trained in operating theory as well as practical operation and maintenance work. Instruction shall be given during the first regular work week after the equipment or system has been accepted and turned over to the Government for regular operation. The number of man-days (8 hours per day) of instruction furnished shall be as specified in the individual section. When more than 4 man-days of instruction are specified, use approximately half of the time for classroom instruction.

Use other time for instruction with equipment or system. When significant changes or modifications in the equipment or system are made under the terms of the contract, provide additional instructions to acquaint the operating personnel with the changes or modifications.

PART 2 PRODUCTS

2.1 FACTORY APPLIED FINISH

Electrical equipment shall have factory-applied painting systems which shall, as a minimum, meet the requirements of NEMA 250 corrosion-resistance test and the additional requirements specified in the technical sections.

PART 3 EXECUTION

3.1 FIELD APPLIED PAINTING

Paint electrical equipment as required to match finish of adjacent surfaces or to meet the indicated or specified safety criteria. Painting shall be as specified in Section 09 90 00 PAINTS AND COATINGS and the section specifying the associated electrical equipment.

3.2 FIELD FABRICATED NAMEPLATE MOUNTING

Provide number, location, and letter designation of nameplates as indicated. Fasten nameplates to the device with a minimum of two

SECTION 26 00 00.00 20 Page 5 sheet-metal screws or two rivets.

3.3 WARNING SIGN MOUNTING

Provide the number of signs required to be readable from each accessible side, but space the signs a maximum of 30 feet apart.

-- End of Section --

SECTION 26 00 00.00 20 Page 6

SECTION 26 08 00

APPARATUS INSPECTION AND TESTING

08/08

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)

NETA ATS (2017; Errata 2017) Standard for Acceptance Testing Specifications for Electrical Power Equipment and Systems

U.S. DEPARTMENT OF DEFENSE (DOD)

UFC 3-501-01 Electrical Engineering

UFC 3-520-01 Interior Electrical Systems

UFC 3-530-01 Interior and Exterior Lighting Systems

UFC 3-550-01 Exterior Power Distribution

UFC 3-560-01 Operations and Maintenance: Electrical Safety

UFC 3-575-01 Lightning and Static Electricity Protection Systems

UFC 3-580-01 Telecommunications Interior Infrastructure Planning and Design

1.2 ADDITIONAL REFERENCES

The latest edition of the publications listed below shall be considered part of this specification. The US Army Corps of Engineers New York District Engineering Planning Standards, Unified Facilities Criteria:

UFC 3-501-01 Electrical Engineering; UFC 3-520-01 Interior Electrical Systems; UFC 3-530-01 Interior and Exterior Lighting Systems;

UFC 3-550-01 Exterior Power Distribution; UFC 3-560-01 Operation and Maintenance: Electrical Safety; UFC 3-575-01 Lightning and Static Electricity Protection Systems; UFC 3-580-01 Telecommunications Interior Infrastructure Planning and Design.

1.3 RELATED REQUIREMENTS

Section 26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS applies to this section with additions and modifications specified herein.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

SECTION 26 08 00 Page 1 submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-06 Test Reports

Acceptance tests and inspections; G

SD-07 Certificates

Qualifications of organization, and lead engineering technician; G

Acceptance test and inspections procedure; G

1.5 QUALITY ASSURANCE

1.5.1 Qualifications

Contractor shall engage the services of a qualified testing organization to provide inspection, testing, calibration, and adjustment of the electrical distribution system and generation equipment listed in paragraph entitled "Acceptance Tests and Inspections" herein.

Organization shall be independent of the supplier, manufacturer, and installer of the equipment. The organization shall be a first tier subcontractor. No work required by this section of the specification shall be performed by a second tier subcontractor.

a. Submit name and qualifications of organization. Organization shall have been regularly engaged in the testing of electrical materials, devices, installations, and systems for a minimum of 5 years. The organization shall have a calibration program, and test instruments used shall be calibrated in accordance with NETA ATS.

b. Submit name and qualifications of the lead engineering technician performing the required testing services. Include a list of three comparable jobs performed by the technician with specific names and telephone numbers for reference. Testing, inspection, calibration, and adjustments shall be performed by an engineering technician, certified by NETA or the National Institute for Certification in Engineering Technologies (NICET) with a minimum of 5 years' experience inspecting, testing, and calibrating electrical distribution and generation equipment, systems, and devices.

1.5.2 Acceptance Tests and Inspections Reports

Submit certified copies of inspection reports and test reports. Reports shall include certification of compliance with specified requirements, identify deficiencies, and recommend corrective action when appropriate.

Type and neatly bind test reports to form a part of the final record.

Submit test reports documenting the results of each test not more than 10 days after test is completed.

1.5.3 Acceptance Test and Inspections Procedure

Submit test procedure reports for each item of equipment to be field tested at least 45 days prior to planned testing date. Do not perform

SECTION 26 08 00 Page 2 testing until after test procedure has been approved.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

3.1 ACCEPTANCE TESTS AND INSPECTIONS

Testing organization shall perform acceptance tests and inspections. Test methods, procedures, and test values shall be performed and evaluated in accordance with NETA ATS, the manufacturer's recommendations, and paragraph entitled "Field Quality Control" of each applicable specification section. Tests identified as optional in NETA ATS are not required unless otherwise specified. Equipment shall be placed in service only after completion of required tests and evaluation of the test results have been completed. Contractor shall supply to the testing organization complete sets of shop drawings, settings of adjustable devices, and other information necessary for an accurate test and inspection of the system prior to the performance of any final testing. Contracting Officer shall be notified at least 14 days in advance of when tests will be conducted by the testing organization. Perform acceptance tests and inspections on applicable equipment and systems specified in the following sections:

a. Section 26 32 15.00 10 DIESEL-GENERATOR SET STATIONARY 100-2500kw, WITH AUXILIARIES. Functional engine shutdown tests, vibration base-line test, and load bank test shall not be performed by the testing organization. These tests shall be performed by the start-up engineer.

b. Section 26 36 00.00 10 AUTOMATIC TRANSFER SWITCHES

c. Section 26 24 13 SWITCHBOARDS

3.2 SYSTEM ACCEPTANCE

Final acceptance of the system is contingent upon satisfactory completion of acceptance tests and inspections.

3.3 PLACING EQUIPMENT IN SERVICE

A representative of the approved testing organization shall be present when equipment tested by the organization is initially energized and placed in service.

SECTION 26 08 00 Page 3

THIS PAGE LEFT INTENTIONALLY BLANK

SECTION 26 09 13

POWER MONITORING SYSTEM

11/08

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI INCITS 154 (1988; R 2004) Office Machines and Supplies - Alphanumeric Machines - Keyboard Arrangement

ANSI/TIA-607-C-2015 Generic Telecommunications Bonding and Grounding (Earthing) for Customer Premises

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

IEEE C37.90.1 (2013) Standard for Surge Withstand Capability (SWC) Tests for Relays and Relay Systems Associated with Electric Power Apparatus

IEEE C62.41.1 (2002; R 2008) Guide on the Surges Environment in Low-Voltage (1000 V and Less) AC Power Circuits

IEEE C62.41.2 (2002) Recommended Practice on Characterization of Surges in Low-Voltage (1000 V and Less) AC Power Circuits

INTERNATIONAL ELECTROTECHNICAL COMMISSION (IEC)

IEC 61000-4-5 (2014) Electromagnetic Compatibility (EMC)

- Part 4-5: Testing and Measurement Techniques - Surge Immunity Test

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

ANSI C12.1 (2014; Errata 2016) Electric Meters Code for Electricity Metering

ANSI C62.61 (1993) American National Standard for Gas Tube Surge Arresters on Wire Line Telephone Circuits

NEMA 250 (2014) Enclosures for Electrical Equipment (1000 Volts Maximum)

NEMA ICS 1 (2000; R 2015) Standard for Industrial Control and Systems: General Requirements

SECTION 26 09 13 Page 1

NEMA WC 74/ICEA S-93-639 (2012) 5-46 kV Shielded Power Cable for Use in the Transmission and Distribution of Electric Energy

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2;

TIA 17-3; TIA 17-4; TIA 17-5; TIA 17-6;

TIA 17-7; TIA 17-8; TIA 17-9; TIA 17-10;

TIA 17-11; TIA 17-12; TIA 17-13; TIA

17-14; TIA 17-15; TIA 17-16; TIA 17-17 )

National Electrical Code

TELECOMMUNICATIONS INDUSTRY ASSOCIATION (TIA)

TIA-232 (1997f; R 2012) Interface Between Data Terminal Equipment and Data Circuit-Terminating Equipment Employing Serial Binary Data Interchange

TIA-485 (1998a; R 2012) Electrical Characteristics of Generators and Receivers for Use in Balanced Digital Multipoint Systems

TIA-568-C.1 (2009; Add 2 2011; Add 1 2012) Commercial Building Telecommunications Cabling Standard

TIA-607 (2015c; Addendum 1 2017) Generic Telecommunications Bonding and Grounding (Earthing) for Customer Premises

U.S. DEPARTMENT OF DEFENSE (DOD)

UFC 3-501-01 Electrical Engineering

UFC 3-520-01 Interior Electrical Systems

UFC 3-530-01 Interior and Exterior Lighting Systems

UFC 3-560-01 Operations and Maintenance: Electrical Safety

UFC 3-575-01 Lightning and Static Electricity Protection Systems

UFC 3-580-01 Telecommunications Interior Infrastructure Planning and DesignI3A Technical Criteria

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

47 CFR 15 Radio Frequency Devices

1.2 ADDITIONAL REFERENCES

The latest edition of the publications listed below shall be considered part of this specification. The US Army Corps of Engineers New York District Engineering Planning Standards Unified Facilities Criteria:

UFC 3-501-01 Electrical Engineering; UFC 3-520-01 Interior Electrical

SECTION 26 09 13 Page 2

Systems; UFC 3-530-01 Interior and Exterior Lighting Systems;

UFC 3-560-01 Operation and Maintenance: Electrical Safety; UFC 3-575-01 Lightning and Static Electricity Protection Systems; UFC 3-580-01 Telecommunications Interior Infrastructure Planning and Design I3A Technical Criteria for the Installation Information Infrastructure Architecture (Outside Plant Only); ANSI/TIA-607-C-2015 , Generic Telecommunications Bonding and Grounding (Earthing) for Customer Premises.

1.3 SYSTEM DESCRIPTION

The power monitoring system, consisting of commercial, off-the-shelf intelligent electronic devices (IEDs), communication channels, and PC-based workstation equipment, will be used to monitor the operation of power usage. Provide a power monitoring system that is a single workstation system utilizing an Ethernet local area network (LAN).

Monitoring pages on workstations shall include a graph showing historical usage data and a gauge to show instantaneous demand. Historical graphs shall display hourly, daily, monthly and yearly dates.

Monitoring Stations shall display the following points:

Main Electrical Service - kW and kWH Lighting - kW and kWH Receptacles - kW and kWH HVAC Equipment - kW and kWH

Point information shall be displayed by Floor and Entire building.

Equipment or systems specified in this section are part of the commissioning process. Refer to Section 01 91 00.15 TOTAL BUILDING COMMISSIONING for additional requirements.

1.3.1 System Response Times

a. Any new display shall begin to update the workstation monitor within 2 seconds after being requested. Preformatted displays shall be completely presented within 5 seconds after the request.

b. All calculated values shall be updated from the database, when displayed at the workstation, at least every 15 seconds.

c. Digital status indications, when displayed at the workstation, shall be updated within 15 seconds from the IED.

d. Analog values, when displayed at the workstation shall be updated within 15 seconds from the IED.

1.3.2 System Accuracy and Display

The system shall maintain the specified end-to-end accuracy from sensor to all workstation displays, including the effects of transmitters, transducers, and engineering units conversions, for one year for the applications specified and shall report and display changes in sensed values as specified. The system accuracy and display requirements are as follows:

a. Current: with a range for the specific application ± 1.0 percent of reading; display and print to nearest ampere.

SECTION 26 09 13 Page 3

b. Voltage: with a range for the specific application ± 1.0 percent of reading; display and print to nearest volt.

c. Power Factor: 1.0 percent of reading; display and print to nearest hundredth.

d. kWh: with a range for the specific application ± 1.0 percent of reading; display and print to nearest kWh.

e. KW: with a range for the specific application ± 1.0 percent of readings.

f. KVA: with a range for the specific application ± 1.0 percent of reading; display and print to nearest KVA.

g. KVAR: with a range for the specific application ± 1.0 percent of reading; display and print to nearest KVAR.

h. Frequency: ± 0.05 Hz; display and print to nearest 0.1 Hz.

i. Total Harmonic Distortion (THD) in percent for current and voltage, each phase.

j. K-Factor (dimensionless ratio based on harmonic content of current waveform).

1.3.3 Electrical Transients and Electromagnetic Interference

1.3.3.1 Power Line Surge Protection

Protect workstation equipment connected to ac circuits from power line surges and meet the requirements of IEEE C62.41.1 and IEEE C62.41.2 location category A3, while equipment is operating. In addition, protect all IEDs to meet the requirements of IEEE C37.90.1 or the requirements of IEC 61000-4-5 , test level 4, while the equipment is operating. Fuses shall not be used for surge protection.

1.3.3.2 Sensor Wiring Surge Protection

Protect all digital and analog inputs of all IEDs against surges induced on sensor wiring to meet the requirements of IEEE C37.90.1 or the requirements of IEC 61000-4-5 , test level 4, while the equipment is operating. Fuses shall not be used for surge protection.

1.3.3.3 Communications Channels Surge Protection

Protect communications equipment against surges induced on its communications channels. Protect communication interfaces to all field equipment to meet the requirements of IEEE C37.90.1 or the requirements of IEC 61000-4-5 , test level 4, while the equipment is operating. Fuses shall not be used for surge protection. Metallic cables and conductors which serve as communications channels between buildings shall have surge protection installed at equipment and additional triple electrode gas surge protectors rated for the application installed at each end per I3A,

3.17.1 PETs and 3.17.2 Terminals and Hardware, within 3 feet of the building cable entrance. Surge protectors shall meet the requirements of

ANSI C62.61 .

SECTION 26 09 13 Page 4

1.3.4 Communications

The Workstation and associated local area network shall be configured to accept a minimum of 32 TIA-232 or TIA-485 data communications channels by way of Ethernet gateways. Each communication channel shall support communication with at least 30 IEDs and shall meet the performance requirements as specified.

1.3.5 Expansion Requirements

Provide workstation hardware and software to accommodate a total of 120 IEDs.

1.3.6 Protocols

The workstation equipment shall include software allowing it to communicate with field equipment using any of the following protocols:

a. A published open protocol.

b. MODBUS RTU/ASCII.

1.3.7 Utility Demand Interval Synchronization

An interface for utility demand interval synchronization signals shall be provided as shown. The synchronization signal shall be used in calculating and displaying demand.

1.3.8 Test Procedures and Reports

The procedures shall consist of detailed instructions for test setup, execution, and evaluation of test results. Use the test reports to document results of the tests. Deliver reports to the Government within 7 days after completion of test.

1.4 DELIVERY OF TECHNICAL DATA AND COMPUTER SOFTWARE

1.4.1 Data, Drawings, CD-ROMS and Manuals

Deliver all items of software and technical data (including technical data which relates to computer software), which are specifically identified in this specification strictly in accordance with the CONTRACT CLAUSES and the Contract Data Requirements List, DD Form 1423. Identify all data delivered by reference to the particular specification paragraph against which it is furnished. All drawings submitted shall be in DXF and AutoCAD v14 file structure. Five sets of CD-ROMs shall be provided after final drawings are approved. Manuals provided shall contain the minimum content specified, although varied packaging and formats are acceptable. The Contractor may submit standard manuals with additions as necessary to conform to the requirements listed below.

1.4.2 Technical Data Package 1 - Existing Conditions Report

The data package shall include the existing conditions report as specified in Paragraph: EXAMINATION, and associated documentation as specified.

SECTION 26 09 13 Page 5

1.4.3 Technical Data Package 2 - System Data

1.4.3.1 System and Installation Drawings

a. Power monitoring system block diagram.

b. Layout plans showing equipment locations and cable routing.

c. Field equipment installation drawings including dimensional drawings of any existing enclosures showing equipment cutouts and mounting locations, and indicating adequate clearance from existing wiring and devices in accordance with manufacturer's recommendations.

d. Instrument transformer wiring and installation drawings.

1.4.3.2 Equipment Data

Deliver a complete data package for all materials and equipment as specified, including the following:

a. Catalog data for workstation equipment demonstrating compliance with specified requirements.

b. Catalog data for field equipment indicating outline and mounting dimensions and schematic external wiring arrangement, and

c. Catalog data for instrument transformers demonstrating compliance with specified requirements.

1.4.3.3 Installation, Setup and Operation Guides

The data package shall include the manufacturer's standard installation, setup and operation guides for workstation equipment and field equipment, and shall include details of the published open protocol for communications.

1.4.3.4 User's Guides

The data package shall include the manufacturer's standard user's guides for all software provided with the system.

1.4.3.5 Certifications

Provide written certifications that system components meet the requirements specified including:

a. 47 CFR 15

b. IEEE C62.41.1 and IEEE C62.41.2

c. ANSI C12.1

d. ANSI C62.61

e. IEEE C37.90.1 or IEC 61000-4-5 .

1.4.4 Technical Data Package 3 - Training Data

Lesson plans and training manuals for the training phases, including type of training to be provided and with a list of reference material shall be submitted for approval as specified.

SECTION 26 09 13 Page 6

1.4.5 Technical Data Package 4 - Performance Verification Testing Procedures

Submit test procedures for the Performance Verification Test (PVT). The test procedures shall explain in detail, step-by-step actions and expected results to demonstrate compliance with the requirements of this specification. Submit the PVT procedures for approval.

1.3.5 1.4.6 Technical Data Package 5 - Performance Verification Testing Data

Submit the performance verification test data to the Government after the Government approves the performance verification test.

1.4.7 Technical Data Package 6 - Operation and Maintenance Manuals

Resubmit the operation and maintenance manuals of all technical data identified as Technical Data Package 2, bound in three-ring binder, with as-built corrections and revisions and with addenda/appendices as necessary to identify any special characteristics or operations not covered in the manufacturer's standard documentation. Submit 6 copies of the operation and maintenance manuals within 30 days following successful completion of the PVT.

1.5 ENVIRONMENTAL REQUIREMENTS

a. Workstation and associated equipment shall operate without damage or degradation under the following ambient conditions, unless otherwise noted.

(1) Operating Temperature: 60 to 85 degrees F.

(2) Operating Humidity: 20 to 80 percent, non-condensing.

b. All field equipment shall operate without damage or degradation under the following ambient conditions, unless otherwise noted.

(1) Operating Temperature: 32 to 122 degrees F.

(2) Operating Humidity: 10 to 90 percent, non-condensing.

1.6 MAINTENANCE AND SERVICE

1.6.1 General Requirements

Provide all maintenance services required and equipment necessary to maintain the entire system operational, as specified, for a period of 1 year after system acceptance. Maintenance shall include preventive maintenance in addition to repairs, replacements, and adjustments and software updates. Written permission shall be obtained from the Government prior to performing any service work or adjustments which have any impact on facility operations.

1.6.2 Description of Work

The adjustment and repair of the system includes all workstation equipment and field equipment including software updates. Perform each manufacturer's required adjustments and all other work necessary for proper operation as specified.

SECTION 26 09 13 Page 7

1.6.3 Service Calls

The Government will initiate service calls when the system is not functioning properly. Provide to the Government a telephone number where the service supervisor can be reached at all times. Service personnel shall be at the site within three working days after receiving a request for service. Restore the system to proper operating condition within seven working days after receiving a request for service.

1.6.4 Records and Logs

Keep records and logs of each maintenance and service task, and organize cumulative records for each major component, and for the complete system chronologically. Maintain a continuous log for all devices on a site-by-site basis containing all initial analog span and zero calibration values and testing of all digital points. Complete logs shall be kept and shall be available for inspection onsite, demonstrating that planned and systematic adjustments and repairs have been accomplished for the system.

Provide the Government with a summary report of the maintenance and service performed during each previous month.

1.6.5 System Modifications

Make any recommendations for system modification as part of maintenance and service in writing to the Government. No system modifications, including operating parameters and control settings, shall be made without prior approval of the Government. Incorporate any modifications made to the system into the system documentation including drawings and manuals.

1.6.6 Software

Provide notices of all software updates and verify operation in the system, if the Government chooses to incorporate the update. These updates shall be accomplished in a timely manner, fully coordinated with system operators, and shall be incorporated into the manuals and software documentation. Install and validate the latest released version of the software, upon receiving written approval by the Government.

1.6.7 Telephone Consultation

Provide up to 40 hours per year of telephone consultation to Government personnel. Keep a log by month, identifying caller, date and length of call, and results of call.

PART 2 PRODUCTS

2.1 MATERIALS AND EQUIPMENT

2.1.1 General

Units of the same type of equipment shall be products of a single manufacturer. Each major component of equipment shall have the manufacturer's name and address, with model and serial number in a conspicuous place. All materials and equipment shall be currently in production at time of delivery to the Government.

2.1.2 Nameplates

Provide laminated plastic nameplates for each equipment enclosure and

SECTION 26 09 13 Page 8 device furnished. Laminated plastic shall be 1/8 inch thick, white with black center core. Nameplates shall be a minimum of 1 by 3 inches, with minimum 1/4 inch high engraved block lettering. Nameplates for devices smaller than 1 by 3 inches shall be attached by a non-ferrous metal chain.

All other nameplates shall be attached to the device. The nameplate for each equipment enclosure or device shall include the designator or number as shown, and the site name. Site names shall be provided after order placement. Attach nameplates to the equipment with stainless steel panhead screws.

2.1.3 Field Wiring, Cabling and Terminal Blocks

a. Install internal wiring in factory pre-wired enclosures according to the Contractor's standard as to wire size, insulation, and method of termination on internal equipment. The individual conductors of the interconnecting cables shall meet the flame resisting test requirements of NEMA WC 74/ICEA S-93-639 . Each individual conductor in individual enclosures shall be uniquely identified in accordance with NEMA ICS 1 . Splices will not be permitted.

b. Provide rail mounted compression clamp terminal blocks for conductors requiring connection to circuits external to the specified equipment, suitable for up to 12 AWG wire. Terminal blocks for analog circuits shall be knife switch disconnecting type. Group terminal blocks for easy accessibility unrestricted by interference from structural members and internal devices. Provide sufficient space on each side of each terminal block to allow an orderly arrangement of all leads to be terminated on the block. Provide plastic wiring duct or other factory mounted cable support devices to support cables for external circuit wiring.

c. Make terminal blocks, interposing relays, switches, or similar devices readily accessible. Locate the equipment in compartments, enclosures, or junction boxes in such arrangement that maintenance personnel shall have direct access to the equipment without removal of barriers, cover plates, or wiring. Provide grouped terminal blocks for all external connections. All wiring leaving an enclosure shall leave from terminal blocks or prefabricated connectors and not from other devices in the enclosure. Terminal blocks and jumpers shall be permanently and uniquely marked in conformance with NEMA ICS 1 .

2.1.4 Power Supplies

Field equipment shall be powered from 120 Vac or shall derive power from the monitored circuit.

2.1.5 Enclosures

Enclosures shall conform to the requirements of NEMA 250 for the types specified. Repair and refinish damaged surfaces using original type finish. Enclosures shall have removable hinged, key-locked front doors.

All enclosure locks shall be keyed alike. A total of 5 keys shall be turned over to the Government.

2.1.6 EMI/RFI Compliance

Equipment shall be designed to minimize the generation of electromagnetic and radio frequency interference. Workstation equipment shall be in compliance with 47 CFR 15 , for Class B computing devices.

SECTION 26 09 13 Page 9

2.2 FIELD EQUIPMENT

2.2.1 Basic Intelligent Electronic Device (IED)

2.2.1.1 Basic IED

Basic IEDs shall be microprocessor based devices providing multiple measurements for 60 Hz single phase or three phase electric systems as shown. Basic IEDs shall utilize a communication protocol in accordance with Paragraph: Protocols for display and transmission of the following parameters as specified plus other parameters as shown:

a. Voltage line-to-neutral plus or minus 0.5 percent

b. Voltage line-to-line: plus or minus 1 percent

c. Current: plus or minus 0.5 percent

d. VA: plus or minus 1 percent

e. kVAR: plus or minus 1.5 percent

f. Power factor: plus or minus 1 percent

g. kW: plus or minus 1.5 percent

h. kWh: plus or minus 1.5 percent of reading

2.2.1.2 Mounting

Basic IEDs shall accommodate mounting in panelboards or switchgear enclosures as required for the installation.

2.2.1.3 Communications

a. Basic IED to workstation: Communications interfaces shall be provided for each Basic IED to the communications channels for data transfer between Basic IED and workstation.

b. Each Basic IED shall have ports and modems or line drivers to perform the specified functions.

2.2.1.4 KWH Value Retention

Basic IEDs shall retain the accumulated KWH value for 72 hours minimum during power outages.

2.2.2 IED Communication Equipment

Repeaters shall be provided where required for extension of communication channel physical media.

2.3 INSTRUMENT TRANSFORMERS

2.3.1 Multi-Ratio Current Transformers

Current transformers shall be compatible with the IEDs furnished. Current transformers shall conform to IEEE C57.13 and the following requirements.

a. Insulation Class: BIL rating shall be equal or greater than the equipment being connected to.

b. Frequency: Nominal 60Hz.

c. Accuracy: plus or minus 0.3 percent at 60Hz.

d. Burden: Burden class shall be selected for the load.

e. Phase Angle Range: 0 to 60 degrees

SECTION 26 09 13 Page 10

2.4 WORKSTATION EQUIPMENT

2.4.1 Workstation Computer

2.4.1.1 Digital Computer

The workstation computer shall function as the overall system coordinator, perform…

This is the start of the file's text. The full file is on GovTribe.