W16ROE81994548
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this modification is to:
1. Revise and Reissue Draw ings
2. Revise and reissue bid schedule
3. Revise but not reissue 007300
4. Revise but not reissue specs
5. Provide Grain size analysis results Bid opening date remains 17 SEP 2018 at 2:00 PM EST.
Bidders must acknow ledge receipt of this amendment by the date specified or as amended in the bid by one of the follow ing methods: In the space provided on the SF 1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENT BY DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE LATE BID, LATE MODIFICATIOM OF BID, OR LATE
WITHDRAWAL OF BID (FAR 14.304).
1. CONTRACT ID CODE PAGE OF PAGES
J 1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 14-Sep-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS18B0032
X 9B. DATED (SEE ITEM 11)
16-Aug-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
14-Sep-2018
CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 1843
NEW YORK NY 10278-0090
W912DS 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DS18B0032
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SUMMARY
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job Mobilization and Demobilization
FFP
FOB: Destination
PURCHASE REQUEST NUMBER: W16ROE81994548
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0002 53,285 Cubic
Yard
Basic Work – Dredging Areas
FFP
Dredging (to -6 feet MLLW + 2 feet allowable overdepth), with placement of material along the shoreline of Smith Point County Park with upland stockpile.
FOB: Destination
NET AMT
TOTALS/NOTES
TOTAL BID (CLIN 0001 THRU 0002)...………………...…………………….….. $ ___________________
NOTES TO BIDDERS:
NOTE 1: Bidders must bid on all items. Failure to bid on all work will be cause for rejection of the bid as nonresponsive.
NOTE 2: Award of contract will be based on the responsible and responsive bidder with the lowest total price for the total of the CLINs 0001-0002.
NOTE 3: The unit price for CLIN 0002, is directly related to the estimated quantities of dredged material available for removal (all material except ledge rock lying above the plane of -6 feet mean lower low water (MLLW), plus 2 feet allowable overdepth), in the contract areas of Long Island Intracoastal Waterway Federal Navigation Project.
The dredged material will be placed along the shoreline of Smith Point County Park with an upland stockpile.
NOTE 4: All bidders are hereby advised that the estimated dredge quantities for placement in the price schedule are estimated and based on the bathometric survey data collected on 17-19 April 2018.
NOTE 5: The Government may reject a bid as non–responsive if the prices bid are materially unbalanced between line items and if there is a reasonable doubt that the bid will result in the lowest overall cost to the Government even though it may be the low bid.
NOTE 6: Bidders are reminded that they must bid on the issued plans and specifications as amended. Any deviations, conditions or attachments made by the bidder himself may render the proposal non-responsive and may be cause for its rejection.
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
SUMMARY OF CHANGES
The purpose of this amendment is to incorporate the following revisions to this solicitation:
SPECIFICATIONS:
Project Drawings “LIIW18_Plans_Sheet_1_thru_9”, the following items have been added to :
1) Drawings No. 2 through 6 has been modified to eliminate the western and eastern most shoals from the proposed dredging area. The remaining dredging area has been increased to 100 foot wide cover the entire width of the LIIW Federal Navigation Project. Coordinates of the dredging limits has been updated on the drawings.
2) Drawing No. 7 and 8 has been modified to move the approximate location of the propose stockpile closer to the Great Gun Marina Path.
W912DS-18-B-0032, the following items have been added to
1) Section 00 10 00 Solicitation - CLIN 0002 Quantity has been changed to 53,285
CY.
2) Section 00 73 00 Part 1.2 - Quantity has been changed to 53,285 CY. Contract Time for Completion has been change to 82 days.
3) Section 00 73 00 Part 1.11 - The Distribution of Volume Table has been changed to reflect the revised total dredging quantity of 53,285 CY
LIIW18 Tech Specs, the following items have been added to:
1) Title Page, Table of Content and Invitation Bid pages of tech specs has been changed to include the IFB No. W912DS-18-B-0032
2) Section 01 11 00 Part 1.2.1 - The total dredging quantity has been changed to “approximately 53,285 CY of Material from a 100-foot wide dredging area”
Grain Size Analysis Results
1) Files “LIIW18 Grain Size Results.pdf” and “LIIW18 Grain Size Sampling Point Map.pdf” are provided to the bidders.
SECTION 00 10 00 - SOLICITATION
The contractor period of performance end date has decreased by 3 days from 85 days to 82 days.
SECTION 00 70 00 – CONDITIONS OF THE CONTRACT
The contractor period of performance end date has decreased in FAR clause 52.211-10 by 3 days from 85 days to 82 days.