AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1. Make some changes to the Specifications.
2. Respond to bidders' questions (FOR INFORMATIONAL PURPOSES ONLY).
The Bid Opening date of 10 July 2018 at 2:00pm EST remains unchanged NOTE: Bidders must acknow ledge receipt of this amendment by the date specified in the solicitation (or as amended) by one of the follow ing methods: In the space provided on the SF1442, by separate letter, or by signing Block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE LATE BID, LATE
MODIFICATIONS OF BIDS OR LATE WITHDRAWAL OF BIDS (FAR 14.304).
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 21-Jun-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS18B0009
X 9B. DATED (SEE ITEM 11)
07-Jun-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
21-Jun-2018
CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 1843
NEW YORK NY 10278-0090
W912DS 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DS18B0009
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0002
Maintenance Dredging, Hudson River, NY, Federal Navigation Project Castleton, Stockport and Hudson Dredge Areas
Amendment 0002
Amendment 0002 to DRAWINGS and SPECIFICATIONS
TO OFFERORS
The following changes shall be made to the drawings and specifications.
DRAWINGS
1. The following DRAWINGS have been REVISED but NOT REISSUED:
- None
2. The following DRAWINGS have been REVISED and REISSUED:
- None
3. The following DRAWINGS have been ADDED:
- None
SPECIFICATIONS:
1. The following SPECIFICATIONS have been ADDED:
- None
2. The following SPECIFICATION SECTION has been REVISED but NOT REISSUED:
Section 00 73 00, Special Contract Requirements, Paragraph 1.2:
Replace sub-paragraph (7) in Paragraph 1.2 in its entirety as below:
Hopper dredge monitoring is required for this project. The contractor is required to comply with Section 35 20 23.23 entitled "NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM, HOPPER DREDGE (10/25/2017)", of these specifications.
3. The following SPECIFICATION SECTIONS has been REVISED and REISSUED:
- None
4. The following SPECIFICATION SECTIONS have been DELETED in their entirety:
- None
The following are responses to questions received from bidders (FOR
INFORMATIONAL PURPOSES ONLY):
(Questions that may be of general interest to all Offerors and/or the Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s).
Questions and answers are issued to the Offerors “for information only” and do not revise the solicitation, plans or specifications.)
Question No. 1: The contractor's bid must remain valid for 120 days after the bid date of July I 0, 2018. That is until November 7, 2018, 67 days into the dredging window.
This leaves 45 days available for preparing the disposal area and dredging. Assuming NTP is provided the same day as the award and considering the 21 anticipated adverse weather delay work days (which is based on working only 5 days a week), there are realistically only 19 days available to complete all work. Question: Can the Corps provide the award and NTP on or before September 1, 2018, to allow for more working time?
Response: Provided the bidder is found to be responsive, responsible and provides all required pre-award documentation, it is anticipated the contract award will be made within 30 days following bid opening.
Question No. 2: Could the Corps provide the XYZ data represented in the project plans?
Response: Amendment #2 has provided all potential bidders with the hydrographic xyz data files.
The .xyz files below, added in this amendment, have been made a part of this contract:
- xyzCastleton.xyz
- xyzHudson.xyz
- xyzStockportN.XYZ
- xyzStockportS.XYZ
Question No. 3: Heavy equipment is expected to be mobilized to placement area U-3A via a -4.5 mile dirt trail through the Schodack Island State Park. Question: Could the contractor be allowed to bring heavy equipment in by barge to bypass the trail?
Response: Providing that the contractor has all pertinent plans approved (e.g. safety, activity hazard analysis, mobilization, etc.) there would be no prohibition on a contractor mobilizing their heavy equipment onto the Houghtaling Island DMPS from a barge on the Hudson River side of the site. The contractor would be required to use the existing influent pipeline corridor identified as "Pipeline Clearing Area 2".
(End of Summary of Changes)