09-B-0020 Amendment 1.pdf

PDF 78 KB Posted

Attached to
RECOVERY--Y--Troy Lock Lighting Renovations, New York
Solicitation number
W912DS-09-B-0020
Issued by

About this file

Amendment 0001

View the file

Other files

File Type Posted
Final Specs.pdf PDF
W912DS-09-B-0020.pdf PDF
Final Plans.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OPS-ALBANY FIELD OFFICE

USACE NEW YORK DISTRICT ATTN: CENAN-OP-A

TROY NY

W16ROE91006327

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this Amendment is to:

1. Revise the Wage Rates to General Decision Number: NY080002 08/21/2009 NY2

2. Replace the Note in Detail 5 / Sheet E-105 of the Plans

The Bid Opening Date of 18 September 2009 at 2:00 p.m. EST remains unchanged.

NOTE: Offerors must acknow ledge receipt of this amendment by the date specif ied in the bid (or as amended) by one of the follow ing methods: In the space provided on the SF 1442, by separate letter, by telegram, or by signing Block 15 of SF 30. FAILURE TO ACKNOWLEDGE AMENDMENT BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH LATE

BID, LATE MODIFICATION OF BID, OR LATE WITHDRAWAL OF BID (FAR 14.304).

1. CONTRACT ID CODE PAGE OF PAGES

J 1 51

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 01-Sep-2009

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS-09-B-0020

X 9B. DATED (SEE ITEM 11)

18-Aug-2009

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

01-Sep-2009

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 1843

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE E3R0150

FACILITY CODECODE

EMAIL:TEL:

W912DS-09-B-0020

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The following have been added by full text:

AMENDMENT 0001

PLANS: DETAIL 5, SHEET E-105

Revise note in Detail 5, Sheet E-105 as follows: replace "Existing Concrete Pad Remove Top 6" Concrete, Provide New Concrete, Slope to Drains" with "Remove Existing 10" Concrete Pad, Provide New 10" Concrete Pad, Slope to Drains."

SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS

The following have been added by full text:

REVISED WAGE RATES

General Decision Number: NY080002 08/21/2009 NY2

Superseded General Decision Number: NY20070002

State: New York JR 28 August 2009

Construction Types: Building, Heavy and Highway

Counties: Albany, Columbia, Fulton, Greene, Montgomery, Rensselaer, Saratoga, Schenectady, Schoharie and Washington

Counties in New York.

BUILDING CONSTRUCTION PROJECTS (For all counties except FULTON)

(does not include single family homes and apartments up to a including 4 stories), HEAVY AND HIGHWAY CONSTRUCTION PROJECTS

Modification Number Publication Date

0 02/08/2008

1 04/04/2008

2 05/02/2008

3 05/16/2008

4 05/30/2008

5 06/06/2008

6 06/13/2008

7 06/20/2008

8 06/27/2008

9 07/04/2008

10 08/08/2008

11 08/22/2008

12 10/03/2008

13 01/02/2009

14 01/23/2009

15 03/20/2009

16 03/27/2009

17 04/17/2009

18 05/01/2009

19 06/05/2009

20 06/12/2009

21 06/19/2009

22 06/26/2009

23 07/03/2009

24 07/10/2009

25 07/17/2009

26 07/24/2009

27 08/21/2009

ASBE0040-002 05/01/2009

Rates Fringes

Asbestos/Insulator Worker

SCOPE OF WORK: includes application of all insulating materials, protective, coverings, coating and finishing to all types of mechanical systems.....................$ 27.14 16.88

HAZARDOUS MATERIAL HANDLER

Duties limited to preparation wetting;

stripping; removal;

scrapping; vacuuming;

bagging; and disposing of all insulation materials, whether they contain asbestos or not from mechancial systems..........$ 17.37 9.95

BOIL0197-002 10/01/2006

BOILERMAKER......................$ 27.45 18.76

BRNY0002-019 06/01/2009

BRICKLAYER

BRICKLAYERS, STONE MASONS,

CEMENT MASONS, PLASTERERS,

POINTERS, CAULKERS &

CLEANERS....................$ 26.91 15.78

HEAVY & HIGHWAY

CONSTRUCTION

CEMENT MASONS..............$ 27.23 13.98

MARBLE, TILE & TERRAZZO

FINISHERS...................$ 21.05 12.32

MARBLE, TILE & TERRAZZO

WORKERS.....................$ 26.81 14.30

CARP0019-002 07/01/2009

Carpenters:

BUILDING CONSTRUCTION

(COLUMBIA COUNTY)

Carpenters, Millwrights, Pile Drivers...............$ 26.86 21.20

BUILDING CONSTRUCTION

(GREENE COUNTY)

Carpenters, Millwrights, Pile Drivers...............$ 26.61 21.20

HEAVY AND HIGHWAY

CONSTRUCTION (COLUMBIA AND

GREENE COUNTIES)

Carpenters, Millwrights, Pile Drivers...............$ 24.40 15.59

CARP0229-003 07/01/2009

SARATOGA COUNTY

HEAVY & HIGHWAY

CONSTRUCTION:

Carpenters.................$ 27.54 13.80

WASHINGTON COUNTY

CONSTRUCTION:

Carpenters.................$ 27.04 13.80

PAID HOLIDAYS: Labor Day, provided the employee has been on the payroll the calender week or any of the holiday week preceding the holiday and works the day after the holiday.

CARP0370-001 06/01/2009

ALBANY, FULTON, MONTGOMERY, RENSSELAER, SCHENECTADY AND

SCHOHARIE COUNTIES

Carpenters & Soft Floor

Layers.....................$ 26.20 14.95

Piledriver.................$ 23.60 8.685

HEAVY & HIGHWAY

CONSTRUCTION

Carpenters.................$ 26.39 14.95

CARP0370-003 07/01/2009

CARPENTERS..................$ 26.39 14.95

DIVER TENDERS...............$ 25.49 14.95

DIVERS (Dry Day)............$ 25.49 14.95

DIVERS......................$ 60.00 14.95

PILEDRIVERS.................$ 24.49 14.95

ELEC0236-001 06/01/2009

ALBANY; COLUMBIA; FULTON; GREENE (that portion North of a line following the south limits of the city of Catskill);

MONTGOMERY; RENSSELAER, SARATOGA; SCHENECTADY; SCHOHARIE;

WASHINGTON

ELECTRICIAN......................$ 30.50 17.09

ELEC0363-004 04/01/2009

GREENE COUNTY (Portion of)

ELECTRICIAN......................$ 37.00 23.12

ELEC1249-003 05/04/2009

LINE CONSTRUCTION: Lineman

(LIGHTING AND TRAFFIC SIGNAL

Including any and all Fiber

Optic Cable necessary for

Traffic Signal Systems, Traffic Monitoring systems and Road Weather information systems)

Flagman.....................$ 22.25 13.50+6.5%+a

Groundman Digging Machine

Operator....................$ 32.74 11.75+6.5%+a

Groundman Truck Driver

(tractor trailer unit)......$ 31.52 13.50+6.5%+a

Groundman Truck Driver......$ 29.66 13.50+6.5%+a

Lineman & Technician........$ 37.08 13.50+6.5%+a

Mechanic....................$ 29.66 13.50+6.5%+a

FOOTNOTE:

a. New Year's Day, Memorial Day, Independence Day, Labor

Day, Thanksgiving Day, Christmas Day, plus President's Day, Good Friday, Decoration Day, Election Day for the President of the United States and Election Day for the Governor of the State of New York, provided the employee works the day before or the day after the holiday.

ELEC1249-004 05/04/2009

Line Construction:

Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities (where no other trades are or have been involved):

Cable Splicer..............$ 44.67 13.50+7%+a

Flagman....................$ 24.37 13.50+7%+a

Groundman digging machine operator...................$ 36.55 13.50+7%+a

Groundman truck driver

(tractor trailer unit).....$ 34.52 13.50+7%+a

Groundman Truck driver.....$ 32.49 13.50+7%+a

Lineman and Technician.....$ 40.61 13.50+7%+a

Mechanic...................$ 32.49 13.50+7%+a

Overhead transmission line work (where 40.09other trades are or have been involved):

Cable Splicer..............$ 46.41 12.00+7%+a

Overhead transmission line work (where other trades are or have been involved):

Cable Splicer..............$ 47.44 13.50+7%+a

Flagman....................$ 25.88 13.50+7%+a

Groundman digging machine operator...................$ 38.82 13.50+7%+a

Groundman truck driver

(tractor trailer unit).....$ 36.66 13.50+7%+a

Groundman truck driver.....$ 34.50 13.50+7%+a

Lineman and Technician.....$ 43.13 13.50+7%+a

Mechanic...................$ 34.50 13.50+7%+a

Substation:

Cable Splicer..............$ 44.67 13.50+7%+a

Flagman....................$ 24.37 13.50+7%+a

Ground man truck driver....$ 32.49 13.50+7%+a

Groundman digging machine operator...................$ 36.55 13.50+7%+a

Groundman truck driver

(tractor trailer unit).....$ 34.52 13.50+7%+a

Lineman & Technician.......$ 40.61 13.50+7%+a

Mechanic...................$ 32.49 13.50+7%+a

Switching structures;

railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation

Cable Splicer..............$ 46.10 13.50+7%+a

Flagman....................$ 25.15 13.50+7%+a

Groundman Digging Machine

Operator...................$ 37.72 13.50+7%+a

Groundman Truck Driver

(tractor-trailer unit).....$ 35.62 13.50+7%+a

Groundman Truck Driver.....$ 33.53 13.50+7%+a

Lineman & Technician.......$ 38.87 11.75+7%+a

Mechanic...................$ 33.53 13.50+7%+a

TELEPHONE, CATV

FIBEROPTICS CABLE AND

EQUIPMENT

Cable splicer/Central

Office Person..............$ 23.07 3.05+3%

Groundman..................$ 11.61 3.05+3%

Installer Repairman-

Teledata

Lineman/Tecnician-

Equipment Operator.........$ 21.91 3.05+3%

TREE TRIMMER................$ 18.92 4.05+3%+b

a. PAID HOLIDAYS: New Year's Day, Presidents' Day, Memorial

Day, Good Friday, Independence Day, Labor Day, Thanksgiving

Day, Christmas Day, and Election Day for the President of the United States and Election Day for the Governor of New

York State, provided the employee works two days before or two days after the holiday.

b. New Years Day, Washington's Birthday, Good Friday, Decoration Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day, Day after Thanksgiving Day and Christmas

Day.

ELEC1249-007 05/04/2009

LINE CONSTRUCTION (LINEMAN) LIGHTING AND TRAFFIC SIGNAL

INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR THE

TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD

WEATHER INFORMATION SYSTEMS

COLUMBIA COUNTY

LINE CONSTRUCTION: Lineman

Flagman.....................$ 23.00 13.50+6.5%+a

Groundman Digging Machine

Operator....................$ 34.51 13.50+6.5%+a

Groundman Truck Driver

(Tractor-trailer unit)......$ 32.59 13.50+6.5%+a

Groundman Truck Driver......$ 30.67 13.50+6.5%+a

Lineman and Technician......$ 38.34 13.50+6.5%+a

Mechanic....................$ 30.67 13.50+6.5%+a

PAID HOLIDAYS:

a. Memorial Day, New Year's Day, President's Day, Good

Friday, Decoration Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, and Election Day for the

President of the United States and Election Day for the

Governor of New York State, provided the employee works two days before or two days after the holiday.

ELEV0035-001 01/01/2009

ALBANY; COLUMBIA (Towns of Claverack, Hillsdale, Ghent, Stockport, Austerlitz, Canaan, New Lebanon, Chatham, Kinderhook, Styvesant and Greenport); FULTON; GREENE (Towns of

Durham, Greenville, New Baltimore, Coxcsackie and Athens);

MONTGOMERY, RENSSELAER, SARATOGA, SCHENECTADY, SCHOHARIE AND

WASHINGTON COUNTIES

Elevator Constructor.............$ 36.46 18.285

FOOTNOTES:

a. 8 PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving

Day, and the day after Thanksgiving Day, Christmas Day.

b. Employer contributes 8% of basic hourly rate for 5 years or more of service or 6% of basic hourly rate for 6 months to 5 years of service as vacation pay credit.

ELEV0138-004 01/01/2009

COLUMBIA COUNTY (THE TOWNS OF ANCRAM, CLERMONT, COPAKE,

GALLATIN, GERMANTOWN, LIVINGSTON, AND TAGHKANIC); GREEN COUNTY

(THE TOWNS OF HUNTER AND CATSKILL)

Elevator Constructor.............$ 46.48 18.285+a+b

a. 8 PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving

Day, the Friday after Thanksgiving Day and Christmas Day.

b. Employer contributes 8% of basic hourly rate for 5 years or more of service or 6% of basic hourly rate for 6 months to 5 years of service as vacation pay credit.

ENGI0106-001 07/01/2009

Power equipment operators:

GROUP 1.....................$ 32.73 18.75+a

GROUP 2.....................$ 32.30 18.75+a

GROUP 3.....................$ 31.39 18.75+a

GROUP 4.....................$ 28.81 18.75+a

GROUP 5.....................$ 33.91 18.75+a

GROUP 6.....................$ 33.23 18.75+a

GROUP 7.....................$ 33.73 18.75+a

POWER EQUIPMENT OPERATOR CLASSIFICATIONS (HEAVY & HIGHWAY)

GROUP 1: Boom Truck (over 5 tons), Crane, Cherry Picker (over

5 ton capacity), Derricks (steel erection), Dragline, Overhead Crane (Gantry or Straddle type), Pile Driver, Truck Crane

GROUP 2: Automated Concrete Spreader (CMI), Automatic Fine

Grader, Backhoe (Except Tractor Mounted, Rubber Tired), Backhoe Excavator Full Swing (CAT 212 or similar type), Belt Placer (CMI type), Black Top Plant (Automated), Boom

Truck (5 tons and under), Cableway, Caisson Auger, Central

Mix Concrete Plant (Automated), Concrete Pump (8" or over), Dredge, Dual Drum Paver, Excavator (All Purpose-Hydraulicly

Operated) (Gradall or similar), Fork Lift (Factory Rated 15

ft. and over), Front End Loader (4 c.y. and over), Head

Tower (Sauerman or equal), Hoist (2 or 3 Drum), Holland

Loader, Mine Hoist, Mucking Machine or Mole, Pavement

Breaker (SP) Wertgen; PB-4 and similar type, Power Grader, Profiler (over 105 H.P), Quad 9, Quarry Master (or equivalent), Scraper, Shovel, Side Boom, Slip Form Paver, Tractor Drawn Belt-Type Truck Crane, Truck or Trailer

Mounted Log Chipper (Self-Feeder), Tug Operator (Except

Manned Rented Equipment), Tunnel Shovel

GROUP 3: Asphalt Paver, Backhoe (Tractor Mounted, Rubber

Tired), Bituminous Spreader and Mixer, Blacktop Plant

(Non-Automated), Blast or Rotary Drill (Truck or Tractor

Mounted), Boring Machine, Cage-Hoist, Central Mix Plant

(Non-Automated) and All Concrete Batching Plants, Cherry

Picker (5 Tons Capacity and Under), Compressors (4 or less)

Exceeding 2000 C.F.M. Combined Capacity, Concrete Paver

(over 16S), Concrete Pump (Under 8"), Crusher, Diesel Power

Unit, Drill Rigs (Tractor Mounted), Front End Loader (under

4 c.y.), Hi-Pressure - Boiler (15 lbs. and over), Hoist

(One Drum), Kolman Plant Loader and Similar Type Loaders, L.C.M. Work Boat Operator, Locomotive, Maintenance

Engineer/Greaseman/ Welder, Mixer (For Stabilized Base

Self-Propelled), Monorail Machine, Plant Engineer, Profiler

(105 H.P. and under), Pug Mill, Pump Crete, Ready Mix

Concrete Plant, Refrigeration Equipment (For Soil

Stabilization), Road Widener, Roller (All Above Subgrade), Sea Mule, Self-contained Ride-on-Rock Drill, excluding

Air-Track Type Drill, Skidder, Tractor with Dozer and/or pusher, Trencher, Tugger Hoist, Vermeer saw (ride on, any size or type), Winch, Winch Cat

GROUP 4: A-Frame Winch Hoist on Truck, Ballast Regulator

(Ride- On), Compressors (4 not to exceed 2000 C.F.M.

Combined Capacity, or 3 or less with more than 1200 C.F.M.

but not to exceed 2000 C.F.M.), Directional Drill Machine

Locator Dust Collectors, Generators, Pumps, Welding

Machines, Light Plants (4 of Any Type Of Combination), Concrete Pavement Spreaders and Finishers, Conveyor, Drill

Core, Drill Well, Electric Pump Used In Conjunction with

Well Point System, Farm Tractor with Accessories, Fine

Grade Machine, Fork Lift (under 15 ft.), Grout Pump, Gunite

Machine, Hammers (Hydraulic-Self-Propelled), Hydra- Spiker

(Ride-On), Hydro-Blaster Water, Post Hole Digger and Post

Driver, Power Sweeper, Roller (Grade and Fill), Scarifier

(Ride-On Spansaw (Ride-On), Skid Steer loader (Bobcat or similar), Submersible Electric Pump (When Used In Lieu Of

Well Point System), Tamper (Ride-On), Tie Extractor

(Ride-On), Tie Handler, Tie Inserter (Ride-On), Tie Spacer

(Ride-On), Tire Repair, Track Liner, Tractor With Towed

Accessories, Vibrator Compactor, Vibro Tamp, Well Point, Aggregate Plant, Boiler (Used In Conjunction With

Production), Cement and Bin Operator, Compressors (3 or less not to Exceed 1200 C.F.M. Combined Capacity), Dust

Collectors, Generators, Pumps, Welding Machines, Light

Plants (3 or less of Any Type or Combination), Concrete or

Mixer (16S and under), Concrete Saw (Self-Propelled), Fireman, Form Tamper, Hydraulic Pump (Jacking System), Light Plants, Mulching Machine, Oiler, Parapet-Concrete or

Pavement Grinder, Power Broom (Towed), Power Heaterman, Revinius Widener, Shell Winder, Steam cleaner, Tractor

GROUP 5: Master Mechanic

GROUP 6: Crane Premium with Boom Length and Jib 150 Ft.- 199

Ft.

GROUP 7: Crane Premium with Boom Length and Jib 200 Ft. and over

Tower Crane Premium .50

Hazmat Work Premium 2.50

Hydrographic .50

a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence

Day, Labor Day, Thanksgiving Day, Christmas Day, Lincoln's

Birthday, Washington's Birthday, Good Friday, Columbus Day, November Election Day and Veteran's Day

ENGI0106-002 07/01/2009

BUILDING

Power equipment operators:

GROUP 1.....................$ 32.74 18.88+a

GROUP 2.....................$ 32.30 18.88+a

GROUP 3.....................$ 31.39 18.88+a

GROUP 4.....................$ 28.82 18.88+a

GROUP 5

1..........................$ 33.24 18.88+a

2..........................$ 33.74 18.88+a

GROUP 6.....................$ 33.24 18.88+a

GROUP 7.....................$ 34.29 18.88+a

GROUP 8.....................$ 36.79 18.88+a

Hazardous work - Anytime Operating Engineers are involved with level C or above, $2.50 per hour over regular rate.

a. Paid Holidays: New Years Day, Memorial Day, Independence

Day, Labor Day, Thanksgiving Day, Christmas Day.

POWER EQUIPMENT OPERATOR CLASSIFICATIONS (BUILDING)

GROUP 1: Crane, hydraulic cranes, tower crane, locomotive crane, piledriver, cableway, derricks, whirlies, dragline, boom truck (over 5 tons)

GROUP 2: Shovel, All backhoe (except tractor mounted rubber tired John Deere 510 or smaller), gradalls, power road grader, all CMI equipment, front-end rubber tire loader, tractor-mounted drill (quarry master), mucking machine, concrete central mix plant, concrete pump, Belcrete system, automated asphalt concrete plant and tractor road paver, boom truck (5 tons and under)

GROUP 3: Backhoe, (tractor mounted rubber tired equivalent to John Deere 510 or less), bulldozer, pushcat, tractor, traxcavator, scraper, LeTourneau grader, form fine grader, road roller, blacktop roller, blacktop spreader, power brooms, sweepers, trenching machine, Barber Green loader, side booms, hydrohammer, concrete spreader, concrete finishing machine, one drum hoist, power hoisting (single drum), hoist - two drum or more, three drum engine, power hoisting (two drum and over), two drum and swinging engine, three drum swinging engine, hod hoist, A-L frame winches, cord and well drillers (one drum), post hole digger, model

CHB Vibro-Tamp or similar machine, batch bin and plant operator, dinkey locomotive, skid steer loader, track excavator 5/8 cu. yd. or smaller

GROUP 4: Fork lift, high lift, lull, oiler, fireman and heavy- duty greaser, boilers, and steam generators, pump, vibrator, motor mixer, air compressor, dust collector, welding machine, well point, mechanical heater, generators, temporary light plants, concrete pumps, electric submersible pump 4" and over, murphy type diesel generator, conveyor, elevators, concrete mixer and belcrete power pack

(belcrete system), seeding, and mulching machines, pumps

GROUP 5: Crane Premiums:

1 over 150'

2 over 200'

GROUP 6: Tower Crane

GROUP 7: Master mechanic (other than nuclear work)

GROUP 8: Master mechanic on nuclear work

IRON0012-011 05/01/2009

ALBANY; COLUMBIA; FULTON (Albin, Bleecker, Broad, Johnstown, Mayfield, Northampton and Perth); GREENE, MONTGOMERY

(Amsterdam, Charleston, Florida, Glen, Mohawk and Root);

RENSSELAER, SARATOGA; SCHENECTADY; SCHOHARIE; and WASHINGTON

COUNTIES:

Ironworkers:

Sheeter, Bucker-up..........$ 25.78 17.96

Sheeter.....................$ 26.50 17.39

Structural, Ornamental, Rodman, Machinery Mover, Rigger, Fence Erector, Reinforcing, Stone

Derrickmen..................$ 26.25 17.39

IRON0440-007 05/01/2009

FULTON (Twps. of Caroga, Ephratah, Oppenheim, Stratford);

MONTGOMERY (Twps of Canajoharie, Minden, Palatine, St.

Johnsville):

Ironworkers:

Structural, Ornamental, Rodman, Machinery Mover, Rigger, Fence Erector, Reinforcement, and Stone

Derrickman..................$ 23.63 19.16

* LABO0017-001 06/01/2009

COLUMBIA COUNTY (Townships of Greenport, Claverack, Clermont, Germantown, Livingston, Hillsdale, Taghkanic, Gallatin, Copake, Ancram, Philmont and the City of Hudson)

Laborers:

COLUMBIA COUNTY (Townships of Greenport, Claverack, Clermont, Germantown, Livingston, Hillsdale, Taghkanic, Gallatin, Copake, Ancram, Philmont and the City of Hudson)

(Asbestos, lead, toxic and hazardous waste abatement and any other environmental related work) BUILDING

CONSTRUCTION:

GROUP 1....................$ 28.75 17.90

GROUP 2:...................$ 33.30 17.90

COLUMBIA COUNTY (Townships of Greenport, Claverack, Clermont, Germantown, Livingston, Hillsdale, Taghkanic, Gallatin, Copake, Ancram, Philmont, and the City of Hudson)

(Asbestos, lead, toxic and hazardous waste abatement and any other environmental related work) HEAVY & HIGHWAY

GROUP 2:...................$ 31.60 17.65+a

GROUP 3:...................$ 35.50 17.65+a

GREENE (Township of

Catskill) LABORERS

BUILDING:

GROUP 1....................$ 28.75 17.90

GROUP 2....................$ 30.55 17.90

GROUP 3....................$ 33.30 17.90

GREENE COUNTY (Township of

Catskill) HEAVY & HIGHWAY:

GROUP 1:...................$ 27.25 17.65+a

GROUP 2:...................$ 31.60 17.65+a

GROUP 3:...................$ 35.50 17.65+a

GROUP 4:...................$ 37.50 17.65+a

TUNNEL, SHAFT & CAISSON

WORK

GROUP 1....................$ 37.50 17.65+a

For BUILDING CONSTRUCTION CLASSIFICATIONS in GREENE COUNTY

(Township of Catskill)

GROUP 1: Custodial work, flag person, portable generator tender, portable pump tender, pitman and dumpman, firewatch, temporary heat tender, temporary light tender, traffic control, tool room tender; Artificial turf, air chipping hammer, acoustic pump and mixer, carpenter tender, concrete, concrete curb and sidewalk form setter, concrete form stripping, concrete sealing, concrete curing, concrete finisher, concrete vibrator, compressor, clean up after trades, dismantling, demolition, excavation, fireproofing, foundation and building piping, pump and mixer, gunite, general clean up, grade checker, grading and backfilling, hoists, hod carrier, landscaping, mason tender, multi building trades tender, jackhammer, pavement breaker, poured gypsum roof work, power tampers, power walk behind roller, pressure blasting, power mixer, scaffolding, snow removal, signal person, sandblasting, styrofoam and similar installation, radio control equipment including but not limited to radio control tampers and rollers, radio control excavator, all erecting and dismantling of scaffold for masonry regardless of height, walking and riding power buggies, temporary weather protection, wrecking waterproofing, stone and tile setter, radio controlled hammers and breakers, unloading of trucks, air track, assembling and placing gabion baskets, asphalt, blaster, bob cat type machine for demo and clean up, chain link fence, chain saw, chipping hammer, concrete conveyor belt, saw, core drill, corrugated pipe, construction specialist, cleaning machine, concrete form setter, conduit layer, cutting torch, discharge pipe, drill chuck tender, duct bank layer, explosive handler, hydraulic splitter, granite or stone curbing, handler, joy and jib drill, Ingersoll

Rand heavy duty crawler master type HCMZ drill machines or equivalent, laser level, nonmetallic pipe layer, metalic pipe layer, LeRoi hydraulic drill or similar, mega mixer, power fork lift, pre-stressed and precast concrete, power brush cutter, pump crete machine, retaining walls, rip rap, retention and hazardous waste liners, setting of block, setting of brick, setting of stone, sound barriers, transit under laborers jurisdiction, tow behind concrete or grout pump, traffic and pedestrian striping, surface planer, manufactured curb, walk behind surface planer, wagon drill, welding; *asbestos abatement work, lead abatement work, toxic and hazardous waste related work; when protective equipment and clothing are not required.

GROUP 2: Forklift for masonry purposes

GROUP 3: Asbestos Abatement work, toxic and hazardous abatement, lead abatement work, environmental work

For BUILDING CONSTRUCTION CLASSIFICATIONS in COLUMBIA COUNTY

(Townships of Greenport, Claverack, Clermont, Germantown, Livingston, Hillsdale, Taghkanic, Gallatin, Copake, Ancram, Philmont and the City of Hudson)

GROUP 1: Asbestos abatement work, lead abatement work, toxic and hazardous waste related work; when protective equipment and clothing are not required

GROUP 2: Asbestos abatement work, toxic and hazardous abatement, lead abatement work, environmental work

For HEAVY & HIGHWAY CLASSIFICATIONS in GREENE COUNTY

(Township of Catskill)

a. PAID HOLIDAYS: New Years Day, President's Day, Memorial

Day, Independence Day, Lincoln's Birthday, Labor Day, Election Day, Veterans Day, Thanksgiving Day, Christmas

Day, provided the employee is an employee of the company prior to the scheduled holiday and reports to work the first day following the holiday unless prevented from doing so for legitimate reasons.

GROUP 1: Flagperson, gateperson

GROUP 2: General laborers, chuck tender, handling and distributing drinking water, distributing all tools and supplies of laborers, nipper, powder carrier, magazine tender, warehouse laborers, concrete man, vibrator man, mason tender, mortar man, spraying, brushing and covering of concrete for curing and preservative purposes, traffic striper, scaffold builder, concrete curb and sidewalk form setter; permanent traffic striping and reflective devices, placing and maintenance of all flares, cones, lights, signs, barricades, traffic patterns, and all temporary reflective type materials for traffic control, custodial work, traffic directors, temporary heat or light tenders, tool room, dewatering pump men, pitman, dumpmen, snow removal and firewatch, asphalt man, joint setter, signal person, pipelayer, pipe lining and relining, wellpoints, conduit and duct layer, wire puller, rip rap and dry stone layer, steel rod carrier, core drill, rock splitter, Hilti gun air or electric, jackhammer, bush hammer, pavement breaker, chipping hammer, wagon drill, air track, jib rig, joy drill, gunite and sand blasting, coal passer and other machine operators, power tool operator, sprayer and nozzle man on mulching and seeding machine, all guard rail and fence, all seeding and sod laying, all landscape work, grade checker, all bridge work, walk behind self-propelled power saw, grinder, groover or similar type machine, walk behind tamper and roller of all types, salvage, stripping, wrecking and dismantling laborer (including barman, cutting torch and burner man), sheeting and shoring coming under laborers jurisdiction, bit grinder, operator of form pin puller and drivers, sandblasting, joint and jet sealer, filling and wiring baskets for gabion walls, permanent sign man, median barrier, sta-wall or similar type product, chain saw operator, railroad track laborer, waterproofer, pre-stressed and pre-cast concrete brick, block and stone pavers, power tools used to perform work usually done by laborers, power buggy and pumpcrete operator, fireproof, plaster and caustic pump, asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous materials abatement when protective clothing and equipment is not required, power brush cutter, retention liners, artificial turf, retaining walls, walk behind surface planer, welding related to laborers work, remote controlled equipment normally operated by laborers, all technician work including but not limited to stitching, seaming, heat welding, fireproof sprayer, mortar mixer, concrete finisher, form setter for concrete curbs and flatwork.

Gunite nozzle man, stone cutters, granite stone layer, manhole, catch basin or inlet installing, laser men.

Ground man on milling machine

GROUP 3 Ingersoll Rand heavy duty crawler-master HCMZ, any drill using a 4" or larger bit, asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous material abatement when protective clothing and equipment is required, all working foremen including grade, pipe concrete, clearing, blacktop, drill, paving and blaster etc., Hydraulic drill or similar, forklift for masonry only, Blaster and asphalt screedman

GROUP 4: Asbestos, toxic, lead or hazardous material abatement foreman

For HEAVY & HIGHWAY CLASSIFICATIONS in COLUMBIA COUNTY

(Townships of Greenport, Claverack, Clermont, Germantown, Livingston, Hillsdale, Taghkanic, Gallatin, Copake, Ancram, Philmont and the City of Hudson)

HEAVY & HIGHWAY CLASSIFICATIONS

GROUP 1: Asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous material abatement when protective equipment and clothing are not required

GROUP 2: Asbestos, toxic, bio-remediation, phyto-remediation, lead or hazardous material abatement when protective clothing and equipment is required

For TUNNEL, SHAFT & CAISSON WORK CLASSIFICATIONS

a. PAID HOLIDAYS: New Years Day, President's Day, Memorial

Day, Independence Day, Labor Day, Election Day, Veterans

Day, Thanksgiving Day, Christmas Day

GROUP 1: Laborer, Pit and Dumpman, Chuck Tender, Brakeman and

Powderman;

Miner and all machine men, Safety Miner, all shaft work, caisson work, drilling, blow pipe, all air tools, tugger, scaling, nipper gunniting from pot to nozzle, bit grinder, signal man (top and bottom), shield driven tunnel, mixed face and soft ground liner plate tunnel in free air

LABO0035-001 07/01/2004

FULTON (TWPS OF CAROGA, EPHRATA, OPPENHEIM, AND STRAFORD);

MONTGOMERY (TWPS OF CANAJOHARIE, MINDEN AND PALATINE, ROOT AND

ST. JOHNSVILLE)

Laborers Building Construction

Asbestos Removal............$ 18.50 6.19

Blasters, Form Setters, MotorBuggy Operator (Rider

Type)......................$ 17.50 6.19

Hazardous Waste Removal

Hazardous waste removal includes wetting, stripping, removal, scrapping, vaccuuming, bagging and disposing of all insulation materials, whether they contain asbestos or not, from mechanical systems.........$ 19.00 6.19

HEAVY & HIGHWAY:

GROUP 1:...................$ 20.40 10.14+a

GROUP 2:...................$ 20.60 10.14+a

GROUP 3:...................$ 20.80 10.14+a

GROUP 4:...................$ 21.00 10.14+a

GROUP 5:...................$ 22.40 10.14+a

Laborers....................$ 17.00 6.19

Pipelayers, Motor Mixers, Motor Buggy Operator

(Walk Behind) Power Lift

(Walk Behind)...............$ 17.15 6.19

Wagon Drill Operator........$ 17.40 6.19

Day, Labor Day, Thanksgiving Day and Christmas Day.

GROUP 1: Common Laborers, Flagman, Outboard and Hand boats

GROUP 2: Bull Float, Chain Saw, Concrete aggregate bin, Concrete Bootman, Gin Buggy, Hand or Machine Vibrator, Jackhammer, Mason Tender, Mortar Mixer, Pavement Breaker, Handlers of all steel mesh, Small generators for laborer's tools, Installation of bridge drainage, Pipelayers, Vibrator type rollers, Tamper, Drill doctor, Tail or Screw

Operator on asphalt paver, Water pump operator (1 1/2" and single diaphragm), Nozzle (asphalt, gunnite, seeding and sand blasting), Laborers on chain link fence erection, Rock splitter and power unit, Pusher type concrete saw and all other gas, electric, oil, and air tool operators, Wrecking laborers

GROUP 3: All rock or drilling machine operators (except quarry master and similar type), Acetylene torch operators, and Asphalt paver, Powderman

GROUP 4: Blasterers, Form setters, Stone or Granite Curb setters

GROUP 5: Hazardous waste removal

LABO0157-001 07/01/2009

FULTON (Twps. of Bleeker, Mayfield, Northhampton, Johnstown, Broadalbin and Perth); MONTGOMERY (Twps. of Mohawk, Glen, Charleston, Amsterdam, and Florida); SARATOGA (Twps. of Day, Hadley, Edinburg, Corinth, Moreau, South Glens Falls, Providence, Greenfield, Wilton, Northcumberland, Galway, Milton, Saratoga Springs, Charlton, Ballston, Malta and Clifton

Park); SCHENECTADY and SCHOHARIE COUNTIES.

LABORER

BUILDING:

GROUP 1....................$ 22.88 13.65

GROUP 2....................$ 24.23 13.65

HEAVY & HIGHWAY:

GROUP 1:...................$ 24.34 14.40+a

GROUP 2:...................$ 24.54 14.40+a

GROUP 3:...................$ 24.74 14.40+a

GROUP 4:...................$ 24.94 14.40+a

GROUP 5:...................$ 26.34 14.40+a

LABORER CLASSIFICATIONS

Group 1: Common Laborers

Group 2: Asbestos and Toxic Materials

Commercial projects valued at $800,000 or less and/or industrial projects valued at $100,000 or less, excluding demolition work (the complete razing of structures) 75% of the basic wage scale with full benefits will apply

a. PAID HOLIDAYS: New Years Day, Memorial Day, Independence

Day, Labor Day, Thanksgiving Day, and Christmas Day

LABORER CLASSIFICATIONS

GROUP 1: Common laborers, flagman, outboard & hand boats

GROUP 2: Bull float, chain saw, concrete aggregate bin, concrete bootman, gin buggy, hand or machine vibrator, jackhammer, mason tender, mortar mixer, pavement breaker, handlers of all steel mesh, small generators for laborers' tools, installation of bridge drainage, pipelayers, vibrator type rollers, tamper, drill doctor, tail or screw operator on asphalt paver, water pump operator (1 1/2") and single diaphragm), nozzle (asphalt, gunnite, seeding, and sand blasting), laborers on chain fence erection, rock splitter and power unit, pusher type concrete saw and all other gas, electric, oil, and air tool operators, wrecking

GROUP 3: All rock drilling machine operators (except quarry master and similar type), acetylene torch operator, and asphalt paver, powderman

GROUP 4: Blasterers, form setters, stone or granite curb

LABO0190-001 07/01/2009

ALBANY; RENSSELAER COUNTY, WASHINGTON COUNTY, GREENE COUNTY

(except Catskill Township); COLUMBIA (Twps. of Styvesant, Stockport, Kinderhook, New Lebanon, Canaan, Ghent, Chatham and

Austerlitz). SARATOGA COUNTY (Townships of Stillwater, Halfmoon, Saratoga)

BUILDING:

GROUP 1....................$ 21.81 14.72

GROUP 2....................$ 23.16 14.72

LABORERS CLASSIFICATIONS

GROUP 1: Common Laborers

GROUP 2: Hazardous waste removal Commercial projects valued at $800,000 or less and/or industrial projects valued at

$100,000 or less excluding demolition work, (complete razing of structures) will receive 75% of basic wage scale with full fringes will apply

LABO0190-002 07/01/2009

ALBANY; RENSSELAER; COLUMBIA (Twps. of Stuyvesant, Stockport, Kinderhook, New Lebanon, Cannan, Ghent, Chatham, Austerlitz).

GREENE (except Catskill Township). WASHINGTON COUNTY. SARATAGO

COUNTY (Townships of Stillwater, Halfmoon Saratoga)

HEAVY & HIGHWAY:

GROUP 1:...................$ 23.89 14.85

GROUP 2:...................$ 24.09 14.85

GROUP 3:...................$ 24.29 14.85

GROUP 4:...................$ 24.49 14.85

GROUP 5:...................$ 25.89 14.85

PAID HOLIDAYS: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day.

LABORERS CLASSIFICATIONS

GROUP 1: Common laborers, flagmen, outboard and hand boats

GROUP 2: Bull float, chain saw, concrete aggregated bin, concrete bootman, gin buggy, hand or machine vibrator, jackhammer, mason tender, mortar mixer, pavement breaker, handlers of all steel mesh, small generators for laborers' tools, installation of bridge drainage, pipelayers, vibrator type rollers, tampers, drill doctor, Tail or screw operator on asphalt paver, Water pump operator (1 1/2" and single diaphragm), Nozzle (asphalt, gunnite, seeding, and sand blasting) Laborers on chain link fence erection, rock splitter and power unit, pusher type concrete saw and all other gas, electric, oil, air tool operators, and wrecking

GROUP 3: All rock air drilling machine operators (except quarry master and similar type), acetylene torch operators, and asphalt paver, powderman

GROUP 4: Blasterers, form setters, stone or granite curb

LABO1000-002 06/01/2006

COLUMBIA (Twps. of Ancram, Claverack, Clermont, Copake, Galtin, Germantown, Greenport, Hillsdale, Hudson, Livingston, Philmont, Taconic)

BUILDING

GROUP 1....................$ 25.10 16.10+a

GROUP 2....................$ 25.60 16.10+a

GROUP 3....................$ 27.45 16.10+a

a. PAID HOLIDAYS: New Years Day, Memorial Day, Independence

Day, Labor Day, Thanksgiving Day and Christmas Day

LABORERS CLASSIFICATIONS (BUILDING)

GROUP 1 - All Laborers except those listed in Groups 2, 3 and

GROUP 2 - Shop Stewards

GROUP 3 - Forklift Operator, Drillers, Blasters, Rakers, Laserbeam

* LABO1000-005 05/01/2009

COLUMBIA (Twps. of Greenport, Claverack, Hillsdale, Livingston, Germantown, Taghkanic, Copake, Clermont, Gallatin, Ancram):

GROUP 1....................$ 24.20 18.75+a

GROUP 2....................$ 27.96 18.75+a

GROUP 3....................$ 28.96 18.75+a

LABORERS CLASSIFICATIONS (HEAVY & HIGHWAY)

GROUP 1: Flagperson; Placing and maintenance of all flares, cones, lights, signs, barricades; traffic control custodial work; traffic directors; temporary heat or light tenders;

tool rooms

GROUP 2: General Laborers, Dumpman, Pitman, Concrete man;

Signal man; Pipelayers; Rip rap; Dry stone layer; Jack hammer; Powderman; Highscalers power buggy operator; Steel rod carrier; Vibratory operator; other machine operator;

wrecking; Vibrator operator-compactor; Gunite and sandblasting; Water pump 2" or under; Nipper; Chucker;

Asphalt Workers

GROUP 3: Asphalt raker; Asphalt Screedman; Drillers (all);

Laser Beam Operator; Form Setter/Aligners; Blasters

a. PAID HOLIDAYS: New Years Day, Presidents Day, Good Friday, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Day, November Election Day, Thanksgiving Day, and

Christmas Day

* PAIN0009-005 05/01/2009

Painters:

Lead Abatement Workers, Structural Steel

Zone 1.....................$ 25.34 6.30

Zone 2.....................$ 24.29 8.70

Painters, Drywall

Finishers, Spray

Zone 1.....................$ 24.34 6.30

Zone 2.....................$ 23.29 8.70

Zone #1 Entire counties of ALBANY, FULTON, MONTGOMERY, RENNSELAER, SCHOHARIE, SCHENECTADY AND SARATOGA

ZONE #2 All of WASHINGTON County

* PAIN0009-013 07/01/2009

GLAZIER..........................$ 22.50 13.46

PAIN0009-017 05/01/2009

COLUMBIA AND GREENE COUNTIES

Drywall Finisher............$ 26.39 15.11

Lead Abatement Work.........$ 26.39 15.11

Painter/Paperhanger.........$ 26.39 15.11

Spray Rate..................$ 27.39 15.11

PAIN0806-002 10/01/2008

ALBANY, COLUMBIA, FULTON, GREENE, MONTGOMERY, RENNSELAER,

SCHOHARIE, SCHENECTADY, SARATOGA AND WASHINGTON

Structural Steel and Bridge.$ 45.25 27.58

PLUM0007-001 05/01/2008

ALBANY; COLUMBIA; FULTON; GREENE; MONTGOMERY; RENSSELAER;

SCHENECTADY; SARATOGA (Towns of Charlton, Clifton Park, Galway, Halfmoon, Milton, Stillwater and Waterford)

PLUMBER/PIPEFITTER...............$ 30.31 17.18

PLUM0773-002 05/01/2009

SARATOGA (Remainder of County); WASHINGTON COUNTY:

PLUMBER/PIPEFITTER...............$ 27.80 18.03

ROOF0203-003 06/01/2007

SCHOHARIE COUNTY:

ROOFER, Including Built Up, Composition and Single Ply

Roofs............................$ 21.20 10.34

ROOF0241-001 06/01/2006

ROOFER, Including Built Up, Composition and Single Ply

Roofs............................$ 21.65 9.42

SFNY0669-001 04/01/2008

SPRINKLER FITTER.................$ 29.90 16.30

SHEE0083-001 06/01/2009

Sheet metal worker...............$ 27.81 20.11+a

Day, Labor Day, Thanksgiving Day, Christmas Day. If any of these holidays fall on a Saturday or Sunday, either the preceding Friday or following Monday will be observed as the holiday.

TEAM0294-002 05/01/2006

Truck drivers:

GROUP 1.....................$ 22.27 9.84+a

GROUP 2.....................$ 22.57 9.84+a

a. One week vacation after 1 year; 2 weeks vacation after 5 years.

TRUCK DRIVERS BUILDING CLASSIFICATIONS

GROUP 1: Straight, winch, transit mix on job site, road oilers, dump, panel, pick-up, water and fuel trucks on site

(including nozzle)

GROUP 2: Euclid or similar equipment, lowboy or lowboy trailers

TEAM0294-003 07/01/2009

Truck drivers:

GROUP 1....................$ 25.07 13.95+a

GROUP 2....................$ 25.12 13.95+a

GROUP 3....................$ 25.17 13.95+a

GROUP 4....................$ 25.32 13.95+a

GROUP 5....................$ 25.47 13.95+a

TRUCK DRIVERS CLASSIFICATIONS (HEAVY & HIGHWAY)

GROUP 1: Pick-ups, panel trucks, flatboy material trucks

(straight jobs), single axle dump trucks, dumpsters, receivers, greasers, truck tireman

GROUP 2: Tandems, batch trucks, mechanics

GROUP 3: Semi-trailers, low-boy trucks, asphalt distributor trucks, agitator, mixer trucks and dumpcrete type vehicles, truck mechanic, fuel truck

GROUP 4: Specialized earth moving equipment - euclid type or similar off-highway equipment, where not self-loaded, straddle (ross) carrier, self-contained concrete unit

GROUP 5: Off-highway tandem back dump, twin engine equipment and double hitched equipment where not self-loaded

Day, Labor Day, Thanksgiving Day, Christmas Day, provided the employee works the day before and the day after the holiday.

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses

(29CFR 5.5 (a) (1) (ii)).

In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour

Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the

Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the

Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations

Wage and Hour Division

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator

(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator

U.S. Department of Labor

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative

Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board

U.S. Department of Labor

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

The following have been deleted:

WAGE RATES

(End of Summary of Changes)

File details come from the government source that posted it. Updated .