W912DR26BA001 MID BAY JAMES ISLAND PHASE 1 BID ABSTRACT 2.23.2026.pdf
PDF 1 MB Posted
- Solicitation number
- W912DR26BA001
About this file
This is an Abstract of Offers for Construction document issued by the Baltimore District, Corps of Engineers, for the Mid-Bay James Island Phase 1 Restoration project located in Dorchester County, Maryland. The solicitation number is W912DR26BA001, issued on November 12, 2025, with offers opened on February 19, 2026. The Contracting Officer is Tamara Bonomolo. One amendment was issued to the solicitation.
Five contractors submitted bids: C AND C Joint Venture LLC (No. 1), Trade West Construction Inc. (No. 2), Michels Construction Inc. (No. 3), H&L Contracting LLC (No. 4), and Agate Construction Company, Inc. (No. 5). All bidders submitted bid bonds of $3.0 million and acknowledged the amendment. The project involves comprehensive coastal restoration work including mobilization, turbidity curtain management, pre-placement surveys, and placement of various armor stone sizes (ranging from 50-lb to 3300-lb), quarry run stone, graded aggregate base, dike fill, geotextile materials, settlement pads, and sand stockpile. The Independent Government Estimate totals $122,185,770.06 for the base work. Bidders' total estimated amounts range from $141,581,394.87 (Trade West Construction) to $170,672,200.00 (Agate Construction Company, Inc.). The contract includes an option for seeding the stockpile area (Item 0018), with total base plus options amounts ranging from approximately $122.2 million to $170.7 million depending on the contractor.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
3. DATE OPENED
2/19/2026
4. ISSUING OFFICE Name and title of Certifying Official (Type) Tamara Bonomolo - Contracting Officer
I CERTIFY that I have opened, read, and recorded on this abstract all offers Signature Date Signed received in response to this solicitation.
Contracting Officer: Tamara Bonomolo
5. PROJECT TITLE
8. GOVERNMENT ESTIMATE
(Check A, B or C and complete D, E, and F.)
A. HIRED LABOR
X B. REASONABLE CONTRACT B. Bid Security (Type and Amount) B. Bid Security (Type and Amount) B. Bid Security (Type and Amount)
(Without Profit)
C. REASONABLE CONTRACT C. Amendments Acknowledged C. Amendments Acknowledged C. Amendments Acknowledged
(Including Profit)
7A. 7B. 7C. D. E. F. G. H. I. J. K. L. M. N. O. P.
ITEM DESCRIPTION OF OFFERED ITEM EST. UNIT UNIT ESTIMATED UNIT ESTIMATED UNIT ESTIMATED UNIT ESTIMATED UNIT ESTIMATED UNIT ESTIMATED
No. QUANTITY PRICE AMOUNT IGE PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
All costs in connection with mobilization, turbidity curtain, and demobilization for Contract 1 of the James Island Restoration Project
JOB 3,841,782.03$ 10,780,750.00$ 16,000,000.00$ 21,936,218.00$ 20,000,000.00$ 66,501,967.65$
Pre-placement Survey and Sections, complete as shown on the drawings and specified
JOB 27,434.26$ 748,403.00$ 900,000.00$ 2,030,000.00$ 2,100,000.00$ 10,000,000.00$
0003AA
All costs in connection with the 750-lb armor stone, quarried, shipped and placed
7,426 TON 178.46$ 1,325,243.96$ 130.40$ 968,350.40$ 160.00$ 1,188,160.00$ 144.00$ 1,069,344.00$ 141.00$ 1,047,066.00$ 67.00$ 497,542.00$
0003AB
All costs in connection with the 450-lb armor stone, quarried, shipped and placed
78,144 TON 174.52$ 13,637,690.88$ 129.00$ 10,080,576.00$ 160.00$ 12,503,040.00$ 143.00$ 11,174,592.00$ 155.00$ 12,112,320.00$ 71.00$ 5,548,224.00$
0003AC
All costs in connection with the 50-lb armor stone, quarried, shipped and placed
963 TON 166.79$ 160,618.77$ 126.00$ 121,338.00$ 150.00$ 144,450.00$ 169.00$ 162,747.00$ 200.00$ 192,600.00$ 80.00$ 77,040.00$
0003AD
All costs in connection with the quarry run, quarried, shipped and placed
5,787 TON 214.11$ 1,239,054.57$ 118.70$ 686,916.90$ 150.00$ 868,050.00$ 101.00$ 584,487.00$ 160.00$ 925,920.00$ 57.00$ 329,859.00$
0003AE
All costs in connection with the #1 stone, quarried, shipped and placed
27,156 TON 192.98$ 5,240,564.88$ 107.72$ 2,925,244.32$ 150.00$ 4,073,400.00$ 113.00$ 3,068,628.00$ 126.00$ 3,421,656.00$ 300.00$ 8,146,800.00$
0003AF
All costs in connection with the #3 stone, quarried, shipped and placed
385 TON 182.01$ 70,073.85$ 106.60$ 41,041.00$ 150.00$ 57,750.00$ 154.00$ 59,290.00$ 200.00$ 77,000.00$ 63.00$ 24,255.00$
0003AG
All costs in connection with the #10 stone, quarried, shipped and placed
3,294 CY 274.69$ 904,828.86$ 174.00$ 573,156.00$ 190.00$ 625,860.00$ 144.00$ 474,336.00$ 165.00$ 543,510.00$ 98.00$ 322,812.00$
0003AH
All costs in connection with the Graded Aggregate Base, quarried, shipped and placed
22,610 SY 193.90$ 4,384,079.00$ 50.21$ 1,135,248.10$ 250.00$ 5,652,500.00$ 57.00$ 1,288,770.00$ 50.00$ 1,130,500.00$ 23.00$ 520,030.00$
0003AJ
All costs in connection with the Dike Fill, dredged, shipped and mechanically placed in Zone A
470,381 CY 20.11$ 9,459,361.91$ 17.92$ 8,429,227.52$ 25.00$ 11,759,525.00$ 38.00$ 17,874,487.00$ 22.00$ 10,348,382.00$ 17.00$ 7,996,477.00$
ABSTRACT OF OFFERS - CONSTRUCTION 2. DATE ISSUED1. SOLICITATION NUMBER
Dorchester County, Maryland
Trade West Construction Inc
No. 4
H&L Contracting LLC
Yes
Bid Bond: $3.0M
W912DR26BA001
Mid-Bay James Island Phase 1 Restoration
No. 1
BALTIMORE DISTRICT, CORPS OF ENIGNEERS
2 HOPKINS PLAZA
9. OFFERS
6. NUMBER OF AMENDMENTS ISSUED: One (1)
C And C Joint Ventures LLC
BALTIMORE, MD 21201
B. Bid Security (Type and Amount)
Bid Bond: 20%
C. Amendments Acknowledged
Yes
No. 3
Michels Construction Inc
B. Bid Security (Type and Amount)
Bid Bond: $3.0M
C. Amendments Acknowledged
Yes
No. 2
Bid Bond: $3.0M
Yes
No. 5
Agate Construction Company, Inc
Bid Bond: $3.0M
Yes
23 February 2026
11/12/2025
0003AK
All costs in connection with Type A geotextile, complete as shown on drawings and specified
10,026 SY 28.03$ 281,028.78$ 19.77$ 198,214.02$ 32.00$ 320,832.00$ 66.00$ 661,716.00$ 32.00$ 320,832.00$ 3.75$ 37,597.50$
0003AL
All costs in connection with Type B geotextile, complete as shown on drawings and specified
87,102 SY 8.46$ 736,882.92$ 16.60$ 1,445,893.20$ 32.00$ 2,787,264.00$ 55.00$ 4,790,610.00$ 20.00$ 1,742,040.00$ 4.00$ 348,408.00$
0003AM All costs in connection with seeding the sand dikes 14,470 SY 5.58$ 80,742.60$ 5.00$ 72,350.00$ 10.00$ 144,700.00$ 7.00$ 101,290.00$ 12.00$ 173,640.00$ 7.65$ 110,695.50$
Weir Boxes, all costs in conneciton with the transportation, construction, installation, grading foundation preparation of the weir boxes, pipes and appurtenances as shown on drawings and specified
1 JOB 131,179.93$ 500,000.00$ 500,000.00$ 100,000.00$ 100,000.00$ 600,000.00$ 600,000.00$ ########## 650,000.00$ 300,000.00$ 300,000.00$
All costs in connection with the Settlement Pads specified
7 EA 2,954.48$ 20,681.36$ 3,000.00$ 21,000.00$ 40,000.00$ 280,000.00$ 50,000.00$ 50,000.00$ 25,000.00$ 175,000.00$ 1,550.00$ 10,850.00$
Sand Stockpile, all costs in connection with the sand dredged, shipped and stockpied to elevation 10.0 ft NAVD88 elevation as shown on the drawings and as specified
1,787,201 CY 10.09$ 18,032,858.09$ 8.20$ 14,655,048.20$ 16.87$ 30,150,080.87$ 12.00$ 21,446,412.00$ 7.15$ 12,778,487.15$ 16.50$ 29,488,816.50$
TOTAL ESTIMATED BID AMOUNT 59,574,106.65$ 53,382,756.66$ 87,555,611.87$ 87,672,918.00$ 67,738,953.15$ 130,261,374.15$
ITEM DESCRIPTION OF OFFERED ITEMS ESTIMATED UNIT E. UNIT F. ESTIMATED G. UNIT H. ESTIMATED I. UNIT J. ESTIMATED K. UNIT L. ESTIMATED M. UNIT N. ESTIMATED O. UNIT P. ESTIMATED NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
0013AA
All costs in connection with the 3300-lb armor stone, quarried, shipped and placed from sta 90+00 to 110+00
24,293 TON 183.09$ 4,447,805.37$ 146.59$ 3,561,110.87$ 95.50$ 2,319,981.50$ 140.00$ 3,401,020.00$ 168.00$ 4,081,224.00$ 85.00$ 2,064,905.00$
0013AB
All costs in conneciton with the 250-lb armor stone, quarried, shipped and placed from sta 90+00 to 110+00
9,840 TON 178.95$ 1,760,868.00$ 117.10$ 1,152,264.00$ 105.50$ 1,038,120.00$ 130.00$ 1,279,200.00$ 138.00$ 1,357,920.00$ 62.00$ 610,080.00$
0013AC
All costs in connection with the quarry run stone, quarried, shipped and placed from sta 90+00 to 110+00
16,151 TON 219.66$ 3,547,728.66$ 110.99$ 1,792,599.49$ 95.50$ 1,542,420.50$ 109.00$ 1,760,459.00$ 125.00$ 2,018,875.00$ 68.00$ 1,098,268.00$
0013AD
All costs in connection with the #10 stone, quarried, shipped and placed from sta 90+00 to 110+00
5,422 CY 281.83$ 1,528,082.26$ 154.26$ 836,397.72$ 115.50$ 626,241.00$ 185.00$ 1,003,070.00$ 165.00$ 894,630.00$ 150.00$ 813,300.00$
0013AE
All costs in connection with Type A geotextile, complete as shown on drawings and specified, from sta 90+00 to 110+00
19,036 SY 28.51$ 542,716.36$ 19.77$ 376,341.72$ 20.00$ 380,720.00$ 46.00$ 875,656.00$ 26.00$ 494,936.00$ 3.65$ 69,481.40$
0014AA
All costs in connection with the 3300-lb armor stone, quarried, shipped and placed from sta 110+00 to 130+00
26,098 TON 183.08$ 4,778,021.84$ 146.59$ 3,825,705.82$ 105.50$ 2,753,339.00$ 140.00$ 3,653,720.00$ 168.00$ 4,384,464.00$ 85.00$ 2,218,330.00$
0014AB
All costs in connection with the 250-lb armor stone, quarried, shipped, and placed from sta 110+00 to 130+00
10,656 TON 178.95$ 1,906,891.20$ 117.10$ 1,247,817.60$ 95.50$ 1,017,648.00$ 130.00$ 1,385,280.00$ 138.00$ 1,470,528.00$ 58.00$ 618,048.00$
0014AC
All costs in connection with the quarry run stone, quarried, shipped and placed from sta 110+00 to 130+00
21,477 TON 219.65$ 4,717,423.05$ 110.99$ 2,383,732.23$ 85.50$ 1,836,283.50$ 109.00$ 2,340,993.00$ 125.00$ 2,684,625.00$ 54.00$ 1,159,758.00$
0014AD
All costs in connection with the #10 stone, quarried, shipped and placed from sta 110+00 to 130+00
5,791 CY 281.82$ 1,632,019.62$ 154.26$ 893,319.66$ 105.50$ 610,950.50$ 185.00$ 1,071,335.00$ 165.00$ 955,515.00$ 150.00$ 868,650.00$
0014AE
All costs in connection with the Type A geotextile, complete as shown on drawings and specified, from sta 110+00 to 130+00
20,156 SY 28.51$ 574,647.56$ 19.77$ 398,484.12$ 20.00$ 403,120.00$ 46.00$ 927,176.00$ 26.00$ 524,056.00$ 3.00$ 60,468.00$
Independent Government Estimate C AND C Joint Venture LLC H&L Contracting LLC
No. 4
Dorchester County, Maryland Mid Bay James Island Phase 1 Restoration
No. 2 No. 3
Trade West Construction Michels Construction Inc
No. 5IGE No. 1
Agate Construction Company, Inc
2. PROJECT TITLE
ITEM DESCRIPTION OF OFFERED ITEMS ESTIMATED UNIT E. UNIT F. ESTIMATED G. UNIT H. ESTIMATED I. UNIT J. ESTIMATED K. UNIT L. ESTIMATED M. UNIT N. ESTIMATED O. UNIT P. ESTIMATED
NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
0007AA
All costs in connection with the 2300-lb armor stone, quarried, shipped and placed from Sta 410+00 to 430+00
17,309 TON 183.09$ 3,169,104.81$ 134.70$ 2,331,522.30$ 105.50$ 1,826,099.50$ 139.00$ 2,405,951.00$ 160.00$ 2,769,440.00$ 80.00$ 1,384,720.00$
0007AB
All costs in connection with the quarry run stone, quarried, shipped and placed from sta 410+00 to 430+00
13,986 TON 219.66$ 3,072,164.76$ 107.54$ 1,504,054.44$ 95.50$ 1,335,663.00$ 109.00$ 1,524,474.00$ 125.00$ 1,748,250.00$ 60.00$ 839,160.00$
0007AC
All costs in connection with the #10 stone, quarried, shipped and placed from Sta 410+00 to 430+00
4,538 CY 281.85$ 1,279,035.30$ 150.57$ 683,286.66$ 155.60$ 705,659.00$ 185.00$ 839,530.00$ 165.00$ 748,770.00$ 150.00$ 680,700.00$
0007AD
All costs in connection with Type A geotextile, complete as shown on drawings and specified, from Sta 410+00 to 430+00
16,393 SY 28.51$ 467,364.43$ 19.77$ 324,089.61$ 24.00$ 393,432.00$ 46.00$ 754,078.00$ 28.00$ 459,004.00$ 3.00$ 49,179.00$
0008AA
All costs in connection with the 2300-lb armor stone, quarried, shipped and placed from Sta 430+00 to 452+35
17,723 TON 183.09$ 3,244,904.07$ 134.70$ 2,387,288.10$ 105.50$ 1,869,776.50$ 139.00$ 2,463,497.00$ 160.00$ 2,835,680.00$ 80.00$ 1,417,840.00$
0008AB
All costs in connection with the quarry run stone, quarried, shipped and placed from sta 430+00 to 452+35
15,654 TON 219.66$ 3,438,557.64$ 107.54$ 1,638,431.16$ 90.50$ 1,416,687.00$ 109.00$ 1,706,286.00$ 125.00$ 1,956,750.00$ 60.00$ 939,240.00$
0008AC
All costs in connection with the #10 stone, quarried, shipped and placed from sta 430+00 to 452+35
5,052 CY 281.83$ 1,423,805.16$ 150.57$ 760,679.64$ 95.50$ 482,466.00$ 185.00$ 934,620.00$ 165.00$ 833,580.00$ 110.00$ 555,720.00$
0008AD
All costs in conneciton with Type A geotextile, complete as shown on drawings and specified, from sta 430+00 to 452+35
18,240 SY 28.51$ 520,022.40$ 19.77$ 360,604.80$ 20.00$ 364,800.00$ 46.00$ 839,040.00$ 28.00$ 510,720.00$ 3.65$ 66,576.00$
Trade West Construction
No. 2
Dorchester County, Maryland Mid Bay James Island Phase 1 Restoration
No. 3 No. 4
Michels Construction Inc H&L Contracting LLC
No. 5IGE No. 1
Agate Construction Company, IncIndependent Government Estimate C AND C Joint Venture LLC
ITEM DESCRIPTION OF OFFERED ITEMS ESTIMATED UNIT E. UNIT F. ESTIMATED G. UNIT H. ESTIMATED I. UNIT J. ESTIMATED K. UNIT L. ESTIMATED M. UNIT N. ESTIMATED O. UNIT P. ESTIMATED
0009AA
All costs in connection with the 3300-lb armor stone, quarried, shipped and placed from sta 0+00 to 22+50
21,498 TON 183.08$ 3,935,853.84$ 141.28$ 3,037,237.44$ 95.50$ ########### 140.00$ 3,009,720.00$ 168.00$ 3,611,664.00$ 85.00$ 1,827,330.00$
0009AB
All costs in conneciton with the 250-lb armor stone, quarried, shipped and placed from sta 0+00 to 22+50
8,393 TON 178.96$ 1,502,011.28$ 113.35$ 951,346.55$ 95.50$ 801,531.00$ 130.00$ 1,091,090.00$ 138.00$ 1,158,234.00$ 62.00$ 520,366.00$
0009AC
All costs in connection with the quarry run stone, quarried, shipped and placed from sta 0+00 to 22+50
2,985 TON 219.71$ 655,834.35$ 107.54$ 321,006.90$ 85.50$ 255,217.50$ 109.00$ 325,365.00$ 125.00$ 373,125.00$ 58.00$ 173,130.00$
0009AD
All costs in connection with the #10 stone, quarried, shipped and placed from sta 0+00 to 22+50
4,947 CY 281.83$ 1,394,213.01$ 150.57$ 744,869.79$ 125.50$ 620,848.50$ 185.00$ 915,195.00$ 165.00$ 816,255.00$ 110.00$ 544,170.00$
0009AE
All costs in connection with Type A geotextile, complete as shown on drawings and specified, from sta 0+00 to 22+50
17,959 SY 28.51$ 512,011.09$ 19.77$ 355,049.43$ 20.00$ 359,180.00$ 46.00$ 826,114.00$ 28.00$ 502,852.00$ 3.65 65,550.35$
0010AA
All costs in connection with the 3300-lb armor stone, quarried, shipped and placed from sta 27+50 to 50+00
24,965 TON 183.09$ 4,570,841.85$ 141.28$ 3,527,055.20$ 95.50$ ########### 140.00$ 3,495,100.00$ 168.00$ 4,194,120.00$ 85.00$ 2,122,025.00$
0010AB
All costs in connection with the 250-lb armor stone, quarried, shipped, and placed from sta 27+50 to 50+00
9,930 TON 178.96$ 1,777,072.80$ 113.35$ 1,125,565.50$ 105.50$ ########### 130.00$ 1,290,900.00$ 138.00$ 1,370,340.00$ 62.00$ 615,660.00$
0010AC
All costs in connection with the quarry run stone, quarried, shipped and placed from sta 27+50 to 50+00
9,901 TON 219.67$ 2,174,952.67$ 107.54$ 1,064,753.54$ 85.50$ 846,535.50$ 109.00$ 1,079,209.00$ 125.00$ 1,237,625.00$ 58.00$ 574,258.00$
0010AD
All costs in connection with the #10 stone, quarried, shipped and placed from sta 27+50 to 50+00
5,644 CY 281.84$ 1,590,704.96$ 150.57$ 849,817.08$ 105.50$ 595,442.00$ 185.00$ 1,044,140.00$ 165.00$ 931,260.00$ 110.00$ 620,840.00$
0010AE
All costs in connection with the Type A geotextile, complete as shown on drawings and specified, from sta 27+50 to 50+00
20,077 SY 28.51$ 572,395.27$ 19.77$ 396,922.29$ 20.00$ 401,540.00$ 46.00$ 923,542.00$ 28.00$ 562,156.00$ 3.00$ 60,231.00$
Dorchester County, Maryland Mid Bay James Island Phase 1 Restoration
No. 4
Michels Construction Inc H&L Contracting LLC
IGE No. 1
Independent Government Estimate C AND C Joint Venture LLC Trade West Construction
No. 2 No. 3 No. 5
Agate Construction Company, Inc
ITEM DESCRIPTION OF OFFERED ITEMS ESTIMATED UNIT E. UNIT F. ESTIMATED G. UNIT H. ESTIMATED I. UNIT J. ESTIMATED K. UNIT L. ESTIMATED M. UNIT N. ESTIMATED O. UNIT P. ESTIMATED
0011AA
All costs in connection with the 3300-lb armor stone, quarried, shipped and placed from sta 50+00 to 70+00
24,229 TON 183.09$ 4,436,087.61$ 141.28$ 3,423,073.12$ 95.50$ 2,313,869.50$ 140.00$ 3,392,060.00$ 168.00$ 4,070,472.00$ 85.00$ 2,059,465.00$
0011AB
All costs in conneciton with the 250-lb armor stone, quarried, shipped and placed from sta 50+00 to 70+00
9,788 TON 178.96$ 1,751,660.48$ 113.35$ 1,109,469.80$ 95.50$ 934,754.00$ 130.00$ 1,272,440.00$ 138.00$ 1,350,744.00$ 62.00$ 606,856.00$
0011AC
All costs in connection with the quarry run stone, quarried, shipped and placed from sta 50+00 to 70+00
15,300 TON 219.67$ 3,360,951.00$ 107.54$ 1,645,362.00$ 85.50$ 1,308,150.00$ 109.00$ 1,667,700.00$ 125.00$ 1,912,500.00$ 58.00$ 887,400.00$
0011AD
All costs in connection with the #10 stone, quarried, shipped and placed from sta 50+00 to 70+00
5,408 CY 281.84$ 1,524,190.72$ 150.57$ 814,282.56$ 105.50$ 570,544.00$ 185.00$ 1,000,480.00$ 165.00$ 892,320.00$ 110.00$ 594,880.00$
0011AE
All costs in connection with Type A geotextile, complete as shown on drawings and specified, from sta 50+00 to 70+00
19,001 SY 28.51$ 541,718.51$ 19.77$ 375,649.77$ 20.00$ 380,020.00$ 46.00$ 874,046.00$ 26.00$ 494,026.00$ 3.00$ 57,003.00$
0012AA
All costs in connection with the 3300-lb armor stone, quarried, shipped and placed from sta 70+00 to 90+00
23,262 TON 183.09$ 4,259,039.58$ 146.59$ 3,409,976.58$ 95.50$ 2,221,521.00$ 140.00$ 3,256,680.00$ 168.00$ 3,908,016.00$ 85.00$ 1,977,270.00$
0012AB
All costs in connection with the 250-lb armor stone, quarried, shipped, and placed from sta 70+00 to 90+00
9,357 TON 178.95$ 1,674,435.15$ 117.10$ 1,095,704.70$ 85.50$ 800,023.50$ 130.00$ 1,216,410.00$ 138.00$ 1,291,266.00$ 62.00$ 580,134.00$
0012AC
All costs in connection with the quarry run stone, quarried, shipped and placed from sta 70+00 to 90+00
12,818 TON 219.65$ 2,815,473.70$ 110.99$ 1,422,669.82$ 75.50$ 967,759.00$ 109.00$ 1,397,162.00$ 125.00$ 1,602,250.00$ 72.50$ 929,305.00$
0012AD
All costs in connection with the #10 stone, quarried, shipped and placed from sta 70+00 to 90+00
5,211 CY 281.85$ 1,468,720.35$ 154.26$ 803,848.86$ 115.50$ 601,870.50$ 185.00$ 964,035.00$ 165.00$ 859,815.00$ 150.00$ 781,650.00$
0012AE
All costs in connection with the Type A geotextile, complete as shown on drawings and specified, from sta 70+00 to 90+00
18,405 SY 28.51$ 524,726.55$ 19.77$ 363,866.85$ 20.00$ 368,100.00$ 46.00$ 846,630.00$ 26.00$ 478,530.00$ 3.65$ 67,178.25$
Agate Construction Company, IncIndependent Government Estimate C AND C Joint Venture LLC Dorchester County, Maryland
Mid Bay James Island Phase 1 Restoration Trade West Construction Michels Construction Inc H&L Contracting LLC
2. PROJECT TITLE
ITEM DESCRIPTION OF OFFERED ITEMS ESTIMATED UNIT E. UNIT F. ESTIMATED G. UNIT H. ESTIMATED I. UNIT J. ESTIMATED K. UNIT L. ESTIMATED M. UNIT N. ESTIMATED O. UNIT P. ESTIMATED NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
0015AA
All costs in connection with the 2300-lb armor stone, quarried, shipped and placed from sta 130+00 to 150+00
21,204 TON 183.09$ 3,882,240.36$ 139.70$ 2,962,198.80$ 95.50$ 2,024,982.00$ 139.00$ 2,947,356.00$ 160.00$ 3,392,640.00$ 80.00$ ###########
0015AB
All costs in connection with the quarry run stone, quarried, shipped and placed from sta 130+00 to 150+00
26,483 TON 219.66$ 5,817,255.78$ 110.99$ 2,939,348.17$ 95.50$ 2,529,126.50$ 109.00$ 2,886,647.00$ 125.00$ 3,310,375.00$ 54.00$ ###########
0015AC All costs in connection with the #10 stone, quarried, shipped and placed, from sta 130+00 to 150+00
5,426 CY 281.83$ 1,529,209.58$ 154.26$ 837,014.76$ 95.50$ 518,183.00$ 185.00$ 1,003,810.00$ 165.00$ 895,290.00$ 150.00$ 813,900.00$
0015AD
All costs in connection with Type A geotextile, complete as shown on drawings and specified, from sta 130+00 to 150+00
19,083 SY 28.51$ 544,056.33$ 19.77$ 377,270.91$ 20.00$ 381,660.00$ 46.00$ 877,818.00$ 28.00$ 534,324.00$ 3.00$ 57,249.00$
0016AA
All costs in connection with 2300-lb armor stone, quarried, shipped and placed from sta 150+00 to 170+00
15,274 TON 183.09$ 2,796,516.66$ 139.70$ 2,133,777.80$ 105.50$ 1,611,407.00$ 139.00$ 2,123,086.00$ 160.00$ 2,443,840.00$ 80.00$ ###########
0016AB
All costs in connection with the quarry run stone, quarried, shipped and placed from sta 150+00 to 170+00
11,441 TON 219.67$ 2,513,244.47$ 110.99$ 1,269,836.59$ 95.50$ 1,092,615.50$ 109.00$ 1,247,069.00$ 125.00$ 1,430,125.00$ 68.00$ 777,988.00$
0016AC All costs in connection with the #10 stone, quarried, shipped and placed from sta 150+00 to 170+00
4,305 CY 281.84$ 1,213,321.20$ 154.26$ 664,089.30$ 95.50$ 411,127.50$ 185.00$ 796,425.00$ 165.00$ 710,325.00$ 150.00$ 645,750.00$
0016AD
All costs in connection with Type A geotextile, complete as shown on drawings and specified, from sta 150+00 to 170+00
15,711 SY 28.51$ 447,920.61$ 19.77$ 310,606.47$ 20.00$ 314,220.00$ 46.00$ 722,706.00$ 28.00$ 439,908.00$ 3.65$ 57,345.15$
No. 4No. 2 OFFERS (Continued)
Dorchester County, Maryland Mid Bay James Island Phase 1 Restoration
No. 3
Trade West Construction Michels Construction Inc
No. 5IGE No. 1
Agate Construction Company, IncIndependent Government Estimate C AND C Joint Venture LLC H&L Contracting LLC
ITEM DESCRIPTION OF OFFERED ITEMS ESTIMATED UNIT E. UNIT F. ESTIMATED G. UNIT H. ESTIMATED I. UNIT J. ESTIMATED K. UNIT L. ESTIMATED M. UNIT N. ESTIMATED O. UNIT P. ESTIMATED
0017AA
All costs in connection with the 2300-lb armor stone, quarried, shipped, and placed from sta 170+00 to 185+00
11,231 TON 183.09$ 2,056,283.79$ 139.70$ 1,568,970.70$ 115.50$ 1,297,180.50$ 139.00$ 1,561,109.00$ 160.00$ 1,796,960.00$ 80.00$ 898,480.00$
0017AB
All costs in connection with the quarry run stone, quarried, shipped and placed from sta 170+00 to 185+00
8,412 TON 219.66$ 1,847,779.92$ 110.99$ 933,647.88$ 95.50$ 803,346.00$ 109.00$ 916,908.00$ 125.00$ 1,051,500.00$ 54.00$ 454,248.00$
0017AC
All costs in connection with the connection with the #10 stone, quarried, shipped and placed from sta 170+00 to 185+00
3,144 CY 281.82$ 886,042.08$ 154.26$ 484,993.44$ 125.50$ 394,572.00$ 185.00$ 581,640.00$ 165.00$ 518,760.00$ 150.00$ 471,600.00$
0017AD
All costs in connection with Type A geotextile, complete as shown on drawings and specified, from sta 170+00 to 185+00
11,510 SY 28.51$ 328,150.10$ 19.77$ 227,552.70$ 20.00$ 230,200.00$ 46.00$ 529,460.00$ 28.00$ 322,280.00$ 3.65$ 42,011.50$
Option 12. All costs in connection with seeding the stockpile area.
277,003 SY 5.43$ 1,504,126.29$ 2.72$ 753,448.16$ 6.00$ 1,662,018.00$ 2.00$ 554,006.00$ 5.00$ 1,385,015.00$ 2.40$ 664,807.20$
168,034,311.08$ 122,185,770.06$ 141,581,394.87$ 163,474,361.00$ 148,316,832.15$ 170,672,200.00$
Dorchester County, Maryland Mid Bay James Island Phase 1 Restoration
No. 5IGE No. 1
Agate Construction Company, Inc
No. 4
Independent Government Estimate C AND C Joint Venture LLC H&L Contracting LLC
No. 2 No. 3
Trade West Construction Michels Construction Inc
Total Base Plus Options Amount
| 2026-02-23T14:50:41-0500 | |
| BONOMOLO.TAMARA.C.1405091751 |
File details come from the government source that posted it. Updated .