PATTON HALL NEW STRATEGIC ENGAGEMENT PLATFORM, JOINT BASE MYER-HENDERSON HALL, VA.
Solicitation number
W912DR25R17WQ
Issued by

About this file

This document is a Draft Request for Proposal (RFP) for the Patton Hall Strategic Engagement Platform project located at Joint Base Myer-Henderson Hall in Arlington, Virginia. The project involves demolishing the existing Patton Hall and constructing a new 70,600-square-foot multi-purpose facility designed to serve as a strategic engagement center for the U.S. Army, hosting events such as promotions, weddings, retirements, and memorial services while also providing a venue for inter-agency collaboration and leadership outreach.

The project requires a design-build approach with specific technical requirements, including achieving LEED Silver certification, complying with antiterrorism and force protection standards, and implementing comprehensive interior design and furnishings. The facility will feature modern amenities like a full kitchen, conference spaces, audio-visual capabilities, and a drop-off area for VIPs and buses. The design must respect the historical context of the Fort Myer National Historic District while providing a contemporary, functional space. Key design considerations include sustainability, cybersecurity, accessibility, and integration with the existing base infrastructure. The project is anticipated to have a budget between $50-100 million and is expected to be completed under a Firm-Fixed-Price contract by the U.S. Army Corps of Engineers Baltimore District.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Army Corps of Engineers

Baltimore District

CONSTRUCTION SPECIFICATIONS AND DESIGN CRITERIA

PATTON HALL STRATEGIC ENGAGEMENT

PLATFORM

JOINT BASE MYER-HENDERSON HALL, VA

REQUEST FOR PROPOSAL. xxxxx-xx-x-xxx

CONTRACT NO. xxxxxxx

DATE: NOVEMBER 2025

DRAFT

This page intentionally left blank.

i | P a g e

TABLE OF CONTENTS

1. PROJECT DESCRIPTION

2. SCOPE

3. SITE ANALYSIS

4. APPLICABLE CRITERIA

5. FUNCTIONAL REQUIREMENTS

A10 FOUNDATIONS

B10 SUPERSTRUCTURE

B20 EXTERIOR ENCLOSURE

B30 ROOFING

C10 INTERIOR CONSTRUCTION

C20 STAIRS

C30 INTERIOR FINISHES

D10 CONVEYING

D20 PLUMBING

D30 HVAC

D40 FIRE PROTECTION

D50 ELECTRICAL

E10 EQUIPMENT

E20 FURNISHINGS

F10 SPECIAL CONSTRUCTION

F20 SELECTIVE BUILDING DEMOLITION

G10 SITE PREPARATION

G20 SITE IMPROVEMENTS

G30 SITE CIVIL/MECHANICAL UTILITIES

G40 SITE ELECTRICAL UTILITIES

APPENDICES

APPENDIX A – PROGRAM REQUIREMENTS

- Program Overview

- Program Summary

- Room Data Sheets

- Space Adjacency Diagrams

- Finishes & FF&E Examples

- Owner’s Project Requirements

APPENDIX B – SITE PLANS

APPENDIX C – SITE INFORMATION

- Site Categorization Memo

- Geotechnical Report

- Soil Investigation Report

- SWM Requirements – Open Green Space

- ASCE Hazardous Report ii | P a g e

APPENDIX D – UTILITY INFORMATION

- JBM-HH Existing Utility GIS

- Utility Bills

- Dominion Load Letter

- Power Reliability Letter

- Fire Hydrant Flow Tests

- Guardhouse FPE Email

- Guardhouse FPE Email 2

- Fire Pump for Patton Hall Email

APPENDIX E – RECORD DRAWINGS

- Current Floor Plans with Room Names

- As Builts B214 HVAC 1994

- As Builts B214 Loading Dock 2012

- Zip File of Building 214 Photos (upon request)

APPENDIX F – BUILDING INFORMATION

- HAZMAT Survey Report_20250827

- HAZMAT Report_20190315

- HAZMAT Reports_Multiyears

- Real Property Records_B214

APPENDIX G – EXISTING FACILITY PHOTOGRAPHS

- Architectural Survey

- Historical Presentation

- Site Notes

- Zip File of Photos (upon request)

APPENDIX H – CONSULTING AGENCY COORDINATION

- Programmatic Agreement

- B214 Historic Report

- Patton Hall Tree Survey Report

- Cultural Resources Report

- Photographs

APPENDIX I – INSTALLATION DESIGN GUIDANCE

- Historic Design Guidelines_20170328

- Real Property Vision Plan

- Interactive 5933 Groups 13, 14, 18, 1930s Quarters

- Interactive 5933 Group 17 Quarters 317

APPENDIX J – TECHNICAL OUTLINE SPECIFICATIONS

iii | P a g e

ACRONYM LIST

ACRONYM MEANING ACRONYM MEANING

ABA Architectural Barriers Act LAN Local Area Network AC Air conditioning lbs pounds ADA Americans with Disabilities Act LCCA Life-Cycle Cost Analysis A/E Architectural and Engineering LEED Leadership in Energy and

Environmental Design AHC Architectural Hardware Consultant LID Low Impact Development AV Audiovisual LOW Limits of Work Ave Avenue m meters AWI Architectural Woodwork Institute MAU Make-up air unit AWWA American Water Works Association MDF Medium-density fiberboard BEAP Base Exterior Architectural Plan mils one-thousandth of an inch BMP Best Management Practices mm millimeter BOD Beneficial Occupancy Date MPI Master Painter Institute BPA Blanket Purchase Agreements MUTCD Manual on Uniform Traffic Control

Devices BVA Best value analysis NACE National Association of Colleges and

Employers BVD Best value determination NCIDQ National Council for Interior Design

Qualification C Celsius NCPC National Counterproliferation Center CAC Ceiling Attenuation Class NEC National Electrical Code/Network

Enterprise Center CCTV Closed-Circuit-Televisions NIPRNET Non-classified Internet Protocol Router

Network CDC Certified Door Consultant NLEB Northern long-eared bat CF/CI Contractor Furnished, Contractor

Installed NRC Noise Reduction Coefficient

CH Chapter OA Outside air CID Comprehensive Interior Design OSP Outside Plant CMU Concrete Masonry Units PCASE Pavement-Transportation Computer

Assisted Structural Engineering COR Contracting Officer Representative PCC Portland cement concrete CRF Condensation Resistance Factor PDA Pile Driver Analyzer CRM Cultural Resources Manager pH potential of hydrogen CRREL Cold Regions Research and Equipment

Laboratory POC point of contact dBA A-weighted decibels PROD Permits of Decision

DBT Design Basis Threat psf pounds per square foot DDC Direct Digital Control psig Pounds per square inch gauge DLA Defense Logistics Agency PVC polyvinyl chloride DOAS Dedicated Outdoor Air System PVF2 polyvinylidene fluoride DoD Department of Defense Rd Road DOR Designer of Record RFP Request for proposal DPW Directorate of Public Works RMSD Roofing materials and systems directory DWV drain waste vent SDDCTEA Military Surface Deployment and

Distribution Command Transportation Engineering Agency e.g. for example sf square feet EHC Electrified Hardware Consultant SHGC Solar Heat Gain Coefficients iv | P a g e

EIFS Exterior Insulation Finish System SHS State Highway specifications EISA Energy Security and Independence Act SID Structural Interior Design ER Engineering Regulation STC Sound Transmission Class ESA Endangered Species Act SWRI Sealant, Waterproofing & Restoration

Institute etc. and so forth TAA Trade Agreement Act EUI Energy Use Index TBD to be determined FF&E Furniture, Fixtures & Equipment TCB tri-colored bat FM Factory Mutual TCNA Tile Council of North America ft feet TR Telecommunications room Ft-C foot-candle TSS Total Suspended Solids GFGI Government Furnished, Government

Installed TV Television gpm gallons per minute UNICOR Federal Prison Industries, Inc GSA General Services Administration US United States GWB Gypsum Wallboard USACE United States Army Corps of Engineers HC Heavy Commercial VAV Variable Air Volume HIPAC High Performance Architectural

Coatings VDEQ Virginia Department of Environmental

Quality HPL High Pressure Laminate VIP very important person ICF Insulated Concrete Forms VLT Visible Light Transmission IDG Installation Design Guide VTC Video teleconferencing IEQ Indoor environmental quality VOC volatile organic compounds IT Information/Technology VPDES Virginia Pollutant Discharge Elimination

System ITN Information Technology Node WG Washington Gas JBM-HH Joint Base Myer – Henderson Hall

[Title]

5 | P a g e

CH 01 – PROJECT DESCRIPTION

JOINT BASE MYER-

HENDERSON HALL

1. PROJECT DESCRIPTION

1.1 OBJECTIVES

MILITARY FACILITY CIVILIAN FACILITY

STRATEGIC ENGAGEMENT PLATFORM CONFERENCE CENTER

U.S. Army's objective is that the building will have a 50-year useful design life before a possible reuse, re-purpose or renovation requirement, to include normal sustainment, restoration, and modernization activities. Therefore, the design and construction should provide an appropriate level of quality to ensure continued use of the facility over that time-period with the application of reasonable preventive maintenance and repairs that would be industry-acceptable to a major civilian sector project OWNER.

Site infrastructure will have at least a 50-year life expectancy with industry-accepted maintenance and repair cycles.

The government is required by Public Law 102-486, Executive Order 13123, and Federal Energy Act 2005 to design and construct facilities in an energy conserving manner while considering life cycle cost over the life of the facilities.

Develop project site for efficiency and to convey a sense of unity or connectivity with the adjacent buildings and with the Installation as a whole.

Requirements stated in this contract are minimums. Innovative, creative, and life cycle cost effective solutions, which meet or exceed these requirements are encouraged. Further, the OFFEROR is encouraged to seek solutions that will expedite construction and shorten the schedule. The intent of the Government is to emphasize the placement of funds into functional/operational requirements. Materials and methods should reflect this by choosing the lowest Type of Construction allowed by code for this occupancy/project allowing the funding to be reflected in the quality of interior/exterior finishes and systems selected.

1.2 SECTION ORGANIZATION

This Section is organized under 5 major chapters.

• Chapter 1 - Defines project objectives and provide a comparison between military facilities and comparable “civilian” type buildings.

• Chapter 2 - Describes scope of the project.

• Chapter 3 - Describes site analysis.

• Chapter 4 - Lists applicable industry and government design criteria, generally applicable to all facility types, unless otherwise indicated in the Section. It is not an all-inclusive list. Other industry and government standards may also be used, where necessary to produce professional designs, unless they conflict with those listed.

• Chapter 5 - Provides general room requirements.

6 | P a g e

CH 02 - SCOPE

2. SCOPE

The project consists of designing and constructing the new Patton Hall – Strategic Engagement Platform (SEP). This project replaces the existing Patton Hall which has been damaged beyond repair. The new facility square footage will be equal to or less than the building square footage to be demolished which is 70,600 square feet (SF). Minimum program space requirements are defined in the Program Requirement provided in Appendix A. The facility configuration and placement must be within the defined Limits of Work (LOW) as shown on CS100 – Site Plan Limits of Work in Appendix B.

The new facility will serve as the heart and embodiment of the U.S. Army’s longstanding tradition of leadership excellence. Patton Hall, for years, provided a gathering place for the Army. This new center will continue to be both an integral hub for internal community engagement, and a prominent platform for external strategic outreach in support of U.S. Army leadership goals.

Within the U.S. Army, the facility will provide a distinguished, ceremonial setting for significant milestones in the lives of soldiers and officers, including promotions, commissions, weddings, retirements, and memorial services. The facility must have a design language that respects both joyous and somber occasions, and which can flexibly accommodate a constantly rotating range of event types.

External to the service, the venue will serve as the central showcase of U.S. Army leadership. It will be the U.S. Army’s primary center to build inter-agency goodwill while promoting U.S. Army leadership’s strategic vision, policies, and culture. As such, the new facility must present an environment of hospitality, respect, cooperation, and unity that extends to other branches and agencies.

Where possible, these goals should be accomplished through thoughtful, comprehensive consideration of user experience, procession, programming, massing, and daylighting. The building’s heritage, permanence, and respectability should be embodied in the building itself rather than relying solely on transitory elements such as finishes and artificial lighting. This attentive approach to fundamentals will ensure that the facility remains hallowed ground for generations to come.

Provide compliance with Department of Defense (DoD) Minimum Antiterrorism for Building standards.

Comprehensive building and furnishings related interior design services are required. Follow the guidelines for the design and treatment of historic properties. Provide Access for individuals with disabilities Architectural Barriers Act (ABA). Incorporate Cyber Security Measures. Design and achieve Sustainability/Energy measures. Provide facilities for a minimum life span of 50 years in accordance with DoD's Unified Facilities Criteria (UFC 1-200-02) including energy efficiencies, building envelope and integrated building systems. All structures must comply with the UFCs, Federal, State, installation and local standards. Where conflict exists between the standards, the most stringent requirements will govern.

2.1 PROJECT BUILDINGS

2.1.1 BUILDING 214 – PATTON HALL

Building 214 at Joint Base Myer-Henderson Hall was constructed in 1896, with expansions in 1957 and 1968. It currently serves as a consolidated club for personnel of all ranks and their guests at Joint Base Myer-Henderson Hall. The building is a contributing element to the Fort Myer National Historic District and a National Historic Landmark. The building is a historic property per 36CFR§800.16 as documented in the Program Agreement (PA) due to its association with individuals such as former base commander George Patton. Its proximity to Washington DC enables Patton Hall to be used as a conferencing center and events venue for the Greater Washington DC Area, including Arlington National Cemetery and senior military leadership.

The original building 214 was constructed as an administration building in 1896 with additions to the building completed in 1910 and 1955. The administration building was enjoined with Building 215, an

7 | P a g e adjacent late 19th century guard house/jail house, in the 1960s, to form what is today referred to as 'Patton Hall. It is a two-story, masonry-constructed building that is capped by a slate-clad hipped roof. The foundation is clad with stone veneer, and the exterior walls are faced with brick laid in running bond. The exterior walls are pierced by 2/2, double-hung wood windows. The windows all have stone sills and brick lintels.

The south (front) elevation has a two-story projecting entry pavilion addition constructed in the 1990s that is capped by a slate clad hipped roof. The first floor of the pavilion contains modern mechanical glass doors with one-light, wood sidelights. The main entrance is sheltered under a hipped roof porch and covered walk, with Tuscan columns, which wraps around the entry pavilion. On the second story of the pavilion above the main entrance is a paired window with a semicircular transom.

A two-story, brick-faced, flat-roof addition was constructed onto the northeast side of the building in the 1950s. A two-story brick, flat roof addition and a one-story brick, flat-roof addition was constructed between the historic buildings and onto the south end of the building’s original main block in the 1960s, west of the entry pavilion. The west end of the 1960s addition is enjoined with Building 215 a one-and-half story 1896 building that originally functioned as a “Guardhouse” and forms what is today referred to as “Patton Hall”.

A site visit and concept design charrette conducted in 2023 identified that many facility systems were either failed or nearing failure, and that spatial arrangements did not comply with current codes. Work classifications and alternative solutions were considered, initially focusing on repairing the existing facility. During the charrette, programmatic changes progressed, but cost estimates were significantly above the expected budget. Due to the limited site area, the proposed three-story building required compliance with UFC 4-010-01, Standard 6, Progressive Collapse, which applied to new construction or major alterations and contributed to higher costs. Historic preservation requirements also added to expenditures.

After evaluating expenses and benefits related to preserving parts of the historic structure, renovation plans were discontinued. A new facility will be built to replace the original building, intended to serve as a modern venue for very important people (VIP) events and functions.

2.1.2 BUILDING 214 – GUARDHOUSE

The Guardhouse is a one-story building clad with brick laid in running bond, and is capped by a slate-clad timber-framed hipped roof with overhanging eaves and exposed rafter ends. The elevations are pierced by 2/2 double-hung, wood-sash windows located in round arched window openings with concrete sills.

The roof contains hipped roof dormers with paired louvered openings. The south (front) elevation has a hipped roof porch with wood post supports. The main entrance is a double-leaf wood paneled door located inside the porch. The south half of the building includes a basement with wood joist framed first floor supported by timber girders and steel posts. The basement exterior walls are cast-in-place concrete with shallow foundations.

2.2 PROJECT DESIGN

Provide overall project design per Section 01 33 16.00 10, Design Data (Design After Award).

2.3 SITE DESIGN

The project site is located within Joint Base Myer – Henderson Hall (JBM-HH) in the National Capital Region, Arlington County, Virginia. The existing Patton Hall building is located on Buffalo Soldier Avenue near the intersection with Arlington Road. The proposed Patton Hall building will be a multi-use building with associated parking facilities. The building will need to have a Drop-Off area for VIP’s and 20-passenger buses. The Drop-Off area will be sheltered via Porte Cochere or other canopy cover, 8 | P a g e installed high enough to allow bus transportation to pass through. Because the building will include a full kitchen facility, an external receiving area sized to accommodate a large box truck for delivery of goods is required for this facility.

The proposed site should be designed to meet the requirements of UFC 3-201-01 Civil Engineering as well as the Installation Design Guide for Joint Base Myer-Henderson Hall.

2.4 BUILDING DESIGNS

Contractor and Designer of Record must be responsible and provide oversight, inspection and overall project coordination throughout. Design and construction approvals are required through review, comment, resolution, and concurrence by Government. Design and construct all structures to comply with UFC 3-301-01 “Structural Engineering” and other criteria listed in Chapter 4.

Design Submittals must be in accordance with Design Submittal Procedures in the Specifications, and other sections of this request for proposal (RFP). Delegated designs and proprietary materials specified in design documents must comply with DoD regulations.

2.5 TECHNICAL AND DESIGN REQUIREMENTS FOR ROOMS, PRODUCTS,

MATERIALS, AND FINISHES

For technical and design requirements of rooms, products, materials, and finishes refer to Room Data Sheets located in Appendix A. As a Strategic Engagement Platform – this facility is expected to be a world-class conference meeting center to be attended by high-ranking officials and dignitaries.

2.6 INTERIOR DESIGN

Excellence in design is a core objective for maximizing mission efficiency and long-term facility performance. Achieving this goal requires commitment to elevated quality standards, where interior design is fully integrated with architectural and engineering disciplines. The Designer of Record will be responsible for delivering Comprehensive Interior Design (CID) that demonstrates seamless coordination between Structural Interior Design (SID) and Furniture, Fixtures & Equipment (FF&E), in alignment with applicable Unified Facilities Criteria (UFC), and sustainability goals consistent with Leadership in Energy and Environmental Design (LEED) certification targets. Finishes, materials, and detailing must reflect a high level of design sophistication, contributing to operational efficiency, aesthetic coherence, livability, functionality, life-cycle value, and productivity. Interior design solutions should incorporate ergonomic principles, sustainable attributes, and a streamlined inventory of components. The quality of finishes is expected to reinforce the project’s identity and mission, while supporting compliance with UFC standards and contributing to LEED credits where applicable.

2.7 COMPREHENSIVE INTERIOR DESIGN (CID)

Comprehensive Interior Design is required for spatial layout of Furniture, Fixtures & Equipment throughout and coordination of overall color scheme of building finishes through development for SID.

Assure coordination of color, patterns, & finishes throughout between SID & FF&E.

2.7.1 STRUCTURAL INTERIOR DESIGN (SID)

SID includes building-related finishes, colors, and materials that are physically part of the building itself, such as walls, ceilings, floor finishes, and coverings, window treatments (blinds, shades), signage, and built-in casework.

9 | P a g e

2.7.2 FURNITURE, FIXTURES & EQUIPMENT (FF&E)

FF&E are defined as all movable / relocatable property and equipment within a building, room, or space.

Designer of Record will develop room designs with FF&E layouts, demonstrating that design integrates physical sizes of FF&E and achieve necessary clearance, access, operability, and coordination with building systems. Development of FF&E includes layout, selection of finishes and colors to be coordinated with SID selections, and creation of specifications and procurement documentation required to procure and install FF&E under a separate contract.

Procurement and installation of FF&E is NOT included in this contract. With separate funding, Government must procure and install FF&E under a separate contract. Contractor will accommodate that effort with allowance for entry of FF&E vendor/installer onto this project site at appropriate time to permit completion of installation for a complete and usable facility coinciding with Beneficial Occupancy Date (BOD). The furniture vendor/installer contract will include all electrical pre-wiring and whips for final connection to the building electrical systems; however, Contractor will make final connections to building systems under this contract. Furthermore, General Contractor will provide all Information/Technology (IT) wiring (i.e. Local Area Network (LAN), phone, etc.) up to and including faceplates. Contractor to perform connections for all freestanding systems furniture, desktops, and equipment as applicable, with services to install cable and face plates in coordination with FF&E vendor/installer to accomplish installation at the appropriate time, along with final IT connections to building systems under this contract.

Preliminary FF&E information, including dimensions and sizes, are provided on Room Data Sheets; refer to Appendix A. Scheduled items of FF&E is not considered an all-inclusive list.

2.8 AMERICANS WITH DISABILITIES ACT (ADA) / ARCHITECTURAL BARRIERS ACT

(ABA)

Project designs will achieve full compliance with ABA as required by federal law. ABA contains scoping and technical requirements for accessibility to sites, facilities, buildings, and elements by individuals with disabilities. Apply requirements during design for new construction, additions, alterations, and lease of sites, facilities, buildings, and elements to the extent required by regulations issued by Federal agencies under the ABA.

2.9 ANTITERRORISM AND FORCE PROTECTION REQUIREMENTS (AT/FP)

There is a Design Basis Threat (DBT) for the building design that requires threat enhancements to the site and the building. The applicable Level of Protection for the new building is indicated in the DBT which is greater than the minimum AT standards outlined in UFC 4-010-01. Contractor’s design solution has to comply with UFC 4-010-01 and UFC 4-020-01 and will incorporate items listed in the DBT. The DBT document is categorized as Controlled Unclassified Information (CUI). A copy of the DBT will be provided by the Contracting Officer upon request by the Contractor. Contractor must manage and protect the DBT in accordance with DoDI 5200.48.

2.10 INSTALLATION DESIGN GUIDE / INSTALLATION PLANNING STANDARD

Built environments develop a sense of community, which affect overall safety, visual appeal, sense of place, and provides visual orientation across the installation. JBM-HH, Installation Planning Standard (IPS) provides guidance for features of Site Planning, Building Standards, Circulation (pedestrian, vehicles, & trails), Signage, Road Networks, Building Material & Colors, Utilities, and Landscaping.

Project design is required to comply with JBM-HH, Installation Planning Standards (IPS). and following design guidelines outlined in the agency Programmatic Agreement (PA)) found in Appendix H. JBM-HH, 10 | P a g e

IPS identifies the project location within the Fort Myer Historic District for building type use being a strategic engagement platform (assembly).

The Government initiated the Section 106 process (36 CFR Part 800) with consulting parties. The Programmatic Agreement that was executed during the development of the RFP can be referenced for more information (see Appendix H). The selected Contractor and their designer of record are responsible for providing the Government supporting design documents as described in the PA to finalize the Section 106 process. As part of this RFP, the Contractor is responsible for adhering to all the requirements stipulated in the PA.

In addition, this project requires coordination with, review and approval by Commission of Fine Arts (CFA) and National Capital Planning Commission (NCPC). During RFP development, the Government initiated contact with the agency staff to describe the project scope and establish design guidelines. The selected Contractor and their designer of record are responsible for understanding and accepting requirements for design approval by these agencies. The Contractor is responsible all aspects of the review process in order to receive project concurrence from NCPC and CFA. Reference the agency web sites for submission requirements. Both agencies necessitate different submittal requirements, timeline, and/or lead-time for concurrence. Contractor is responsible for developing and coordinating various submittal criteria with appropriate lead-time, and documents necessary to achieve required approvals prior to start of construction. Contractor will coordinate requirements for each agency and provide all necessary submittal documents to the Contracting Officer for review prior to submitting to the outside agency. The Government will support the submissions with required signatures or cover letters from the owner, JBM-HH DPW.

2.11 SUSTAINABLE DESIGN AND CONSTRUCTION

Design and construct project to comply with sustainability requirements identified in Part 2 Section 01 33 29, Sustainability Reporting for Design-Build. Design and construct all scope items in accordance with UFC 1-200-02, High Performance and Sustainable Building Requirements.

2.12 LEADERSHIP IN ENERGY AND ENVIRONMENTAL DESIGN (LEED)

Project is required to achieve, at a minimum, a LEED rating of Silver under Version 4 of LEED. Offerors will not assume LEED credit points, propose strategies or decisions not within control of the Contractor.

Develop Sustainability strategies during design and achieve objective through management of construction processes. The project has been registered with USGBC. The Project ID is 1000222332.

Upon award contractor has to request access/control of the project from the Contracting Officer.

2.13 CYBERSECURITY

Design, acquire and execute all control systems (including systems separate from management utility monitoring and control system) in accordance with UFC 4-010-06 Cybersecurity of Facility-Related Control Systems. The DOR is required to create a tailored CCI and Controls list for each identified FRCS that is applicable to the project. Coordination between the DOR and each system’s Authorizing Official and Systems Owner is required to establish the Confidentiality-Integrity-Availability (CIA) of each

FRCS.

Several Facility Related Control Systems have been identified for the new building. A smart electric meter will be installed by Dominion Electric to track power consumption. Additionally, a Monaco-based fire alarm reporting system will receive a new extension card at the D21 console. Both of these systems will require cybersecurity controls per UFC 4-010-06.

11 | P a g e

2.14 OPERATION

The facility will have normal operating hours; however, due to the nature of the facility, there will be times when the facility is occupied after hours for special events such as military balls, conferences, and weddings.

2.15 STAFFING/OCCUPANCY

The number of occupants specified in the RFP are identified for programming purposes. DOR is to determine the final occupancy necessary for designing standard building features such as structural, egress, and plumbing fixtures as specified in applicable building or life safety codes.

2.16 SPECIAL DESIGN CHALLENGES

Pool must remain open and accessible during normal summer operations (Memorial Weekend to Labor Day; daily from 1100 to 1900). Access to a pool house (gender specific restrooms, shower, locker room, pool storage) must remain available during pool operations. Once the Patton Hall building has been demolished, the pool area will have a gap in perimeter security. The pool area perimeter security will need to be preserved at all times with permanent measures IAW UFC 4-750-07 Recreational Aquatic Facilities paragraph 4-2.4.

Traffic cannot be hindered or blocked along Buffalo Soldier, Custer Road, and Johnson Lane without prior approval and coordination with Contracting Officer. Request must be submitted to Contracting Officer a minimum of 14 calendar days. Request has to be made by submitting JBM-HH Form 7 (JBM- HH_Request_for_Support_Form_7_Blank.pdf).

During demolition of Building 214, the Guardhouse must not be structurally compromised or degraded beyond current condition.

Phasing requirements of the project are to be determined and proposed for approval by the Contractor.

2.17 GOVERNMENT-FURNISHED GOVERNMENT INSTALLED EQUIPMENT (GFGI)

Contractor must coordinate with Contracting Officer for requirements of Government Furnished Government Installed (GFGI) items scheduled, and provide design and deliver suitable structural support, brackets for projectors/ TVs, with all utility connections and space with required clearances for all GFGI items. Fire extinguishers, fire extinguisher brackets, and cabinets are Contractor furnished and installed (CF/CI). All Computers and related hardware, copiers, faxes, printers, video projectors, and TVs are GFGI. For scheduled GFGI items, refer to Room Data Sheets.

2.18 BUILDING COMMISSIONING

Provide commissioning to meet requirements identified in Section 01 91 00.15 Total Building Commissioning, ER 1110-345-723 Total Building Commissioning and UFC 1-200-02 High Performance and Sustainable Building Requirements. A draft copy of the Owner’s Project Requirement (OPR) can be found in Appendix A.

12 | P a g e

CH 03 – SITE ANALYSIS

3. SITE ANALYSIS

Site work consists of all aspects of a complete project site. This includes site planning and design of all new site features (buildings, roads, parking, walkways, fencing, etc.), demolition, earthwork / grading, storm drainage, utilities, signage, landscaping, force protection, stormwater management and erosion and sediment control, and obtaining necessary permits.

The existing site consists of a 77,600 square foot (SF) building that consists of several building additions from the original 1896 building. The building was expanded between the years 1957-1968. Building 214 will be demolished under this project with the exception of the “Guardhouse” located on the west side of Patton Hall. The Guardhouse will be preserved by this project; in addition to restoring the original exterior condition of the Guardhouse, all utilities services and accessibility will need to be restored. The Guardhouse must be occupiable once Building 214 is demolished. The current building orientation has multiple entrances with a main entrance and drop off along Buffalo Soldier Ave on the south. There is an additional entrance on the south side of the building at the historic guardhouse and an entrance on the east side of the building adjacent to Custer Road and the parking lot. The rear of the building that is connected to the swimming pools is accessed from the lower level and secured with fencing.

Custer Road is situated along the east side of the building. It provides access to the facilities located to the north of Building 214 as well as provide an area for parents to drop children off and access the swimming pools from the exterior. The existing parking lot has two entrances on Custer Road. The boomerang-shaped parking lot has 107 existing parking spaces with five ABA accessible parking spaces positioned closest to the building entrance. The parking lot is 5ft-6ft higher than Custer Road with the grade differential accommodated by steep slopes and a concrete retaining wall.

The area east of the existing parking lot has been designated by the installation as a dedicated green field as part of their existing stormwater permit. The “green space” was required as part of another project on the installation as an exchange for impervious surface to promote water quality and stormwater infiltration. This green space has always been an open area on post. It was a historic parade ground during the late 19th century and used for tennis courts throughout much of the 20th century. The tennis courts were recently demolished for stormwater compliance. The permitted green space is delineated on CS100 Site Plan Limits of Work (Appendix B); permitting/pollution reduction requirements are illustrated in site drawings provided in Appendix B.

3.1 EXISTING SITE DESCRIPTION

The existing site consists of the Patton Hall building which is located on the north side of Buffalo Soldier Avenue (Ave) near the intersection with Arlington Road. The existing Patton Hall building is bound by Custer Road (Rd) and parking to the east, residential housing and Buffalo Soldier Ave to the south, the historic Guardhouse and Building 216 to the west, and three existing swimming pools to the north. Custer Road intersects with Arlington Ave at a point slightly east of alignment, resulting in a non-standard, angled junction rather than a traditional four-way intersection. The project site includes the existing Patton Hall building, but also Custer Road, parking lots, and the green space to the east of the Patton Hall building. The site boundary can be seen in Appendix B - CS100 and CS101 – Site Plan (Limits of Work).

Native files of the site plan can be provided to the contractor upon request to the Contracting Officer.

The existing parking lot associated with Patton Hall has 107 parking spaces located east of Custer Rd.

Access to the parking lot is via two entrances on Custer Rd with one-way traffic flow from south to north with a 23.5-foot-wide drive aisle. It should be noted that the existing parking lot does not meet the current UFC parking lot requirements. There is additional parking space for the facility along Buffalo Soldier Ave via on-street parallel parking and in the parking lot to the southwest of Patton Hall.

13 | P a g e

3.2 CONSTRUCTION PHASING, STAGING, AND CONTRACTOR ACCESS

There is limited available land for contractor staging and laydown. The contractor staging will be within the LOW as shown on CS100 – Site Plan Limits of Work in Appendix B. Contractor is to submit a construction phasing plan for review and approval by Directorate of Public Works (DPW). Contractors will access Patton Hall through the JBM-HH Visitor Control gate located at 101 Carpenter Rd, Fort Myer, Virginia 22211. After entering the installation, contractors should head northeast, turn left onto McNair Road, then left again on Buffalo Soldier Avenue to reach the project site. Safe pedestrian and vehicular access to the swimming pools is required during the operational months.

3.3 DEMOLITION

Demolition of the existing Patton Hall building with the exception of the Historic Guardhouse is part of this RFP. Along with the demolition of the building, there will be existing utility service demolition. All of the services to the existing building will be removed and cut and capped at the main. Demolition of the exterior electrical equipment (medium voltage pad-mounted switchgear, pad-mounted transformer, generator, and automatic transformer switch) will be removed by Dominion Energy. Demolition of telecommunications duct bank and cabling from existing manhole unknown D to the Patton Hall 5-foot line. New electrical and communications services will need to be established to the guardhouse in order for it to be occupiable. The excavated area from the removal of the Patton Hall building and lower level, should be backfilled with suitable material, compacted, and seeded. The area should be graded with slopes at a maximum of 5:1 with positive drainage towards the existing or proposed storm drainage system. Preserve or improve upon stormwater flow ensuring not to add stormwater flow into the pool area. Depending on the location of the new facility, the existing parking lot may be demolished along with Custer Road and associated concrete retaining wall. Following the demolition of Building 214, it will be necessary to install a new fence to secure the pool area and ensure continuity with the existing fencing. Perform a structural assessment of the existing foundations at the interface between the existing Guardhouse and the Patton Hall building prior to demolition to establish a demolition plan that ensures the Guardhouse foundations will not be undermined at any point during the demolition process. If determined necessary by structural analysis, provide underpinning for the guardhouse foundations. At the completion of demolition, the Guardhouse walls foundations will have the same or higher load bearing capacity as they did prior to demolition. Any foundation or basement wall for which loading is increased after demolition must be analyzed in accordance with International Existing Building Code (IEBC) and strengthened as required to meet code requirements. This includes Guardhouse basement walls that may experience an increase in lateral earth pressure when the adjacent demolished Patton Hall building basement is backfilled with earth fill.

Depending on the location of the new facility, several mature trees are located within the LOW that may need to be removed. Due to the Northern long-eared bat (NLEB) and the Tri-colored bat (TCB) and their status on the Endangered Species List, tree clearing will be limited to the non-active, overwintering season November 15 – April 1.

3.4 NEW CONSTRUCTION SITE LAYOUT GUIDELINES

The new site layout will be required to be within the LOW shown on CS100 Site Plan in Appendix B.

According to the Installation Planning Standards and DPW, a minimum separation of twelve feet between buildings is required. The minimum building separation distance will be governed by the DBT. At the conclusion of the project, within the LOW, a minimum of 107 parking spaces must be provided to preserve the existing capability. The proposed parking layout is required to be per UFC 3-201-01 Civil Engineering and Military Surface Deployment and Distribution Command Transportation Engineering Agency (SDDCTEA) Pamphlet 55-17 with 9-foot wide by 18.5-foot-long standard ninety-degree parking spaces. Additionally, parking has to comply with current ABA guidelines. Parking lot pavement markings will be provided in accordance with SDDCTEA Pamphlet 55-17 and the Manual on Uniform Traffic

14 | P a g e

Control Devices (MUTCD) including the Department of Defense supplement to the MUTCD. Any existing pavement that will be reused to satisfy the parking lot authorization must be milled and overlaid with a minimum 1.5-inch asphalt surfacing.

The parking area may be constructed of asphalt, concrete, or pervious surface. The parking lot will be bound by concrete barrier curb with concrete curb and gutter in areas that provide a stormwater flow path.

The pavement thickness has to be in accordance with the project geotechnical report, designed with the Pavement-Transportation Computer Assisted Structural Engineering (PCASE) software, and in accordance with UFC 3-250-01 Pavement Design for Roads and Parking Areas.

A 20-foot-wide drop-off lane is to be provided at the main entrance to the proposed building. The queue length should accommodate a minimum of three vehicles (approximately 60 feet). The drop-off area at the building should have a covered canopy that allows for the drop-off lane and entrance to be undercover. The canopy should be tall enough to accommodate emergency vehicles. The drop-off lane can also serve as emergency vehicle access to the building. The drop-off lane access should be coordinated with the ATO.

Pedestrian circulation must be provided that connects the parking lot to the new building and existing pedestrian facilities. Sidewalks is to be a minimum of 4-inch-thick Portland cement concrete that are a minimum of 4-foot wide in typical pedestrian areas and a minimum of 6-foot wide in main sidewalks with higher pedestrian traffic areas. Sidewalks are to comply with ABA guidelines and provide an accessible path connecting the main entrance, ABA parking spaces, main sidewalk network, and site amenities.

Because the building will include a full kitchen facility, an external receiving area sized to accommodate a large box truck for delivery of goods is required for this facility. The receiving area adjacent drive should accommodate the turning radii of the large box truck. The receiving area will require security with access control for vehicles to be able to drive up to the building.

Betterments - Enlarged drop-off lanes and larger canopy to accommodate more vehicles; longer queue drop-off length, recessed loading dock and dock leveler, landscaping; exterior gathering space with outdoor seating; and additional parking.

3.5 EXISTING FACILITIES

The Guardhouse located on the west side of Patton Hall Building 214 is to remain operational.

Demolition of Building 214 will require structural stabilization of the Guardhouse as well as restoration of utility service and building envelope restoration. The Guardhouse must be occupiable at the conclusion of this project. Additionally, the existing swimming pool area is to remain and have access during the operational months.

The green field to the east of the existing parking lot is a Virginia Department of Environmental Quality (VDEQ) permitted green space. If development occurs in this area resulting in reduced permitted green space, the permitted area will require modification or relocation and must be reestablished in an alternative location. This will be in addition to the VDEQ pollutant reduction requirements established for this project. This will need to be coordinated with installation staff and VDEQ. The Pollutant reduction credits obtained in the permitted green space are listed below. The existing Stormwater permitting documents and the Fort Myer Tennis Court Demolition Plan can be seen in Appendix C.

• Total Nitrogen: 5.59 lbs/year

• Total Phosphorus: 1.61 lbs/year

• Total Suspended Solids (TSS): 1,624.40 lbs/year

15 | P a g e

3.6 GRADING

Grading for the site must direct water towards new or existing drainage features and away from impervious site features. Grading must not result in low spots that hold or direct water towards new or existing site features. Grading for the project has to comply with applicable sections of UFC 3-201-01 Civil Engineering. The Finished First Floor Elevation is required to be 6 inches higher than adjacent ground. The grading should provide positive drainage throughout meeting UFC required minimum and maximum grades as shown in Table 2-2. The grading is to be integral with the storm water management plan.

3.7 UTILITIES

The existing utilities within the LOW consist of water, wastewater, stormwater collection, electric, telecommunications, and natural gas. Existing site utility drawings are provided in Appendix B.

Equipment and connection costs for the privatized utilities will be paid directly to the Defense Logistics Agency (DLA) by United States Army Corps of Engineers (USACE); it will not be the responsibility of the Contractor to contract directly with the private utility provider for the utility installations and/or connections in support of this project.

Utilities will need to be restored to the Guardhouse when Building 214 is demolished. Currently there appears to be water and sewer service directly supporting the Guardhouse; all other utilities and building services are provided from Building 214.

Utility Government or Privatized

POC

Water Government – DPW David Mayeda

Wastewater Government – DPW David Mayeda

Natural Gas Government – Washington Gas (WG)

**Contractor to work directly with WG for utility hookup/acceptance – will pay WG directly then transfer to DPW at building acceptance** https://www.washingtongas.com/services/contractors/service-territory

Bill Lucas

William.f.lucas14.civ@army.mil

703.357.8311

Electric Privatized – Dominion Energy

James Bakos james.s.bakos@dominionenergy.com

571-271-2180

Telecommunication Government – Fort Myer

NEC

Privatized – Verizon

NEC – Jose Molina Delgado

Verizon POC TBD

Stormwater Government – VA Department of Water Quality for Arlington County

3.8 WATER

The water conveyance system on JBM-HH is owned and operated by the installation. The exiting site is served by a 10-inch water main running parallel along the south side of Patton Hall and the north side of

16 | P a g e

Buffalo Soldier Ave. The 10-inch main has several service connections to Patton Hall and a 4-inch main that connects the swimming pool area. Existing fire hydrants are positioned along Buffalo Solider Ave to the east and the west of Patton Hall. The fire service and hydrant locations are required to comply with UFC 3-600-01 Fire Protection for Facilities with Change 6.

3.9 WASTEWATER

The gravity sanitary sewer system on JBM-HH is owned and operated by the installation. There is a sanitary sewer main that runs along the south side of Patton Hall then gravity flows to the south along Arlington Ave and ultimately to the treatment plant off the installation. Per discussions with DPW, this main is a 6-inch clay pipe that is aged and not adequate for the new sewer connection. There are several sanitary sewer laterals connecting to the rear of the building (north side). There is an 8-inch PVC sanitary sewer located north of Swimming Pool #3 that can provide a potential gravity sewer connection. There is a manhole located at the curve in Custer Road with an invert of 215.66 and a manhole located north of Swimming Pool #3 near Building 203 with an invert of 210.92. To access the manhole near Building 203, the connection can be directional bored between Swimming Pool #2 and Swimming Pool #3.

3.10 ELECTRIC

The existing exterior electrical equipment consists of a 4-way medium voltage pad-mounted switchgear, pad-mounted transformer, automatic transfer switch, and emergency generator. All of the exterior electrical equipment is owned and operated by the base privatized utility company, Dominion Energy.

The sizes of the exterior electrical equipment have been confirmed with Dominion Energy. JBMHH DPW electrical engineer provided an e-letter confirming the medium voltage distribution system is considered reliable in accordance with NFPA 20.

NATURAL GAS

There is a gas main that runs along the north side of Buffalo Soldier Ave. The gas is owned and operated by Washington Gas. Per DWP Utilities contact, the gas main should be adequate to service Patton Hall.

Once the gas equipment is specified, a load sheet should be submitted to Washington Gas, and they will determine the meter size. Once the load sheet is submitted, Washington Gas can verify that the main is adequate.

3.11 COMMUNICATIONS

Building 214, Patton Hall is serviced with incoming fiber optic cable from a manhole located North of the building. Two lines are necessary, one Non-classified Internet Protocol Router Network (NIPRNET) and one privatized, coordination with both required.

3.12 EROSION AND SEDIMENT CONTROL, STORMWATER MANAGEMENT, AND

CONSTRUCTION GENERAL PERMIT

Erosion and sediment controls will minimize the discharge of pollutants from earth disturbing activities in conformance with VDEQ. Pre-coordination has occurred with VDEQ, Mr. Chantz Ballard during the RFP development.

a. To meet VDEQ water quality requirements, the purchasing of water quality credits may be utilized in accordance with VDEQ standards. The Contractor’s DOR must take into account the existing permitted pollution reduction (as noted in Section 3.5) for any development within the Dedicated Green Space in addition to the water quality requirements of the new development.

The Contractor and their designer of record are responsible for obtaining Erosion and Sediment Control (E&S) and Stormwater Management Plan (SWM) Plan approval and the Construction General Permit from the Viriginia Department of Environmental Quality (VDEQ). The

17 | P a g e

Contractor is responsible for all permit and/or review fees. The Contractor and their Designer of Record (DOR) are required to be thoroughly knowledgeable of the latest VDEQ E&S and SWM requirements. Design the site to comply with the most recent version of the Virginia Stormwater

Management Handbook, Virginia Runoff Reduction Method (VRRM) for water quality, and VA Code Chapter 875 (9VAC25-875-600) for water quantity.

b. During design phase, the Contractor’s DOR is to initiate and coordinate with the VDEQ Plan Review Manager to ensure the design will comply with E&S and SWM requirements. USACE and DPW-EMD representatives need to be invited to all meetings with DEQ.

c. Prior to the first VDEQ submission, submit the E&S/SWM Plans and report to the COR for review by USACE and DPW-Environmental Management Division (DPW-EMD). The government will have 14 days to review. Once EMD and USACE comments have been addressed to the satisfaction of USACE and EMD, submit to VDEQ.

d. Submissions to VDEQ Plan Review are electronic. Submission files need to include a transmittal form, submission checklist, cover letter, plans, and report. More information can be found on https://www.deq.virginia.gov/water/stormwater/stormwater-construction/plan-review. Copy USACE and DPW-EMD on all submissions to VDEQ.

e. It is the responsibility of the Contractor to account for all submission review periods within the design schedule. Each submission should be scheduled to allow the reviewing authority time to make comments and request resubmission. It is the Contractor's responsibility to accommodate the review process such that the start of construction is not delayed.

f. If the limit of disturbance is one acre or more, the Contractor has to submit a Construction General Permit (VPDES) Registration Statement and obtain the permit prior to the start of construction.