This document is a pre-solicitation notice for a competitive Invitation for Bid (IFB) solicitation issued by the U.S. Army Corps of Engineers, Baltimore District for the Raystown Lake Water Treatment Plant Upgrades in Hesston, Pennsylvania.
The proposed procurement is for construction services under NAICS code 237110 "Water and Sewer Line and Related Structures Construction" with a size standard of $39,500,000. It will be a 100% small business set-aside contract awarded as a firm-fixed-price contract procured through sealed bidding. The project consists of upgrades to the existing Seven Points Water Treatment Plant at Raystown Lake, including reconfiguring the clearwell piping, installing actuated valves, modifying the sampling and flow measurement, replacing filter media and controls, and replacing the clarifier/filter components. The construction duration is estimated at 180 calendar days from the notice to proceed. The magnitude of construction is estimated between $500,000 and $2,000,000. The solicitation is expected to be issued around June 28, 2024, with bids due around August 9, 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B.01.03 Pre-Solicitation Notice.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRE-SOLICITATION NOTICE
SOLICITATION: W912DR24B0015
RAYSTOWN LAKE WATER TREATMENT PLANT UPGRADES IN HESSTON,
PENNSYLVANIA
This proposed procurement is a Competitive Invitation for Bid (IFB); NAICS 237110 " Water and Sewer Line and Related Structures Construction” with a size standard of $39,500,000.00. This will be a 100% small business set aside.
The U.S. Army Corps of Engineers, Baltimore District (NAB), has been tasked to solicit for and award construction services for Raystown Water Treatment Plant and Supply System Upgrades, in Hesston, Pennsylvania. The proposed project will be a competitive, firm-fixed-price, contract procured in accordance with FAR 14, Sealed Bidding, via an Invitation for Bid (IFB).
The purpose of the proposed action is detailed below:
The Raystown Lake Project provides potable water to approximately 600,000 visitors annually at Seven Points Recreation Area and marina in Hesston, PA. The Seven Points Water Treatment Plant (WTP) at Raystown Lake is located at 6764 Seven Points Road. It is a surface WTP with clarification and filtration package treatment units, using sodium hypochlorite for primary disinfection providing potable water to the Seven Points Area campsites, marina, and administrative facilities within the recreation area. The WTP went into operation in 1992.
The list below identifies the improvements to bring the plant into compliance with PADEP regulations and requirements.
The project consists of but is not limited to the following:
• Reconfigure the piping of the WTP clearwell
• Install actuated valves or pump controls
• Modify the water sampling location and add flow measurement
• Modify the pressure distribution system discharge pump
• Drain, inspect, and clean the clearwell
• Replace filter media in both filters.
• Replace the filter control panel
• May include bid items to install fiber and make required connections along with a fiber-optic connection
• Replace PLC and install autodialer with signal callouts and VTScada software
• Replacement of the clarifier / filter media, underdrains, and air scour piping in both clarifier/filter units.
The water treatment plant and reservoir are critical components of the distribution system and so the outage period is restricted. An experienced contractor with resources and expertise to handle the following project constraints is needed:
1. Have all materials and equipment on site once Notice to Proceed is issued.
2. The WTP will remain in operation through November 1. After November 1 the contractor will have 60 day work periods to work during shutdown mode.
3. The WTP Clearwell and the Booster Pump Station Clearwell will remain in operation during the entire period that the WTP is in operation.
4. The existing fiber-optic communications line will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with this utility.
5. Access into the clearwell is limited and all work within is considered confined space.
The magnitude of construction is between $500,000.00 and $2,000,000.00. Construction duration is approximately 180 calendar days from Notice to Proceed.
Additional information in accordance with the statement of work will be included in the IFB package.
This solicitation will be available on or about 28 June 2024, bids due on or about 9 August 2024. The solicitation will be provided in an electronic format, free of charge to all authenticated account holders of the SAM.gov system. Please note that all USACE acquisitions are considered sensitive, but unclassified documents.
Vendors must be registered with the System for Award Management (SAM) database to receive a government contract award. Vendors must also be registered in Representations and Certifications Applications (included in SAM). The North American Industry Classification System (NAICS) Code (237110) applicable to this acquisition must be in vendor’s SAM registration. Note: Update SAM profile to include all applicable NAICS Codes associated with your company. Vendors may register for SAM online at www.sam.gov or by calling 1-866-606-8220.