SM-1A_AFE_Presentation_10Feb2022.pdf
PDF 4 MB Posted
- Attached to
- Decommissioning and Disposal (D&D) Activities for the SM-1A reactor Facility located at Fort Greely, AK
- Solicitation number
- W912DR22R0027
About this file
This notice provides details for the Decommissioning and Disposal Activities for the SM-1A Reactor Facility located at Fort Greely, Alaska procurement. The Army Corps of Engineers seeks to decommission and dismantle the SM-1A deactivated nuclear power plant, including removal of all reactor components and radiologically contaminated materials. Offerors must be prepared to prepare decommissioning plans, perform post-decommissioning radiological surveys, and adhere to Nuclear Regulatory Commission and Army standards. The pre-solicitation for proposal number W912DR22R0027 will be issued on or around February 11th, 2022 on SAM.gov under NAICS code 562910 with a size standard of $22 million. The period of performance is 72 months from date of award. A site visit is scheduled for March 2nd-4th, 2022 with details forthcoming.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEACTIVATED SM-1A NUCLEAR POWER PLANT
DECOMMISSIONING AND DISMANTLEMENT
Project Overview For
Alaska Forum for the Environment
10 Feb 2022
Program Manager: Brenda M. Barber, P.E. | U.S. Army Corps of Engineers
TODAY’S KEY TOPICS
• SM-1A Operational History
• Decommissioning Planning
• NEPA
• Section 106
• Decommissioning Plan
• Utility Separation Project
• Contract Acquisition
• Closing Remarks
OPERATIONAL HISTORY OF
SM-1A
FORT GREELY LOCATION
Distances from Fort Greely:
• Delta Junction – 5 miles
• Fairbanks – 100 miles
• Valdez – 263 miles
• Anchorage – 328 miles
• Whittier – 386 miles
FORT GREELY
SM-1A OPERATING HISTORY
• Built on Fort Greely between 1958 and 1962.
• Designed, constructed, and operated as part of the Army Nuclear Power
Program.
• Single-loop, 20.2 MW pressurized water reactor.
• Used highly enriched uranium dioxide fuel to generate 2,000 kW of electrical power and 37,850 pounds of extraction steam per hour.
• Supplied electrical power and heating steam for on-post buildings and facilities from 1962 to 1972.
• Used as an in-service test facility to understand how equipment functions in an arctic environment.
SM-1A DEACTIVATION AND ENCASEMENT HISTORY
• The decommissioning process began upon the reactor’s final shutdown in
March 1972.
• Initial deactivation consisted of placing the facility in a safe storage
(SAFSTOR) configuration, after which it was maintained and monitored in a condition that allows radioactivity to decay over time.
• Regular inspection and monitoring is conducted by USACE in accordance with AR 50-7 and SM-1A Reactor
Possession Permit Number
SM1A-1-19, Amendment 1-20.
• Buildings 606 North and 606 South contain infrastructure and equipment associated with Fort Greely’s conventional utility systems and are owned by Doyon Utilities, LLC.
AFFECTED AREAS OF SM-1A
AFFECTED AREAS OF SM-1A
SM-1A TIMELINE OF ACTIVITIES
March
March
June
SM-1A
Construction
Start
SM-1A Reactor Startup
• Core II: April 1964
• Core III : Jan 1966
• Core IV: Aug 1970
Last Operation
August
Pressure
Vessel
Annealed
Initial
Deactivation &
Entombment
USACHPPM
Survey
1997 -
BRAC Pipeline
& Dilution
Well Removal
2008 2011 2014 2018 2019;
2021 2022
Core
Component
Activation
Analysis
USACE
Historical Site
Assessment
USACE
Characterization
Survey Report
USACE Gamma
Walkover Report
Decommissioning
Planning Award
Additional
Characterization
Effort
Environmental
Assessment
Decommissioning
Contract Award
SM-1A TIMELINE OF ACTIVITIES (CONT.)
DECOMMISSIONING
PLANNING
NEPA
NATIONAL ENVIRONMENTAL POLICY ACT PROCESS
• The National Environmental Policy Act (NEPA) requires federal agencies to assess the environmental and socioeconomic effects of their proposed actions prior to making decisions.
• NEPA also provides opportunities for the public to learn about and comment on federal proposed actions.
• USACE has prepared an Environmental Assessment (EA) to analyze the potential impacts from the proposed decommissioning (the "Proposed Action”).
• The EA is a concise public document that provides sufficient evidence and analysis for determining whether to prepare an Environmental Impact Statement (EIS). The EA includes brief discussions of the following:
oThe purpose of and need for the proposal.
oAlternatives to the proposal (as required under Section 102 [2] [E] of NEPA).
oThe environmental impacts of the proposed action and alternatives.
oA listing of agencies and persons consulted.
PROPOSED ACTION
• USACE proposed to:
– Complete the decommissioning and dismantlement of SM-1A in accordance with the Army Reactor
Office (ARO) - approved Decommissioning Plan;
– Terminate the U.S. Army Nuclear and Countering Weapons of Mass Destruction Agency (USANCA)
- issued SM-1A decommissioning permit; and
– Release the SM-1A site for unrestricted use in accordance with U.S. Nuclear Regulatory Commission
(NRC) regulations at 10 code of Federal Regulations (CFR) 20.1402 and adopted by the Army.
The Final Environmental Assessment (EA) and Finding of No Significant
Impact (FNSI) found that the Proposed Action would have no significant adverse impacts on the environment.
The documents were finalized and released to the public in June 2021.
SECTION 106
SECTION 106 OF THE NHPA CONSULTATION PROCESS
• Section 106 of the National Historic Preservation Act (NHPA) requires federal agencies to consider effects of undertakings on resources listed in or eligible for inclusion in the National Register of Historic Places (NRHP).
• Section 106 provides opportunities for public input on federal actions potentially affecting historic properties.
• USACE is the Lead Federal Agency
– U.S. Army Garrison involvement
• USACE Consulting Parties
– Alaska SHPO / Office of History and Archeology
– Tribal Governments and other interested parties
– Nuke Digest
– Delta Junction City Council
• USACE Consultation
– Defined the Area of Potential Effect (June 2020)
– TPP Involvement
– Cultural Resources Technical Report & Adverse Effect Determination (December 2020)
• MemorandumofAgreement (MOA)(completed June 2021)
AREA OF POTENTIAL EFFECT AND HISTORIC PROPERTIES
• SM-1A is individually eligible for listing in the National Register of Historic
Places (NRHP).
• SM-1A is a contributing resource in the
NRHP-eligible Fort Greely New
Post/Cold War Historic District.
ADVERSE EFFECTS TO
HISTORIC PROPERTIES
• Demolition of SM-1A Reactor Facility
• Demolition of a contributing resource in the Fort Greely New Post/Cold War
Historic District
606 N
606 S
RESOLUTION OF ADVERSE EFFECTS
• USACE will resolve the
Undertaking’s adverse effect by executing an MOA with participating consulting parties and adhering to stipulations specified therein.
• Avoidance or minimization is not feasible due to NRC regulations and Army
Regulation 50-7, Army
Reactor Program.
DECOMMISSIONING
PLAN
DECOMMISSIONING PLAN – AFFECTED BUILDINGS
DECOMMISSIONING PLAN
• Provides overview of the project
• Discusses radiological contamination present at the site
• Documents the release criteria and clean up criteria for the site
• Outlines project management and overall organization
• Provides the framework for the radiation safety and health of the project
• Outlines overarching approach to waste management and disposal
• Documents the release of prior associated buildings – 670 and 675
UTILITY SEPARATION
PROJECT
• The USACE team worked with a joint team including IMCOM FGAK and DLA to have Doyon complete the utility separation work under the existing Utilities Privatization contract
• DLA finalized the contract modification to have Doyon implement the utility separation work – issued on
28 Jul 2021
• Doyon began implementation of the project in Aug 2021 and has until April 2023 to complete the utility separation work and relocate to the south end of Bldg. 606 South
• USACE will be providing construction support throughout the utility separation work through USACE staff and the Engineer of Record – APTIM Federal Services
RELOCATION OF DOYON UTILITIES
CONTRACT ACQUISITION
SM-1A DECOMMISSIONING CONTRACT ACQUISITION
APPROACH
• Stand alone, hybrid C contract with Firm Fixed Price, Cost Plus Incentive Fee, and cost reimbursement contract line items. Solicited under full and open competition
• Major Steps:
• Market Research is complete
• Acquisition Planning is complete
• Issue Request for Proposal – mid Feb 2022
• Evaluate Proposals – Mar 2022 - Apr 2022
• Discussions/Revaluations – May 2022 – Jun 2022
• Award Decommissioning Contract – end of Jul 2022
• Requires a DCAA audited cost accounting system and a validated Earned Value
Management that is compliant with the guidelines in ANSI/EIA 748 is required
• Work anticipated to take 6 years to implement (FY22-FY28)
REQUEST FOR PROPOSAL WILL INCLUDE THE FOLLOWING
REQUIREMENTS
• Combination of large and small companies with capabilities and expertise in the following key areas:
• Prior experience working in Alaska; familiarity with Alaska working conditions and regulations
• Project Management
– Scheduling
– Cost Estimating
– Risk Assessment and Analysis
• Radiological Expertise
• Health and Safety Expertise
• Decommissioning Expertise
• Demolition Expertise
• Regulatory Compliance
• Waste Transportation and Disposal
• Small Business Participation – goal for the project will be 20% (minimum)
SM-1A CONTRACT OUTREACH TO DATE
• Community Updates at the Delta Junction City Hall – annually since 2018
• Presentation at the Alaska Forum for the Environment – Feb 2019
• Industry Day hosted at the Alaska Forum for the Environment – Feb 2019
• Pre-solicitation site visit – August 2019
• Release of historical documents – August 2019
• Sources sought notices for Market Research
• July 2020
• Feb 2021
• Monthly Stakeholder updates (email distribution and posted on website)
• Release of historical documents and Decommissioning Planning documents – November
• All presentations and updates are posted on the project website
SM-1A CONTRACT SITE VISIT (ANTICIPATED)
• A site visit will be hosted at SM-1A at Fort Greely in AK from 02 – 04 March 2022
• Site access requirements are:
• No more than four (4) attendees per contractor and/or team
• Attendees must be registered with the Contract Specialist prior to the event
• USACE will host an afternoon session on 02 March and a morning and afternoon session 03 and 04
March
• Session size is limited to 16 attendees so the sessions will be filled based on timely responses to the
Contract Specialist (first come basis)
• Attendees will need to identify a 1st and 2nd option for sessions
• Due to COVID protocols, base access is as follows:
– Vaccination proof will be requested; however, the attendee can sign a memo for non-vaccine status and/or if they choose not to disclose their status. This will be done with base security personnel only
(no disclosure to USACE is required)
– Masks must be worn at all times on the base
– Social distancing will be required
– All attendees will be escorted by USACE employees
– If the base changes access requirements, USACE will notify the attendees prior the visit
Please review the final solicitation for any changes in the above site visit information
SM-1A DECOMMISSIONING IMPLEMENTATION ACTIVITIES
• The selected contractor will prepare plans that will support the decommissioning of the SM-1A in accordance with contract PWS and the Decommissioning Permit issued to the USACE;
• Decommission/disposal of materials in accordance with final plans, decommissioning permits, and relevant Federal and State requirements; and
• Project management (cost controls, scheduling, manpower resourcing, etc.)
• Prepare work plans, safety and radiological plans, and prepare complex engineering assessments
• Removal of all reactor components and radiologically contaminated materials
• Prepare all radiological waste for proper shipment; then transport and dispose of the waste
• Perform radiological surveys
• Perform demolition of non-contaminated equipment and building components
• Excavate contaminated soils
• Final site restoration
Adherence to NRC and Army, as well as other Federal standards and guidance where relevant and as required by the Army Reactor Office and USACE.
ENGAGE AND LEARN MORE
Learn more about the SM-1A Project online at:
https://www.nab.usace.army.mil/SM-1A/
Sign up for the SM-1A stakeholder update email list by emailing:
CENAB-SM1A@usace.army.mil
Stay engaged with us online:
@USACEBaltimore https://www.facebook.com/USACEBaltimore/ www.nab.usace.army.mil https://www.nab.usace.army.mil/SM-1A/ mailto:CENAB-SM1A@usace.army.mil https://www.facebook.com/USACEBaltimore/ http://www.nab.usace.army.mil/
THANK YOU FOR ATTENDING
TODAY’S EVENT
USACE appreciates your input on the SM-1A Deactivated Nuclear Power Plant Decommissioning Project.
We look forward to engaging with you in this process.