This document provides an amendment to a solicitation for maintenance dredging services. The amendment revises the response to a request for information question regarding survey criteria for acceptance and volume computations. A 25-foot by 25-foot cell size average posted to the cell center will be used for both acceptance and volume computations. The survey manual referenced in the specifications is also updated. The related federal contract opportunity is for maintenance dredging of the Cape Henry Channel in Virginia, Baltimore Harbor, and channels. The work involves removal of approximately 2.35 million cubic yards of material using a hopper dredge, to be placed in the government-furnished Dam Neck Ocean Disposal Site. The estimated cost is up to $20 million and performance period should not exceed 160 calendar days from notice to proceed.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 20-Aug-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DR21B0017

X 9B. DATED (SEE ITEM 11)

27-Jul-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Project Title: MAINTENANCE DREDGING of CAPE HENRY CHANNEL (VA), BALTIMORE HARBOR and CHANNELS

The purpose of this amendment is to provide a revised response to RFI # 9361788.

All other terms and conditions remain unchanged.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

20-Aug-2021

CODE

USACE, BALTIMORE

2 HOPKINS PLAZA

BALTIMORE MD 21201

W912DR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DR21B0017

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

The following have been added by full text:

AMD 0002

Response to Request for Information (RFI)

Question:

Based on past lengthy debates and experience here (especially along the toe), it is vital that all contractors know what the survey criteria will be for acceptance. We understand that you have the flexibility to conduct single or multi beam surveys. However, if multibeam is to be used for acceptance, contractors need to know the criteria (spacing grid), i.e. 25’x25’ Average Sounding for acceptance and 25’x25’ Average Sounding for volume computations. The Corps EM1110-2- 1003 (2013) Survey Manual only provides recommendations. Can you please identify via an amendment what the Pay Volume Computations and Acceptance grid size and criteria will be (??ft x ??ft, average, cell centered, xy, etc.)?

Response: Revised Response to ProNet RFI # 9361788 (Change highlighted in red)

This new text supercedes ALL previous replies.

The Government intends to perform pre-dredge and post-dredge surveys of the channels utilizing multi-beam (400kHz), or single-beam (200kHz) transducers. However, the Government reserves the right to take soundings by any method deemed necessary. A 25-foot by 25-foot cell size average posted to the cell center will be used for acceptance and volume computations.

Additionally, the survey manual referenced in the specifications is outdated, and should be the

EM 1110-2-1003 (2013).

(End of Summary of Changes)