RECAP 3 RFI Questions and Responses.pdf

PDF 420 KB Posted

Attached to
RECAPTIILIZATION OF UTILITIES (RECAP 3) Federal contract opportunity
Solicitation number
W912DR20R0026
Issued by
Department of the Army Corps of Engineers Engineering District Baltimore

About this file

This document contains a federal contract opportunity notice and related questions and responses file. The U.S. Army Corps of Engineers, Baltimore District is soliciting comments from the construction community on the potential use of a Project Labor Agreement for the RECAPTIILIZATION OF UTILITIES project at Buckley Air Force Base, Colorado. The project scope involves expanding the existing power plant by 15MW, demolishing a 10MW plant, replacing medium voltage distribution systems, and developing a new SCADA controls system. Respondents are invited to provide feedback on any experience with PLAs on similar projects in the local area, potential labor shortages, scheduling requirements, and factors regarding how a PLA may or may not advance economy and efficiency on this project. Responses must be submitted by March 12, 2020.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RECAP 3 SOURCES SOUGHT NOTICE

REQUEST FOR INFORMATION QUESTIONS AND RESPONSES

Date Question Answer 28 Feb.

1. Will this be a design-build solicitation or bid-build?

2. Will all of the work described for RECAP 3 be awarded under a single contract or will there multiple solicitations?

3. What is the estimated release date for the solicitation(s)?

4. What is the MW size of the existing power plant?

5. Is there an estimated range for the size of the power plant expansion in MW’s?

1. This will be a Design Bid Build (DBB) Solicitation.

2. All of the work described for RECAP 3 will be awarded under one single contract.

3. The estimated release date of the solicitation has yet to be determined; late FY20 / early FY21 is the closest estimate at this time.

4. There are two power plants on site. 465 Plant contains 10MW and is ultimately demolished at the end of the project. 494 Plant contains 12.5MW that will remain.

5. Power plant expansion will add 15MW of generation to the 494 Plant.

File details come from the government source that posted it. Updated .