This solicitation requests proposals for the repair of barracks at Fort Myer in Arlington, Virginia. The project includes renovation of an existing four-wing barracks building and common use areas with a construction budget between $25-100 million and duration of approximately 780 calendar days. Scope of work encompasses repair and upgrade of building systems including HVAC, electrical, plumbing and removal of hazardous materials. Offerors must submit proposals by June 22, 2020 for the firm-fixed-price design-build contract awarded on a best value basis by the Department of the Army Corps of Engineers, Baltimore District. Evaluation criteria include past performance, management approach, project approach and small business participation with an emphasis on design-build experience and military housing renovations. Vendors must register in SAM to receive consideration for this full and open competition opportunity.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B.08.02_Solicitation_05.22.2020.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Project Title: Repair of Barracks, Building 416, Ft. Myer, Virginia
The purpose of this amendment is to include the responses to the Request for Information (RFI) as w ell as modify language w ithin the Phase I solicitation submission.
1. CONTRACT ID CODE PAGE OF PAGES
1 24
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 08-Jun-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DR20R0020
X 9B. DATED (SEE ITEM 11)
22-May-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
08-Jun-2020
CODE
USACE BALTIMORE
2 HOPKINS PLAZA
BALTIMORE MD 21201
W912DR 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
ProjNet: Logged In User Page 2 of 3 https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll... 6/3/2020
W912DR20R0020
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 20 00 - INSTRUCTIONS FOR PROCUREMENT
The following have been added by full text:
RFIS
UNCLASSIFIED\\FOR OFFICIAL USE ONLY
Bid Inquiry Contractor Report All Inquiries
Project: Repair of Barracks, Building 416, Fort Myer Review: W912DR20R0020-Repair of Barracks, Building 416, Fort Myer (00001) (sorted by CommentID ) Displaying 6 inquiries.
Id Discipline Sheet Detail Spec 8598340 General 11 B.08.02 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
For Phase 1, Factor 1, Experience in Relevant Projects, would the USACE consider extending the performance date for past projects to 10 years? Also, would you consider removing the requirement for all of the projects to be design build?
On: May 26 2020.
Government Response. . The current solicitation requirement is that all project must be completed within eight (8) years preceding the original date issuance of the solicitation and will remain the same. Design bid build projects will be accepted and changed via amendment to include the language that follows. The Offeror shall submit information on at least three (3) but no more than five (5) completed projects. At least three (3) projects must demonstrate Design Build experience. The remaining project can demonstrate Design Bid Build experience. At least one Design Build project must demonstrate experience from the proposed designer. On: Jun 03 2020
Current Request Status: Request Closed Information for this report is procurement sensitive.
8598869 General RFP N/A N/A Comment Classification: UNCLASSIFIED (U)
For Factor 1 Past Performance and Experience, please consider allow CM at Risk (where the general contractor supports the design process during pre-construction services) and/or Design-Bid-Build experience for some relevant projects with Design-Build being a requirement for a minimal number of projects.
On: May 26 2020.
Government Response. . Design bid build projects will be accepted and changed via amendment to include the language that follows. The Offeror shall submit information on at least three (3) but no more than five (5) completed projects. At least three (3) projects must demonstrate Design Build experience. The remaining project can demonstrate Design Bid Build experience. At least one Design Build project must demonstrate experience from the proposed designer. On: Jun 03 2020
Current Request Status: Request Closed Information for this report is procurement sensitive.
8612433 Contracting RFP pages 11-12 of 58
ProjNet: Logged In User Page 3 of 3
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Regarding Factor 1, would the government consider reducing the minimum completion value from $60,000,000 to $25,000,000 and requesting that offerors demonstrate individual-project bonding capability at $60,000,000? The Corps' magnitude for this project is $25,000,000 to $100,000,000. The industry considers this range to indicate that experience with $25,000,000 construction is comparable to $60,000,000 and even $100,000,000 projects; that if a contractor can perform a $25,000,000 project, it can perform a $60,000,000 project. Contractors with 3-5 design/build projects over $60,000,000 (or over 170,000 SF) within the past six years are rare. The solicitation requirements as currently written would likely (and probably severely) limit the Corps' pool of qualified contractors to evaluate. This requested adjustment would, per the Corps' magnitude range, still demonstrate relevant experience and capability without any material sacrifice to the quality or relevancy of the government's evaluation. And it should allow the government to receive additional qualified proposals to consider.
On: Jun 01 2020.
Government Response. . The current solicitation reads,"...These projects must be of relevant scope and complexity and have either a minimum project size of 63,000 Building Gross Square Foot (BGSF) or demonstrate a minimum completion value of $18,000,00 considering adjustment for escalation from project completion to 2020 (all escalation values are to be labeled as escalated and the Offeror must explain in
ProjNet: Logged In User Page 4 of 3 detail their escalation rationale, which must include any formulas, calculations, assumptions, etc.) and address the discussions requested on Attachment A while meeting the teaming agreement requirements above. All projects must have a construction completion date no earlier than eight (8) years preceding the original date of issuance of this solicitation. Projects that have a Beneficial Occupancy Date (BOD) within the same date range will also be considered...". Please review the solicitation requirements. On: Jun 03
Current Request Status: Request Closed Information for this report is procurement sensitive.
8612453 Contracting RFP pages 11 - 12 of 58 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Regarding Factor 1, would the government also allow offerors to submit design/bid/build projects to demonstrate relevant experience, so long as at least one of the projects presented is design/build? Contractors with 3-5 design/build projects of the magnitude presently required by solicitation Factor 1 (and completed within the past six years) are rare. The Factor 1 solicitation requirements as currently written would likely (and probably severely) limit the Corps' pool of qualified contractors to evaluate. This requested adjustment would allow offerors more options to demonstrate relevant work, would be relevant to an offeror's construction phase capability specifically, and should allow the government to receive additional qualified proposals to consider.
On: Jun 01 2020.
Government Response. . Design bid build projects will be accepted and changed via amendment to include the language that follows. The Offeror shall submit information on at least three (3) but no more than five (5) completed projects. At least three (3) projects must demonstrate Design Build experience. The remaining project can demonstrate Design Bid Build experience. At least one Design Build project must demonstrate experience from the proposed designer. On: Jun 03 2020
Current Request Status: Request Closed Information for this report is procurement sensitive.
8612456 Contracting RFP pages 11 - 12 of 58 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Regarding Factor 1, and in addition to the preceding two requests, would the government also consider extending the project recency requirement from six years to ten years? Contractors with 3-5 design/build projects over $60,000,000 (or over 170,000 SF) within the past six years are rare. The solicitation requirements as currently written would likely (and probably severely) limit the Corps' pool of qualified contractors to evaluate. Project completion in 2010 as opposed to 2014 would not be less relevant and would demonstrate capability to perform just as well. And it should allow the government to receive additional qualified proposals to consider.
On: Jun 01 2020.
Government Response. . The current solicitation requirement is that all project must be completed within eight (8) years preceding the original date issuance of the solicitation and will remain the same. The current solicitation reads,"...These projects must be of relevant scope and complexity and have either a minimum project size of 63,000 Building Gross Square Foot (BGSF) or demonstrate a minimum completion value of $18,000,00 considering adjustment for escalation from project completion to 2020 (all escalation values are to be labeled as escalated and the Offeror must explain in detail their escalation rationale, which must include any formulas, calculations, assumptions, etc.) and address the discussions requested on Attachment A while meeting the teaming agreement requirements above. All projects must have a construction completion date no earlier than eight (8) years preceding the original date of issuance of this solicitation.
Projects that have a Beneficial Occupancy Date (BOD) within the same date range will also be considered...". Please review the solicitation requirements. On: Jun 03 2020
Current Request Status: Request Closed Information for this report is procurement sensitive.
8614067 General Section 2.2.1 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Section 2.2.1 - Experience in Relevant Projects defines relevant project size as "either a minimum project size of 63,000 Building Gross Square Foot (BGSF) or demonstrate a minimum completion value of $18,000,000 considering adjustment for escalation from project completion to 2020." Can the government please clarify if this minimum square footage and/or minimum completion value is applicable to a single building, or if multiple buildings under a single task order are equally relevant and compliant?
ProjNet: Logged In User Page 5 of 3
On: Jun 02 2020.
Government Response. . The requirement identified in the RFI for Factor 1 is in regard to the square footage of the entire project (whether contract or task order). If the project consists of multiple buildings, it will be accepted. The square footage per building must be clearly identified. On: Jun 03 2020
Current Request Status: Request Closed Information for this report is procurement sensitive.
Report Complete
UNCLASSIFIED\\FOR OFFICIAL USE ONLY
Patent 11/892,984 ProjNet property of ERDC since 2004.
SECTION 00 21 16 - INSTRUCTIONS TO PROPOSERS
The following have been modified:
PHASE I PROPOSAL SUBMISSION
PHASE I SOLICITATION PROVISIONS
1. PROPOSAL SUBMISSION INSTRUCTIONS
1.1 General: This Request for Proposal (“RFP”) seeks proposals from Offerors interested in being selected for the repair of barracks, Building 416, Fort Myer located in Arlington, Virginia. This is Phase I of a two-phase RFP.
This RFP is requesting submission of proposals under Phase I submission criteria ONLY. After evaluating Phase I proposals, the Contracting Officer will select the most highly qualified Offerors and request that only those Offerors submit proposals for Phase II. The maximum number of Offerors that will be selected to submit Phase II proposals shall not exceed five (5). Offerors shall not submit any proposals under Phase II submission criteria at this time. Phase II of the solicitation will be issued in an amendment directly to those Offerors selected for Phase II. Submitting any information under Phase II criteria may lead to disqualification of your proposal. This is an unrestricted competitive RFP. Offerors responding to this RFP are required to submit their proposals in accordance with the instructions contained in this Section 00 21 16.
The objective of this project is for the repair of barracks, Building 416. In addition to the repair, renovation, and upgrade to Building 416, building systems and components will also be repaired that include roofing, HVAC, electrical distribution, sanitary sewer system, and fire alarm system and fire suppression system, building information systems, lighting & illumination fixtures and plumbing fixtures, exterior doors, windows, ceilings, flooring and floor finishes, living and common area will be repaired. This project will require updates to the existing storm water management and site grading to address water infiltration issues. Additional repairs include existing interior doors and walls, some reconfiguration to maximize capacity and improve efficiency of interior space. HAZMAT were identified during the recent building condition survey and inspection. Removal of ACM and LBP will be required in this repair project in accordance with the governing Federal and State requirements.
This project will bring this building into the compliance with the current minimum AT/FP requirements and current standards of UEPH entry, kitchenette, vanity, bathroom, bedroom, closet, and living room to the extent possible within the existing building structure. The direction is to upgrade to barracks standards as much as possible with 121 single units as a minimum. During a surge, rooms could double up as necessary.
1.2 Basis for Award: A contract will be awarded to the Offeror whose proposal represents the “best value” to the
Government. The best value determination will be based on a comparative assessment of proposals against all source selection criteria in the solicitation, considering recommendations and minority opinions presented to the
ProjNet: Logged In User Page 6 of 3
Source Selection Authority (SSA). While the SSA may use reports and analyses prepared by others, the source selection decision shall represent the SSA's independent judgment.
For the purposes of this solicitation, the Government will utilize the best value Trade-Off Process. The following evaluation factors will be used to evaluate each proposal. Award will be made to the Offeror whose proposal is the most advantageous to the Government based on an integrated assessment of the evaluation factors described below.
PHASE I
Factor 1 – Past Performance and Experience Factor 2 – Management Approach
For Phase I, Past Performance and Experience (Factor 1) and Management Approach (Factor 2) will be will be adjectivally rated. Past Performance and Experience (Factor 1) is more important than Management Approach (Factor 2). Past Performance & Experience (Factor 1) and Management Approach (Factor 2) will not carry over to Phase II.
Each factor is rated individually based on the information contained in that specific factor; that is, evaluations will not be made across the factors.
PHASE II
Factor 3 – Project Approach Factor 4 – Small Business Participation Plan (SBPP) Factor 5 – Price
For Phase II, Project Approach (Factor 3) and SBPP (Factor 4) will be adjectivally rated. Project Approach (Factor 3) is more important than SBPP (Factor 4). When combined, Project Approach (Factor 3) and SBPP (Factor 4) are approximately of equal importance to Price (Factor 5).
1.3 Source Selection: It is the intent of the Government to seek proposals from qualified Offerors with experience in the significant features of this RFP and who can demonstrate a successful performance history in completing relevant projects. For the purposes of this solicitation, the Government will utilize the Trade-Off Process. The successful Offeror will be selected based on the “Best Overall Value to the Government”. The Government will not make an award at a significantly higher price to obtain only slightly superior technical advantages; however, the degree of importance of price as a factor could become greater depending upon the equality of the proposals submitted. Where the technical merits of competing proposals are determined to be substantially equal, price could become the controlling factor.
1.4 Each Offeror is required to submit a proposal consisting of the following volumes:
a. Phase I: Volume I – Technical Proposal (Factors 1 and 2), (digital copy)
b. Phase I: Volume II – Administrative Documents (digital copy)
*NOTE: Electronic submission instructions are outlined in section 1.7, below.
1.5 Specific Requirements: An Offeror’s proposal shall consist of all information and material submitted in writing for evaluation in response to this solicitation. The submission of false or misleading information shall be grounds for disqualification of the proposal. The Offeror’s name, solicitation number and solicitation Closing Time and Date, must be identified for each volume. Offerors must organize their proposals as described and outlined below.
Each volume must have a table of contents and a Cover Sheet to include the Offeror’s CAGE Code, address, NAICS and business size in accordance with the System for Award Management (SAM) and Point of Contact information, such as email and phone number. Each volume’s contents must be separated by tabs/page as discussed below. The proposals must be in an 8-1/2” x 11” format (except for organization chart, in which a
ProjNet: Logged In User Page 7 of 3 folded 11” x 17” format may be used and shall be counted as one page provided the only information presented is the organization chart). Pages must be numbered. The minimum acceptable type size is eleven (11) point with a minimum of one inch margins on all sides. The information in each volume must be organized as follows.
1.5.1 Volume I (Factors 1 and 2): Offerors must submit the information identified in section 2, below. The information must be divided by tabs/pages and shall be organized as follows:
Tab 1 – Factor 1 – Past Performance and Experience Tab 2 – Factor 2 – Management Approach
The total number of pages must not exceed 30 pages in the aggregate. The data appearing in Factor 1 relating to past performance evaluations and awards, are not counted in the overall page limitation. Offerors may distribute the pages among the Factors at their discretion. If the Offeror exceeds the page limitation, then the excess page(s) after page 30 will not be evaluated (actual tabs are not included in count).
1.5.2 Volume II (Administrative Documents): The Administrative Documents must be placed in a separate file and shall be organized as follows:
a. SF 1442 (Solicitation, Offer and Award). Note – All amendments must be acknowledged in block 19;
b. Certificate of Corporate Principal/Authority;
c. Section 00 45 00; and
d. Proof of Bonding Capability of at least $5,000,000.
Those Offerors selected for Phase II will have to resign the SF1442.
1.6 Proposal shall be marked with the Offeror’s Name, Solicitation Number, and the Solicitation Closing Time and
Date. (See SF 1442 Block 1 and Block 13)
1.7 Offerors shall submit their proposals using the link, https://safe.apps.mil, to the Contract Specialist, Leigha
Arnold, at Leigha.M.Arnold@usace.army.mil for both phases of this procurement.
ALL PROPOSALS SHALL BE SUBMITTED ELECTRONICALLY THROUGH THE SAFE SITE.
Submission shall be in searchable Adobe PDF format. You are limited to five (5) maximum files per upload (total size cannot exceed 2 GB). If you have a large number of files, it is recommend that you combine or ZIP your files before uploading to the SAFE site. Offerors may use compression utility software such as WinZip or PKZip to reduce file size and facilitate transmission.
REQUEST FOR UPLOAD CODE: Offerors must email the Contract Specialist, Leigha Arnold, at Leigha.M.Arnold@usace.army.mil no later than five (5) business days prior to the proposal due date to receive a request code which will allow for file uploads via the SAFE site. Offerors that fail to email for a request code five (5) business days before proposal submission date may not be able to receive a request code in time to upload their submission. THIS MUST BE DONE FOR BOTH PHASES OF THE PROCUREMENT.
FILE DESCRIPTION: Include a “File Description” for each file(s) you upload. The “File Description” will be included in the email notice to the recipient you choose to have access your file(s). NOTE: Do NOT enter Privacy Act Data (Personal Identification Information (PII)) in the File Description.)
Submission shall be in searchable Adobe PDF format and legible.
INSTRUCTIONS TO FOLLOW ON THE SAFE WEBSITE:
1. Once at the SAFE website select the “Drop-off” icon. This allows users without a CAC or users whose computer is not configured to read a CAC, the option to access the SAFE site as a guest.
2. After selecting the “Click Here” link you will be prompted to add your personal information, file information, recipient (Government representative) information and email settings.
3. When completing your file information for transmittal via the SAFE website, you will be required to enter the email address for the recipient. For this solicitation, the recipient is the Contract Specialist. The Contract
ProjNet: Logged In User Page 8 of 3
Specialist for this solicitation is Leigha Arnold, Leigha.M.Arnold@usace.army.mil. The E-Mail address of the Government Employee who initiated the request code will be automatically entered. The Proposer must enter the E-Mail address for the Contract Specialist After entering the email address, click the ADD button to add the person(s) email to the “Recipients List” of your response. When your proposal is submitted, a notification will be sent to the recipient you added.
NOTE: Do NOT send the SAFE site packages to group email accounts.
Even if you successfully upload your proposal to the SAFE site, notification will not be sent to the Government recipient until you verify your email address. Entering an incorrect email may result in the rejection of your submission for lateness. A Proposer can confirm proper submission by the ‘Drop-Off Completed” screen which generates based on proper file submission.
NOTE: It has been reported that documents are more quickly uploaded into the SAFE website when using a Firefox web browser. The Government cannot verify that this is true and offers no guarantee that Offerors will have more success utilizing any particular browser.
RECEIPT OF SUBMISSIONS:
For the purposes of establishing whether a proposal submission is considered timely, the Government considers the date and time the submission is completely uploaded into the SAFE website. For proposals larger than the 2GB capacity of the SAFE website and require multiple submissions, the Government will consider the date and time the last submission is completely uploaded into the SAFE website. Do not assume that electronic communication is instantaneous. It can take several minutes or even hours in some cases. The Government will not be responsible for submissions delivered to any location or to anyone other than those designated to receive proposals. Offerors are responsible for ensuring that proposals are submitted so as to reach the designated recipient. Offerors are responsible for allowing sufficient time for the proposal to be received in accordance with the instructions provided.
All proposal shall be submitted no later than the time and date specified on SF 1442, block 13. Offeror’s proposal received after the required time and date deadline will not be evaluated. Offerors should not assume that they will have an opportunity to clarify or correct anything in their proposals after submitting it in response to the original Solicitation, and so any submissions should be submitted on the best terms possible and free of errors.
2. SUBMISSION CRITERIA
2.1 VOLUME I – MINIMUM SUBMISSION CRITERIA (FACTORS 1&2): For purposes of this solicitation, an
“Offeror” may include a group of two (2) or more entities that have formed a “contractor team arrangement,” as that term is defined in the Federal Acquisition Regulation (FAR) subpart 9.6. In the case of entities that have formed a contractor team arrangement, the experience and performance history of any member of the team, whether or not gained while working with the other member(s) of the currently-proposed contractor team arrangement, will be considered as a part of the evaluation of the Offeror’s proposal.
An Offeror that relies upon the experience and performance history of a member, members or affiliates of a proposed contractor team arrangement must provide a teaming agreement or commitment (in the case of any affiliates) signed by all parties. The Teaming agreement/commitment shall:
a. Identify the legal name(s) and cage code(s) of all entities.
b. Describe the nature of each entity’s relationship (partnership, joint venture, prime/sub or mentor/protégé) and their role on this project as a part of their proposal. The Offeror will be expected to maintain that arrangement during performance of any contract awarded to that Offeror under this solicitation.
c. The estimated percentage of work to be completed by each member submitted for the solicitation. This can be a rough order of magnitude for Phase I; however, this agreement/letter must be resubmitted with Phase II to include that actual proposed percentages.
In the case of affiliates, past performance of an Offeror’s “affiliate,” as that term is defined in FAR 2.101, will be evaluated (as described within this section) if the Offeror demonstrates a firm commitment that the affiliate
ProjNet: Logged In User Page 9 of 3 will participate meaningfully (e.g. roles, responsibilities, etc.) in the performance of the contract. This commitment, nature of each entity’s relationship and meaningful participation shall be described in a document signed by authorized representatives of both the Offeror and its affiliate.
The following are to be used in determining the status of the Offeror’s team for the evaluation of project submissions under Factor 1:
In the case of contractor team arrangements involving a Prime Contractor and Subcontractor(s), where the
Prime Contractor submits the proposal in response to this solicitation, the Prime Contractor is considered the “Prime Offeror”.
In the case of joint ventures, the “Prime Offeror” experience can come from any of the entities involved in the venture.
In the case of mentor/protégé relationships, the relationship must be established by the two Offerors and approved by the chosen Government Agency prior to proposal submission. Once the relationship has been approved, the “Prime Offeror” experience can come from any of the entities involved in the relationship.
The approved mentor/protégé document from the Government Agency must be submitted along with the teaming agreement.
In the case of additional projects submitted by subcontractors, the subcontractor must submit the final cost of their portion of the project along with total project cost and all other required information.
In the case of Offerors that are large, multi-function firms (consisting of subsidiaries), experience must only be submitted by the segment of the firm (e.g., division, group, and unit) that is submitting a proposal in response to this solicitation.
In the case of affiliates, Past performance of an Offeror's "affiliate," as that term is defined in FAR 2.101, will be evaluated (as described within this section) if the Offeror demonstrates a firm commitment that the affiliate will participate meaningfully in the performance of the contract. This commitment and meaningful participation shall be described in a document signed by authorized representatives of both the Offeror and its affiliate.
If a teaming agreement or commitment is not provided, the projects of any team members outside of the Prime Offeror will not be considered. If the Joint Venture/Mentor Protégé is a Small and Large business, the Small Business will be evaluated as the Prime Offeror.
2.2 FACTOR 1 – PAST PERFORMANCE & EXPERIENCE: The submitted material MUST be organized sequentially under tabs for each numbered section to facilitate evaluation. All narratives must contain sufficient detail to demonstrate technical capability.
An Offeror that relies upon the experience and performance history of a member, members or affiliates of a proposed contractor team arrangement, as indicated above, must provide a teaming agreement or commitment (in the case of any affiliates) signed by all parties. The Offeror shall provide a teaming agreement with their proposed Designer.
In the case of contractor team arrangements involving a prime contractor and subcontractor(s), where the prime contractor submits the proposal in response to this solicitation, the prime contractor must have completed at least fifty percent (50%) of the total number of projects that meet the requirements for Factor 1 for consideration in response to the experience requirements of this solicitation.
All teaming agreements/commitment shall be provided at the beginning of the Offeror’s technical proposal, prior to Factor 1, and will not be included in the overall page count.
2.2.1 EXPERIENCE IN RELEVANT PROJECTS: The Offeror shall submit information on at least three (3) but no more than five (5) completed DB projects. At least three (3) projects must demonstrate DB projects.
The remaining project(s) can demonstrate Design-Bid-Build (DBB) experience. If the Offeror’s submission exceeds the maximum project limitation of five (5) completed projects, the first five (5) projects submitted will be evaluated only, while the remaining additional project(s) will not be evaluated. These projects must be of relevant scope and complexity and have either a minimum project size of 63,000 Building Gross
ProjNet: Logged In User Page 10 of
Square Foot (BGSF) or demonstrate a minimum completion value of $18,000,000 considering adjustment for escalation from project completion to 2020 (all escalation values are to be labeled as escalated and the Offeror must explain in detail their escalation rationale, which must include any formulas, calculations, assumptions, etc.) and address the discussions requested on Attachment A while meeting the teaming agreement requirements above. All projects must have a construction completion date no earlier than eight (8) years preceding the original date of issuance of this solicitation. Projects that have a Beneficial Occupancy Date (BOD) within the same date range will also be considered.
*Note: In reference to Task Order Construction Contracts (TOCCs)/Indefinite Delivery/Indefinite Quantity (ID/IQ) contracts: Contracts will not be accepted as a project submission; however, individual task orders/delivery orders on TOCCs and/or ID/IQ contracts can be submitted under Factor 1. Each task/delivery order submitted must individually meet the requirements of the factor. Submissions of multiple task/delivery orders as a project will not be accepted or evaluated.
At least one (1) DB project must demonstrate experience from the proposed designer. For projects demonstrating past experience from the designer, one hundred percent (100%) of the design and at least seventy five percent (75%) of the construction of each project must be completed at the time of proposal submission.
For projects demonstrating past experience for the construction contractor, one hundred percent (100%) of the construction must be complete.
Each of the submitted projects shall also include a detailed discussion of at least two (2) or more of the following elements.
Experience performing construction/renovation of military dormitories or barracks Experience performing construction/renovation of apartments Experience removing asbestos containing material and lead based paint Installing/upgrading HVAC System to manage moisture build up in rooms and common areas to include commissioning Employing physical security and anti-terrorism/force protection measures Experience with building envelope repair/testing Experience with storm water management/grading.
*Lists, charts/matrices and bullets will not be accepted when identifying relevant elements.
Each element must have a description of how the project meets the element (e.g. concrete paving – For this project, 500 LF of concrete sidewalks were installed, 300 LF of curbs were removed and re-installed, etc.).
It is the responsibility of the Offeror to identify, detail and demonstrate the relevancy of the submitted projects to the solicitation criteria elements. The evaluation committee WILL NOT make assumptions.
The information that is required to be supplied is identified on the form provided entitled “EXPERIENCE IN RELEVANT PROJECTS” (Attachment A). Offerors are not required to use the form itself as part of their proposal, but the information requested on the form must be in the Offeror’s proposal and should be in the same format as the form. Offerors may expand the form as necessary to accommodate the required project information.
The only submissions under the tab for this section are to be the completed “Attachment A” forms or similar format as indicated above. Only the information provided in either of these formats will be considered. Company summaries/introductions, project summary charts/matrixes, etc. will not be accepted or evaluated.
ProjNet: Logged In User Page 11 of
2.2.2 PAST PERFORMANCE QUESTIONNAIRES FOR EXPERIENCE IN RELEVANT PROJECTS:
For each of the projects submitted, provide a copy of the Contractor Performance Assessment Reporting System (CPARS) report, or USACE Past Performance Questionnaire (PPQ-0) (Attachment B) from a representative of the owner. The Offeror must request that their client complete the USACE Past Performance Questionnaire for Relevant Experience (Form PPQ-0) and submit the questionnaire as part of the Offeror’s technical proposal. The Offeror may provide an explanation if the performance evaluation rating is less than satisfactory. Offerors are encouraged to follow-up with clients/references to ensure timely submittal of questionnaires.
If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before the proposal closing date, the Offeror must complete and submit with the proposal the first page of the PPQ (Attachment B) for projects submitted under the tab for EXPERIENCE IN RELEVANT PROJECTS, which will provide contract and client information for the respective project(s). Ensure correct phone numbers and email addresses are provided for the owner point of contact.
Previously completed PPQ-0s may be submitted provided that the documents do not reference any other solicitations. Submitted PPQ-0s must only reference this solicitation. Contractor Performance Assessment Reporting System (CPARS) ratings will take precedence over PPQs.
While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.
2.3. FACTOR 2 – MANAGEMENT APPROACH: The submitted material MUST be organized sequentially under tabs/pages for each numbered section to facilitate evaluation. All narratives must contain sufficient detail to demonstrate technical capability.
2.3.1 Describe the proposed management structure for the team to include both the construction and design firms, the resources and how the resources will be utilized, their roles and responsibilities, and what subcontracting firms the Offeror is considering utilizing. Offerors are encouraged to describe prior experience working with their proposed designer.
The Offerors must also provide a statement that, in accordance with the specifications of the RFP, all individuals, including subcontractors, will be able to gain access to the Fort Myer Installation.
2.3.2 Describe how subcontractors are managed by the prime contractor to include flow-down of contract requirements, duties, responsibilities and coordination. Discuss how non-performance by subcontractors is handled by the prime contractor.
2.3.3 Describe the role and interaction of the design team with the construction team during construction to include addressing, as a minimum, design quality control; tracking design evolution and changes during design to meet the schedule; management of the design during construction, including control and approval of revisions to the accepted design; requests for information; shop drawing and submittal reviews and approvals; progress meetings; site visits, if any; and as-built drawings.
3. EVALUATION CRITERIA
3.1 VOLUME I – EVALUATION CREITERIA (TECHNICAL PROPOSAL, PHASE I – FACTORS 1 AND 2)
Offerors are cautioned that “parroting” of the Technical requirements with a statement of intent to perform does not reflect an understanding of the requirement or capability to perform. Offerors are responsible for including sufficient details to permit a complete and accurate evaluation of each proposal.
3.2 FACTOR 1 – PAST PERFORMANCE & EXPERIENCE: All submissions by Offerors must demonstrate the minimum requirements for experience in relevant projects, as stated in paragraph 2.2 above.
ProjNet: Logged In User Page 12 of
Past Performance evaluations will be rated in terms of performance confidence for the Government; that is, projects that are considered to be less relevant in terms of size, scope or complexity, dollar value, and/or demonstrating low past performance evaluation ratings will be interpreted as indicators of less confidence that the Offeror can successfully perform the work. More relevant projects and high past performance evaluations will typically be a stronger predictor of future success and have more influence on the past performance confidence assessment than past performance of lesser relevance. Higher confidence assessments will be given for higher past performance evaluation ratings.
Past performance information may be obtained from any other sources available to the Government, to include, but not limited to, the Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS), Contractor Performance Assessment Reporting System (CPARS) or other databases using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the Offeror’s proposal; interviews with Program Managers, Contracting Officers, and Fee Determining Officials; and the Defense Contract Management Agency. The information obtained from these sources will be evaluated supplementary to the past performance questionnaires. In reference to the contracts pulled from these sources, the relevancy of the projects, completion dates, ratings and comments in the individual categories and overall ratings will be considered in making the overall confidence assessment.
In the case of Offerors for which there is no information on past contract performance or where past contract performance information is not available, the Offeror may not be evaluated favorably or unfavorably on the factor of past contract performance (see FAR 15.305(a)(2)(iv).) In this case, the Offeror’s past performance is unknown and assigned a performance confidence rating of “neutral.”
3.3 FACTOR 2 – MANAGEMENT CAPABILITY: The Offeror’s narrative will meet the requirements of this RFP if the narrative is a specific discussion that addresses the elements identified in paragraphs 2.3 in sufficient detail to demonstrate management capability. The narrative must clearly demonstrate a reasonable approach to the contract, an understanding of the requirements of this contract and a plan that has clearly applied the information provided in paragraphs 2.3 which will lead to successful completion of all work within the contract duration.
4. EVALUATION PROCESS
4.1 Proposal Compliance Review: A proposal compliance review will be performed to ensure that all required forms and certifications are complete, that the technical proposals have been received and that the Offerors are eligible to propose. Offerors are advised that the evaluation and ratings of all proposals will be conducted in strict confidence. However, an Offeror’s failure to provide all of the requested information may adversely affect the evaluation or result in rejection of the proposal as nonresponsive.
4.2 Volume I (Technical Proposal, Factors 1 and 2) of the proposals will be evaluated, by the SSEB as established by the SSA, based upon the factors listed below. Offerors submitting proposals for this project should limit submissions to data essential for evaluation of proposals. Each factor is rated individually based on the information contained in that specific factor; that is, evaluations will not be made across the factors, nor will information found in one factor be used in the evaluation of another factor. Factors 1 and 2 will be adjectivally rated. Factor 1 is more important than Factor 2.
Factor 1 – Past Performance and Experience Factor 2 – Management Approach
See section 2 and 3 above for a discussion of the evaluation criteria applicable to these factors.
Past Performance Ratings: There are three aspects to the past performance evaluation. The first is to evaluate the recency of the Offeror’s past performance. The second is to determine how relevant a recent effort accomplished by the Offeror is to the effort to be acquired through the source selection. The third aspect of the past performance evaluation is to establish the overall quality of the Offeror’s past performance.
ProjNet: Logged In User Page 13 of
Past Performance for Factor 1 (Past Performance & Experience) will be evaluated by examining the projects submitted under the tab for paragraph 2.2.1, Experience in Relevant Projects, to determine the relevancy of a recent effort accomplished by the Offeror and assigning one of the relevancy ratings below. These ratings will then influence the overall Confidence Assessment for Factor 1:
Past Performance Relevancy Ratings:
Adjectival Rating Definition
Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.
Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.
Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
The following ratings will be used to identify the Government’s confidence in the Offeror’s Past Performance.
These ratings will be influenced by the relevancy ratings, above, as well as any Contractor Performance Assessment Reporting System (CPARS) ratings; information gathered from POCs, Program Managers, Contracting Officers, and Fee Determining Officials listed for and associated with the submitted projects; and any awards received for the submitted projects:
Performance Confidence Assessments:
Adjectival Rating Description
Substantial Confidence Based on the Offeror’s recent/relevant performance record, the Government has a high expectation that the Offeror will successfully perform the required effort.
Satisfactory Confidence
Based on the Offeror’s recent/relevant performance record, the Government has a reasonable expectation that the Offeror will successfully perform the required effort.
Neutral Confidence
No recent/relevant performance record is available or the Offeror’s performance report is so sparse that no meaningful confidence assessment rating can be reasonably assigned. The Offeror may not be evaluated favorably or unfavorably on the factor of past performance.
Limited Confidence Based on the Offeror’s recent/relevant performance record, the Government has a low expectation that the Offeror will successfully perform the required effort.
No Confidence
Based on the Offeror’s recent/relevant performance record, the Government has no expectation that the Offeror will be able to successfully perform the required effort.
The Combined Technical/Risk Ratings will be utilized in the evaluation of Factor 2 Management Approach.
The Offeror will be assigned one (1) of the Combined Technical/Risk ratings from the following table:
Combined Technical/Risk Ratings:
Adjectival Rating
Description
Outstanding Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is low.
ProjNet: Logged In User Page 14 of
Good Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate.
Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.
Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.
Unacceptable Proposal does not meet requirements of the RFP, and thus, contains one or more deficiencies, and/or risk of unsuccessful performance is unacceptable. Proposal is unawardable.
4.3 SSEB: The SSEB will conduct a review of the proposals against the solicitation requirements and the approved evaluation criteria to ensure an equitable, impartial, and comprehensive evaluation against the solicitation requirements. The SSEB does not compare proposals against each other. The fundamental responsibility of the SSEB is to provide the SSA with information to make an informed and reasoned selection. The SSEB will therefore prepare a summary report containing adjectival assessments for each factor and their supporting rationale for each Offeror; brief the SSA; and prepare any other necessary items.
4.4 Phase I Down Select: After all of the evaluations described above have been completed, the SSA will consider all factors to determine which Offerors submitted the proposals that represents the best value to the Government for this project. The SSA will compare the proposals to determine the offers that represent the best value to the Government, taking into consideration the stated evaluation factors and their respective weightings as specified in the RFP. The selection process is complex and depending upon the evaluation factors, the SSA may exercise a significant degree of judgment in selecting the Offerors. The adjectival ratings assigned by the evaluation team are labels and not the sole basis for proposal comparison. The SSA will not base his/her decision merely on the adjectival ratings or the comparative analysis and recommendations, which compares the strengths and weaknesses of the competing proposals, but shall exercise independent judgment. Up to five (5) Offerors, which are determined to be the most highly qualified Offerors, will advance to Phase II.
4.5 Miscellaneous: The Government reserves the right to reject any or all proposals at any time prior to award, to negotiate with Offerors in a competitive range, if one is established, and to award a contract to the Offeror with the most advantageous proposal to the Government.
5. SUBMISSION DEFINITIONS
Adverse past performance is defined as past performance information that supports a less than satisfactory rating from sources where the information is from other than formal rating systems such as "PPIRS or FAPIIS."
Best Value is the expected outcome of an acquisition that, in the Government’s estimation, provides the greatest overall benefit in response to the requirement.
Beneficial Occupancy Date (BOD) is the point at which the customer determines the facility or area can be occupied from both a regulatory and work function standpoint.
Building Gross Square Foot (BGSF) is the floor area of the entire building or project, which includes floor area occupied by rooms/spaces, walls, corridors, conveyances, mechanical/utility rooms,…