This document contains a report of inquiries and responses related to solicitation number W912DR20R0016 for Pentagon RDF Roof Repair. The solicitation is seeking a contractor to perform roof repair work at the Pentagon in Virginia. Key details include that the work must be completed between the hours of 4:00pm and 4:00am to minimize disruption to operations, as occupied areas below will remain in use. The technical proposal is limited to 30 pages not including covers, dividers, or tables of content. Clarification was provided that experience submitted for evaluation must have been completed within the last six years. The U.S. Army Corps of Engineers Engineering District Baltimore is the contracting agency.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNCLASSIFIED\\FOR OFFICIAL USE ONLY
Bid Inquiry Contractor Report All Inquiries
Project: Pentagon RDF Roof Repair, Pentagon, VA Review: Pentagon RDF Roof Repair, Pentagon, VA (00001) (sorted by CommentID ) Displaying 13 inquiries.
Id Discipline Sheet Detail Spec
8507095 General RFP 2.2.1. Experience in Relevant Projects
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Section 2.2.1. Experience in Relevant Projects indicates that projects must have a construction completion date no earlier than six (6)years. Section 3.2. Past Performance Experience indicates that projects must be completed within five (5) years to be relevant. Please confirm that Section 3.2. Past Performance Experience should also be six (6) years.
On: Apr 13 2020.
Government Response. . The Past performance project submissions must be completed within six (6) years of the date of issuance of the RFP with the exception of the construction percentage completion requirement for the required designer projects. On: Apr 28 2020
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8507099 Project Management N/A N/A
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Will work on this project be allowed during operational hours (0400 - 1600) or will all work be required in the evening and at night after normal operational hours (1600 - 0400)?
On: Apr 13 2020.
Government Response. . NO - No work will be allowed during operational hours, thus the 1600-0400 as listed in the SOW. On: Apr 28 2020
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8507100 Project Management N/A N/A
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Will work on this project be allowed during operational hours (0400 - 1600) or will all work be required in the evening and at night after normal operational hours (1600 - 0400)?
On: Apr 13 2020.
Government Response. . NO - No work will be allowed during operational hours, thus the 1600-0400 as listed in the SOW. On: Apr 28 2020
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8507111 General SF1442 N/A N/A
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The SF 1442 shows that 1 Original and 1 Copy of the submission is required. Section 1.2 indicates that Volume I Technical Proposal is to be submitted electronically (further clarified as via https://safe.apps.mil)and Volume II - Administrative Documents is to be submitted as an Original with no copies. Should Volume II also be submitted electronically via the SAFE website? Is an original hard copy of Volume I or Volume II required to be submitted to USACE Baltimore on or before the submission date and time?
On: Apr 13 2020.
Government Response. . The administrative documents will be submitted electronically as a separate file. On: Apr 28 2020
Current Request Status: Request Closed
Information for this report is procurement sensitive.
Page 1 of 3ProjNet: Logged In User
4/28/2020https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAl...
8510886 Contracting RFP Para 1.3.1
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The beginning of paragraph 1.3.1 identifies the page limit as 30 pages, and the end of the same paragraph says pages over 40 won't be evaluated. Please confirm the page limit for the technical proposal and if this this limit also excludes cover sheets and a table of contents, in addition to those items already excluded in 1.3.1.
On: Apr 14 2020.
Government Response. . The technical proposal volume has a total page limit of 30 pages. On: Apr 28
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8522465 Design Team Leader N/A N/A N/A
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Will the list of required design codes be provided in Phase 2?
On: Apr 20 2020.
Government Response. . YES On: Apr 28 2020
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8522466 Design Team Leader N/A N/A N/A
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Will any requirements for protective design, force protection or progressive collapse be provided in Phase 2?
On: Apr 20 2020.
Government Response. . Yes On: Apr 28 2020
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8522470 Other N/A N/A N/A
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Will as-built drawings, including details of previous repairs and strengthening be provided in Phase 2?
On: Apr 20 2020.
Government Response. . Yes, to the maximum extent available. On: Apr 28 2020
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8522472 Other N/A N/A N/A
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Will lessons learned from previous repairs and strengthening be provided in Phase 2?
On: Apr 20 2020.
Government Response. . NO - There have been no previous repairs made for the scope of this project so there will be no lessons learned. On: Apr 28 2020
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8522493 Other N/A N/A N/A
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The RFP states that the facility will remain operational and that all swing spaces and relocations will be the responsibility of the government. Will all areas below the work area be vacant when construction starts or will relocations be phased? If phasing will be required then does the government have a tenative phasing plan that identifies the size of each work area that will be allowed?
Page 2 of 3ProjNet: Logged In User
On: Apr 20 2020.
Government Response. . NO - Areas below the work areas will remain occupied during construction.
Work hours between 1600 and 0400 have been defined to minimize disruption to occupied operations during peak operation hours. Phasing will be indicated as part of the Phase 2 documentation issued. On:
Apr 28 2020
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8522494 Other N/A N/A N/A
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
The Amendment 1 Statement of Work (April 2020) has significantly less detail than the original 10-18-19 Statement of Work. Was the intention to delete the 10-18-19 SOW and is that scope information still relevant for the purposes of understanding the project requirements since we don't currently have any bridging documents or narratives.
On: Apr 20 2020.
Government Response. . NO - The intention was to delete the 10-18-19 Statement of Work in its entirety as it was accidently posted. The Amendment 1 Statement of Work (April 2020) is to be the sole source of information for the Phase 1 Submission and is sufficient for the Phase 1 submission. Phase 2 documentation with significantly more technical detail will be provided. On: Apr 28 2020
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8525556 General RFP N/A N/A
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Please confirm that the cover, title page, cover letter, table of contents, tab/dividers and flysheets do not count toward the 30 page maximum limit for the Technical Proposal.
On: Apr 21 2020.
Government Response. . Correct, these pages will not count towards the page count. On: Apr 28 2020
Current Request Status: Request Closed
Information for this report is procurement sensitive.
8533226 Design Team Leader RFP
Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)
Have the bridging documents received any preliminary approvals/comments from CFA and/or Arlington County?
On: Apr 23 2020.
Government Response. . No. On: Apr 28 2020
Current Request Status: Request Closed
Information for this report is procurement sensitive.
Report Complete
UNCLASSIFIED\\FOR OFFICIAL USE ONLY