AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to include the Request for Information (RFI) questions and answ ers. All other terms and conditions remain unchanged.

Contracting POC: McKenna Heath mckenna.n.heath@usace.army.mil

1. CONTRACT ID CODE PAGE OF PAGES

1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 02-Sep-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DR20Q0076

X 9B. DATED (SEE ITEM 11)

17-Aug-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

02-Sep-2020

CODE

U.S ARMY CORPS OF ENGINEERS

2 HOPKINS PLAZA 03-B-07

BALTIMORE MD 21201

W912DR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DR20Q0076

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

REQUEST FOR INFORMATION

Wet Well Repair RFI

1. Please confirm that a bid/payment/performance bond is not required for this project.

a. Answer: Bid/payment/performance bonds not required for this project.

2. The solicitation states the timeframe for completing the job is 60 calendar days. The statement of work says 90 calendar days. Can you please advise which one we should base our bid on.

a. Answer: Work shall commence no later than 30 days after the issuance of the notice to proceed and be completed within 90 days of notice to proceed.

3. There are existing steel cages around each ladder which need to be removed in order to build access to perform the repairs. Does the owner want the contractor to remove and reinstall the steel cages or remove and dispose of the cages at each work location.

a. Answer: Steel cages that must be removed can be scrapped and disposed. Disposal of cages, concrete, and other construction materials off site will be the responsibility of the contractor.

4. Could you please tell me if the Combined Synopsis/Solicitation posted as solicitation number

W912DR20Q0076 will be a follow-on requirement to any work performed currently or in the past, or will this be a new requirement?

a. Answer: This project is a new requirement.

5. If possible, can you please provide the most recent contract or task order number?

a. Answer: See Answer to Question 4.

6. Do you foresee requiring any diving services, or will the wet well be dry? I may turn this over to my saw cutting division.

a. Answer: The work may only be performed in conditions where the wet well is not inundated with water, i.e. the gates are open and water is not being impounded. Diving will not be required or allowed.

7. I wanted to write wondering if you have ever considered sealing the new repair with a structural polyurethane coating. The material is called SprayWall and it is manufactured by Spray Roq. Our typical jobs include manholes, culverts, wells, and pipes for stormwater, drinking water, and sanitary water. I have attached a few documents to help you get a feel of Spray Wall if you have any interest. At the end of the day, you would be sealing any exposed concrete in that well. The product is only 30 years old, so we don’t have data going back any further that can speak for its life span. But if you asked around, you would be hard pressed to find a failure so far.

a. Answer: At this time the government does not intend to modify the specifications to add polyurethane coating. Vendors may make value based suggestions at any time for consideration.

(End of Summary of Changes)